Professional Documents
Culture Documents
Final Final MPB Caliber
Final Final MPB Caliber
00
***CONCRETE-MASONRY***
CONCRETE 20.70MPa 3,965.00 per cu.m
CONCRETE 24.10MPa 4,535.00 per cu.m
CEMENT 285.00 per bag
CHB 4" 12.00 per pc.
CHB 6" 15.00 per pc.
Sahara Cement 40.00 per bag
Moulding 120.00 per l.m.
***FILLING MATERIALS***
Sand 900.00 per cu.m
Crushed Gravel (G-1) 950.00 per cu.m
BASECOARSE 650.00 per cu.m
BANDA Y BANDA 350.00 per cu.m
***REBARS-METALS***
RSB 42.00 per kilo
Nails 85.00 per kilo
Mooring Ring 2 1/2"Ø 600.00 per set
Angle Bar (50mm x 50mm x 6mm) 825.00 per pc.
12mm SQUARE BARS 220.00 per pc.
37.5 mmØ SS Pipe 4,000.00 per pc.
50mm dia. G.I.pipe sch.40 2,800.00 per pc.
Door knob 500.00 per pc.
Aluminum signage ga. 22 25,000.00 per set
tie wire 135.00 per kilo
***WOODS-ALUMINUM***
1/2" PLYWOOD 950.00 per sht.
1/4" PLYWOOD 450.00 per sht.
WOOD/LUMBER 15.00 per bdft.
WOOD/LUMBER 35.00 per bdft.
Cornice Moulding wood 50.00 per l.m.
Panel Door 0.70 ( Inc. jamb/header, hinges) 6,050.00 per set
Panel Door 0.80 ( Inc. jamb/header, hinges) 6,600.00 per set
Panel Door 0.90 ( Inc. jamb/header, hinges.) 7,700.00 per set
Aluminum Screen Door 6,050.00 per set
Aluminum Screen Windows 60.50 per sq.m.
Aluminum frame Glass Door, 0.75 m x 2.1 m 9,900.00 per set
Alum Framed Fixed w/ Sliding Glass Window 5,500.00 per set
Alum. Frame Glass Fixed w/ Sliding Window, 7,700.00 per set
Aluminum Sliding Window, 1.20 m x 1.20 m 4,950.00 per set
Awning Type Window, 0.60 x 0.60 m 1,650.00 per set
Awning Type Window, 0.60 x 1.20m 2,970.00 per set
Awning Type Window, 0.60 x 1.80m 4,400.00 per set
0.60 m x 2.1 m PVC Flush 2,310.00 per set
0.90 m x 2.1 m PVC Flush 3,520.00 per set
0.60 m x1.50 m PVC Flush 1,760.00 per set
***PAINTING-MISCELLANEOUS***
FILTER FABRIC 120.00 per sq.m.
Asphalt filler 40.00 per kg.
Traffic Paint 720.00 per gal.
4"Ø PVC Pipe 800.00 per pc.
3"Ø PVC Pipe 550.00 per pc.
2"Ø PVC Pipe 285.00 per pc.
4"Ø PVC Elbow 98.00 per pc.
3"Ø PVC Elbow 60.00 per pc.
2"Ø PVC Elbow 35.00 per pc.
4"Ø PVC Wye 195.00 per pc.
3"Ø PVC Wye 160.00 per pc.
2"Ø PVC Wye 90.00 per pc.
2"x4"Ø PVC Wye Reducer 115.00 per pc.
3"x4"Ø PVC Wye Reducer 140.00 per pc.
2"x3"Ø PVC Wye Reducer 90.00 per pc.
4"Ø PVC P-Trap 195.00 per pc.
3"Ø PVC P-Trap 150.00 per pc.
PVC Cap 60.00 per pc.
Floor Drain 185.00 per pc.
Epoxy Paint 820.00 per gal.
FLAT LATEX 600.00 per gal.
Semi-Gloss Latex 680.00 per gal.
Flatwall Enamel 650.00 per gal.
Quick Drying Enamel 700.00 per gal.
Primer Epoxy w/ Catalyst 900.00 per gal.
Enamel Paint 700.00 per gal.
Automotive Paint 1,300.00 per gal.
Lacquer Primer 1,100.00 per gal.
PME 901 2,200.00 per gal.
PME 902 2,300.00 per gal.
Turoseal 1,200.00 per gal.
