Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 313

DETAILED UNIT PRICE ANALYSIS (DUPA)

Project Name : Construction of 2 Units 4 Storey 20 CL, School Building


Location : Barangay Nazareth, Cagayan de Oro City
Item No. : SPL 2.87 Quantity : 130.20
Description : d) roll-up door Unit : sq.m
###
Designation No. of Person No. of Hours Hourly Rate Amount
A. Labor

a. Construction Foreman 1 45.29 76.77 3,477.28


b. Skilled Laborer 1 45.29 54.25 2,457.24
c. Laborer 2 45.29 41.87 3,792.99

Sub - Total for A 9,727.52


Name and Capacity No of Units No. of Hours Hourly Rate Amount
B. Equipment

minor tools (10% of labor) 972.75

Sub - Total for B 972.75


C. Total (A + B) 10,700.27
D. Output per hour = 2.875 sq.m.
E. Direct Unit Cost (C ÷ D) 3,722.48
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

roll-up door (ga. 26) complete with accessories sq.m 130.20 2,510.60 326,880.12

Sub - Total for F 326,880.12


G. Direct Unit Cost (E + F) 330,602.60
H. Overhead, Contingencies & Miscellaneous (OCM) 12% of G 39,672.31
I. Contractor's Profit (CP) 10% of G 33,060.26
J. Value Added Tax (VAT) 5% of (G + H + I) 20,166.76
K. Total Unit Cost (G + H + I + J) 423,501.54
L. Total Adjusted Unit Cost 3,252.70

Prepared by: Checked by: Submitted by:

FFJJ Construction JAICEL MAE G. ROSAS HELEN A. MONTES


Contractor Project Inspector Project Engineer
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 100(2)a Individual Removal of Trees (small a, 150-300 mm. Ø)


Unit of Measurement : ea.
Output per hour : 3.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Skilled Laborer 1 1 79.70 79.70
c. Laborer 2 1 61.44 122.88

Sub - Total for A 311.77


Name and Capacity No of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Backhoe (0.80 cu.m.) 1 0.50 1,537.00 768.50


b. Dump Truck (10 cu.m.) 1 0.50 1,352.00 676.00
c. Chain Saw 1 0.50 75.00 37.50
Minor Tools (5% of labor) 15.59

* Boom Truck - if necessary for trimming in Urban Areas

Sub - Total for B 1,497.59


C. Total (A + B) 1,809.36
D. Output per hour = 3.0000 ea.
E. Direct Unit Cost (C ÷ D) 603.12
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Rope, 1" dia. m. 20.00 3.50 70.00

Sub - Total for F 70.00


G. Direct Unit Cost (E + F) 673.12
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 60.58
I. Contractor's Profit (CP) 8% of G 53.85
J. Value Added Tax (VAT) 12% of (G + H + I) 94.51
K. Total Unit Cost (G + H + I + J) 882.06

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 100(2)b Individual Removal of Trees (small b, 301-500 mm. Ø)


Unit of Measurement : ea.
Output per hour : 1.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor
a. Construction Foreman 1 1 109.19 109.19
b. Skilled Laborer 1 1 79.70 79.70
c. Laborer 2 1 61.44 122.88

Sub - Total for A 311.77


Name and Capacity No of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Backhoe (0.80 cu.m.) 1 0.50 1,537.00 768.50


b. Dump Truck (10 cu.m.) 1 0.50 1,352.00 676.00
c. Chain Saw 1 0.50 75.00 37.50
Minor Tools (5% of labor) 15.59

* Boom Truck - if necessary for trimming in Urban Areas

Sub - Total for B 1,497.59


C. Total (A + B) 1,809.36
D. Output per hour = 1.0000 ea.
E. Direct Unit Cost (C ÷ D) 1,809.36
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Rope, 1" dia. m. 20.00 3.50 70.00

Sub - Total for F 70.00


G. Direct Unit Cost (E + F) 1,879.36
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 169.14
I. Contractor's Profit (CP) 8% of G 150.35
J. Value Added Tax (VAT) 12% of (G + H + I) 263.86
K. Total Unit Cost (G + H + I + J) 2,462.71

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 100(3)a Individual Removal of Trees (large a, 501-750 mm. Ø)


Unit of Measurement : ea.
Output per hour : 0.25

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Skilled Laborer 1 1 79.70 79.70
c. Laborer 2 1 61.44 122.88

Sub - Total for A 311.77


Name and Capacity No of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Backhoe (0.80 cu.m.) 1 1 1,537.00 1,537.00


b. Dump Truck (10 cu.m.) 1 1 1,352.00 1,352.00
c. Chain Saw 1 1 75.00 75.00
Minor Tools (5% of labor) 15.59

* Boom Truck - if necessary for trimming in Urban Areas

Sub - Total for B 2,979.59


C. Total (A + B) 3,291.36
D. Output per hour = 0.25 ea.
E. Direct Unit Cost (C ÷ D) 13,165.43
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Rope, 1" dia. m. 20.00 3.50 70.00

Sub - Total for F 70.00


G. Direct Unit Cost (E + F) 13,235.43
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 1,191.19
I. Contractor's Profit (CP) 8% of G 1,058.83
J. Value Added Tax (VAT) 12% of (G + H + I) 1,858.25
K. Total Unit Cost (G + H + I + J) 17,343.71

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 100(3)b Individual Removal of Trees (large b, 751-900 mm. Ø)


Unit of Measurement : ea.
Output per hour : 0.125

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Skilled Laborer 1 1 79.70 79.70
c. Laborer 2 1 61.44 122.88

Sub - Total for A 311.77


Name and Capacity No of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Backhoe (0.80 cu.m.) 1 1 1,537.00 1,537.00


b. Dump Truck (10 cu.m.) 1 1 1,352.00 1,352.00
c. Chain Saw 1 1 75.00 75.00
Minor Tools (5% of labor) 15.59

* Boom Truck - if necessary for trimming in Urban Areas

Sub - Total for B 2,979.59


C. Total (A + B) 3,291.36
D. Output per hour = 0.125 ea.
E. Direct Unit Cost (C ÷ D) 26,330.87
Name and Specification Unit Quantity Unit Cost Amount
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Rope, 1" dia. m. 20.00 3.50 70.00

Sub - Total for F 70.00


G. Direct Unit Cost (E + F) 26,400.87
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 2,376.08
I. Contractor's Profit (CP) 8% of G 2,112.07
J. Value Added Tax (VAT) 12% of (G + H + I) 3,706.68
K. Total Unit Cost (G + H + I + J) 34,595.70

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 101(1) Removal of Structures and Obstruction (other than concrete)
Unit of Measurement : 20 cu.m. 2
Output per hour : 10.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 2 109.19 218.38


b. Skilled Laborer 1 1 79.70 79.70
c. Laborer 2 1 61.44 122.88

Sub - Total for A 420.96


Name and Capacity No of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Backhoe (0.80 cu.m.) 1 1 1,537.00 1,537.00


b. Dump Truck (10 cu.m.) 1 1 1,352.00 1,352.00
Minor Tools (10% of Labor) 42.10

Sub - Total for B 2,931.10


C. Total (A + B) 3,352.06
D. Output per hour = 10.0000 cu.m.
E. Direct Unit Cost (C ÷ D) 335.21
Name and Specification Unit Quantity Unit Cost Amount
F. Materials
Sub - Total for F -
G. Direct Unit Cost (E + F) 335.21
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 30.17
I. Contractor's Profit (CP) 8% of G 26.82
J. Value Added Tax (VAT) 12% of (G + H + I) 47.06
K. Total Unit Cost (G + H + I + J) 439.25

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 101(2) Removal of Concrete Bridge Structures


Unit of Measurement : cu.m.
Output per hour : 1.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Skilled Laborer 2 1 79.70 159.40
c. Laborer 4 1 61.44 245.76

Sub - Total for A 514.35


Name and Capacity No of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Backhoe w/ Breaker (0.80 cu.m.) 1 0.50 2,074.95 1,037.48


b. Jackhammer 2 1 514.31 1,028.62
c. Air Compressor (103 Hp) 1 1 675.00 675.00
d. Dump Truck (10 cu.m.) 1 0.25 1,352.00 338.00
e. Payloader (1.50 cu.m.) 1 0.125 1,733.00 216.63
f. Truck Mounted Crane (35 T) 1 0.25 1,553.00 388.25
g. Cutting Outfit 1 1 45.00 45.00

* Disposal area (within five (5) km)

Sub - Total for B 3,728.97


C. Total (A + B) 4,243.32
D. Output per hour = 1.0000 cu.m.
E. Direct Unit Cost (C ÷ D) 4,243.32
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Oxy/Acytelene set 0.10 2,500.00 250.00

Sub - Total for F 250.00


G. Direct Unit Cost (E + F) 4,493.32
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 404.40
I. Contractor's Profit (CP) 8% of G 359.47
J. Value Added Tax (VAT) 12% of (G + H + I) 630.86
K. Total Unit Cost (G + H + I + J) 5,888.05

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 101(2)a Removal of Steel Bridge Structures


Unit of Measurement : kg
Output per hour : 1,000.00

Designation No. of Person No. of Hours Hourly Rate Amount


Designation No. of Person No. of Hours Hourly Rate Amount
A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Skilled Laborer 2 1 79.70 159.40
c. Laborer 4 1 61.44 245.76

Sub - Total for A 514.35


Name and Capacity No of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Service Truck/Cargo Truck 1 1 712.00 712.00


b. Welding Machine 1 1 75.00 75.00
c. Truck Mounted Crane (35 T) 1 1 1,553.00 1,553.00
d. Cutting Outfit 1 1 45.00 45.00
Minor Tools (10% of Labor) 51.44

* Disposal area (within five (5) km)

Sub - Total for B 2,436.44


C. Total (A + B) 2,950.79
D. Output per hour = 1000.0000 kg.
E. Direct Unit Cost (C ÷ D) 2.95
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Oxy/Acytelene set 0.00025 2,500.00 0.63


b. Welding Rod kg 0.002 70.00 0.14
c. Rope 1" dia. m 0.05 3.50 0.18

* Include shoring materials if needed based on actual field


condition

Sub - Total for F 0.94


G. Direct Unit Cost (E + F) 3.89
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 0.35
I. Contractor's Profit (CP) 8% of G 0.31
J. Value Added Tax (VAT) 12% of (G + H + I) 0.55
K. Total Unit Cost (G + H + I + J) 5.10

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 101(2) Removal of Concrete Bridge Structures


Unit of Measurement : cu.m.
Output per hour : 1.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Skilled Laborer 2 1 79.70 159.40
c. Laborer 4 1 61.44 245.76

Sub - Total for A 514.35


Name and Capacity No of Units No. of Hours Hourly Rate Amount
B. Equipment
a. Backhoe w/ Breaker (0.80 cu.m.) 1 0.50 2,074.95 1,037.48
b. Jackhammer 2 1 514.31 1,028.62
c. Air Compressor (103 Hp) 1 1 675.00 675.00
d. Dump Truck (10 cu.m.) 1 0.25 1,352.00 338.00
e. Payloader (1.50 cu.m.) 1 0.125 1,733.00 216.63
f. Truck Mounted Crane (35 T) 1 0.25 1,553.00 388.25
g. Cutting Outfit 1 1 45.00 45.00

* Disposal area (within five (5) km)

Sub - Total for B 3,728.97


C. Total (A + B) 4,243.32
D. Output per hour = 1.0000 cu.m.
E. Direct Unit Cost (C ÷ D) 4,243.32
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Oxy/Acytelene set 0.10 2,500.00 250.00

Sub - Total for F 250.00


G. Direct Unit Cost (E + F) 4,493.32
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 404.40
I. Contractor's Profit (CP) 8% of G 359.47
J. Value Added Tax (VAT) 12% of (G + H + I) 630.86
K. Total Unit Cost (G + H + I + J) 5,888.05

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 101(2) Removal of Stone Masonry Lined Drainage Structures


Unit of Measurement : cu.m.
Output per hour : 5.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Skilled Laborer 2 1 79.70 159.40
c. Laborer 4 1 61.44 245.76

Sub - Total for A 514.35


Name and Capacity No of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Backhoe w/ Breaker (0.80 cu.m.) 1 0.50 2,074.95 1,037.48


b. Backhoe (0.80 cu.m.) 1 0.50 1,537.00 768.50
c. Dump Truck (10 cu.m.) 1 0.50 1,352.00 676.00

* Disposal area (within five (5) km)

Sub - Total for B 2,481.98


C. Total (A + B) 2,996.33
D. Output per hour = 5.0000 cu.m.
E. Direct Unit Cost (C ÷ D) 599.27
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

Sub - Total for F -


G. Direct Unit Cost (E + F) 599.27
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 53.93
I. Contractor's Profit (CP) 8% of G 47.94
J. Value Added Tax (VAT) 12% of (G + H + I) 84.14
K. Total Unit Cost (G + H + I + J) 785.28

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 101(2) Removal of Concrete Drainage Structures


Unit of Measurement : cu.m.
Output per hour : 2.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Skilled Laborer 2 1 79.70 159.40
c. Laborer 4 1 61.44 245.76

Sub - Total for A 514.35


Name and Capacity No of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Backhoe w/ Breaker (0.80 cu.m.) 1 0.50 2,074.95 1,037.48


b. Backhoe (0.80 cu.m.) 1 0.50 1,537.00 768.50
d. Dump Truck (10 cu.m.) 1 0.50 1,352.00 676.00
e. Cutting Outfit 1 1 45.00 45.00

* Disposal area (within five (5) km)

Sub - Total for B 2,526.98


C. Total (A + B) 3,041.33
D. Output per hour = 2.0000 cu.m.
E. Direct Unit Cost (C ÷ D) 1,520.66
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Oxy/Acetylene set 0.10 2,500.00 250.00


Sub - Total for F 250.00
G. Direct Unit Cost (E + F) 1,770.66
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 159.36
I. Contractor's Profit (CP) 8% of G 141.65
J. Value Added Tax (VAT) 12% of (G + H + I) 248.60
K. Total Unit Cost (G + H + I + J) 2,320.28

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 101(2)a Removal of RCPC and Storm Drain (24" dia.) - 610mm
Unit of Measurement : l.m.
Output per hour : 6.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Laborer 2 1 61.44 122.88

Sub - Total for A 232.07


Name and Capacity No of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Backhoe (0.80 cu.m.) 1 1 1,537.00 1,537.00


b. Cargo Truck (5 T) 1 1 712.00 712.00
Minor Tools (10 % of Labor) 23.21

Note: Exclude Excavation Works

* Disposal area (within five (5) km)

Sub - Total for B 2,272.21


C. Total (A + B) 2,504.28
D. Output per hour = 6.0000 l.m.
E. Direct Unit Cost (C ÷ D) 417.38
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

