Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 19

REKAPITULASI RAP

PEMBANGUNAN HOTEL D' BIG SaMe

CILACAP - JAWA TENGAH


PENAWARAN

URAIAN
10/10/203
(Ribu Rp.) (%)

I BIAYA LANGSUNG 9,515,576.47 75.52


1 PEKERJAAN PERSIAPAN 46,500.00 0.37
2 PEKERJAAN STRUKTURE 8,474,576.47 67.26
3 ALAT PRODUKSI 994,500.00 7.89

II BIAYA TAK LANGSUNG 646,630.00 5.13

1 ALAT PENUNJANG 212,480.00 1.69


2 GAJI PEGAWAI 303,000.00 2.40
3 BUNGA BANK (PROVISI BANK) -
4 BIAYA UMUM ADMINISTRASI 131,150.00 1.04

III BIAYA KONSTRUKSI 10,162,206.47 80.65

1 RESIKO -
2 PEMASARAN 630,000.00 5.00
3 PPH 2.5% - -
4 MARGIN 1,807,793.53 14.35
12,600,000.00
IV OK Netto 100.00

V SUB JUMLAH 12,600,000.00


PPN 11 % 1,386,000.00
VI OK Bruto 13,986,000.00
Dibulatkan
HSat Net/m2 6,000.00
Hsat. OK Netto thd luas ars Rp/M2.
Hsat. OK Bruto thd luas ars Rp/M2.
Kurs US Dollar 1 USD
Kurs US Singapura 1 SGD

Jakarta, 15 Oktober 2023


Prepared by :

Christoporus.P
RABT PEGAWAI & ALAT
PEMBANGUNAN HOTEL D' BIG SaMe

CILACAP - JAWA TENGAH


Item Category Qty Duration Unit Cost (Rp/mo.) Over Time THR Total Cost (Rp)

PEGAWAI
1 Project Manager - -
2 Site Manager 1.00 Org 6.00 Bln 8,000,000.00 - 48,000,000.00
3 Supervisor CSA 2.00 Org 6.00 Bln 6,000,000.00 - 72,000,000.00
4 Supervisor MEP
5 Quality CSA - -
6 Quality MEP - -
7 Safety Officer
8 Admin project 1.00 Org 6.00 Bln 4,000,000.00 24,000,000.00
9 Engineering -
10 Surveyor 1.00 Org 6.00 Bln 6,000,000.00 36,000,000.00
11 Ass Surveyor 1.00 Org 6.00 Bln 4,500,000.00 27,000,000.00
12 Safety man -
13 Koordinator sekurity
14 Sekurity
15 Gudang 1.00 Org 6.00 Bln 5,000,000.00 30,000,000.00
16 Leader harian mekanikal Elektrikal 1.00 Org 6.00 Bln 5,000,000.00 30,000,000.00
17 Harian Mekanik Elektrikal 1.00 Org 6.00 Bln 3,500,000.00 - 21,000,000.00
18 Harian Gudang 1.00 Org 6.00 Bln 2,500,000.00 15,000,000.00
10.00 Org
44,500,000.00 303,000,000.00

ALAT Solar Mobilisasi


1 Molen manual beli 2.00 bh 15,000,000.00 30,000,000.00
2 Vibrator electrik beli 2.00 bh 45,000,000.00 90,000,000.00
3 Concrete pump sewa 20.00 rit 7,000,000.00 140,000,000.00
4 Water Pump beli - 2.00 bh 3,500,000.00 7,000,000.00
5 Pompa Sumpit, summersible beli - bh 75,000,000.00 -
6 Cutting Wheel beli 2.00 bh 5,000,000.00 10,000,000.00
7 Bar Bending sewa 1.00 bh 25,000,000.00 25,000,000.00
8 Bar Cutting sewa 1.00 bh 25,000,000.00 25,000,000.00
9 Jack drill beli bh 20,000,000.00 -
10 Mesin Las beli 1.00 bh 1,500,000.00 1,500,000.00
11 Circle kayu beli - 2.00 bh 36.00 1,500,000.00 3,000,000.00
12 Shoring (Skafolding) sewa 1,620.00 m2 4.00 75,000.00 486,000,000.00
13 Theodolite sewa 1.00 unit 6.00 8,500,000.00 51,000,000.00
14 Waterpass sewa 1.00 unit 6.00 6,000,000.00 36,000,000.00
15 Crane 25 Ton sewa 1.00 unit 2.00 35,000,000.00 10,000,000.00 90,000,000.00
16 Hidraulik pile 1.00 1.00 75,000,000.00 75,000,000.00
- 994,500,000.00
RABT - BU.ADM. / PELAKS.
PEMBANGUNAN HOTEL D' BIG SaMe