***MANPOWER RATES***
engineer 700.00 per day
foreman 400.00 per day
driver 300.00 per day
operator 300.00 per day
Electrician 300.00 per day
carpenter 300.00 per day
mason 300.00 per day
painter 300.00 per day
steelman 300.00 per day
Tinsmith 300.00 per day
welder 300.00 per day
riggerman 300.00 per day
laborer 250.00 per day
***EQUIPMENTS RATES***
Fuel 50.00 per lit.
Forklift 5,250.00 per day
Crane 25 tons 13,850.00 per day
Crane 6-10 tons 6,200.00 per day
Dredging Machine 12,000.00 per day
Mini-backhoe 6,000.00 per day
backhoe 16,380.00 per day
grader 16,580.00 per day
dumptruck (11-15 cu.m.) 16,340.00 per day
loader (1 cu.m.) 8,760.00 per day
Roller compactor, 10 T 8,830.00 per day
Plate Compactor 738.00 per day
Concrete Bagger Mixer 1,360.00 per day
BID FORM
PAGE 1/3
Bid Proposal form
Page ____ of ____
ITEM UNIT COST
NO. DESCRIPTION OF WORK PFDA BIDDER UNITS Estimated Direct Cost & TOTAL COST
Value Added Tax & Mark-ups
5.0 #REF!
WINDOWS
3600 mm x 2400 mm x 12.5 mm thk fixed window clear and smoke glass
with aluminum frame 6.00 set
2400 mm x 2400 mm x 12.5 mm thk fixed window clear and smoke glass
with aluminum frame 8.00 set
2400 mm x 1200 mm x 12.5 mm thk fixed window clear and smoke glass
with aluminum frame 4.00 set
Alum. Frame Glass, 3200 mm x 2400 mm x 1/4" thk clear glass Sliding
Window with aluminum frame 7.00 set
Alum. Frame Glass, 3200 mm x 1200 mm x 1/4" thk clear glass Sliding
Window with aluminum frame 20.00 set
Alum. Frame Glass, 1600 mm x 1200 mm x 1/4" thk clear glass Sliding
Window with aluminum frame 6.00 set
Alum. Frame Glass, 700 mm x 700 mm x 1/4" thk clear glass Sliding
Window with aluminum frame 7.00 set
6.0 PLUMBING/SANITARY WORKS
A. Sanitary Pipes, Fittings and Accessories
PVC Pipe, 150mm Ø series 1000 20.00 pcs
PVC Pipe, 100mm Ø series 1000 38.00 pcs
PVC Pipe, 75mm Ø series 1000 6.00 pcs
PVC Pipe, 50mm Ø series 1000 14.00 pcs
PVC Elbow, 90° x 100mm Ø 32.00 pcs
PVC Elbow, 90° x 75mm Ø 84.00 pcs
PVC Elbow, 45° x 100mm Ø 25.00 pcs
PVC Elbow, 45° x 75mm Ø 40.00 pcs
PVC TEE 150 mm x 100 mm dia. 8.00 pcs
PVC TEE 150 mm x 75 mm dia. 2.00 pcs
PVC TEE 100 mm x 100 mm dia. 16.00 pcs
Bid Proposal form
Page ____ of ____
ITEM UNIT COST
NO. DESCRIPTION OF WORK PFDA BIDDER UNITS Estimated Direct Cost & TOTAL COST
Value Added Tax & Mark-ups
PVC TEE 100 mm x 75 mm dia. 33.00 pcs
PVC TEE 75 mm x 75 mm dia. 20.00 pcs
PAGE 2/3
PAGE 3/3
Republic of the Philippines
PROVINCE OF CAMIGUIN
Municipality of Sagay
PROGRAM OF WORK/BUDGET COST
E Q U I P M E N T
DESCRIPTION OF WORK TO BE DONE NUMBER
DESCRIPTION
NEEDED AVAILABLE
Mobilization & Demobilization 0.27% welding machine 1
Concrete and Masonry Works 24.34% Dumptruck 1
Roof Framing and Roofing Works 37.84% Conc. Mixer 1
Concrete Stairs 1.74% Bar Cutter 1
Metal Works 6.70% Conrete vibrator 1
#REF! 21.54%