Sub - Total for F -


G. Direct Unit Cost (E + F) 417.38
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 37.56
I. Contractor's Profit (CP) 8% of G 33.39
J. Value Added Tax (VAT) 12% of (G + H + I) 58.60
K. Total Unit Cost (G + H + I + J) 546.93

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 101(2)b Removal of RCPC and Storm Drain (30" dia.) - 760mm
Unit of Measurement : l.m.
Output per hour : 5.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Laborer 2 1 61.44 122.88

Sub - Total for A 232.07


Name and Capacity No of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Backhoe (0.80 cu.m.) 1 1 1,537.00 1,537.00


b. Cargo Truck (5 T) 1 1 712.00 712.00
Minor Tools (10 % of Labor) 23.21

Note: Exclude Excavation Works

* Disposal area (within five (5) km)

Sub - Total for B 2,272.21


C. Total (A + B) 2,504.28
D. Output per hour = 5.0000 l.m.
E. Direct Unit Cost (C ÷ D) 500.86
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

Sub - Total for F -


G. Direct Unit Cost (E + F) 500.86
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 45.08
I. Contractor's Profit (CP) 8% of G 40.07
J. Value Added Tax (VAT) 12% of (G + H + I) 70.32
K. Total Unit Cost (G + H + I + J) 656.32

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 101(2)c Removal of RCPC and Storm Drain (36" dia.) - 910mm
Unit of Measurement : l.m.
Output per hour : 4.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Laborer 2 1 61.44 122.88

Sub - Total for A 232.07


Name and Capacity No of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Backhoe (0.80 cu.m.) 1 1 1,537.00 1,537.00


b. Cargo Truck (5 T) 1 1 712.00 712.00
Minor Tools (10 % of Labor) 23.21

Note: Exclude Excavation Works

* Disposal area (within five (5) km)

Sub - Total for B 2,272.21


C. Total (A + B) 2,504.28
D. Output per hour = 4.0000 l.m.
E. Direct Unit Cost (C ÷ D) 626.07
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

Sub - Total for F -


G. Direct Unit Cost (E + F) 626.07
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 56.35
I. Contractor's Profit (CP) 8% of G 50.09
J. Value Added Tax (VAT) 12% of (G + H + I) 87.90
K. Total Unit Cost (G + H + I + J) 820.40

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 101(2)d Removal of RCPC and Storm Drain (42" dia.) - 1070mm
Unit of Measurement : l.m.
Output per hour : 4.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Laborer 2 1 61.44 122.88

Sub - Total for A 232.07


Name and Capacity No of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Backhoe (0.80 cu.m.) 1 1 1,537.00 1,537.00


b. Cargo Truck (5 T) 1 1 712.00 712.00
Minor Tools (10 % of Labor) 23.21

Note: Exclude Excavation Works

* Disposal area (within five (5) km)


Sub - Total for B 2,272.21
C. Total (A + B) 2,504.28
D. Output per hour = 4.000 l.m.
E. Direct Unit Cost (C ÷ D) 626.07
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

Sub - Total for F -


G. Direct Unit Cost (E + F) 626.07
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 56.35
I. Contractor's Profit (CP) 8% of G 50.09
J. Value Added Tax (VAT) 12% of (G + H + I) 87.90
K. Total Unit Cost (G + H + I + J) 820.40

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 101(2)e Removal of RCPC and Storm Drain (48" dia.) - 1220mm
Unit of Measurement : l.m.
Output per hour : 3.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Laborer 2 1 61.44 122.88

Sub - Total for A 232.07


Name and Capacity No of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Backhoe (0.80 cu.m.) 1 1 1,537.00 1,537.00


b. Cargo Truck (5 T) 1 1 712.00 712.00
Minor Tools (10 % of Labor) 23.21

Note: Exclude Excavation Works

* Disposal area (within five (5) km)

Sub - Total for B 2,272.21


C. Total (A + B) 2,504.28
D. Output per hour = 3.000 l.m.
E. Direct Unit Cost (C ÷ D) 834.76
Name and Specification Unit Quantity Unit Cost Amount
F. Materials
Sub - Total for F -
G. Direct Unit Cost (E + F) 834.76
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 75.13
I. Contractor's Profit (CP) 8% of G 66.78
J. Value Added Tax (VAT) 12% of (G + H + I) 117.20
K. Total Unit Cost (G + H + I + J) 1,093.87

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 101(2)f Removal of RCPC and Storm Drain (60" dia.) - 1520mm
Unit of Measurement : l.m.
Output per hour : 2.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Laborer 2 1 61.44 122.88

Sub - Total for A 232.07


Name and Capacity No of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Backhoe (0.80 cu.m.) 1 1 1,537.00 1,537.00


b. Cargo Truck (5 T) 1 1 712.00 712.00
Minor Tools (10 % of Labor) 23.21

Note: Exclude Excavation Works

* Disposal area (within five (5) km)

Sub - Total for B 2,272.21


C. Total (A + B) 2,504.28
D. Output per hour = 2.000 l.m.
E. Direct Unit Cost (C ÷ D) 1,252.14
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

Sub - Total for F -


G. Direct Unit Cost (E + F) 1,252.14
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 112.69
I. Contractor's Profit (CP) 8% of G 100.17
J. Value Added Tax (VAT) 12% of (G + H + I) 175.80
K. Total Unit Cost (G + H + I + J) 1,640.80
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 101(2)g Removal of Pipes other than Pipe Culverts (PVC/GI/Asbestos, up to 200 mm. Ø), L=10 ft.
Unit of Measurement : ea.
Output per hour : 2.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Skilled Laborer 1 1 79.70 79.70
c. Laborer 2 1 61.44 122.88

Sub - Total for A 311.77


Name and Capacity No of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Cargo Truck (10 T) 1 0.25 1,102.00 275.50


Minor Tools (10% of Labor) 31.18

Note: Exclude Excavation Works

* Disposal area (within five (5) km)

Sub - Total for B 306.68


C. Total (A + B) 618.45
D. Output per hour = 2.0000 ea.
E. Direct Unit Cost (C ÷ D) 309.22
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

Sub - Total for F -


G. Direct Unit Cost (E + F) 309.22
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 27.83
I. Contractor's Profit (CP) 8% of G 24.74
J. Value Added Tax (VAT) 12% of (G + H + I) 43.41
K. Total Unit Cost (G + H + I + J) 405.21

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 101(3)a1 Removal of Existing Concrete Pavement (0.23m thk.)


Unit of Measurement : sq.m.
Output per hour : 40.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Laborer 2 1 61.44 122.88
Sub - Total for A 232.07
Name and Capacity No of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Backhoe w/ Pavement Breaker (0.80 cu.m.) 1 1 2,074.95 2,074.95


b. Payloader (1.50 cu.m.), LX80-2C 1 1 1,733.00 1,733.00
c. Dump Truck (10 cu.m.) 1 1 1,352.00 1,352.00
Minor Tools (10% of Labor) 23.21

* Disposal area (within five (5) km)

Sub - Total for B 5,183.16


C. Total (A + B) 5,415.23
D. Output per hour = 40.00 sq.m.
E. Direct Unit Cost (C ÷ D) 135.38
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

Sub - Total for F -


G. Direct Unit Cost (E + F) 135.38
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 12.18
I. Contractor's Profit (CP) 8% of G 10.83
J. Value Added Tax (VAT) 12% of (G + H + I) 19.01
K. Total Unit Cost (G + H + I + J) 177.40

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 101(3)a2 Removal of Existing PCC Pavement, 0.23m thk. (for Reblocking at intermittent section
Unit of Measurement : sq.m.
Output per hour : 30.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Laborer 2 1 61.44 122.88

Sub - Total for A 232.07


Name and Capacity No of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Backhoe w/ Pavement Breaker (0.80 cu.m.) 1 1 2,074.95 2,074.95


b. Payloader (1.50 cu.m.), LX80-2C 1 1 1,733.00 1,733.00
c. Dump Truck (10 cu.m.) 1 1 1,352.00 1,352.00
d. Concrete Saw, Blade Ø 14" (7.5 Hp) 1 0.50 167.38 167.38
Minor Tools (10% of Labor) 23.21

* Disposal area (within five (5) km)


Sub - Total for B 5,350.54
C. Total (A + B) 5,582.61
D. Output per hour = 30.00000 sq.m.
E. Direct Unit Cost (C ÷ D) 186.09
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Concrete Saw (diamond blade 14") pc. 0.00015 8,000.00 1.20

Sub - Total for F 1.20


G. Direct Unit Cost (E + F) 187.29
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 16.86
I. Contractor's Profit (CP) 8% of G 14.98
J. Value Added Tax (VAT) 12% of (G + H + I) 26.30
K. Total Unit Cost (G + H + I + J) 245.42

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 101(3)b Removal of Existing Asphalt Pavement (100mm thk.)


Unit of Measurement : sq.m.
Output per hour : 60.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Laborer 2 1 61.44 122.88

Sub - Total for A 232.07


Name and Capacity No of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Motorized Road Grader w/ Scarifier, G710A 1 1 2,173.00 2,173.00


b. Payloader (1.50 cu.m.), LX80-2C 1 1 1,733.00 1,733.00
c. Dump Truck (10 cu.m.) 1 1 1,352.00 1,352.00
Minor Tools (10% of Labor) 23.21

* Disposal area (within five (5) km)

Sub - Total for B 5,281.21


C. Total (A + B) 5,513.28
D. Output per hour = 60.00000 sq.m.
E. Direct Unit Cost (C ÷ D) 91.89
Name and Specification Unit Quantity Unit Cost Amount
F. Materials
Sub - Total for F -
G. Direct Unit Cost (E + F) 91.89
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 8.27
I. Contractor's Profit (CP) 8% of G 7.35
J. Value Added Tax (VAT) 12% of (G + H + I) 12.90
K. Total Unit Cost (G + H + I + J) 120.41

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 101(4)c Removal of Sidewalk


Unit of Measurement : sq.m.
Output per hour : 60.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Laborer 2 1 61.44 122.88

Sub - Total for A 232.07


Name and Capacity No of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Backhoe w/ Pavement Breaker (0.80 cu.m.) 1 0.50 2,074.95 1,037.48


b. Backhoe (0.80 cu.m.) 1 0.50 1,537.00 768.50
c. Dump Truck (10 cu.m.) 1 1 1,352.00 1,352.00

* Disposal area (within five (5) km)

Sub - Total for B 3,157.98


C. Total (A + B) 3,390.05
D. Output per hour = 60.00000 sq.m.
E. Direct Unit Cost (C ÷ D) 56.50
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

Sub - Total for F -


G. Direct Unit Cost (E + F) 56.50
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 5.09
I. Contractor's Profit (CP) 8% of G 4.52
J. Value Added Tax (VAT) 12% of (G + H + I) 7.93
K. Total Unit Cost (G + H + I + J) 74.04

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 101(4)a Removal of Curb


Unit of Measurement : l.m.
Output per hour : 50.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Laborer 2 1 61.44 122.88

Sub - Total for A 232.07


Name and Capacity No of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Backhoe w/ Breaker (0.80 cu.m.) 1 0.50 2,074.95 1,037.48


b. Backhoe (0.80 cu.m.) 1 0.50 1,537.00 768.50
c. Dump Truck (10 cu.m.) 1 1 1,352.00 1,352.00

* Disposal area (within five (5) km)

Sub - Total for B 3,157.98


C. Total (A + B) 3,390.05
D. Output per hour = 50.00000 l.m.
E. Direct Unit Cost (C ÷ D) 67.80
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

Sub - Total for F -


G. Direct Unit Cost (E + F) 67.80
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 6.10
I. Contractor's Profit (CP) 8% of G 5.42
J. Value Added Tax (VAT) 12% of (G + H + I) 9.52
K. Total Unit Cost (G + H + I + J) 88.85

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 101(4)b Removal of Curb & Gutter


Unit of Measurement : l.m.
Output per hour : 30.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Laborer 2 1 61.44 122.88
Sub - Total for A 232.07
Name and Capacity No of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Backhoe w/ Breaker (0.80 cu.m.) 1 0.50 2,074.95 1,037.48


b. Backhoe (0.80 cu.m.) 1 0.50 1,537.00 768.50
c. Dump Truck (10 cu.m.) 1 1 1,352.00 1,352.00

* Disposal area (within five (5) km)

Sub - Total for B 3,157.98


C. Total (A + B) 3,390.05
D. Output per hour = 30.00000 l.m.
E. Direct Unit Cost (C ÷ D) 113.00
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

Sub - Total for F -


G. Direct Unit Cost (E + F) 113.00
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 10.17
I. Contractor's Profit (CP) 8% of G 9.04
J. Value Added Tax (VAT) 12% of (G + H + I) 15.87
K. Total Unit Cost (G + H + I + J) 148.08

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 102(1) Roadway Excavation (Unsuitable)


Unit of Measurement : cu.m.
Output per hour : 20.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Laborer 3 1 61.44 184.32

Sub - Total for A 293.51


Name and Capacity No of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Dump Truck (10 cu.m.) 2 1 1,352.00 2,704.00


b. Backhoe (0.80 cu.m.) 1 1 1,537.00 1,537.00
c. Payloader (1.50 cu.m.) at disposal site 1 0.10 1,733.00 173.30
Minor Tools (10% of Labor) 29.35
* Disposal area (within five (5) km)

Sub - Total for B 4,443.65


C. Total (A + B) 4,737.16
D. Output per hour = 20.0000 cu.m.
E. Direct Unit Cost (C ÷ D) 236.86
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

Sub - Total for F -


G. Direct Unit Cost (E + F) 236.86
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 21.32
I. Contractor's Profit (CP) 8% of G 18.95
J. Value Added Tax (VAT) 12% of (G + H + I) 33.25
K. Total Unit Cost (G + H + I + J) 310.38

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 102(2)a Roadway Excavation (Surplus Common)


Unit of Measurement : cu.m.
Output per hour : 60.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Laborer 2 1 61.44 122.88

Sub - Total for A 232.07


Name and Capacity No of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Bulldozer (155 Hp), D65A-8 1 1 2,299.00 2,299.00


b. Payloader (1.50 cu.m.) 1 1.00 1,733.00 1,733.00
c. Payloader (1.50 cu.m.) - at disposal area 1 0.25 1,733.00 433.25
d. Dump Truck (10 cu.m.) 2 1 1,352.00 2,704.00

(Hauling Distance - within five (5) kilometers)

Sub - Total for B 7,169.25


C. Total (A + B) 7,401.32
D. Output per hour = 60.0000 cu.m.
E. Direct Unit Cost (C ÷ D) 123.36
Name and Specification Unit Quantity Unit Cost Amount
F. Materials
Sub - Total for F -
G. Direct Unit Cost (E + F) 123.36
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 11.10
I. Contractor's Profit (CP) 8% of G 9.87
J. Value Added Tax (VAT) 12% of (G + H + I) 17.32
K. Total Unit Cost (G + H + I + J) 161.64