CILACAP - JAWA TENGAH


Waktu pelaksanaan 6.00 BK 24 MK 168 HK Unit Jumlah

1 Transport/konsumsi dir. = - Or x 6 Bln x 1,000,000 -


2 Konsumsi rapat = 1 24 Mgg x 200,000 4,800,000.00
3 Makan siang = - Or x 6 Bln x 700,000 -
4 Makan lembur = 4 Or x 3 Bln x 700,000 8,400,000.00
5 Transportasi dinas = - Or x - kali x 1,000,000 -
6 Upacara - Bulanan = Bln x 5,000,000 -
- Start/Fnsh = 1 Kl x 5,000,000 3,000,000.00
7 Alat2 tulis/kantor = 1 6 Bln x 250,000 1,500,000.00
8 Photocopy (sewa) = 1 - Bln x 1,000,000 -
9 Supplies photocopy = 1 - Bln x 500,000 -
10 Ijin-ijin (biaya tdk resmi) = - Bln x 500,000 -
11 Shop drawing/Lichdruck = - Jt x 1 Bln x 3,000,000 3,000,000.00
12 Asbuilt drawing = 1 Ls x 5,000,000 5,000,000.00
13 Rumah sewa dan perabot = 1 unit 6 bln x 5,000,000 30,000,000.00
14 Beli Ruko unit bh 750,000,000 -
15 BPJS Ketenagakerjaan = 0.12 %o x - -
16 CAR = %o x - -
17 Biaya Provisi Bank (menggunakan asuransi) -
18 Jaminan Penawaran 0 % x -
19 Jaminan Uang Muka - % x - -
20 Jaminan Pelaksanaan - % x - -
21 Rumah tangga kantor = 6 Bln x 500,000 3,000,000.00
22 Dispenser = 1 Bh x 1,500,000 1,500,000.00
23 Kulkas - bh 6,500,000 -
24 Air mineral = 30 Hr x 6 Bln x 20,000 3,600,000.00
25 Mess dan RT mess = 1 6 Bln x 500,000 3,000,000.00
26 IMB = - Ls x 5,000,000 -
27 Gambar Pelaksanaan = 1 Ls x 5,000,000 5,000,000.00
28 Penagihan + Adm Pajak = - Bln x 500,000 -
29 Photographi = - ls x 5,000,000 -
30 - bh x 1,000,000 -
31 P3K dan safety = - Bln x 500,000 -
32 Perawatan = 1 Ls x - -
33 Test material = Beton 100 Kbs x 25,000 2,500,000.00
34 Tanah - Ls x 12,000,000 -
35 = Besi - set x 12,000,000 -
36 Komputer + Penyusutan = 2 unit x 7,000,000 14,000,000.00
37 Laptop core 7 i5' ex Asus 1 unit x 7,500,000 7,500,000.00
38 Laptop gen 10 i7' ex Dell unit x 22,000,000 -
39 Plotter - unit 50,000,000 -
40 Printer A3 ex Brother 1 bh x 12,000,000 12,000,000.00
41 Lembur pengawas = Bln x 2,500,000 -
42 Fas. direksi keet = - Ls x - -
43 Fas. kontraktor keet = 1 Ls x 16,850,000 16,850,000.00
44 Seragam proyek = 10 set x 350,000 3,500,000.00
45 Koordinasi keamanan = 1 - Bln x 1,500,000 -
46 Intertainment relasi Natal = - org x 3,000,000 -
47 Lebaran = - org x 5,000,000 -
48 Asuransi Personal Accident = 2 % - Org x 200,000,000 -
49 Rekening listrik (Keet) = 1 6 Bln x 500,000 3,000,000.00
50 Biaya membantu proses Perijinan ke Instansi terkait ls x 125,000,000 -

JUMLAH 131,150,000.00

Rata2/Bulan 3,643,055.56

Check oleh,
______________________ Christoporus.P
RABT - ALAT PENUNJANG
PEMBANGUNAN HOTEL D' BIG SaMe

CILACAP - JAWA TENGAH


Waktu pelaksanaan 6.0 BK 24.0 MK 168 HK. Harsat Jumlah

1 Gerobak dorong Roda Besar = 10 Bh x 750,000 = 7,500,000


2 Gerobak dorong Roda kecil 10 Bh x 350,000 = 3,500,000
3 Ember karet = 100 Bh x 15,000 = 1,500,000
4 Terpal = Rol x 360,000 = -
5 Talang cor = M' x 30,000 = -
6 Plastik cor = rol x 160,000 = -
7 Karung / goni = - BH x 2,500 = -
8 Kaos = 100 bh x 30,000 = 3,000,000
9 Jaring pengaman = M2 x 15,000 = -
10 Safety Shoes staff = 10 psg x 375,000 = 3,750,000
11 Safety Shoes pekerja = 50 psg x 120,000 = 6,000,000
12 Safety Helmet (Untuk staf) = 10 Bh x 50,000 = 500,000
13 Safety Helmet (Untuk pekerja) 50 Bh x 30,000 = 1,500,000
14 Body harnes = Bh x 450,000 = -
15 Rompi = 60 Bh x 27,500 = 1,650,000
16 Jas hujan / payung = 10 Bh x 75,000 = 750,000
17 Meteran (50 mtr) = 2 Bh x 550,000 = 1,100,000
18 Meteran ( 5 mtr) = 2 Bh x 150,000 = 300,000
19 Waterpass/slang = 10 Rol x 50,000 = 500,000
20 Bucket TC ( beli ) = - Bh x 17,000,000 = -
21 HT + baterey = 6 Bh x 1,000,000 = 6,000,000
22 Railing pengaman (pakai tali) = 400 M' x 25,000 = 10,000,000
23 Tangga Acces = 1 Ls x 10,000,000 = 10,000,000
24 Platform untuk acces equipment = 1 set x 10,000,000 = 10,000,000
25 Slang plastik = 6 Rol x 1,000,000 = 6,000,000
26 Alat2 bantu finishing = 1 Ls x 5,000,000 = 5,000,000
27 Cerobong sampah = Lok x - M' x 150,000 = -
28 Kotak sampah = - Bh x 1,000,000 = -
29 Sarana pengukuran = 1 Ls x 5,000,000 = 5,000,000
30 Resibon besar = 30 Bh x 55,000 = 1,650,000
31 Resibon kecil = Bh x 10,000 = -
32 Hammer drill = - Bh x 5,000,000 = -
33 Ramset = Bh x - Bln x 1,500,000 = -
34 Grinda = Bh x Bln x 1,250,000 = -