PLUMBING/SANITARY WORKS 0.00%
A. Sanitary Pipes, Fittings and Accessories 3.26%
B. Water Line, Pipes, Fittings & accessories 1.50%
C. Holding Tank 15.0 cu.m 2.83%
Total 100.00%
A Mobilization / Demobilization OF Facilities 1.00 lot 16,340.00 12.00% 10% 22% 817.00 817.00 17,157.00 17,157.00
TOTAL OF I -
-
B BUILDINGS FINISHES
17,157.00
1,881,154.67
2,924,165.82
134,187.27
517,711.26
1,664,382.69
7,708,920.00
44,400.00
0.58
252,238.40
7,708,920.00
115,879.68
218,383.20 17,157.00
7,725,260.00 8,070,794.40
7,708,103.00 7,725,260.00
7,725,260.00
0.00
231,757.80
386,263.00
a
COMPUTATION OF ESTIMATED DIRECT COST (EDC) Page ________of _______
Alum. Frame Glass, 3200 mm x 1200 mm x 1/4" thk clear glass Sliding
Window with aluminum frame 20.00 set 15,000.00 300,000.00 638.58 12,771.58 312,771.58
Alum. Frame Glass, 1600 mm x 1200 mm x 1/4" thk clear glass Sliding
6.00 set 10,000.00 60,000.00 425.72 2,554.32 62,554.32
Window with aluminum frame
Alum. Frame Glass, 700 mm x 700 mm x 1/4" thk clear glass Sliding
7.00 set 3,000.00 21,000.00 127.72 894.01 21,894.01
Window with aluminum frame
6.0 PLUMBING/SANITARY WORKS
A. Sanitary Pipes, Fittings and Accessories -
PVC Pipe, 150mm Ø series 1000 20.00 pcs 2,115.00 42,300.00 372.82 7,456.41 49,756.41
PVC Pipe, 100mm Ø series 1000 38.00 pcs 1,150.00 43,700.00 202.72 7,703.19 51,403.19
PVC Pipe, 75mm Ø series 1000 6.00 pcs 780.00 4,680.00 137.49 824.96 5,504.96
PVC Pipe, 50mm Ø series 1000 14.00 pcs 385.00 5,390.00 67.87 950.12 6,340.12
PVC Elbow, 90° x 100mm Ø 32.00 pcs 115.00 3,680.00 20.27 648.69 4,328.69
PVC Elbow, 90° x 75mm Ø 84.00 pcs 95.00 7,980.00 16.75 1,406.67 9,386.67
PVC Elbow, 45° x 100mm Ø 25.00 pcs 115.00 2,875.00 20.27 506.79 3,381.79
PVC Elbow, 45° x 75mm Ø 40.00 pcs 95.00 3,800.00 16.75 669.84 4,469.84
PVC TEE 150 mm x 100 mm dia. 8.00 pcs 650.00 5,200.00 114.58 916.63 6,116.63
PVC TEE 150 mm x 75 mm dia. 2.00 pcs 600.00 1,200.00 105.76 211.53 1,411.53
PVC TEE 100 mm x 100 mm dia. 16.00 pcs 198.00 3,168.00 34.90 558.44 3,726.44
PVC TEE 100 mm x 75 mm dia. 33.00 pcs 198.00 6,534.00 34.90 1,151.78 7,685.78
PVC TEE 75 mm x 75 mm dia. 20.00 pcs 120.00 2,400.00 21.15 423.06 2,823.06
PVC Elbow Reducer, 75 x 50mm Ø 2.00 pcs 60.00 120.00 10.58 21.15 141.15
Wye, 100mmØ 16.00 pcs 195.00 3,120.00 34.37 549.98 3,669.98
Wye Reducer, 100 x 50 4.00 pcs 115.00 460.00 20.27 81.09 541.09
Wye Reducer, 100 x75 2.00 pcs 140.00 280.00 24.68 49.36 329.36
Solvent Cement 5.00 liter 1,200.00 6,000.00 211.53 1,057.65 7,057.65
Floor Drain 24.00 pcs 280.00 6,720.00 49.36 1,184.56 7,904.56
P. Trap, 75mm Ø 32.00 pcs 420.00 13,440.00 74.04 2,369.13 15,809.13
hangers 1.00 l0t 7,142.21 7,142.21 1,258.99 1,258.99 8,401.19
B. Water Line, Pipes, Fittings & accessories
MATERIAL LABOR AND EQUIPMENTPage ________of _______
ITEM
DESCRITION OF WORK QUANTITY TOTAL COST
No.