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 102(2)b Roadway Excavation (Surplus Common)


Unit of Measurement : cu.m.
Output per hour : 80.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Laborer 2 1 61.44 122.88

Sub - Total for A 232.07


Name and Capacity No of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Bulldozer (155 Hp), D65A-8 1 1 2,299.00 2,299.00


b. Payloader (1.50 cu.m.) 1 1.00 1,733.00 1,733.00
c. Payloader (1.50 cu.m.) - at disposal area 1 0.30 1,733.00 519.90
d. Dump Truck (10 cu.m.) 3 1 1,352.00 4,056.00
e. Backhoe (0.80 cu.m.) 1 1 1,537.00 1,537.00

(Hauling Distance - within five (5) kilometers)

Sub - Total for B 10,144.90


C. Total (A + B) 10,376.97
D. Output per hour = 80.0000 cu.m.
E. Direct Unit Cost (C ÷ D) 129.71
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

Sub - Total for F -


G. Direct Unit Cost (E + F) 129.71
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 11.67
I. Contractor's Profit (CP) 8% of G 10.38
J. Value Added Tax (VAT) 12% of (G + H + I) 18.21
K. Total Unit Cost (G + H + I + J) 169.97

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 102(3)a Roadway Excavation (Surplus Soft Rock)


Unit of Measurement : cu.m.
Output per hour : 56.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Laborer 2 1 61.44 122.88

Sub - Total for A 232.07


Name and Capacity No of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Bulldozer w/ Ripper (155 Hp), D65A-8 1 1 2,758.80 2,758.80


b. Payloader (1.50 cu.m.) 1 1 1,733.00 1,733.00
c. Payloader (1.50 cu.m.) at disposal area 1 0.25 1,733.00 433.25
d. Dump Truck (10 cu.m.) 3 1 1,352.00 4,056.00
e. Backhoe (0.80 cu.m.) w/ attachment 1 1 2,074.95 2,074.95

(Hauling Distance - within five (5) kilometers)

Sub - Total for B 11,056.00


C. Total (A + B) 11,288.07
D. Output per hour = 56.0000 cu.m.
E. Direct Unit Cost (C ÷ D) 201.57
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

Sub - Total for F -


G. Direct Unit Cost (E + F) 201.57
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 18.14
I. Contractor's Profit (CP) 8% of G 16.13
J. Value Added Tax (VAT) 12% of (G + H + I) 28.30
K. Total Unit Cost (G + H + I + J) 264.14

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 102(3)b Roadway Excavation (Surplus Soft Rock)


Unit of Measurement : cu.m.
Output per hour : 42.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor
a. Construction Foreman 1 1 109.19 109.19
b. Laborer 2 1 61.44 122.88

Sub - Total for A 232.07


Name and Capacity No of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Bulldozer w/ Ripper (155 Hp), D65A-8 1 1 2,758.80 2,758.80


b. Payloader (1.50 cu.m.) 1 1 1,733.00 1,733.00
c. Payloader (1.50 cu.m.) at disposal area 1 0.20 1,733.00 346.60
d. Dump Truck (10 cu.m.) 3 1 1,352.00 4,056.00

(Hauling Distance - within five (5) kilometers)

Sub - Total for B 8,894.40


C. Total (A + B) 9,126.47
D. Output per hour = 42.0000 cu.m.
E. Direct Unit Cost (C ÷ D) 217.30
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

Sub - Total for F -


G. Direct Unit Cost (E + F) 217.30
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 19.56
I. Contractor's Profit (CP) 8% of G 17.38
J. Value Added Tax (VAT) 12% of (G + H + I) 30.51
K. Total Unit Cost (G + H + I + J) 284.75

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 102(3)c Roadway Excavation (Surplus Hard Rock) - Blasting


Unit of Measurement : cu.m.
Output per hour : 10.00

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor
a. Construction Foreman (Drilling) 1 1 109.19 109.19
b. Skilled Laborer 2 1 79.70 159.40
c. Laborer 4 1 61.44 245.76
a. Construction Foreman (Blasting) 1 1 109.19 109.19
b. Skilled Laborer 1 1 79.70 79.70
c. Laborer 2 1 61.44 122.88
a. Construction Foreman (Disposal) 1 1 109.19 109.19
b Laborer 2 1 61.44 122.88
Sub - Total for A 1,058.19
Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Backhoe (0.80 cu.m.) 1 0.25 1,537.00 384.25


b. Payloader (1.50 cu.m.) 1 0.25 1,733.00 433.25
c. Payloader (1.50 cu.m.) at disposal area 1 0.05 1,733.00 86.65
d. Dump Truck (10 cu.m.) 1 1 1,352.00 1,352.00
e. Pneumatic Drilling Machine 2 1 514.31 1,028.62
f. Compressor 1 1 358.00 358.00
(Hauling Distance - within five (5) kilometers)

Sub - Total for B 3,642.77


C. Total (A + B) 4,700.96
D. Output per hour = 10.0000 cu.m.
E. Direct Unit Cost (C ÷ D) 470.10
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. Dynamite kg. 0.40 280.00 112.00


b. Detonation Cord m. 2.00 80.00 160.00
c. Detonator pc. 0.15 260.00 39.00
d. Ammonium Sulfate kg. 0.20 75.00 15.00
e. Blasting Cap pc. 0.30 45.00 13.50
f. Safety Fuse m. 0.10 40.00 4.00

Sub - Total for F 343.50


G. Direct Unit Cost (E + F) 813.60
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 73.22
I. Contractor's Profit (CP) 8% of G 65.09
J. Value Added Tax (VAT) 12% of (G + H + I) 114.23
K. Total Unit Cost (G + H + I + J) 1,066.14

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 102(3)d Roadway Excavation (Surplus Hard Rock) - Blasting (Tunnel Excavation)
Unit of Measurement : cu.m.
Output per hour : 6.50

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor
a. Construction Foreman (Drilling) 1 4 109.19 436.76
b. Skilled Laborer 1 4 79.70 318.80
c. Laborer 2 4 61.44 491.52
a. Construction Foreman (Blasting) 1 1.50 109.19 163.79
b. Skilled Laborer 1 1.50 79.70 119.55
c. Laborer 2 1.50 61.44 184.32
a. Construction Foreman (Disposal) 1 1 109.19 109.19
b Laborer 1 1 61.44 61.44
Sub - Total for A 1,885.37
Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Backhoe (0.80 cu.m.) 1 0.50 1,537.00 768.50


b. Dump Truck (10 cu.m.) 1 1.00 1,352.00 1,352.00
c. Pneumatic Drilling Machine 2 4.00 514.31 4,114.48
d. Compressor 1 4.00 358.00 1,432.00
e. Payloader (1.50 cu.m.) at disposal area 1 0.03 1,733.00 51.99
f. Payloader (1.50 cu.m.) 1 0.15 1,733.00 259.95
(Hauling Distance - within five (5) kilometers)

Sub - Total for B 7,978.92


C. Total (A + B) 9,864.29
D. Output per hour = 6.50 cu.m.
E. Direct Unit Cost (C ÷ D) 1,517.58
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. Dynamite kg. 3.10 280.00 868.00


b. Detonation Cord m. 2.30 80.00 184.00
c. Detonator pc. 3.10 260.00 806.00
d. Ammonium Sulfate kg. 1.50 75.00 112.50
e. Blasting Cap pc. 0.50 45.00 22.50
f. Safety Fuse m. 0.15 40.00 6.00

Sub - Total for F 1,999.00


G. Direct Unit Cost (E + F) 3,516.58
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 316.49
I. Contractor's Profit (CP) 8% of G 281.33
J. Value Added Tax (VAT) 12% of (G + H + I) 493.73
K. Total Unit Cost (G + H + I + J) 4,608.13

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 102(4) Roadway Excavation (Unclassified)


Unit of Measurement : cu.m.
Output per hour : 50.00

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Laborer 2 1 61.44 122.88

Sub - Total for A 232.07


Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Bulldozer (155 hp), D65A-8 1 1 2,299.00 2,299.00


b. Payloader (1.50 cu.m.) 1 1 1,733.00 1,733.00
c. Dump Truck (10 cu.m.) 2 1 1,352.00 2,704.00

Sub - Total for B 6,736.00


C. Total (A + B) 6,968.07
D. Output per hour = 50.0000 cu.m.
E. Direct Unit Cost (C ÷ D) 139.36
Name and Specification Unit Quantity Unit Cost Amount

F. Materials
Sub - Total for F -
G. Direct Unit Cost (E + F) 139.36
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 12.54
I. Contractor's Profit (CP) 8% of G 11.15
J. Value Added Tax (VAT) 12% of (G + H + I) 19.57
K. Total Unit Cost (G + H + I + J) 182.62

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 103(1)a Structure Excavation (Common Soil)


Unit of Measurement : cu.m.
Output per hour : 20.00

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Laborer 3 1 61.44 184.32

Sub - Total for A 293.51


Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Dump Truck (10 cu.m.) 2 1 1,352.00 2,704.00


b. Backhoe (0.80 cu.m.) 1 1 1,537.00 1,537.00
Minor Tools (10% of Labor) 29.35

Sub - Total for B 4,270.35


C. Total (A + B) 4,563.86
D. Output per hour = 20.0000 cu.m.
E. Direct Unit Cost (C ÷ D) 228.19
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

Sub - Total for F -


G. Direct Unit Cost (E + F) 228.19
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 20.54
I. Contractor's Profit (CP) 8% of G 18.26
J. Value Added Tax (VAT) 12% of (G + H + I) 32.04
K. Total Unit Cost (G + H + I + J) 299.02

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 103(1)b Structure Excavation (Soft Rock)


Unit of Measurement : cu.m.
Output per hour : 14.00

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Laborer 3 1 61.44 184.32

Sub - Total for A 293.51


Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Dump Truck (10 cu.m.) 2 1 1,352.00 2,704.00


b. Backhoe (0.80 cu.m.) 1 0.50 1,537.00 768.50
c. Backhoe w/ Breaker (0.80 cu.m.) 1 0.50 2,074.95 1,037.48
Minor Tools (10% of Labor) 29.35

Sub - Total for B 4,539.33


C. Total (A + B) 4,832.84
D. Output per hour = 14.0000 cu.m.
E. Direct Unit Cost (C ÷ D) 345.20
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

Sub - Total for F -


G. Direct Unit Cost (E + F) 345.20
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 31.07
I. Contractor's Profit (CP) 8% of G 27.62
J. Value Added Tax (VAT) 12% of (G + H + I) 48.47
K. Total Unit Cost (G + H + I + J) 452.35

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 103(1)c Structure Excavation (Solid Rock)


Unit of Measurement : cu.m.
Output per hour : 4.00

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Laborer 3 1 61.44 184.32
Sub - Total for A 293.51
Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Dump Truck (10 cu.m.) 1 1 1,352.00 1,352.00


b. Backhoe (0.80 cu.m.) 1 0.50 1,537.00 768.50
c. Backhoe w/ Breaker (0.80 cu.m.) 1 0.50 2,074.95 1,037.48
Minor Tools (10% of Labor) 29.35

Sub - Total for B 3,187.33


C. Total (A + B) 3,480.84
D. Output per hour = 4.0000 cu.m.
E. Direct Unit Cost (C ÷ D) 870.21
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

Sub - Total for F -


G. Direct Unit Cost (E + F) 870.21
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 78.32
I. Contractor's Profit (CP) 8% of G 69.62
J. Value Added Tax (VAT) 12% of (G + H + I) 122.18
K. Total Unit Cost (G + H + I + J) 1,140.32

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 103(2)a Bridge Excavation (Common Soil)


Unit of Measurement : cu.m.
Output per hour : 20.00

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Skilled Laborer 1 1 79.70 79.70
c. Laborer 2 1 61.44 122.88

Sub - Total for A 311.77


Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

b. Backhoe (0.80 cu.m.) 1 1 1,537.00 1,537.00


b. Dump Truck (10 cu.m.) 2 1 1,352.00 2,704.00
Minor Tools (10% of Labor) 31.18
Sub - Total for B 4,272.18
C. Total (A + B) 4,583.95
D. Output per hour = 20.0000 cu.m.
E. Direct Unit Cost (C ÷ D) 229.20
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

Sub - Total for F -


G. Direct Unit Cost (E + F) 229.20
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 20.63
I. Contractor's Profit (CP) 8% of G 18.34
J. Value Added Tax (VAT) 12% of (G + H + I) 32.18
K. Total Unit Cost (G + H + I + J) 300.34

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 103(2)b Bridge Excavation (Soft Rock)


Unit of Measurement : cu.m.
Output per hour : 14.00

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Skilled Laborer 1 1 79.70 79.70
c. Laborer 2 1 61.44 122.88

Sub - Total for A 311.77


Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Backhoe (0.80 cu.m.) 1 0.50 1,537.00 768.50


b. Backhoe w/ Breaker (0.80 cu.m.) 1 0.50 2,074.95 1,037.48
c. Dump Truck (10 cu.m.) 2 1 1,352.00 2,704.00
Minor Tools (10% of Labor) 31.18

Sub - Total for B 4,541.15


C. Total (A + B) 4,852.92
D. Output per hour = 14.0000 cu.m.
E. Direct Unit Cost (C ÷ D) 346.64
Name and Specification Unit Quantity Unit Cost Amount

F. Materials
Sub - Total for F -
G. Direct Unit Cost (E + F) 346.64
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 31.20
I. Contractor's Profit (CP) 8% of G 27.73
J. Value Added Tax (VAT) 12% of (G + H + I) 48.67
K. Total Unit Cost (G + H + I + J) 454.23

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 103(2)c Bridge Excavation (Solid Rock)


Unit of Measurement : cu.m.
Output per hour : 4.00

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Skilled Laborer 1 1 79.70 79.70
c. Laborer 2 1 61.44 122.88

Sub - Total for A 311.77


Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Backhoe (0.80 cu.m.) 1 0.50 1,537.00 768.50


b. Backhoe w/ Breaker (0.80 cu.m.) 1 0.50 2,074.95 1,037.48
c. Dump Truck (10 cu.m.) 1 1 1,352.00 1,352.00
Minor Tools (10% of Labor) 31.18

Sub - Total for B 3,189.15


C. Total (A + B) 3,500.92
D. Output per hour = 4.0000 cu.m.
E. Direct Unit Cost (C ÷ D) 875.23
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

Sub - Total for F -


G. Direct Unit Cost (E + F) 875.23
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 78.77
I. Contractor's Profit (CP) 8% of G 70.02
J. Value Added Tax (VAT) 12% of (G + H + I) 122.88
K. Total Unit Cost (G + H + I + J) 1,146.90