JUMLAH = 85,200,000

Rata2/Bulan 14,200,000

RABT - KENDARAAN
PEMBANGUNAN HOTEL D' BIG SaMe

Waktu pelaksanaan 12.00 BK/ 48.00 MK/ 336 HK. Jumlah

1 Sepeda motor beli = 2.00 Bh x 1 bh x 12,000,000.00 = 24,000,000


2 Pick Up sewa = 1.00 Bh x 6 bln x 5,000,000.00 = 30,000,000
3 Avanza sewa 1.00 Bh x 6 bln x 6,000,000.00 36,000,000
4 Service 4.00 Bh x 8 Kali x 500,000.00 = 16,000,000
5 Bahan bakar = 280.00 ltr 8 Bln x 9,500.00 = 21,280,000
6 Biaya Angkut dari Jkt - kl 8 Bln x 1,250,000.00 = -
7 Biaya tol = - Bh x 8 Bln x 350,000.00 = -

JUMLAH = 127,280,000

Rata2/Bulan 21,213,333
RABT PERSIAPAN
PEMBANGUNAN HOTEL D' BIG SaMe

CILACAP - JAWA TENGAH


Waktu Pelaksanaan 6.0 BK 24 MK 168 HK. Harsat Jumlah

1 Pagar proyek = - m' x 150,000 = -


Renovasi pagar 2 x = - M' x 20,000 = -
2 Bouwplank = 350 M' x 15,000 = 5,250,000
Land clearing - M2 1,500 -
3 Direksi keet (container) = - bh x 58,000,000 = -
4 Kontraktor keet = - bh x 58,000,000 = -
Kontraktor keet semi permanen - M2 500,000 = -
5 Bongkar pasang etc. = - M2 x 50,000 = -
6 Sub-kontraktor keet = - M2 x 500,000 = -
7 MCK pekerja = - bh x 4,000,000 = -
MCK dalam bangunan - Bh 5,000,000 -
8 Barak pekerja = - m2 x 500,000 = -
9 Sewa tanah = - Th x 25,000,000 = -
10 Gudang = - m2 x 450,000 = -
11 Stock material = - M2 x 150,000 = -
12 Los kerja = - M2 x 250,000 = -
13 Pos jaga = - Bh x 5,000,000 = -
14 Ruang Genset = - M2 x 250,000 = -
15 Kanteen = - M2 x 200,000 = -
16 Papan nama = - Bh x 2,500,000 = -
Ukuran 12 m x 6 - Bh x 14,400,000 = -
17 Jalan kerja (perkuatan jembatan) = - Ls x 20,000,000 = -
18 Telephone Biaya Sambung = 6 bln 10 Line x 1,000,000 =
Telephone - line - bln x 1,500,000 = -
18 Hand phone = - Org x 6 Bln x 200,000 = -
19 Air kerja = 1 Jt. + - bln x 1,000,000 = -
Sarana Air kerja 1 - Ls x 10,000,000 = -
20 Listrik kerja = - Jt. + 1 LS x =
- Penyambungan 10 KVA - kl 12,000,000 -
- Biaya Pemakaian 1 - Bln 2,500,000 = -
- Sarana listrik kerja - Ls 5,000,000 = -
21 Pemadam kebakaran = Bh x 900,000 = -
22 Listrik kerja untuk kontraktor spesialis = - Ls x - = -
23 Bak curing = 1 Ls x 2,500,000 = 2,500,000
23 Safety = 1 ls x 5,000,000 = 5,000,000
24 Pembersihan : -
- Rutin = - Org x - Bln x 400,000 = -
- Akhir (Cleaning service) = - - M2 x 10,000 = -
- Ritasi beton = 200 rit x 20,000 = 4,000,000
- Calbond = BL 1 ls x 5,000,000 = 5,000,000
25 Buang sampah / puing = 5 Rit x - bln x 250,000 = -
26 Penangkal petir = - Ls x 15,000,000 = -
27 Ramp cuci kendaraan = - Ls x 6,000,000 = -
28 Plastic cover Galian = 1 rol x 1,250,000 = 1,250,000
29 Pintu Masuk / Keluar = - Bh x 10,000,000 = -
30 Bongkar Rumah existing = - m2 x 250,000 = -
31 Temporary drainase = - m2 100,000 = -
32 Proteksi Pekerjaan = 1 ls x 5,000,000 5,000,000
33 Perbaikan jln untuk acces = - Ls x 50,000,000 = -
34 Biaya Perbaikan beton dan lain-lain - m2 x 300,000 = -
35 Angkut material di dalam proyek 6 Org x 1 ls x 1,000,000 = 6,000,000
36 Biaya Transoprtasi Pekerja 50 org x 250,000 = 12,500,000
37 Biaya Preman - ls x 50,000,000 = -
JUMLAH = 46,500,000

Rata2/Bulan 7,750,000

Jakarta, 15 Oktober 2023


disusun oleh :

