Landscaping

Sr No Description Length in Km Nos Total Length in Km Remarks

1 Total Length 138.20 2.00 276.40

Deductions

2 Forest Area 6.38 1.00 6.38

Structure Length - Box Culvert and


3 Pipe Culverts 1.77 2.00 3.55

Structure Length - Major and Minor


4 Bridges 3.16 2.00 6.32

Minor Junctions - Other than Built


5 up Area 0.02 57.00 0.86 Including Bell mouth considering 15 mtrs Length

Major Junctions- Other than Bulit Considering = 1000mtrs per junctions considering both
6 up area 1.00 25.00 25.00 sides

7 Truck Lay bye 0.36 6.00 2.16

8 Bus Lay Bye - Rural Area 0.11 56.00 5.88

9 Built Up area 14.64 2.00 29.29

Total Length in Km 196.98

Total Length in Mtrs 196,976.00

Spacing 10.00 As per Schedule W of Ann 8.12

Total No. of Trees 19,698

Rate of one nos Tree 421.17 Ref No 11.21, Pg no. 147

Total Cost of Project 8,296,017.82

GST 995,522.14

Total Amount incld GST 9,291,539.95 67,233