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 103(3) Foundation Fill


Unit of Measurement : cu.m.
Output per hour : 1.25

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Laborer 4 1 61.44 245.76

Sub - Total for A 354.95


Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Plate Compactor 1 1 123.00 123.00


b. Water Truck (1000 gal.) 1 0.01 1,065.00 10.65
Minor Tools (10% of Labor) 35.50

Sub - Total for B 169.15


C. Total (A + B) 524.10
D. Output per hour = 1.25 cu.m.
E. Direct Unit Cost (C ÷ D) 419.28
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. Filling Materials cu.m. 1.15 465.00 534.75

Sub - Total for F 534.75


G. Direct Unit Cost (E + F) 954.03
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 85.86
I. Contractor's Profit (CP) 8% of G 76.32
J. Value Added Tax (VAT) 12% of (G + H + I) 133.95
K. Total Unit Cost (G + H + I + J) 1,250.16

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 103(4) Excavation ordered below Plan Elevation


Unit of Measurement : cu.m.
Output per hour : 20.00

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor
a. Construction Foreman 1 1 109.19 109.19
b. Laborer 3 1 61.44 184.32

Sub - Total for A 293.51


Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Dump Truck (10 cu.m.) 2 1 1,352.00 2,704.00


b. Backhoe (0.80 cu.m.) 1 1 1,537.00 1,537.00
Minor Tools (10% of Labor) 29.35

Sub - Total for B 4,270.35


C. Total (A + B) 4,563.86
D. Output per hour = 20.0000 cu.m.
E. Direct Unit Cost (C ÷ D) 228.19
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

Sub - Total for F -


G. Direct Unit Cost (E + F) 228.19
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 20.54
I. Contractor's Profit (CP) 8% of G 18.26
J. Value Added Tax (VAT) 12% of (G + H + I) 32.04
K. Total Unit Cost (G + H + I + J) 299.02

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 103(5)a Shoring and other related works (assumed footing area = 15 sq.m.)
Unit of Measurement : sq.m.
Output per hour : 1.25

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Skilled Laborer 2 1 79.70 159.40
c. Laborer 4 1 61.44 245.76

Sub - Total for A 514.35


Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Crawler Crane (45 T) 1 1 1,772.00 1,772.00


b. Vibro Hammer (Hydraulic Operated) 1 1 3,069.00 3,069.00
c. Welding Machine 1 0.25 391.00 97.75
d. Cutting Outfit 1 0.25 45.45 11.36

Sub - Total for B 4,950.11


C. Total (A + B) 5,464.46
D. Output per hour = 1.25 sq.m.
E. Direct Unit Cost (C ÷ D) 4,371.57
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. Steel Sheet Piles KSP-II (FY36) kg. 384.00 71.90 27,609.60


40 pcs. - 400mm x 3m
b. Welding Rod (1 kg./2000 kg. of Steel) kg. 0.192 90.00 17.28
c. Oxy/Acetylene (1 set/5000 kg. of Steel) set 0.077 2,500.00 192.50
Miscellaneous (10% of Materials) 2,781.94

Area = 3m x 5m = 15 sq.m.
Perimeter = (3+5)2 =16 /0.40 = 40 pcs.
40 pcs. x 3m/pc. x 48kg/m. = 5,760 kg.

Sub - Total for F 30,601.32


G. Direct Unit Cost (E + F) 34,972.89
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 3,147.56
I. Contractor's Profit (CP) 8% of G 2,797.83
J. Value Added Tax (VAT) 12% of (G + H + I) 4,910.19
K. Total Unit Cost (G + H + I + J) 45,828.47

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 103(5)b Shoring and other related works (assumed footing area = 15 sq.m.)
Unit of Measurement : sq.m.
Output per hour : 0.80

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Skilled Laborer 2 1 79.70 159.40
c. Laborer 4 1 61.44 245.76

Sub - Total for A 514.35


Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Crawler Crane (45 T) 1 1 1,772.00 1,772.00


b. Drop Hammer 1 1 200.00 200.00

Sub - Total for B 1,972.00


C. Total (A + B) 2,486.35
D. Output per hour = 0.80 sq.m.
E. Direct Unit Cost (C ÷ D) 3,107.94
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. Coco Log 0.325m dia. x 3m. bd.ft. 351.30 20.00 7,026.00


b. Wheeler & Squarehole bd.ft. 8.889 40.00 355.56
(10pcs.x 2"x8"x10')/12 = 133.33 bd.ft.
c. Assorted CWN (1 kg./100 bd.ft. of Lumber) kg. 0.089 68.00 6.05
Miscellaneous (10% of Materials) 738.76

Area = 3m x 5m = 15 sq.m.
Perimeter = (3+5)2 =16 /0.325 = 49.23 pcs., say 50 pcs.
50 pcs. x 3m/pc. x 35.13bd.ft./m. = 5,269.50 bd.ft.

Sub - Total for F 8,126.37


G. Direct Unit Cost (E + F) 11,234.31
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 1,011.09
I. Contractor's Profit (CP) 8% of G 898.74
J. Value Added Tax (VAT) 12% of (G + H + I) 1,577.30
K. Total Unit Cost (G + H + I + J) 14,721.44

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 103(5)c Shoring and other related works (assumed slope protection length = 20 l.m.)
Unit of Measurement : l.m.
Output per hour : 10.00

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Skilled Laborer 2 1 79.70 159.40
c. Laborer 4 1 61.44 245.76

Sub - Total for A 514.35


Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Crawler Crane (45 T) 1 1 1,772.00 1,772.00


b. Vibro Hammer (Hydraulic Operated) 1 1 3,069.00 3,069.00
c. Welding Machine 1 0.50 391.00 195.50
d. Cutting Outfit 1 0.50 45.45 22.73

Sub - Total for B 5,059.23


C. Total (A + B) 5,573.58
D. Output per hour = 10.000 l.m.
E. Direct Unit Cost (C ÷ D) 557.36
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. Steel Sheet Piles KSP-II (FY36) kg. 48.00 71.90 3,451.20


50 pcs. - 400mm x 3m
b. Welding Rod (1 kg./2000 kg. of Steel) kg. 0.024 90.00 2.16
c. Oxy/Acetylene (1 set/5000 kg. of Steel) set 0.010 2,500.00 25.00
Miscellaneous (10% of Materials) 347.84

20 l.m./0.40 = 50 pcs.
50 pcs. x 3m/pc. x 48kg/m. = 7,200.00 kg.
Sub - Total for F 3,826.20
G. Direct Unit Cost (E + F) 4,383.55
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 394.52
I. Contractor's Profit (CP) 8% of G 350.68
J. Value Added Tax (VAT) 12% of (G + H + I) 615.45
K. Total Unit Cost (G + H + I + J) 5,744.21

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 103(5)d Shoring and other related works (assumed slope protection length = 20 l.m.)
Unit of Measurement : l.m.
Output per hour : 8.00

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Skilled Laborer 2 1 79.70 159.40
c. Laborer 4 1 61.44 245.76

Sub - Total for A 514.35


Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Crawler Crane (45 T) 1 1 1,772.00 1,772.00


b. Drop Hammer 1 1 200.00 200.00

Sub - Total for B 1,972.00


C. Total (A + B) 2,486.35
D. Output per hour = 8.000 l.m.
E. Direct Unit Cost (C ÷ D) 310.79
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. Coco Log 0.325m dia. x 3m. bd.ft. 35.13 20.00 702.60


b. Wheeler & Squarehole bd.ft. 0.717 40.00 28.68
(10pcs.x 2"x8"x10')/12 = 133.33 bd.ft.
c. Assorted CWN (1 kg./100 bd.ft. of Lumber) kg. 0.007 68.00 0.48
Miscellaneous (10% of Materials) 73.18

20 l.m./0.325 = 61.54 pcs., say 62 pcs.


62 pcs. x 3m/pc. x 35.13bd.ft./m. = 6,534.18 bd.ft.

Sub - Total for F 804.93


G. Direct Unit Cost (E + F) 1,115.73
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 100.42
I. Contractor's Profit (CP) 8% of G 89.26
J. Value Added Tax (VAT) 12% of (G + H + I) 156.65
K. Total Unit Cost (G + H + I + J) 1,462.05

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 103(6) Pipe Culvert and Drain Excavation


Unit of Measurement : cu.m.
Output per hour : 20.00

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Laborer 3 1 61.44 184.32

Sub - Total for A 293.51


Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Dump Truck (10 cu.m.) 2 1 1,352.00 2,704.00


b. Backhoe (0.80 cu.m.) 1 1 1,537.00 1,537.00
Minor Tools (10% of Labor) 29.35

Sub - Total for B 4,270.35


C. Total (A + B) 4,563.86
D. Output per hour = 20.00000 cu.m.
E. Direct Unit Cost (C ÷ D) 228.19
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

Sub - Total for F -


G. Direct Unit Cost (E + F) 228.19
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 20.54
I. Contractor's Profit (CP) 8% of G 18.26
J. Value Added Tax (VAT) 12% of (G + H + I) 32.04
K. Total Unit Cost (G + H + I + J) 299.02

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 104(1)a Embankment (from Borrow)


Unit of Measurement : cu.m.
Output per hour : 50.00

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Laborer 2 1 61.44 122.88

Sub - Total for A 232.07


Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Motorized Road Grader, G710A 1 1 2,173.00 2,173.00


b. Vibratory Roller (10 m.t.), SP56 1 1 1,507.00 1,507.00
c. Water Truck (1000 gal.) 1 0.25 1,065.00 266.25

Sub - Total for B 3,946.25


C. Total (A + B) 4,178.32
D. Output per hour = 50.00000 cu.m.
E. Direct Unit Cost (C ÷ D) 83.57
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. Common Borrow (w/ 25% Shrinkage Factor) cu.m. 1.25 400.00 500.00

Sub - Total for F 500.00


G. Direct Unit Cost (E + F) 583.57
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 52.52
I. Contractor's Profit (CP) 8% of G 46.69
J. Value Added Tax (VAT) 12% of (G + H + I) 81.93
K. Total Unit Cost (G + H + I + J) 764.71
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 104(1)b Embankment from Roadway Excavation


Unit of Measurement : cu.m.
Output per hour : 50.00

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor
For Excavation Work:
a. Construction Foreman 1 0.83 109.19 90.63
b. Laborer 2 0.83 61.44 101.99

Spreading and Compaction:


a. Construction Foreman 1 1 109.19 109.19
b. Laborer 2 1 61.44 122.88

Sub - Total for A 424.69


Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment
For Excavation Work:
a. Bulldozer (155 Hp), D65A-8 1 0.83 2,299.00 1,908.17
b. Payloader (1.50 cu.m.) 1 0.83 1,733.00 1,438.39
c. Dump Truck (10 cu.m.) 2 0.83 1,352.00 2,244.32

Spreading and Compaction


a. Motorized Road Grader, G710A 1 1 2,173.00 2,173.00
b. Vibratory Roller (10 m.t.), SP56 1 1 1,507.00 1,507.00
c. Water Truck (1000 gal.) 1 0.25 1,065.00 266.25

Sub - Total for B 9,537.13


C. Total (A + B) 9,961.82
D. Output per hour = 50.00000 cu.m.
E. Direct Unit Cost (C ÷ D) 199.24
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

Sub - Total for F -


G. Direct Unit Cost (E + F) 199.24
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 17.93
I. Contractor's Profit (CP) 8% of G 15.94
J. Value Added Tax (VAT) 12% of (G + H + I) 27.97
K. Total Unit Cost (G + H + I + J) 261.08
Prepared by: Checked by:

ALLISTER G. NACALABAN
Contractor Project Engineer
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 104(2) Selected Borrow for topping , case 1


Unit of Measurement : cu.m.
Output per hour : 50.00

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Laborer 2 1 61.44 122.88

Sub - Total for A 232.07


Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Motorized Road Grader, G710A 1 1 2,173.00 2,173.00


b. Vibratory Roller (10 m.t.) 1 1 1,507.00 1,507.00
c. Water Truck (1000 gal.) 1 0.25 1,065.00 266.25

Sub - Total for B 3,946.25


C. Total (A + B) 4,178.32
D. Output per hour = 50.00000 cu.m.
E. Direct Unit Cost (C ÷ D) 83.57
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. Selected Borrow (w/ 25% Shrinkage Factor) cu.m. 1.25 420.00 525.00

Sub - Total for F 525.00


G. Direct Unit Cost (E + F) 608.57
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 54.77
I. Contractor's Profit (CP) 8% of G 48.69
J. Value Added Tax (VAT) 12% of (G + H + I) 85.44
K. Total Unit Cost (G + H + I + J) 797.47

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 104(3) Selected Borrow for topping , case 2


Unit of Measurement : cu.m.
Output per hour : 50.00

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Laborer 2 1 61.44 122.88
Sub - Total for A 232.07
Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Motorized Road Grader, G710A 1 1 2,173.00 2,173.00


b. Vibratory Roller (10 m.t.) 1 1 1,507.00 1,507.00
c. Water Truck (1000 gal.) 1 0.25 1,065.00 266.25

Sub - Total for B 3,946.25


C. Total (A + B) 4,178.32
D. Output per hour = 50.00000 cu.m.
E. Direct Unit Cost (C ÷ D) 83.57
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. Selected Borrow (w/ 25% Shrinkage Factor) cu.m. 1.25 420.00 525.00

Sub - Total for F 525.00


G. Direct Unit Cost (E + F) 608.57
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 54.77
I. Contractor's Profit (CP) 8% of G 48.69
J. Value Added Tax (VAT) 12% of (G + H + I) 85.44
K. Total Unit Cost (G + H + I + J) 797.47

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 104(4) Earth Berm


Unit of Measurement : cu.m.
Output per hour : 1.25

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Laborer 4 1 61.44 245.76

Sub - Total for A 354.95


Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Plate Compactor 1 1 123.00 123.00


b. Water Truck (1000 gal.) 1 0.01 1,065.00 10.65
Minor Tools (10% of Labor) 35.50
Sub - Total for B 169.15
C. Total (A + B) 524.10
D. Output per hour = 1.25 cu.m.
E. Direct Unit Cost (C ÷ D) 419.28
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. Filling Materials cu.m. 1.25 420.00 525.00

Sub - Total for F 525.00


G. Direct Unit Cost (E + F) 944.28
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 84.98
I. Contractor's Profit (CP) 8% of G 75.54
J. Value Added Tax (VAT) 12% of (G + H + I) 132.58
K. Total Unit Cost (G + H + I + J) 1,237.38

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 105(1) Subgrade Preparation (Common Excavation)