Christoporus.P
REKAPITULASI RENCANA ANGGARAN BIAYA
PEMBANGUNAN HOTEL D'Big SaMe CILACAP JAWA TENGAH

NO URAIAN JUMLAH
1 2 3
PEMBANGUNAN TAHAP - PERTAMA, BANGUNAN HOTEL @ 6 LANTAI

I HOTEL

A PEKERJAAN STRUKTUR 8,474,576,467.59


B PEKERJAAN ARSITEKTUR

II MEKANIKAL,ELEKTRIKAL DAN PLUMBING

III INTERIOR HOTEL ,GALERY AND RESTO


JUMLAH
RENCANA ANGGARAN BIAYA PEMBANGUNAN HOTEL D'BIG SAME CILACAP JAWA TENGAH
PEKERJAAN STRUKTUR

NO URAIAN PEKERJAAN Satuan Volume Harga satuan Total (Rp.) Keterang an


(Rp.)
B. PEKERJAAN STRUKTUR
PEKERJAAN TIANG PANCANG DAN GALIAN
I. PEK. PONDASI
1. Pancang tiang pancang uk. 40/40 m1 2,800.00 225,000.00 630,000,000.00 ###
Biaya pemancangan m1 2,800.00 75,000.00 210,000,000.00 ###
Bobok tiang pancang buah 80.00 110,000.00 8,800,000.00 ###
2. Galian tanah pile cap m3 205.00 55,000.00 11,275,000.00 ###
3. Urugan pasir bawah poor tbl. 10 cm m3 35.45 155,000.00 5,494,750.00 ###
4. Urugan tanah peninggian lantai tbl. 40 cm m3 170.30 181,807.85 30,961,876.86 ###
5. Urugan pasir bawah lantai tbl. 10 cm m3 126.40 155,000.00 19,592,000.00 ###
II PEK. BETON STRUKTUR
1. Lantai kerja bawah poor tbl. 5 cm m3 17.70 461,965.00 8,176,780.50 ###
2. Lantai kerja bawah plat lantai dasar tbl. 5 cm m3 74.00 461,965.00 34,185,410.00 ###
3. Poer Tiang teras uk. 150.150.50 m3 2.25 3,057,856.55 6,880,177.24 ###
4. Poer Tiang tepi uk. 250.250.60 m3 98.00 3,057,856.55 299,669,941.90 ###
5. Poer Tiang tengah uk. 250.250.60 m3 84.00 3,057,856.55 256,859,950.20 ###
6. Cor sloof 35/70 m3 72.30 4,099,203.74 296,372,430.19 ###
LANTAI I
PEK. BETON STRUKTUR
1. Cor kolom 70/70 m3 47.04 4,223,926.87 198,693,520.16 ###
2. Cor kolom 20/20 m3 1.40 4,412,357.42 6,177,300.39 ###
3. Dinding Shearwall tbl. 12 cm m3 20.70 3,259,925.20 67,480,451.64 ###
4. Cor balok 35/70 m3 86.40 4,178,152.68 360,992,391.26 ###
5. Cor balok 20/40 m3 15.20 4,014,361.30 61,018,291.82 ###
6. Cor balok 20/30 m3 5.20 4,126,281.87 21,456,665.72 ###
7. Cor plat lantai tbl. 12 cm (plat lantai 2) m3 97.24 2,912,479.52 283,209,508.92 ###
8. Cor listplank 10/90 m3 1.30 3,371,617.55 4,383,102.82 ###
9. Tangga beton tbl. 12 cm dari lt. 1 ke lt.2 m3 10.48 3,277,817.55 34,351,527.92 ###
LANTAI 2
PEK. BETON STRUKTUR
1. Cor kolom 70/70 m3 47.04 4,223,926.87 198,693,520.16 ###
2. Cor kolom 20/20 m3 1.40 4,412,357.42 6,177,300.39 ###
3. Dinding Shearwall tbl. 12 cm m3 20.70 3,306,825.20 68,451,281.64 ###
4. Cor balok 35/70 m3 86.40 4,178,152.68 360,992,391.26 ###
5. Cor balok 20/40 m3 15.20 4,014,361.30 61,018,291.82 ###
6. Cor balok 20/30 m3 5.20 4,126,281.87 21,456,665.72 ###
7. Cor plat lantai tbl. 12 cm (plat lantai 3) m3 97.24 2,912,479.52 283,209,508.92 ###
8. Cor listplank 10/90 m3 1.30 3,371,617.55 4,383,102.82 ###
9. Tangga beton tbl. 12 cm dari lt. 2 ke lt.3 m3 10.48 3,371,617.55 35,334,551.92 ###
LANTAI 3
RENCANA ANGGARAN BIAYA PEMBANGUNAN HOTEL D'BIG SAME CILACAP JAWA TENGAH
PEKERJAAN STRUKTUR