Unit Cost Total Cost Unit Cost Total Cost
50 mm dia GI pipe sched. 40 18.00 length 2,300.00 41,400.00 559.70 10,074.63 51,474.63
50 mm dia GI coupling 18.00 pcs 160.00 2,880.00 38.94 700.84 3,580.84
50 mm heavy duty Ball Valve 3.00 pcs 1,500.00 4,500.00 365.02 1,095.07 5,595.07
1/2" dia uPVC pipe class 150 50.00 length 115.00 5,750.00 27.99 1,399.25 7,149.25
1/2" dia uPVC coupling 50.00 pcs 25.00 1,250.00 6.08 304.19 1,554.19
1/2" G.I Coupling 40.00 pcs 20.00 800.00 4.87 194.68 994.68
1/2" Ball Valve 7.00 pcs 250.00 1,750.00 60.84 425.86 2,175.86
2" x 1/2" G.I Tee 5.00 pcs 350.00 1,750.00 85.17 425.86 2,175.86
1/2' dia PVC male adapter 45.00 pcs 30.00 1,350.00 7.30 328.52 1,678.52
upvc tee 1/2" 25.00 pcs 30.00 750.00 7.30 182.51 932.51
90 deg upvc elbow Elbow 1/2" 90.00 pcs 30.00 2,700.00 7.30 657.04 3,357.04
teplon Tape 40.00 pcs 35.00 1,400.00 8.52 340.69 1,740.69
solvent cement 1.00 liters 1,200.00 1,200.00 292.02 292.02 1,492.02
hanger support 1.00 lot 6,488.00 6,488.00 1578.84 1,578.84 8,066.84
C. Holding Tank 15.0 cu.m 1.00 unit 140,450.00 140,450.00 32,870.00 32,870.00 173,320.00
TOTAL OF II 6,117,542.06
TOTAL DIRECT COST 5,284,933.52 848,948.55 6,133,882.06
TOTAL INDIRECT COST 5,284,933.52 848,948.5460 1,936,912.34
OCM 12.00% 734,105.05 734,105.05
PROFIT 8.00% 489,403.36 489,403.36
VAT 5.00% 367,869.52 367,869.52
ADMINISTRATIVE COST 4.47% 345,534.40
TOTAL PROJECT COST 8,070,794.40
0.12 6,177
0.12 430
0.12 671
0.12 858
0.12 187
0.12 119
0.12 261
0.12 261
0.12 201
0.12 112
0.12 403
0.12 209
0.12 179
0.12 968
0.12 20,798
6,133,882.06
1,051,130.32
8,070,794.40 345,532.35
7,725,260.00
0.00
DETAILED COST ESTIMATE
Page _____ of ______
Unit Cost P 326,401.00
DERIVATION OF UNIT COST
Quantity 491.80 sm
Item of Work : Concrete and Masonry Works
Work Description : 100mm thk., 350 psi. CHB (Include mortar and rebars)
5 SQM PER HOUR = 99
116.13 62,350.00
62,350.00
= 17,814.30
3.50
VAT 5 19,584.06
VII. TOTAL COST OF WORK ITEM 411,265.26
VIII. TOTAL UNIT COST (Total Cost of Work Item/Quantity) 836.24
11613
DETAILED COST ESTIMATE
Page _____ of ______
Unit Cost P 16,340.00
DERIVATION OF UNIT COST
Quantity 1.00 lot
Item of Work : I. Mobilization / Demobilization OF Facilities
Item No. :
Work Description :
VAT 5 817.00
VII. TOTAL COST OF WORK ITEM 17,157.00
VIII. TOTAL UNIT COST (Total Cost of Work Item/Quantity)
DETAILED COST ESTIMATE
Page _____ of ______
Unit Cost P 132,999.00
DERIVATION OF UNIT COST
Quantity 167.75 sm
Item of Work : Concrete and Masonry Works
Work Description : 150mm thk., 350 psi. CHB (Include mortar and rebars)
3.75 SQM PER HOUR = 45
27,950.00
27,950.00
= 7,985.70
3.50
VAT 5 7,979.94
VII. TOTAL COST OF WORK ITEM 167,578.74