Unit of Measurement : sq.m.
Output per hour : 300.00

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Laborer 2 1 61.44 122.88

Sub - Total for A 232.07


Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Motorized Road Grader, G710A 1 1 2,173.00 2,173.00


b. Vibratory Roller (10 m.t.), SP56 1 1 1,507.00 1,507.00
c. Water Truck (1000 gal.) 1 0.25 1,065.00 266.25

Sub - Total for B 3,946.25


C. Total (A + B) 4,178.32
D. Output per hour = 300.00000 sq.m.
E. Direct Unit Cost (C ÷ D) 13.93
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

Sub - Total for F -


G. Direct Unit Cost (E + F) 13.93
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 1.25
I. Contractor's Profit (CP) 8% of G 1.11
J. Value Added Tax (VAT) 12% of (G + H + I) 1.96
K. Total Unit Cost (G + H + I + J) 18.25

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 105(2) Subgrade Preparation (Existing Pavement)


Unit of Measurement : sq.m.
Output per hour : 300.00

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Laborer 2 1 61.44 122.88

Sub - Total for A 232.07


Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Motorized Road Grader, G710A 1 1 2,173.00 2,173.00


b. Vibratory Roller (10 m.t.), SP56 1 1 1,507.00 1,507.00
c. Water Truck (1000 gal.) 1 0.25 1,065.00 266.25

Sub - Total for B 3,946.25


C. Total (A + B) 4,178.32
D. Output per hour = 300.00000 sq.m.
E. Direct Unit Cost (C ÷ D) 13.93
Name and Specification Unit Quantity Unit Cost Amount

F. Materials
Sub - Total for F -
G. Direct Unit Cost (E + F) 13.93
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 1.25
I. Contractor's Profit (CP) 8% of G 1.11
J. Value Added Tax (VAT) 12% of (G + H + I) 1.96
K. Total Unit Cost (G + H + I + J) 18.25

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 105(3) Subgrade Preparation (Unsuitable Excavation)


Unit of Measurement : sq.m.
Output per hour : 300.00

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Laborer 2 1 61.44 122.88

Sub - Total for A 232.07


Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Motorized Road Grader, G710A 1 1 2,173.00 2,173.00


b. Vibratory Roller (10 m.t.), SP56 1 1 1,507.00 1,507.00
c. Water Truck (1000 gal.) 1 0.25 1,065.00 266.25

Sub - Total for B 3,946.25


C. Total (A + B) 4,178.32
D. Output per hour = 300.00000 sq.m.
E. Direct Unit Cost (C ÷ D) 13.93
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

Sub - Total for F -


G. Direct Unit Cost (E + F) 13.93
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 1.25
I. Contractor's Profit (CP) 8% of G 1.11
J. Value Added Tax (VAT) 12% of (G + H + I) 1.96
K. Total Unit Cost (G + H + I + J) 18.25
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 200 Aggregate Subbase Course


Unit of Measurement : cu.m
Output per hour : 50.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Laborers 2 1 61.44 122.88

Sub - Total for A 232.07


Name and Capacity No of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Motorized Road Grader, G710A 1 1 2,173.00 2,173.00


b. Vibratory Roller (10 m.t.), SP56 1 1 1,507.00 1,507.00
c. Water Truck (1000 gal.) 1 0.25 1,065.00 266.25

Sub - Total for B 3,946.25


C. Total (A + B) 4,178.32
D. Output per hour = 50.0000 cu.m.
E. Direct Unit Cost (C ÷ D) 83.57
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Aggregate Subbase Course cu.m. 1.15 580.00 667.00


(w/ 15% Shrinkage Factor)

Sub - Total for F 667.00


G. Direct Unit Cost (E + F) 750.57
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 67.55
I. Contractor's Profit (CP) 8% of G 60.05
J. Value Added Tax (VAT) 12% of (G + H + I) 105.38
K. Total Unit Cost (G + H + I + J) 983.54
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 200(1) Aggregate Subbase Course (for Intermittent Reblocking)


Unit of Measurement : cu.m
Output per hour : 40.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Laborers 2 1 61.44 122.88

Sub - Total for A 232.07


Name and Capacity No of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Motorized Road Grader, G710A 1 1 2,173.00 2,173.00


b. Vibratory Roller (10 m.t.), SP56 1 1 1,507.00 1,507.00
c. Plate Compactor 1 0.25 123.00 30.75
d. Water Truck (1000 gal.) 1 0.25 1,065.00 266.25

Sub - Total for B 3,977.00


C. Total (A + B) 4,209.07
D. Output per hour = 40.0000 cu.m.
E. Direct Unit Cost (C ÷ D) 105.23
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Aggregate Subbase Course cu.m. 1.15 580.00 667.00


(w/ 15% Shrinkage Factor)

Sub - Total for F 667.00


G. Direct Unit Cost (E + F) 772.23
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 69.50
I. Contractor's Profit (CP) 8% of G 61.78
J. Value Added Tax (VAT) 12% of (G + H + I) 108.42
K. Total Unit Cost (G + H + I + J) 1,011.93

DETAILED UNIT PRICE ANALYSIS (DUPA)


Item No./Description : 201 Aggregate Base Course
Unit of Measurement : cu.m
Output per hour : 50.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Laborers 2 1 61.44 122.88

Sub - Total for A 232.07


Name and Capacity No of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Motorized Road Grader, G710A 1 1 2,173.00 2,173.00


b. Vibratory Roller (10 m.t.), SP56 1 1 1,507.00 1,507.00
c. Water Truck (1000 gal.) 1 0.25 1,065.00 266.25

Sub - Total for B 3,946.25


C. Total (A + B) 4,178.32
D. Output per hour = 50.0000 cu.m.
E. Direct Unit Cost (C ÷ D) 83.57
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Aggregate Base Course cu.m. 1.15 650.00 747.50


(w/ 15% Shrinkage Factor)

Sub - Total for F 747.50


G. Direct Unit Cost (E + F) 831.07
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 74.80
I. Contractor's Profit (CP) 8% of G 66.49
J. Value Added Tax (VAT) 12% of (G + H + I) 116.68
K. Total Unit Cost (G + H + I + J) 1,089.03

DETAILED UNIT PRICE ANALYSIS (DUPA)


Item No./Description : 201(1) Aggregate Base Course (for Reblocking)
Unit of Measurement : cu.m
Output per hour : 40.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Laborers 2 1 61.44 122.88

Sub - Total for A 232.07


Name and Capacity No of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Motorized Road Grader, G710A 1 1 2,173.00 2,173.00


b. Vibratory Roller (10 m.t.), SP56 1 1 1,507.00 1,507.00
c. Plate Compactor 1 0.25 123.00 30.75
d. Water Truck (1000 gal.) 1 0.25 1,065.00 266.25

Sub - Total for B 3,977.00


C. Total (A + B) 4,209.07
D. Output per hour = 40.0000 cu.m.
E. Direct Unit Cost (C ÷ D) 105.23
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Aggregate Base Course cu.m. 1.15 650.00 747.50


(w/ 15% Shrinkage Factor)

Sub - Total for F 747.50


G. Direct Unit Cost (E + F) 852.73
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 76.75
I. Contractor's Profit (CP) 8% of G 68.22
J. Value Added Tax (VAT) 12% of (G + H + I) 119.72
K. Total Unit Cost (G + H + I + J) 1,117.41

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 202 Crushed Aggregate Base Course


Unit of Measurement : cu.m
Output per hour : 50.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Laborers 2 1 61.44 122.88

Sub - Total for A 232.07


Name and Capacity No of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Motorized Road Grader, G710A 1 1 2,173.00 2,173.00


b. Vibratory Roller (10 m.t.), SP56 1 1 1,507.00 1,507.00
c. Water Truck (1000 gal.) 1 0.25 1,065.00 266.25

Sub - Total for B 3,946.25


C. Total (A + B) 4,178.32
D. Output per hour = 50.0000 cu.m.
E. Direct Unit Cost (C ÷ D) 83.57
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Crushed Aggregate Base Course cu.m. 1.15 700.00 805.00


(w/ 15% Shrinkage Factor)

Sub - Total for F 805.00


G. Direct Unit Cost (E + F) 888.57
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 79.97
I. Contractor's Profit (CP) 8% of G 71.09
J. Value Added Tax (VAT) 12% of (G + H + I) 124.75
K. Total Unit Cost (G + H + I + J) 1,164.38

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 202(1) Crushed Aggregate Base Course (for Reblocking)


Unit of Measurement : cu.m
Output per hour : 50.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Laborers 2 1 61.44 122.88

Sub - Total for A 232.07


Name and Capacity No of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Motorized Road Grader, G710A 1 1 2,173.00 2,173.00


b. Vibratory Roller (10 m.t.), SP56 1 1 1,507.00 1,507.00
c. Plate Compactor 1 0.25 123.00 30.75
d. Water Truck (1000 gal.) 1 0.25 1,065.00 266.25

Sub - Total for B 3,977.00


C. Total (A + B) 4,209.07
D. Output per hour = 50.0000 cu.m.
E. Direct Unit Cost (C ÷ D) 84.18
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Crushed Aggregate Base Course cu.m. 1.15 700.00 805.00


(w/ 15% Shrinkage Factor)

Sub - Total for F 805.00


G. Direct Unit Cost (E + F) 889.18
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 80.03
I. Contractor's Profit (CP) 8% of G 71.13
J. Value Added Tax (VAT) 12% of (G + H + I) 124.84
K. Total Unit Cost (G + H + I + J) 1,165.18

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 203 Lime Stabilized Road Mix Base Course


Unit of Measurement : cu.m.
Output per hour : 15.00
Designation No. of Person No. of Hours Hourly Rate Amount
A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Laborer 10 1 61.44 614.40

Sub - Total for A 723.59


Name and Capacity No of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Motorized Road Grader (140 Hp) 1 1 2,173.00 2,173.00


b. Vibratory Roller (10 m.t.), SP56 1 1 1,507.00 1,507.00
c. Water Truck (1000 gal.) 1 0.25 1,065.00 266.25

Sub - Total for B 3,946.25


C. Total (A + B) 4,669.84
D. Output per hour = 15.0000 cu.m.
E. Direct Unit Cost (C ÷ D) 311.32
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Hydrated Lime, Type N (Normal) bag 2.80 180.00 504.00


b. Aggregate Base Course cu.m. 1.15 650.00 747.50

Sub - Total for F 1,251.50


G. Direct Unit Cost (E + F) 1,562.82
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 140.65
I. Contractor's Profit (CP) 8% of G 125.03
J. Value Added Tax (VAT) 12% of (G + H + I) 219.42
K. Total Unit Cost (G + H + I + J) 2,047.92

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 203(1) Lime Stabilized Road Mix Base Course (for Reblocking)
Unit of Measurement : cu.m.
Output per hour : 15.00

Designation No. of Person No. of Hours Hourly Rate Amount


Designation No. of Person No. of Hours Hourly Rate Amount
A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Laborer 10 1 61.44 614.40

Sub - Total for A 723.59


Name and Capacity No of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Motorized Road Grader (140 Hp) 1 1 2,173.00 2,173.00


b. Vibratory Roller (10 m.t.), SP56 1 1 1,507.00 1,507.00
c. Plate Compactor 1 0.25 123.00 30.75
d. Water Truck (1000 gal.) 1 0.25 1,065.00 266.25

Sub - Total for B 3,977.00


C. Total (A + B) 4,700.59
D. Output per hour = 15.0000 cu.m.
E. Direct Unit Cost (C ÷ D) 313.37
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Hydrated Lime, Type N (Normal) bag 2.80 180.00 504.00


b. Aggregate Base Course cu.m. 1.15 650.00 747.50

Sub - Total for F 1,251.50


G. Direct Unit Cost (E + F) 1,564.87
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 140.84
I. Contractor's Profit (CP) 8% of G 125.19
J. Value Added Tax (VAT) 12% of (G + H + I) 219.71
K. Total Unit Cost (G + H + I + J) 2,050.61

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 204 Portland Cement Stabilized Road Mix Base Course
Unit of Measurement : cu.m.
Output per hour : 15.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Laborer 10 1 61.44 614.40

Sub - Total for A 723.59


Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Motorized Road Grader (140 Hp) 1 1 2,173.00 2,173.00


b. Vibratory Roller (10 m.t.), SP56 1 1 1,507.00 1,507.00
c. Water Truck (1000 gal.) 1 0.25 1,065.00 266.25

Sub - Total for B 3,946.25


C. Total (A + B) 4,669.84
D. Output per hour = 15.0000 cu.m.
E. Direct Unit Cost (C ÷ D) 311.32
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. Cement bag 3 220.00 660.00


b. Aggregate Base Course cu.m. 1.15 650.00 747.50

Sub - Total for F 1,407.50


G. Direct Unit Cost (E + F) 1,718.82
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 154.69
I. Contractor's Profit (CP) 8% of G 137.51
J. Value Added Tax (VAT) 12% of (G + H + I) 241.32
K. Total Unit Cost (G + H + I + J) 2,252.35

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 205 Asphalt Stabilized Road Mix Base Course


Unit of Measurement : cu.m.
Output per hour : 15.00

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor
a. Construction Foreman 1 1 109.19 109.19
b. Laborer 10 1 61.44 614.40

Sub - Total for A 723.59


Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Motorized Road Grader (140 Hp) 1 1 2,173.00 2,173.00


b. Vibratory Roller (10 m.t.), SP56 1 1 1,507.00 1,507.00
c. Water Truck (1000 gal.) 1 0.25 1,065.00 266.25
d. Asphalt Distributor, 10 ft. wide (5 tons) 1 1 936.00 936.00

Sub - Total for B 4,882.25


C. Total (A + B) 5,605.84
D. Output per hour = 15.0000 cu.m.
E. Direct Unit Cost (C ÷ D) 373.72
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. Emulsified Asphalt SS-1 m.t. 0.07 44,000.00 3,080.00


b. Aggregate Base Course cu.m. 1.15 650.00 747.50

Sub - Total for F 3,827.50


G. Direct Unit Cost (E + F) 4,201.22
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 378.11
I. Contractor's Profit (CP) 8% of G 336.10
J. Value Added Tax (VAT) 12% of (G + H + I) 589.85
K. Total Unit Cost (G + H + I + J) 5,505.28

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 206 Portland Cement Treated Plant Mix Base Course
Unit of Measurement : cu.m.
Output per hour : 15.00

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor
a. Construction Foreman 1 1 109.19 109.19
b. Skilled Laborer 2 1 79.70 159.40
c. Laborer 4 1 61.44 245.76