NO URAIAN PEKERJAAN Satuan Volume Harga satuan Total (Rp.) Keterang an


(Rp.)
PEK. BETON STRUKTUR
1. Cor kolom 70/70 m3 47.04 4,223,926.87 198,693,520.16 ###
2. Cor kolom 20/20 m3 1.40 4,412,357.42 6,177,300.39 ###
3. Dinding Shearwall tbl. 12 cm m3 20.70 3,306,825.20 68,451,281.64 ###
4. Cor balok 35/70 m3 86.40 4,178,152.68 360,992,391.26 ###
5. Cor balok 20/40 m3 15.20 4,014,361.30 61,018,291.82 ###
6. Cor balok 20/30 m3 5.20 4,126,281.87 21,456,665.72 ###
7. Cor plat lantai tbl. 12 cm (plat lantai 4) m3 97.24 2,912,479.52 283,209,508.92 ###
8. Cor listplank 10/90 m3 1.30 3,371,617.55 4,383,102.82 ###
9. Tangga beton tbl. 12 cm dari lt. 3 ke lt.4 m3 10.48 3,371,617.55 35,334,551.92 ###
LANTAI 4
PEK. BETON STRUKTUR
1. Cor kolom 70/70 m3 47.04 4,223,926.87 198,693,520.16 ###
2. Cor kolom 20/20 m3 1.40 4,412,357.42 6,177,300.39 ###
3. Dinding Shearwall tbl. 12 cm m3 20.70 3,306,825.20 68,451,281.64 ###
4. Cor balok 35/70 m3 86.40 4,178,152.68 360,992,391.26 ###
5. Cor balok 20/40 m3 15.20 4,014,361.30 61,018,291.82 ###
6. Cor balok 20/30 m3 5.20 4,126,281.87 21,456,665.72 ###
7. Cor plat lantai tbl. 12 cm (plat lantai 5) m3 97.24 2,912,479.52 283,209,508.92 ###
8. Cor listplank 10/90 m3 1.30 3,371,617.55 4,383,102.82 ###
9. Tangga beton tbl. 12 cm dari lt. 4 ke lt.5 m3 10.48 3,371,617.55 35,334,551.92 ###
LANTAI 5
PEK. BETON STRUKTUR
1. Cor kolom 70/70 m3 47.04 4,223,926.87 198,693,520.16 ###
2. Cor kolom 20/20 m3 1.40 4,412,357.42 6,177,300.39 ###
3. Dinding Shearwall tbl. 12 cm m3 20.70 3,306,825.20 68,451,281.64 ###
4. Cor balok 35/70 m3 86.40 4,178,152.68 360,992,391.26 ###
5. Cor balok 20/40 m3 15.20 4,014,361.30 61,018,291.82 ###
6. Cor balok 20/30 m3 5.20 4,126,281.87 21,456,665.72 ###
7. Cor plat lantai tbl. 12 cm (plat lantai 6) m3 97.24 2,912,479.52 283,209,508.92 ###
8. Cor listplank 10/90 m3 1.30 3,371,617.55 4,383,102.82 ###
9. Tangga beton tbl. 12 cm dari lt. 5 ke lt.6 m3 20.96 3,371,617.55 70,669,103.85 ###
LANTAI 6
PEK. BETON STRUKTUR
1. Cor kolom 70/70 m3 47.04 4,223,926.87 198,693,520.16 ###
2. Cor kolom 20/20 m3 1.40 4,412,357.42 6,177,300.39 ###
3. Dinding Shearwall tbl. 12 cm m3 20.70 3,306,825.20 68,451,281.64 ###
4. Cor balok 35/70 m3 86.40 4,178,152.68 360,992,391.26 ###
5. Cor balok 20/40 m3 15.20 4,014,361.30 61,018,291.82 ###
6. Cor balok 20/30 m3 5.20 4,126,281.87 21,456,665.72 ###
7. Cor plat lantai tbl. 12 cm (plat lantai 6) m3 97.24 2,912,479.52 283,209,508.92 ###
8. Cor listplank 10/90 m3 1.30 3,371,617.55 4,383,102.82 ###
9. Tangga beton tbl. 12 cm dari lt. 5 ke lt.6 m3 20.96 3,371,617.55 70,669,103.85 ###
LANTAI ATAP
PEK. BETON STRUKTUR
1. Cor balok 15/30 (balok listplank lantai atap) m3 5.80 3,371,617.55 19,555,381.79 ###
2. Cor plat lantai tbl. 12 cm (plat lantai atap m3 97.24 2,912,479.52 283,209,508.92 ###
3. Cor listplank 10/90 m3 13.80 3,371,617.55 46,528,322.19 ###
TOTAL PEKERJAAN STRUKTUR 8,474,576,467.59
PEKERJAAN : PEMBANGUNAN HOTEL D'BIG SAME CILACAP JAWA TENGAH
JENIS PEKERJAAN : Beton 1 : 2 : 3
SATUAN : M3

Harga Jumlah
No. Uraian Sat Volume Satuan Harga
(Rp.) (Rp.)

A. BAHAN
1 Semen @50 Kg Zak 5.3200 75,000.00 399,000.00
2 Pasir Pasang M3 0.5429 221,800.00 120,405.71
3 Batu Kerikil M3 0.7622 249,525.00 190,193.50

Sub Total A 709,599.21

B. UPAH BORONGAN GELAR PAKAI POMPA BETON 1.0000 50,000.00 50,000.00

Sub Total B 50,000.00


C. Jumlah Harga ( A + B ) 759,599.21

PEKERJAAN : PEMBANGUNAN HOTEL D'BIG SAME CILACAP JAWA TENGAH


JENIS PEKERJAAN : Membuat 1 m3 beton mutu fc = 21,93 Mpa ( K225 )
SATUAN : M3

Harga Jumlah
No. Uraian Sat Volume Satuan Harga
(Rp.) (Rp.)

A. BAHAN
1 Semen @50 Kg Kg 371.0000 1,500.00 556,500.00
2 Pasir Pasang M3 0.4986 221,800.00 110,583.14
3 Batu Kerikil M3 0.7756 249,525.00 193,520.50

Sub Total A 860,603.64

B. UPAH BORONGAN GELAR PAKAI POMPA BETON 1.0000 50,000.00 50,000.00

Sub Total B 50,000.00


C. Jumlah Harga ( A + B ) 910,603.64

PEKERJAAN : PEMBANGUNAN HOTEL D'BIG SAME CILACAP JAWA TENGAH


JENIS PEKERJAAN : Membuat 1 m3 beton mutu fc = 20 Mpa ( K250 )
SATUAN : M3

Harga Jumlah
No. Uraian Sat Volume Satuan Harga
(Rp.) (Rp.)

A. BAHAN
1 Semen @50 Kg Kg 384.0000 1,500.00 576,000.00
2 Pasir Beton M3 0.4943 221,800.00 109,632.57
3 Batu Kerikil M3 0.7696 249,525.00 192,041.83

Sub Total A 877,674.40

B. UPAH BORONGAN GELAR PAKAI POMPA BETON 1.0000 50,000.00 50,000.00

Sub Total B 50,000.00


C. Jumlah Harga ( A + B ) 927,674.40
PEKERJAAN : PEMBANGUNAN HOTEL D'BIG SAME CILACAP JAWA TENGAH
JENIS PEKERJAAN : Membuat 1 m3 beton mutu fc = 25 Mpa ( K300 )
SATUAN : M3

Harga Jumlah
No. Uraian Sat Volume Satuan Harga
(Rp.) (Rp.)