VIII. TOTAL UNIT COST (Total Cost of Work Item/Quantity) 998.98
26.6066
DETAILED COST ESTIMATE
Page _____ of ______
Unit Cost P 476,199.90
DERIVATION OF UNIT COST
Quantity 3,384.64 sm
Item of Work : Concrete and Masonry Works
Work Description : Plain Cement Plaster Finish (For columns, parapet, beams and walls)
364,400.00
364,400.00
= 107.66
3384.64
476,199.90
= 140.69
3384.64
VAT 5 28,571.99
VII. TOTAL COST OF WORK ITEM 600,011.87
VIII. TOTAL UNIT COST (Total Cost of Work Item/Quantity) 177.27
using
100mmclass-B mixture
thk. CHB
624,012.35
###
###
###
capacity
- mason 10.00
carpenter 3.00
steelman 60.00
painter 28.00
111,799.90
476,199.90
30.6805
DETAILED COST ESTIMATE
Page _____ of ______
Unit Cost P 557,380.00
DERIVATION OF UNIT COST
Quantity 535.74 sm
Item of Work : Concrete and Masonry Works
Item No. :
462,380.00
462,380.00 863.07
=
535.74
95,000.00
95,000.00 177.30
=
535.74
VAT 5 33,442.80
VII. TOTAL COST OF WORK ITEM 702,298.80
VIII. TOTAL UNIT COST (Total Cost of Work Item/Quantity) 1,310.89
DETAILED COST ESTIMATE
Page _____ of ______
Unit Cost P 1,187,534.02
DERIVATION OF UNIT COST
Quantity 981.43 sm
Item of Work : Roof Framing and Roofing Works
1,111,634.02
= 1,132.66
981.43
75,900.00
75,900.00
= 77.34
981.43
VAT 5 71,252.04
VII. TOTAL COST OF WORK ITEM 1,496,292.87
VIII. TOTAL UNIT COST (Total Cost of Work Item/Quantity) 1,524.60
DETAILED COST ESTIMATE
Page _____ of ______
Unit Cost P 61,977.75
DERIVATION OF UNIT COST
Quantity 130.20 lm
Item of Work : Roof Framing and Roofing Works
Item No. :
Work Description : Fabricated Metal Roofing accessory ( Riged Roll, .6mm thk )
56,877.75 436.85
=
130.20
5,100.00 39.20
=
130.20
VAT 5 3,718.66
VII. TOTAL COST OF WORK ITEM 16,114.21
VIII. TOTAL UNIT COST (Total Cost of Work Item/Quantity) 78,091.97
DETAILED COST ESTIMATE
Page _____ of ______
Unit Cost P 66,483.42
DERIVATION OF UNIT COST
Quantity 141.80 0
Item of Work : Roof Framing and Roofing Works
Item No. :
61,883.42 436.41
=
141.80
4,600.00 32.40
=
141.80
VAT 5 3,989.00
VII. TOTAL COST OF WORK ITEM 17,285.69
VIII. TOTAL UNIT COST (Total Cost of Work Item/Quantity) 83,769.10
DETAILED COST ESTIMATE
Page _____ of ______
Unit Cost P 1,004,771.34
DERIVATION OF UNIT COST
Quantity 14,435.11 kgs
Item of Work : Roof Framing and Roofing Works
817,571.34
817,571.34 56.64
=
1.00
187,200.00 12.97
=
14435.11
VAT 5 60,286.28
VII. TOTAL COST OF WORK ITEM 1,266,011.88
VIII. TOTAL UNIT COST (Total Cost of Work Item/Quantity) 87.70
DETAILED COST ESTIMATE
Page _____ of ______
Unit Cost P 42,640.00
DERIVATION OF UNIT COST
Quantity 6.28 cm
Item of Work : Concrete Stairs
Item No. :
33,640.00 5,356.69 -
=
6.28
-
II. SUB-TOTAL OF MATERIAL COST : say 33,640.00
III. LABOR :
(assumed: 1.00 sq.m.)