Sub - Total for A 514.35


Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Batching Plant (30 cu.m.) 1 0.50 1,208.03 604.02


b. Dump Truck (10 cu.m.) 3 0.50 1,352.00 2,028.00
c. Motorized Road Grader, G710A 1 0.50 2,173.00 1,086.50
d. Vibratory Roller (10 m.t.), SP56 1 0.50 1,507.00 753.50
e. Payloader (1.50 cu.m.), LX80-2C 1 0.50 1,733.00 866.50
f. Water Truck (1000 gal.) 1 0.25 1,065.00 266.25
g. Asphalt Distributor, 10 ft. wide (5 tons) 1 0.10 936.00 93.60

Sub - Total for B 5,698.37


C. Total (A + B) 6,212.72
D. Output per hour = 15.0000 cu.m.
E. Direct Unit Cost (C ÷ D) 414.18
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. Cement bag 3 220.00 660.00


b. Aggregate Base Course cu.m. 1.15 650.00 747.50
c. MC 70 Cut-back Asphalt m.t. 0.0075 40,300.00 302.25

Sub - Total for F 1,709.75


G. Direct Unit Cost (E + F) 2,123.93
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 191.15
I. Contractor's Profit (CP) 8% of G 169.91
J. Value Added Tax (VAT) 12% of (G + H + I) 298.20
K. Total Unit Cost (G + H + I + J) 2,783.20
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 300(1) Gravel Surface Course (Uncrushed)


Unit of Measurement : cu.m
Output per hour : 50.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Laborer 2 1 61.44 122.88

Sub - Total for A 232.07


Name and Capacity No of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Motorized Road Grader, G710A 1 1 2,173.00 2,173.00


b. Vibratory Roller (10 m.t.), SP56 1 1 1,507.00 1,507.00
c. Water Truck (1000 gal.), All Make 1 0.25 1,065.00 266.25

Sub - Total for B 3,946.25


C. Total (A + B) 4,178.32
D. Output per hour = 50.0000 cu.m.
E. Direct Unit Cost (C ÷ D) 83.57
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Uncrushed Aggregate Surface Course cu.m. 1.15 700.00 805.00


(w/ 15% Shrinkage Factor)

Sub - Total for F 805.00


G. Direct Unit Cost (E + F) 888.57
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 79.97
I. Contractor's Profit (CP) 8% of G 71.09
J. Value Added Tax (VAT) 12% of (G + H + I) 124.75
K. Total Unit Cost (G + H + I + J) 1,164.38
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 300(2) Crushed Aggregate Surface Course


Unit of Measurement : cu.m
Output per hour : 50.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Laborer 2 1 61.44 122.88

Sub - Total for A 232.07


Name and Capacity No of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Motorized Road Grader, G710A 1 1 2,173.00 2,173.00


b. Vibratory Roller (10 m.t.), SP56 1 1 1,507.00 1,507.00
c. Water Truck (1000 gal.), All Make 1 0.25 1,065.00 266.25

Sub - Total for B 3,946.25


C. Total (A + B) 4,178.32
D. Output per hour = 50.0000 cu.m.
E. Direct Unit Cost (C ÷ D) 83.57
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Crushed Aggregate Surface Course cu.m. 1.15 750.00 862.50


(w/ 15% Shrinkage Factor)

Sub - Total for F 862.50


G. Direct Unit Cost (E + F) 946.07
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 85.15
I. Contractor's Profit (CP) 8% of G 75.69
J. Value Added Tax (VAT) 12% of (G + H + I) 132.83
K. Total Unit Cost (G + H + I + J) 1,239.73

DETAILED UNIT PRICE ANALYSIS (DUPA)


Item No./Description : 301(1) Bituminous Prime Coat (MC Cut-back Asphalt)
Unit of Measurement : m.t.
Output per hour : 0.30

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Laborer 3 1 61.44 184.32

Sub - Total for A 293.51


Name and Capacity No of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Asphalt Distributor, 10 ft. wide (5 tons) 1 1 936.00 936.00


b. Power Broom (20 m. wide) 1 1 130.54 130.54

Sub - Total for B 1,066.54


C. Total (A + B) 1,360.05
D. Output per hour = 0.300 m.t.
E. Direct Unit Cost (C ÷ D) 4,533.50
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. MC 70 Cut-back Asphalt m.t. 1.05 40,300.00 42,315.00


(w/ 5% wastage)

Sub - Total for F 42,315.00


G. Direct Unit Cost (E + F) 46,848.50
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 4,216.37
I. Contractor's Profit (CP) 8% of G 3,747.88
J. Value Added Tax (VAT) 12% of (G + H + I) 6,577.53
K. Total Unit Cost (G + H + I + J) 61,390.27

DETAILED UNIT PRICE ANALYSIS (DUPA)


Item No./Description : 301(2) Bituminous Prime Coat (RC Cut-back Asphalt)
Unit of Measurement : m.t.
Output per hour : 0.30

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Laborer 3 1 61.44 184.32

Sub - Total for A 293.51


Name and Capacity No of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Asphalt Distributor, 10 ft. wide (5 tons) 1 1 936.00 936.00


b. Power Broom (20 m. wide) 1 1 130.54 130.54

Sub - Total for B 1,066.54


C. Total (A + B) 1,360.05
D. Output per hour = 0.300 m.t.
E. Direct Unit Cost (C ÷ D) 4,533.50
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. RC 70 Cut-back Asphalt m.t. 1.05 41,575.00 43,653.75


(w/ 5% wastage)

Sub - Total for F 43,653.75


G. Direct Unit Cost (E + F) 48,187.25
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 4,336.85
I. Contractor's Profit (CP) 8% of G 3,854.98
J. Value Added Tax (VAT) 12% of (G + H + I) 6,765.49
K. Total Unit Cost (G + H + I + J) 63,144.57

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 302(1) Bituminous Tack Coat (RC Cut-back Asphalt)


Unit of Measurement : m.t.
Output per hour : 0.30

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Laborer 3 1 61.44 184.32

Sub - Total for A 293.51


Name and Capacity No of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Asphalt Distributor, 10 ft. wide (5 tons) 1 1 936.00 936.00


b. Power Broom (20 m. wide) 1 1 130.54 130.54

Sub - Total for B 1,066.54


C. Total (A + B) 1,360.05
D. Output per hour = 0.300 m.t.
E. Direct Unit Cost (C ÷ D) 4,533.50
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. RC 70 Cut-back Asphalt m.t. 1.05 41,575.00 43,653.75


(w/ 5% wastage)

Sub - Total for F 43,653.75


G. Direct Unit Cost (E + F) 48,187.25
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 4,336.85
I. Contractor's Profit (CP) 8% of G 3,854.98
J. Value Added Tax (VAT) 12% of (G + H + I) 6,765.49
K. Total Unit Cost (G + H + I + J) 63,144.57

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 302(2) Bituminous Tack Coat (Emulsified Asphalt)


Unit of Measurement : m.t.
Output per hour : 0.30

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Laborer 3 1 61.44 184.32

Sub - Total for A 293.51


Name and Capacity No of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Asphalt Distributor, 10 ft. wide (5 tons) 1 1 936.00 936.00


b. Power Broom (20 m. wide) 1 1 130.54 130.54

Sub - Total for B 1,066.54


C. Total (A + B) 1,360.05
D. Output per hour = 0.300 m.t.
E. Direct Unit Cost (C ÷ D) 4,533.50
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Emulsified Asphalt SS-1 m.t. 1.05 44,000.00 46,200.00


(w/ 5% wastage)

Sub - Total for F 46,200.00


G. Direct Unit Cost (E + F) 50,733.50
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 4,566.01
I. Contractor's Profit (CP) 8% of G 4,058.68
J. Value Added Tax (VAT) 12% of (G + H + I) 7,122.98
K. Total Unit Cost (G + H + I + J) 66,481.18

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 303(1) Bituminous Seal Coat (Cover Aggregate)


Unit of Measurement : m.t.
Output per hour : 16.00 (10 m³)
Designation No. of Person No. of Hours Hourly Rate Amount
A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Laborer 20 1 61.44 1,228.80

Sub - Total for A 1,337.99


Name and Capacity No of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Tandem Steel Roller (10.1 m.t.), CC421 1 1 1,652.00 1,652.00


b. Water Truck (1000 gal.) 1 0.25 1,065.00 266.25

Sub - Total for B 1,918.25


C. Total (A + B) 3,256.24
D. Output per hour = 16.0000 m.t.
E. Direct Unit Cost (C ÷ D) 203.52
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Cover Aggregate m.t. 1.15 406.25 467.19


(w/ 15% Shrinkage Factor)

Note: 1.60 m.t./cu.m.


using unit wt. of 1,600 kg./m³

Sub - Total for F 467.19


G. Direct Unit Cost (E + F) 670.70
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 60.36
I. Contractor's Profit (CP) 8% of G 53.66
J. Value Added Tax (VAT) 12% of (G + H + I) 94.17
K. Total Unit Cost (G + H + I + J) 878.89

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 303(2) Bituminous Seal Coat (MC Cut-back Asphalt)


Unit of Measurement : m.t.
Output per hour : 0.30

Designation No. of Person No. of Hours Hourly Rate Amount


Designation No. of Person No. of Hours Hourly Rate Amount
A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Laborer 3 1 61.44 184.32

Sub - Total for A 293.51


Name and Capacity No of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Asphalt Distributor, 10 ft. wide (5 tons) 1 1 936.00 936.00


b. Power Broom (20 m. wide) 1 1 130.54 130.54

Sub - Total for B 1,066.54


C. Total (A + B) 1,360.05
D. Output per hour = 0.300 m.t.
E. Direct Unit Cost (C ÷ D) 4,533.50
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. MC Cut-back Asphalt m.t. 1.05 40,300.00 42,315.00


(w/ 5% Wastage)

Sub - Total for F 42,315.00


G. Direct Unit Cost (E + F) 46,848.50
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 4,216.37
I. Contractor's Profit (CP) 8% of G 3,747.88
J. Value Added Tax (VAT) 12% of (G + H + I) 6,577.53
K. Total Unit Cost (G + H + I + J) 61,390.27

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 303(3) Bituminous Seal Coat (RC Cut-back Asphalt)


Unit of Measurement : m.t.
Output per hour : 0.30

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor
a. Construction Foreman 1 1 109.19 109.19
b. Laborer 3 1 61.44 184.32

Sub - Total for A 293.51


Name and Capacity No of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Asphalt Distributor, 10 ft. wide (5 tons) 1 1 936.00 936.00


b. Power Broom (20 m. wide) 1 1 130.54 130.54

Sub - Total for B 1,066.54


C. Total (A + B) 1,360.05
D. Output per hour = 0.300 m.t.
E. Direct Unit Cost (C ÷ D) 4,533.50
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. RC 70 Cut-back Asphalt m.t. 1.05 41,575.00 43,653.75


(w/ 5% Wastage)

Sub - Total for F 43,653.75


G. Direct Unit Cost (E + F) 48,187.25
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 4,336.85
I. Contractor's Profit (CP) 8% of G 3,854.98
J. Value Added Tax (VAT) 12% of (G + H + I) 6,765.49
K. Total Unit Cost (G + H + I + J) 63,144.57

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 303(4) Bituminous Seal Coat (Asphalt Cement Penetration Grade 120-150)
Unit of Measurement : m.t.
Output per hour : 0.30

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor
a. Construction Foreman 1 1 109.19 109.19
b. Laborer 3 1 61.44 184.32

Sub - Total for A 293.51


Name and Capacity No of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Asphalt Distributor, 10 ft. wide (5 tons) 1 1 936.00 936.00


b. Power Broom (20 m. wide) 1 1 130.54 130.54

Sub - Total for B 1,066.54


C. Total (A + B) 1,360.05
D. Output per hour = 0.300 m.t.
E. Direct Unit Cost (C ÷ D) 4,533.50
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Asphalt Cement Penetration Grade 120-150 m.t. 1.05 50,775.00 53,313.75


(w/ 5% Wastage)

Sub - Total for F 53,313.75


G. Direct Unit Cost (E + F) 57,847.25
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 5,206.25
I. Contractor's Profit (CP) 8% of G 4,627.78
J. Value Added Tax (VAT) 12% of (G + H + I) 8,121.75
K. Total Unit Cost (G + H + I + J) 75,803.04

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 304(1) Bituminous Surface Treatment (Aggregate Grading)


Unit of Measurement : m.t.
Output per hour : 16.00 (10 m³)

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Laborer 20 1 61.44 1,228.80

Sub - Total for A 1,337.99


Name and Capacity No of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Vibratory Roller (10 m.t.), SP56 1 1 1,507.00 1,507.00


b. Water Truck (1000 gal.) 1 0.25 1,065.00 266.25

Sub - Total for B 1,773.25


C. Total (A + B) 3,111.24
D. Output per hour = 16.0000 m.t.
E. Direct Unit Cost (C ÷ D) 194.45
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Aggregates m.t. 1.15 406.25 467.19


(w/ 15% Shrinkage Factor)

Sub - Total for F 467.19


G. Direct Unit Cost (E + F) 661.64
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 59.55
I. Contractor's Profit (CP) 8% of G 52.93
J. Value Added Tax (VAT) 12% of (G + H + I) 92.89
K. Total Unit Cost (G + H + I + J) 867.01

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 304(2) Bituminous Surface Treatment (Asphalt Cement Penetration Grade 120-150)
Unit of Measurement : m.t.
Output per hour : 0.30

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Laborer 3 1 61.44 184.32
Sub - Total for A 293.51
Name and Capacity No of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Asphalt Distributor, 10 ft. wide (5 tons) 1 1 936.00 936.00


b. Power Broom (20 m. wide) 1 1 130.54 130.54

Sub - Total for B 1,066.54


C. Total (A + B) 1,360.05
D. Output per hour = 0.300 m.t.
E. Direct Unit Cost (C ÷ D) 4,533.50
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Asphalt Cement Penetration Grade 120-150 m.t. 1.05 50,775.00 53,313.75


(w/ 5% Wastage)

Sub - Total for F 53,313.75


G. Direct Unit Cost (E + F) 57,847.25
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 5,206.25
I. Contractor's Profit (CP) 8% of G 4,627.78
J. Value Added Tax (VAT) 12% of (G + H + I) 8,121.75
K. Total Unit Cost (G + H + I + J) 75,803.04

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 304(3) Bituminous Surface Treatment (MC Cut-back Asphalt)


Unit of Measurement : m.t.
Output per hour : 0.30

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Laborer 3 1 61.44 184.32
Sub - Total for A 293.51
Name and Capacity No of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Asphalt Distributor, 10 ft. wide (5 tons) 1 1 936.00 936.00


b. Power Broom (20 m. wide) 1 1 130.54 130.54

Sub - Total for B 1,066.54


C. Total (A + B) 1,360.05
D. Output per hour = 0.300 m.t.
E. Direct Unit Cost (C ÷ D) 4,533.50
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. MC Cut-back Asphalt m.t. 1.05 40,300.00 42,315.00


(w/ 5% Wastage)