A. BAHAN
1 Semen @50 Kg Kg 413.0000 1,500.00 619,500.00
2 Pasir Beton M3 0.4864 221,800.00 107,889.86
3 Batu Kerikil M3 0.7563 249,525.00 188,714.83
4 Air Ltr 215.0000 25.00 5,375.00

Sub Total A 921,479.69

B. UPAH BORONGAN GELAR PAKAI POMPA BETON 1.0000 50,000.00 50,000.00

Sub Total B 50,000.00


C. Jumlah Harga ( A + B ) 971,479.69

PEKERJAAN : PEMBANGUNAN HOTEL D'BIG SAME CILACAP JAWA TENGAH


JENIS PEKERJAAN : Beton mutu f = 14,5 MPa (K 175), slump (12 2) cm, w/c = 0,66
SATUAN : M3

Harga Jumlah
No. Uraian Sat Volume Satuan Harga
(Rp.) (Rp.)

A. BAHAN
1 Semen @50 Kg Kg 326.0000 1,500.00 489,000.00
2 Pasir Beton M3 0.5429 221,800.00 120,405.71
3 Batu Kerikil M3 0.7622 249,525.00 190,193.50

Sub Total A 799,599.21

B. UPAH BORONGAN GELAR PAKAI POMPA BETON 1.0000 50,000.00 50,000.00

Sub Total B 50,000.00


C. Jumlah Harga ( A + B ) 849,599.21

PEKERJAAN : PEMBANGUNAN HOTEL D'BIG SAME CILACAP JAWA TENGAH


JENIS PEKERJAAN : Beton mutu fc = 7,4 MPa (K 100)
SATUAN : M3

Harga Jumlah
No. Uraian Sat Volume Satuan Harga
(Rp.) (Rp.)

A. BAHAN
1 Semen @50 Kg Kg 247.0000 1,500.00 370,500.00
2 Pasir Beton M3 0.6207 221,800.00 137,674.43
3 Batu Kerikil M3 0.7400 249,525.00 184,648.50

Sub Total A 692,822.93

B. UPAH BORONGAN GELAR PAKAI POMPA BETON 1.0000 50,000.00 50,000.00

Sub Total B 50,000.00


C. Jumlah Harga ( A + B ) 742,822.93
PEKERJAAN : PEMBANGUNAN HOTEL D'BIG SAME CILACAP JAWA TENGAH
JENIS PEKERJAAN : Beton mutu fc = 12,2 MPa (K 150)
SATUAN : M3

Harga Jumlah
No. Uraian Sat Volume Satuan Harga
(Rp.) (Rp.)

A. BAHAN
1 Semen @50 Kg Kg 299.0000 1,500.00 448,500.00
2 Pasir Beton M3 0.5707 221,800.00 126,584.43
3 Batu Kerikil M3 0.7533 249,525.00 187,975.50

Sub Total A 763,059.93

B. UPAH BORONGAN GELAR PAKAI POMPA BETON 1.0000 50,000.00 50,000.00

Sub Total B 50,000.00


C. Jumlah Harga ( A + B ) 813,059.93

PEKERJAAN : PEMBANGUNAN HOTEL D'BIG SAME CILACAP JAWA TENGAH


JENIS PEKERJAAN : Beton mutu fc = 12,2 MPa (K 200)
SATUAN : M3

Harga Jumlah
No. Uraian Sat Volume Satuan Harga
(Rp.) (Rp.)

A. BAHAN
1 Semen @50 Kg Kg 352.0000 1,500.00 528,000.00
2 Pasir Beton M3 0.5221 221,800.00 115,811.29
3 Batu Kerikil M3 0.7637 249,525.00 190,563.17

Sub Total A 834,374.45

B. UPAH BORONGAN GELAR PAKAI POMPA BETON 1.0000 50,000.00 50,000.00

Sub Total B 50,000.00


C. Jumlah Harga ( A + B ) 884,374.45
PEKERJAAN : PEMBANGUNAN HOTEL D'BIG SAME CILACAP JAWA TENGAH
JENIS PEKERJAAN : Beton Ready Mix Fc'30 Mpa (K-350)
SATUAN : M3

Harga Jumlah
No. Uraian Sat Volume Satuan Harga
(Rp.) (Rp.)

A. BAHAN
1 Semen @50 Kg Kg 448.0000 1,500.00 672,000.00
2 Pasir Beton M3 0.4764 221,800.00 105,671.86
3 Batu Kerikil M3 0.7407 249,525.00 184,833.33
4 Air Ltr 215.0000 25.00 5,375.00

Sub Total A 967,880.19

B. UPAH BORONGAN GELAR PAKAI POMPA BETON 1.0000 50,000.00 50,000.00

Sub Total B 50,000.00


C. Jumlah Harga ( A + B ) 1,017,880.19

PEKERJAAN : PEMBANGUNAN HOTEL D'BIG SAME CILACAP JAWA TENGAH


JENIS PEKERJAAN : Pekerjaan Pembesian Polos
SATUAN : Kg

Harga Jumlah
No. Uraian Sat Volume Satuan Harga
(Rp.) (Rp.)