1 Foreman days 2.00 400.00 800.00
6 Carpenter days 2.00 300.00 3,600.00
10 Helper days 2.00 230.00 4,600.00
0.27 9,000.00
9,000.00 1,433.10
=
6.28
VAT 5 2,558.40
VII. TOTAL COST OF WORK ITEM 53,726.40
VIII. TOTAL UNIT COST (Total Cost of Work Item/Quantity) 8,555.16
DETAILED COST ESTIMATE
Page _____ of ______
Unit Cost P 42,702.50
DERIVATION OF UNIT COST
Quantity 582.57 kgs
Item of Work : Concrete Stairs
Item No. :
34,142.50 58.61 -
=
582.57
-
II. SUB-TOTAL OF MATERIAL COST : say 34,142.50
III. LABOR :
(assumed: 80.00 kgs
1 Foreman days 2.00 400.00 800.00
4 skilled days 2.00 300.00 2,400.00
4 Helper days 2.00 230.00 1,840.00
0.25 8,560.00
8,560.00 14.70
=
582.57
Item No. :
16,655.33 477.23 -
=
34.90
-
II. SUB-TOTAL OF MATERIAL COST : say 16,655.33
III. LABOR :
(assumed: 5.00 kgs
1 Foreman days 1.00 400.00 400.00
6 skilled days 1.00 300.00 1,800.00
10 Helper days 1.00 230.00 2,300.00
0.27 4,500.00
4,500.00 128.90
=
34.90
VAT 5 1,269.32
VII. TOTAL COST OF WORK ITEM 26,655.72
VIII. TOTAL UNIT COST (Total Cost of Work Item/Quantity) 763.77
DETAILED COST ESTIMATE
Page _____ of ___
Unit Cost P 233,421.57
DERIVATION OF UNIT COST
Quantity 3,097.12 kgs
Item of Work : Metal Works
Item No. :
172,941.57 55.84 -
=
3097.12
-
II. SUB-TOTAL OF MATERIAL COST : say 172,941.57
III. LABOR :
(assumed: 35.00 kgs
1 Foreman days 12.00 400.00 4,800.00
4 skilled days 12.00 300.00 14,400.00
8 Helper days 12.00 230.00 22,080.00
0.35 60,480.00
60,480.00 19.50
=
3097.12
VAT 5 14,005.29
VII. TOTAL COST OF WORK ITEM 294,111.17
VIII. TOTAL UNIT COST (Total Cost of Work Item/Quantity) 0.03 94.96
DETAILED COST ESTIMATE
Page _____ of ___
Unit Cost P 177,460.39
DERIVATION OF UNIT COST
Quantity 2,364.55 kgs
Item of Work : Metal Works
Item No. :
132,100.39 55.87 -
=
2364.55
-
II. SUB-TOTAL OF MATERIAL COST : say 132,100.39
III. LABOR :
(assumed: 35.00 kgs
1 Foreman days 9.00 400.00 3,600.00
4 skilled days 9.00 300.00 10,800.00
8 Helper days 9.00 230.00 16,560.00
0.34 45,360.00
45,360.00 19.18
=
2364.55
VAT 5 10,647.62
VII. TOTAL COST OF WORK ITEM 223,600.09
VIII. TOTAL UNIT COST (Total Cost of Work Item/Quantity) 0.04 94.56
channel bar
angle bar
steel plate
177,460.39
34.33752157
DETAILED COST ESTIMATE
Page _____ of ___
Unit Cost P 6,528.27
DERIVATION OF UNIT COST
Quantity 254.95 sm
Item of Work : #REF!
53,938.65
53,938.65
211.60
254.95
V. SUB-TOTAL OF LABOR AND EQUIPMENT : 53,938.65
VI. ESTIMATED DIRECT COST, EDC (A) 1,320,938.65
73,968.00
73,968.00
= 73,968.00
1.00
18,000.00
18,000.00
= 18,000.00
1.00
VAT 5 5,518.08
VII. TOTAL COST OF WORK ITEM 115,879.68
VIII. TOTAL UNIT COST (Total Cost of Work Item/Quantity) 115,879.68
DETAILED COST ESTIMATE
Page _____ of ______
Unit Cost P 200,189.21
DERIVATION OF UNIT COST
Quantity 1.00 lot
Item of Work : PLUMBING/SANITARY WORKS 20
Item No. : 6
0.18 30,000.00
30,000.00
= 30,000.00
1.00
VAT 5 12,011.35
VII. TOTAL COST OF WORK ITEM 252,238.40
VIII. TOTAL UNIT COST (Total Cost of Work Item/Quantity) 252,238.40
DETAILED COST ESTIMATE
Page _____ of ______
Unit Cost P 173,320.00
DERIVATION OF UNIT COST
Quantity 1.00 lot
Item of Work : PLUMBING/SANITARY WORKS
Item No. :
140,449.95
140,449.95
= 140,449.95
1.00
32,870.00
32,870.00
= 32,870.00
1.00
VAT 5 10,399.20
VII. TOTAL COST OF WORK ITEM 218,383.20
VIII. TOTAL UNIT COST (Total Cost of Work Item/Quantity) 218,383.20