Sub - Total for F 42,315.00


G. Direct Unit Cost (E + F) 46,848.50
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 4,216.37
I. Contractor's Profit (CP) 8% of G 3,747.88
J. Value Added Tax (VAT) 12% of (G + H + I) 6,577.53
K. Total Unit Cost (G + H + I + J) 61,390.27

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 304(4) Bituminous Surface Treatment (RC Cut-back Asphalt)


Unit of Measurement : m.t.
Output per hour : 0.30

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Laborer 3 1 61.44 184.32
Sub - Total for A 293.51
Name and Capacity No of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Asphalt Distributor, 10 ft. wide (5 tons) 1 1 936.00 936.00


b. Power Broom (20 m. wide) 1 1 130.54 130.54

Sub - Total for B 1,066.54


C. Total (A + B) 1,360.05
D. Output per hour = 0.300 m.t.
E. Direct Unit Cost (C ÷ D) 4,533.50
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. RC 70 Cut-back Asphalt m.t. 1.05 41,575.00 43,653.75


(w/ 5% Wastage)

Sub - Total for F 43,653.75


G. Direct Unit Cost (E + F) 48,187.25
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 4,336.85
I. Contractor's Profit (CP) 8% of G 3,854.98
J. Value Added Tax (VAT) 12% of (G + H + I) 6,765.49
K. Total Unit Cost (G + H + I + J) 63,144.57

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 304(5) Bituminous Surface Treatment (Emulsified Asphalt)


Unit of Measurement : m.t.
Output per hour : 0.30

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Laborer 3 1 61.44 184.32
Sub - Total for A 293.51
Name and Capacity No of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Asphalt Distributor, 10 ft. wide (5 tons) 1 1 936.00 936.00


b. Power Broom (20 m. wide) 1 1 130.54 130.54

Sub - Total for B 1,066.54


C. Total (A + B) 1,360.05
D. Output per hour = 0.300 m.t.
E. Direct Unit Cost (C ÷ D) 4,533.50
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Emulsified Asphalt SS-1 m.t. 1.05 44,000.00 46,200.00


(w/ 5% wastage)

Sub - Total for F 46,200.00


G. Direct Unit Cost (E + F) 50,733.50
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 4,566.01
I. Contractor's Profit (CP) 8% of G 4,058.68
J. Value Added Tax (VAT) 12% of (G + H + I) 7,122.98
K. Total Unit Cost (G + H + I + J) 66,481.18

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 305(1) Bituminous Penetration Macadam Pavement (Aggregates)


Unit of Measurement : m.t.
Output per hour : 16.00 (10 m³)

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Laborer 20 1 61.44 1,228.80
Sub - Total for A 1,337.99
Name and Capacity No of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Vibratory Roller (10 m.t.), SP56 1 1 1,507.00 1,507.00


b. Water Truck (1000 gal.) 1 0.25 1,065.00 266.25

Sub - Total for B 1,773.25


C. Total (A + B) 3,111.24
D. Output per hour = 16.0000 m.t.
E. Direct Unit Cost (C ÷ D) 194.45
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Aggregates m.t. 1.15 406.25 467.19


(w/ 15% Shrinkage Factor)

Sub - Total for F 467.19


G. Direct Unit Cost (E + F) 661.64
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 59.55
I. Contractor's Profit (CP) 8% of G 52.93
J. Value Added Tax (VAT) 12% of (G + H + I) 92.89
K. Total Unit Cost (G + H + I + J) 867.01

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 305(2) Bituminous Penetration Macadam Pavement (Asphalt Cement)


Unit of Measurement : m.t.
Output per hour : 0.30

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Laborer 3 1 61.44 184.32
Sub - Total for A 293.51
Name and Capacity No of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Asphalt Distributor, 10 ft. wide (5 tons) 1 1 936.00 936.00


b. Power Broom (20 m. wide) 1 1 130.54 130.54

Sub - Total for B 1,066.54


C. Total (A + B) 1,360.05
D. Output per hour = 0.300 m.t.
E. Direct Unit Cost (C ÷ D) 4,533.50
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Asphalt Cement (w/ 5% Wastage) m.t. 1.05 50,775.00 53,313.75

Sub - Total for F 53,313.75


G. Direct Unit Cost (E + F) 57,847.25
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 5,206.25
I. Contractor's Profit (CP) 8% of G 4,627.78
J. Value Added Tax (VAT) 12% of (G + H + I) 8,121.75
K. Total Unit Cost (G + H + I + J) 75,803.04

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 305(3) Bituminous Penetration Macadam Pavement (RC Cut-back Asphalt)
Unit of Measurement : m.t.
Output per hour : 0.30

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Laborer 3 1 61.44 184.32

Sub - Total for A 293.51


Name and Capacity No of Units No. of Hours Hourly Rate Amount
Name and Capacity No of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Asphalt Distributor, 10 ft. wide (5 tons) 1 1 936.00 936.00


b. Power Broom (20 m. wide) 1 1 130.54 130.54

Sub - Total for B 1,066.54


C. Total (A + B) 1,360.05
D. Output per hour = 0.300 m.t.
E. Direct Unit Cost (C ÷ D) 4,533.50
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. RC 70 Cut-back Asphalt m.t. 1.05 41,575.00 43,653.75


(w/ 5% Wastage)

Sub - Total for F 43,653.75


G. Direct Unit Cost (E + F) 48,187.25
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 4,336.85
I. Contractor's Profit (CP) 8% of G 3,854.98
J. Value Added Tax (VAT) 12% of (G + H + I) 6,765.49
K. Total Unit Cost (G + H + I + J) 63,144.57

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 305(4) Bituminous Penetration Macadam Pavement (Emulsified Asphalt)


Unit of Measurement : m.t.
Output per hour : 0.30

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Laborer 3 1 61.44 184.32

Sub - Total for A 293.51


Name and Capacity No of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Asphalt Distributor, 10 ft. wide (5 tons) 1 1 936.00 936.00


b. Power Broom (20 m. wide) 1 1 130.54 130.54

Sub - Total for B 1,066.54


C. Total (A + B) 1,360.05
D. Output per hour = 0.300 m.t.
E. Direct Unit Cost (C ÷ D) 4,533.50
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Emulsified Asphalt SS-1 m.t. 1.05 44,000.00 46,200.00


(w/ 5% wastage)

Sub - Total for F 46,200.00


G. Direct Unit Cost (E + F) 50,733.50
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 4,566.01
I. Contractor's Profit (CP) 8% of G 4,058.68
J. Value Added Tax (VAT) 12% of (G + H + I) 7,122.98
K. Total Unit Cost (G + H + I + J) 66,481.18

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 306a Bituminous Road Mix Surface Course


Unit of Measurement : m.t.
Output per hour : 12.00 (12 m³)

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Skilled Laborer 1 1 79.70 79.70
c. Laborer 3 1 61.44 184.32

Sub - Total for A 373.21


Name and Capacity No of Units No. of Hours Hourly Rate Amount
B. Equipment
a. Road Grader w/ Scarifier, G710A 1 1 2,933.55 2,933.55
b. Tandem Steel Roller (10.1 m.t.), CC421 1 1 1,652.00 1,652.00
c. Pneumatic Tire Roller (10 m.t.) 1 1 553.00 553.00
d. Asphalt Distributor, 10 ft. wide (5 tons) 1 1 936.00 936.00
e. Water Truck (1000 gal.) 1 0.25 1,065.00 266.25
Minor Tools (10% of Labor) 37.32

Sub - Total for B 6,378.12


C. Total (A + B) 6,751.33
D. Output per hour = 12.0000 m.t.
E. Direct Unit Cost (C ÷ D) 562.61
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Crushed Gravel m.t. 1.15 406.25 467.19


b. MC Cut-back Asphalt (7%) m.t. 0.07 40,300.00 2,821.00
c. Hydrated Lime (0.75%) bag 0.30 180.00 54.00

0.0575(2.335)(1.05) = 0.141
0.0075(35.29) = 0.26, say 0.30

Sub - Total for F 3,342.19


G. Direct Unit Cost (E + F) 3,904.80
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 351.43
I. Contractor's Profit (CP) 8% of G 312.38
J. Value Added Tax (VAT) 12% of (G + H + I) 548.23
K. Total Unit Cost (G + H + I + J) 5,116.85

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 306b Bituminous Road Mix Surface Course


Unit of Measurement : m.t.
Output per hour : 12.00 (12 m³)

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Skilled Laborer 1 1 79.70 79.70
c. Laborer 3 1 61.44 184.32

Sub - Total for A 373.21


Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment
a. Road Grader w/ Scarifier, G710A 1 1 2,933.55 2,933.55
b. Tandem Steel Roller (10.1 m.t.), CC421 1 1 1,652.00 1,652.00
c. Pneumatic Tire Roller (10 m.t.) 1 1 553.00 553.00
d. Asphalt Distributor, 10 ft. wide (5 tons) 1 1 936.00 936.00
e. Water Truck (1000 gal.) 1 0.25 1,065.00 266.25
Minor Tools (10% of Labor) 37.32

Sub - Total for B 6,378.12


C. Total (A + B) 6,751.33
D. Output per hour = 12.0000 m.t.
E. Direct Unit Cost (C ÷ D) 562.61
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. Crushed Gravel m.t. 1.15 406.25 467.19


b. Emulsified Asphalt (10%) m.t. 0.10 44,000.00 4,400.00
c. Hydrated Lime (0.75%) bag 0.30 180.00 54.00

0.08(2.335)(1.05) = 0.196
0.0075(35.29) = 0.26, say 0.30

Sub - Total for F 4,921.19


G. Direct Unit Cost (E + F) 5,483.80
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 493.54
I. Contractor's Profit (CP) 8% of G 438.70
J. Value Added Tax (VAT) 12% of (G + H + I) 769.93
K. Total Unit Cost (G + H + I + J) 7,185.97

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 306(1) Aggregates for Bituminous Road Mix Surface Course
Unit of Measurement : m.t.
Output per hour : 12.00 (12 m³)

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Skilled Laborer 1 1 79.70 79.70
c. Laborer 3 1 61.44 184.32

Sub - Total for A 373.21


Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Road Grader w/ Scarifier, G710A 1 1 2,933.55 2,933.55


b. Tandem Steel Roller (10.1 m.t.), CC421 1 1 1,652.00 1,652.00
c. Pneumatic Tire Roller (10 m.t.) 1 1 553.00 553.00
d. Water Truck (1000 gal.) 1 0.25 1,065.00 266.25
Minor Tools (10% of Labor) 37.32

Sub - Total for B 5,442.12


C. Total (A + B) 5,815.33
D. Output per hour = 12.0000 m.t.
E. Direct Unit Cost (C ÷ D) 484.61
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. Crushed Gravel m.t. 1.15 406.25 467.19

Sub - Total for F 467.19


G. Direct Unit Cost (E + F) 951.80
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 85.66
I. Contractor's Profit (CP) 8% of G 76.14
J. Value Added Tax (VAT) 12% of (G + H + I) 133.63
K. Total Unit Cost (G + H + I + J) 1,247.24

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 306(2) Bituminous Material for Bituminous Road Mix Surface Course
Unit of Measurement : m.t.
Output per hour : 1.00

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Skilled Laborer 1 1 79.70 79.70
c. Laborer 3 1 61.44 184.32

Sub - Total for A 373.21


Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Asphalt Distributor, 10 ft. wide (5 tons) 1 1.00 936.00 936.00


Sub - Total for B 936.00
C. Total (A + B) 1,309.21
D. Output per hour = 1.0000 m.t.
E. Direct Unit Cost (C ÷ D) 1,309.21
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. MC Cut-back Asphalt m.t. 1.05 40,300.00 42,315.00

Sub - Total for F 42,315.00


G. Direct Unit Cost (E + F) 43,624.21
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 3,926.18
I. Contractor's Profit (CP) 8% of G 3,489.94
J. Value Added Tax (VAT) 12% of (G + H + I) 6,124.84
K. Total Unit Cost (G + H + I + J) 57,165.16

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 307 Bituminous Plant Mix Surface Course-General (50 mm. thick)
Unit of Measurement : sq.m.
Output per hour : 171.30

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Skilled Laborer 6 1 79.70 478.20
c. Laborer 12 1 61.44 737.28

Sub - Total for A 1,324.67


Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Asphalt Paver (80 Hp), NF220BIIVDM 1 1 1,833.00 1,833.00


b. Pneumatic Tire Roller (10 m.t.) 1 1 553.00 553.00
c. Tandem Steel Roller (10.1 m.t.), CC421 1 1 1,652.00 1,652.00
d. Dump Truck (10 cu.m.) 2 1 1,352.00 2,704.00
e. Asphalt Batch Plant ( 60-80 TPH) 1 1 1,214.73 1,214.73
f. Water Truck (1000 gal.) 1 1 1,065.00 1,065.00
g. Payloader (1.50 cu.m.), LX80-2C 1 1 1,733.00 1,733.00
Minor Tools (10% of Labor) 132.47

Sub - Total for B 10,887.20


C. Total (A + B) 12,211.87
D. Output per hour = 171.300 sq.m.
E. Direct Unit Cost (C ÷ D) 71.29
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. Bituminous Material (8%) m.t 0.00981 44,000.00 431.64


b. Aggregates (93%) cu.m. 0.0488 650.00 31.72
c. Mineral Filler (7%) bag 0.13 240.56 31.27
(w/ 5% wastage)

0.065(2.335)(0.05)(1.05) = 0.00797

Sub - Total for F 494.63


G. Direct Unit Cost (E + F) 565.92
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 50.93
I. Contractor's Profit (CP) 8% of G 45.27
J. Value Added Tax (VAT) 12% of (G + H + I) 79.46
K. Total Unit Cost (G + H + I + J) 741.58

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 308a Cold Asphalt Plant Mix (50 mm. thick)
Unit of Measurement : sq.m.
Output per hour : 171.30

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Skilled Laborer 6 1 79.70 478.20
c. Laborer 12 1 61.44 737.28

Sub - Total for A 1,324.67


Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Asphalt Paver (80 Hp), NF220BIIVDM 1 1 1,833.00 1,833.00


b. Pneumatic Tire Roller (10 m.t.) 1 1 553.00 553.00
c. Tandem Steel Roller (10.1 m.t.), CC421 1 1 1,652.00 1,652.00
d. Dump Truck (10 cu.m.) 2 1 1,352.00 2,704.00
e. Asphalt Batch Plant ( 60-80 TPH) 1 1 1,214.73 1,214.73
f. Water Truck (1000 gal.) 1 1 1,065.00 1,065.00
g. Payloader (1.50 cu.m.), LX80-2C 1 1 1,733.00 1,733.00
Minor Tools (10% of Labor) 132.47