A. BAHAN
1 Besi Beton Kg 1.0500 9,700.00 10,185.00
2 Kawat Beton Kg 0.0150 22,180.00 332.70

Sub Total A 10,517.70

B. UPAH
1 Mandor OH 0.0003 130,014.00 39.00
2 Kepala Tukang OH 0.0007 131,062.50 91.74
3 Tukang Besi OH 0.0070 132,111.00 924.78
4 Pekerja OH 0.0070 128,441.25 899.09

Sub Total B 1,954.61


C. Jumlah Harga ( A + B ) 12,472.31
PEKERJAAN : PEMBANGUNAN HOTEL D'BIG SAME CILACAP JAWA TENGAH
JENIS PEKERJAAN : Pekerjaan Pembesian Ulir
SATUAN : Kg

Harga Jumlah
No. Uraian Sat Volume Satuan Harga
(Rp.) (Rp.)

A. BAHAN
1 Besi Beton Kg 1.0500 9,700.00 10,185.00
2 Kawat Beton Kg 0.0150 22,180.00 332.70

Sub Total A 10,517.70

B. UPAH
1 Mandor OH 0.0003 130,014.00 39.00
2 Kepala Tukang OH 0.0007 131,062.50 91.74
3 Tukang Besi OH 0.0070 132,111.00 924.78
4 Pekerja OH 0.0070 128,441.25 899.09

Sub Total B 1,954.61


C. Jumlah Harga ( A + B ) 12,472.31

PEKERJAAN : PEMBANGUNAN HOTEL D'BIG SAME CILACAP JAWA TENGAH


JENIS PEKERJAAN : Pekerjaan Pembesian Wiremash
SATUAN : Kg

Harga Jumlah
No. Uraian Sat Volume Satuan Harga
(Rp.) (Rp.)

A. BAHAN
1 Wiremash M8 Kg 1.0500 9,700.00 10,185.00
2 Kawat Beton Kg 0.0150 22,180.00 332.70

Sub Total A 10,517.70

B. UPAH
1 Mandor OH 0.0003 130,014.00 39.00
2 Kepala Tukang OH 0.0007 131,062.50 91.74
3 Tukang Besi OH 0.0070 132,111.00 924.78
4 Pekerja OH 0.0070 128,441.25 899.09

Sub Total B 1,954.61


C. Jumlah Harga ( A + B ) 12,472.31

PEKERJAAN : PEMBANGUNAN HOTEL D'BIG SAME CILACAP JAWA TENGAH


JENIS PEKERJAAN : Memasang Bekisting Untuk Pondasi 2 X Pakai
SATUAN : M2

Harga Jumlah
No. Uraian Sat Volume Satuan Harga
(Rp.) (Rp.)

A. BAHAN
1 Kayu Kls III M3 0.0400 1,150,000.00 46,000.00
2 Paku Kg 0.3000 25,000.00 7,500.00
3 Minyak Bekisting Lt 0.1000 20,000.00 2,000.00

Sub Total A 55,500.00

B. UPAH
1 Mandor OH 0.0260 130,014.00 3,380.36
2 Kepala Tukang OH 0.0260 131,062.50 3,407.63
3 Tukang Kayu OH 0.2600 132,111.00 34,348.86
4 Pekerja OH 0.5200 128,441.25 66,789.45

Sub Total B 107,926.30


C. Jumlah Harga ( A + B ) 163,426.30
PEKERJAAN : PEMBANGUNAN HOTEL D'BIG SAME CILACAP JAWA TENGAH
JENIS PEKERJAAN : Memasang Bekisting Untuk Sloef 2 x Pakai
SATUAN : M2

Harga Jumlah
No. Uraian Sat Volume Satuan Harga
(Rp.) (Rp.)

A. BAHAN
1 Kayu Kls III M3 0.0450 1,150,000.00 51,750.00
2 Paku Kg 0.3000 25,000.00 7,500.00
3 Minyak Bekisting Lt 0.1000 20,000.00 2,000.00

Sub Total A 61,250.00

B. UPAH
1 Mandor OH 0.0260 130,014.00 3,380.36
2 Kepala Tukang OH 0.0260 131,062.50 3,407.63
3 Tukang Kayu OH 0.2600 132,111.00 34,348.86
4 Pekerja OH 0.5200 128,441.25 66,789.45

Sub Total B 107,926.30


C. Jumlah Harga ( A + B ) 169,176.30

PEKERJAAN : PEMBANGUNAN HOTEL D'BIG SAME CILACAP JAWA TENGAH


JENIS PEKERJAAN : Memasang Bekisting Untuk Kolom 2 x Pakai
SATUAN : M2

Harga Jumlah
No. Uraian Sat Volume Satuan Harga
(Rp.) (Rp.)

A. BAHAN
1 Kayu Terentang Kls III M3 0.0400 1,150,000.00 46,000.00
2 Kayu Balok Kls III M4 0.0150 1,150,000.00 17,250.00
3 Paku Kg 0.4000 25,000.00 10,000.00
4 Minyak Bekisting Lt 0.2000 20,000.00 4,000.00
5 Multipleks T = 6 mm Lbr 0.3500 87,888.25 30,760.89
6 Dolken Kayu Galam Dia. 8-10 Cm Pjg 4 M Btg 2.0000 13,585.25 27,170.50

Sub Total A 135,181.39

B. UPAH
1 Mandor OH 0.0330 130,014.00 4,290.46
2 Kepala Tukang OH 0.0330 131,062.50 4,325.06
3 Tukang Kayu OH 0.3300 132,111.00 43,596.63
4 Pekerja OH 0.6600 128,441.25 84,771.23

Sub Total B 136,983.38


C. Jumlah Harga ( A + B ) 272,164.77
PEKERJAAN : PEMBANGUNAN HOTEL D'BIG SAME CILACAP JAWA TENGAH
JENIS PEKERJAAN : Memasang Bekisting Untuk Balok 2 x Pakai
SATUAN : M2

Harga Jumlah
No. Uraian Sat Volume Satuan Harga
(Rp.) (Rp.)

A. BAHAN
1 Kayu Terentang Kls III M3 0.0400 1,150,000.00 46,000.00
2 Kayu Balok Kls III M4 0.0180 1,150,000.00 20,700.00
3 Paku Kg 0.4000 25,000.00 10,000.00
4 Minyak Bekisting Lt 0.2000 20,000.00 4,000.00
5 Multipleks T = 6 mm Lbr 0.3500 87,888.25 30,760.89
6 Dolken Kayu Galam Dia. 8-10 Cm Pjg 4 M Btg 2.0000 13,585.25 27,170.50

Sub Total A 138,631.39

B. UPAH
1 Mandor OH 0.0330 130,014.00 4,290.46
2 Kepala Tukang OH 0.0330 131,062.50 4,325.06
3 Tukang Kayu OH 0.3300 132,111.00 43,596.63
4 Pekerja OH 0.6600 128,441.25 84,771.23

Sub Total B 136,983.38


C. Jumlah Harga ( A + B ) 275,614.77

PEKERJAAN : PEMBANGUNAN HOTEL D'BIG SAME CILACAP JAWA TENGAH


JENIS PEKERJAAN : Memasang Bekisting Untuk Plat Lantai 2 x Pakai
SATUAN : M2

Harga Jumlah
No. Uraian Sat Volume Satuan Harga
(Rp.) (Rp.)

A. BAHAN
1 Kayu Terentang Kls III M3 0.0400 1,150,000.00 46,000.00
2 Kayu Balok Kls III M4 0.0150 1,150,000.00 17,250.00
3 Paku Kg 0.4000 25,000.00 10,000.00
4 Minyak Bekisting Lt 0.2000 20,000.00 4,000.00
5 Multipleks T = 6 mm Lbr 0.3500 87,888.25 30,760.89
6 Dolken Kayu Galam Dia. 8-10 Cm Pjg 4 M Btg 6.0000 13,585.25 81,511.50

Sub Total A 189,522.39

B. UPAH
1 Mandor OH 0.0330 130,014.00 4,290.46
2 Kepala Tukang OH 0.0330 131,062.50 4,325.06
3 Tukang Kayu OH 0.3300 132,111.00 43,596.63
4 Pekerja OH 0.6600 128,441.25 84,771.23

Sub Total B 136,983.38


C. Jumlah Harga ( A + B ) 326,505.77
PEKERJAAN : PEMBANGUNAN HOTEL D'BIG SAME CILACAP JAWA TENGAH
JENIS PEKERJAAN : Membongkar Cetakan dan Menyiram Beton
SATUAN : Ls

Harga Jumlah
No. Uraian Sat Volume Satuan Harga
(Rp.) (Rp.)

A. BAHAN

Sub Total A -

B. UPAH
1 Pekerja OH 2.0000 128,441.25 256,882.50

Sub Total B 256,882.50


C. Jumlah Harga ( A + B ) 256,882.50

PEKERJAAN : PEMBANGUNAN HOTEL D'BIG SAME CILACAP JAWA TENGAH


JENIS PEKERJAAN : Membongkar Bekisting
SATUAN : Ls

Harga Jumlah
No. Uraian Sat Volume Satuan Harga
(Rp.) (Rp.)

A. BAHAN

Sub Total A -

B. UPAH
1 Pekerja OH 0.0400 128,441.25 5,137.65
2 Mandor OH 0.0040 130,014.00 520.06

Sub Total B 5,657.71


C. Jumlah Harga ( A + B ) 5,657.71
PEKERJAAN : PEMBANGUNAN HOTEL D'BIG SAME CILACAP JAWA TENGAH
JENIS PEKERJAAN : Membuat Beton Bertulang Ad 1 : 2 : 3
SATUAN : M3

Harga Jumlah
No. Uraian Sat Volume Satuan Harga
(Rp.) (Rp.)

A. Pek. Beton M3 1.0000 971,479.69 971,479.69


B. Pek. Pembesian Kg 1.0000 12,472.31 12,472.31

C. Memasang Bekisting Untuk Pondasi 2 X M2 1.0000 54,475.43 54,475.43


Pakai

D. Memasang Bekisting Untuk Sloef 2 x M2 1.0000 56,392.10 56,392.10


Pakai

E. Memasang Bekisting Untuk Kolom 2 x M2 1.0000 90,721.59 90,721.59


Pakai

F. Memasang Bekisting Untuk Balok 2 x M2 1.0000 91,871.59 91,871.59


Pakai

G. Memasang Bekisting Untuk Plat Lantai 2 M2 1.0000 108,835.26 108,835.26


x Pakai
H. Membongkar & Menyiram Beton Ls 1.0000 5,657.71 5,657.71

C. Jumlah Harga Beton / M3 977,137.40


Jumlah
Dengan Dengan Memakai Besi
No. Uraian Sat Memasang Harga
(Kg)
Bekisting (M2) (Rp.)

1 Beton Sloof (35 X 70) M3 5.60 225.00 4,099,203.74


2 Beton Kolom (70 X70 ) M3 5.60 235.00 4,223,926.87
3 Beton Kolom (20 X20 ) M3 20.00 185.00 4,412,357.42
4 Beton Balok Latei (20 X 30) M3 13.60 191.00 4,126,281.87
Beton Balok Latei (20 X 40) M3 12.50 187.00 4,014,361.30
Beton Balok Latei (35 X 70) M3 7.00 225.00 4,178,152.68
5 Beton Plat Lantai M3 8.00 119.00 2,912,479.52

You might also like