Sub - Total for B 10,887.20


C. Total (A + B) 12,211.87
D. Output per hour = 171.300 sq.m.
E. Direct Unit Cost (C ÷ D) 71.29
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. Emulsified Asphalt (10%) m.t 0.01226 44,000.00 539.44


b. Aggregates (93%) cu.m. 0.0488 650.00 31.72
c. Mineral Filler (7%) bag 0.13 240.56 31.27
(w/ 5% wastage)

0.08(2.335)(0.05)(1.05) = 0.00981

Sub - Total for F 602.43


G. Direct Unit Cost (E + F) 673.72
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 60.63
I. Contractor's Profit (CP) 8% of G 53.90
J. Value Added Tax (VAT) 12% of (G + H + I) 94.59
K. Total Unit Cost (G + H + I + J) 882.85

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 308b Cold Asphalt Plant Mix (50 mm. thick)
Unit of Measurement : sq.m.
Output per hour : 171.30

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Skilled Laborer 6 1 79.70 478.20
c. Laborer 12 1 61.44 737.28

Sub - Total for A 1,324.67


Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Asphalt Paver (80 Hp), NF220BIIVDM 1 1 1,833.00 1,833.00


b. Pneumatic Tire Roller (10 m.t.) 1 1 553.00 553.00
c. Tandem Steel Roller (10.1 m.t.), CC421 1 1 1,652.00 1,652.00
d. Dump Truck (10 cu.m.) 2 1 1,352.00 2,704.00
e. Asphalt Batch Plant ( 60-80 TPH) 1 1 1,214.73 1,214.73
f. Water Truck (1000 gal.) 1 1 1,065.00 1,065.00
g. Payloader (1.50 cu.m.), LX80-2C 1 1 1,733.00 1,733.00
Minor Tools (10% of Labor) 132.47

Sub - Total for B 10,887.20


C. Total (A + B) 12,211.87
D. Output per hour = 171.300 sq.m.
E. Direct Unit Cost (C ÷ D) 71.29
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. MC - 70 Cut-back Asphalt (7%) m.t 0.00858 40,300.00 345.77


b. Aggregates (93%) cu.m. 0.0488 650.00 31.72
c. Mineral Filler (7%) bag 0.13 240.56 31.27
(w/ 5% wastage)

0.0575(2.335)(0.05)(1.05) = 0.00705

Sub - Total for F 408.77


G. Direct Unit Cost (E + F) 480.06
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 43.21
I. Contractor's Profit (CP) 8% of G 38.40
J. Value Added Tax (VAT) 12% of (G + H + I) 67.40
K. Total Unit Cost (G + H + I + J) 629.07

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 309 Bituminous Plant Mix (Stockpile Maintenance Mixture)


Unit of Measurement : sq.m.
Output per hour : 171.30

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Skilled Laborer 6 1 79.70 478.20
c. Laborer 12 1 61.44 737.28

Sub - Total for A 1,324.67


Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Dump Truck (10 cu.m.) 2 1 1,352.00 2,704.00


b. Asphalt Batch Plant ( 60-80 TPH) 1 1 1,214.73 1,214.73
c. Water Truck (1000 gal.) 1 1 1,065.00 1,065.00
d. Payloader (1.50 cu.m.), LX80-2C 1 1 1,733.00 1,733.00
Minor Tools (10% of Labor) 132.47
Sub - Total for B 6,849.20
C. Total (A + B) 8,173.87
D. Output per hour = 171.300 sq.m.
E. Direct Unit Cost (C ÷ D) 47.72
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. MC - 70 Cut-back Asphalt (10%) m.t 0.00981 40,300.00 395.34


b. Aggregates (93%) cu.m. 0.0488 650.00 31.72
c. Mineral Filler (7%) bag 0.13 240.56 31.27
(w/ 5% wastage)

0.07(2.335)(0.05)(1.05) = 0.00858

Sub - Total for F 458.34


G. Direct Unit Cost (E + F) 506.05
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 45.54
I. Contractor's Profit (CP) 8% of G 40.48
J. Value Added Tax (VAT) 12% of (G + H + I) 71.05
K. Total Unit Cost (G + H + I + J) 663.13

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 310(a1) Bituminous Concrete Surface Course


Unit of Measurement : sq.m.
Output per hour : 285.51

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Skilled Laborer 4 1 79.70 318.80
c. Laborer 8 1 61.44 491.52

Sub - Total for A 919.51


Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Asphalt Paver (80 Hp) 1 1 1,833.00 1,833.00


b. Pneumatic Tire Roller (10 m.t.) 1 1 553.00 553.00
c. Tandem Steel Roller (10.1 m.t.), CC421 1 1 1,652.00 1,652.00
d. Water Truck (1000 gal.) 1 1 1,065.00 1,065.00
Minor Tools (10% of Labor) 91.95
Sub - Total for B 5,194.95
C. Total (A + B) 6,114.46
D. Output per hour = 285.51 sq.m.
E. Direct Unit Cost (C ÷ D) 21.42
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. Bituminous Concrete Surface Course m.t. 0.074 4,500.00 333.00


thickness = 30 mm. (w/ 5% wastage)

0.03(2.335)(1.05) = 0.074

Sub - Total for F 333.00


G. Direct Unit Cost (E + F) 354.42
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 31.90
I. Contractor's Profit (CP) 8% of G 28.35
J. Value Added Tax (VAT) 12% of (G + H + I) 49.76
K. Total Unit Cost (G + H + I + J) 464.43

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 310(a2) Bituminous Concrete Surface Course


Unit of Measurement : sq.m.
Output per hour : 214.13

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Skilled Laborer 4 1 79.70 318.80
c. Laborer 8 1 61.44 491.52

Sub - Total for A 919.51


Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Asphalt Paver (80 Hp) 1 1 1,833.00 1,833.00


b. Pneumatic Tire Roller (10 m.t.) 1 1 553.00 553.00
c. Tandem Steel Roller (10.1 m.t.), CC421 1 1 1,652.00 1,652.00
d. Water Truck (1000 gal.) 1 1 1,065.00 1,065.00
Minor Tools (10% of Labor) 91.95
Sub - Total for B 5,194.95
C. Total (A + B) 6,114.46
D. Output per hour = 214.13 sq.m.
E. Direct Unit Cost (C ÷ D) 28.55
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. Bituminous Concrete Surface Course m.t. 0.098 4,500.00 441.00


thickness = 40 mm. (w/ 5% wastage)

0.04(2.335)(1.05) = 0.098

Sub - Total for F 441.00


G. Direct Unit Cost (E + F) 469.55
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 42.26
I. Contractor's Profit (CP) 8% of G 37.56
J. Value Added Tax (VAT) 12% of (G + H + I) 65.93
K. Total Unit Cost (G + H + I + J) 615.30

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 310(a3) Bituminous Concrete Surface Course


Unit of Measurement : sq.m.
Output per hour : 171.30

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Skilled Laborer 4 1 79.70 318.80
c. Laborer 8 1 61.44 491.52

Sub - Total for A 919.51


Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Asphalt Paver (80 Hp) 1 1 1,833.00 1,833.00


b. Pneumatic Tire Roller (10 m.t.) 1 1 553.00 553.00
c. Tandem Steel Roller (10.1 m.t.), CC421 1 1 1,652.00 1,652.00
d. Water Truck (1000 gal.) 1 1 1,065.00 1,065.00
Minor Tools (10% of Labor) 91.95
Sub - Total for B 5,194.95
C. Total (A + B) 6,114.46
D. Output per hour = 171.300 sq.m.
E. Direct Unit Cost (C ÷ D) 35.69
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. Bituminous Concrete Surface Course m.t. 0.123 4,500.00 553.50


thickness = 50 mm. (w/ 5% wastage)

0.05(2.335)(1.05) = 0.123

Sub - Total for F 553.50


G. Direct Unit Cost (E + F) 589.19
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 53.03
I. Contractor's Profit (CP) 8% of G 47.14
J. Value Added Tax (VAT) 12% of (G + H + I) 82.72
K. Total Unit Cost (G + H + I + J) 772.08

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 310(b1) Bituminous Concrete Surface Course (30 mm. thick)
Unit of Measurement : sq.m.
Output per hour : 285.51

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Skilled Laborer 6 1 79.70 478.20
c. Laborer 12 1 61.44 737.28

Sub - Total for A 1,324.67


Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Asphalt Paver (80 Hp), NF220BIIVDM 1 1 1,833.00 1,833.00


b. Pneumatic Tire Roller (10 m.t.) 1 1 553.00 553.00
c. Tandem Steel Roller (10.1 m.t.), CC421 1 1 1,652.00 1,652.00
d. Dump Truck (10 cu.m.) 2 1 1,352.00 2,704.00
e. Asphalt Batch Plant ( 60-80 TPH) 1 1 1,214.73 1,214.73
f. Water Truck (1000 gal.) 1 1 1,065.00 1,065.00
g. Payloader (1.50 cu.m.), LX80-2C 1 1 1,733.00 1,733.00
Minor Tools (10% of Labor) 132.47
Sub - Total for B 10,887.20
C. Total (A + B) 12,211.87
D. Output per hour = 285.51 sq.m.
E. Direct Unit Cost (C ÷ D) 42.77
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. Asphalt Cement (8%) m.t 0.00588 50,775.00 298.56


b. Aggregates (93%) cu.m. 0.0488 650.00 31.72
c. Mineral Filler (7%) bag 0.13 240.56 31.27
(w/ 5% wastage)

0.08(2.335)(0.03)(1.05) = 0.00588

Sub - Total for F 361.55


G. Direct Unit Cost (E + F) 404.32
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 36.39
I. Contractor's Profit (CP) 8% of G 32.35
J. Value Added Tax (VAT) 12% of (G + H + I) 56.77
K. Total Unit Cost (G + H + I + J) 529.82

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 310(b2) Bituminous Concrete Surface Course (40 mm. thick)
Unit of Measurement : sq.m.
Output per hour : 214.13

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Skilled Laborer 6 1 79.70 478.20
c. Laborer 12 1 61.44 737.28

Sub - Total for A 1,324.67


Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Asphalt Paver (80 Hp), NF220BIIVDM 1 1 1,833.00 1,833.00


b. Pneumatic Tire Roller (10 m.t.) 1 1 553.00 553.00
c. Tandem Steel Roller (10.1 m.t.), CC421 1 1 1,652.00 1,652.00
d. Dump Truck (10 cu.m.) 2 1 1,352.00 2,704.00
e. Asphalt Batch Plant ( 60-80 TPH) 1 1 1,214.73 1,214.73
f. Water Truck (1000 gal.) 1 1 1,065.00 1,065.00
g. Payloader (1.50 cu.m.), LX80-2C 1 1 1,733.00 1,733.00
Minor Tools (10% of Labor) 132.47
Sub - Total for B 10,887.20
C. Total (A + B) 12,211.87
D. Output per hour = 214.13 sq.m.
E. Direct Unit Cost (C ÷ D) 57.03
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. Asphalt Cement (8%) m.t 0.00785 50,775.00 398.58


b. Aggregates (93%) cu.m. 0.0488 650.00 31.72
c. Mineral Filler (7%) bag 0.13 240.56 31.27
(w/ 5% wastage)

0.08(2.335)(0.04)(1.05) = 0.00785

Sub - Total for F 461.58


G. Direct Unit Cost (E + F) 518.61
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 46.67
I. Contractor's Profit (CP) 8% of G 41.49
J. Value Added Tax (VAT) 12% of (G + H + I) 72.81
K. Total Unit Cost (G + H + I + J) 679.58

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 310(b3) Bituminous Concrete Surface Course (50 mm. thick)
Unit of Measurement : sq.m.
Output per hour : 171.30

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Skilled Laborer 6 1 79.70 478.20
c. Laborer 12 1 61.44 737.28

Sub - Total for A 1,324.67


Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Asphalt Paver (80 Hp), NF220BIIVDM 1 1 1,833.00 1,833.00


b. Pneumatic Tire Roller (10 m.t.) 1 1 553.00 553.00
c. Tandem Steel Roller (10.1 m.t.), CC421 1 1 1,652.00 1,652.00
d. Dump Truck (10 cu.m.) 2 1 1,352.00 2,704.00
e. Asphalt Batch Plant ( 60-80 TPH) 1 1 1,214.73 1,214.73
f. Water Truck (1000 gal.) 1 1 1,065.00 1,065.00
g. Payloader (1.50 cu.m.), LX80-2C 1 1 1,733.00 1,733.00
Minor Tools (10% of Labor) 132.47
Sub - Total for B 10,887.20
C. Total (A + B) 12,211.87
D. Output per hour = 171.300 sq.m.
E. Direct Unit Cost (C ÷ D) 71.29
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. Asphalt Cement (8%) m.t 0.00981 50,775.00 498.10


b. Aggregates (93%) cu.m. 0.0488 650.00 31.72
c. Mineral Filler (7%) bag 0.13 240.56 31.27
(w/ 5% wastage)

0.065(2.335)(0.05)(1.05) = 0.00797

Sub - Total for F 561.10


G. Direct Unit Cost (E + F) 632.38
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 56.91
I. Contractor's Profit (CP) 8% of G 50.59
J. Value Added Tax (VAT) 12% of (G + H + I) 88.79
K. Total Unit Cost (G + H + I + J) 828.68

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 311(1)a PCC Pavement (Plain) - Conventional Method, 150 mm. thk.
Unit of Measurement : sq.m.
Output per hour : 107.33

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Skilled Laborer 4 1 79.70 318.80
c. Laborer 12 1 61.44 737.28

Sub - Total for A 1,165.27


Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Transit Mixer (5 cu.m.) 4 1 1,279.00 5,116.00


b. Concrete Vibrator 2 1 148.88 297.76
c. Batching Plant (30 cu.m.) 1 1 1,208.03 1,208.03
d. Payloader (1.50 cu.m.), LX80-2C 1 1 1,733.00 1,733.00
e. Concrete Screeder (5.5 Hp) 1 1 545.00 545.00
f. Water Truck (1000 gal.) 1 1 1,065.00 1,065.00
g. Concrete Saw, Blade Ø 14" (7.5 Hp) 1 1 167.38 167.38
h. Bar Cutter, Single Phase 1 0.10 219.75 21.98
Minor Tools (5% of Labor) 58.26
Sub - Total for B 10,212.41
C. Total (A + B) 11,377.68
D. Output per hour = 107.33 sq.m.
E. Direct Unit Cost (C ÷ D) 106.01
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. Reinforcing Steel Bar kg. 0.33 40.00 13.20


b. Curing Compound lit. 0.29 28.00 8.12
c. Asphalt Sealant lit. 0.12 44.00 5.28
d. Steel Forms (Rental) l.m. 0.46 50.00 23.00
e. Sand cu.m. 0.0825 850.00 70.13
f. Gravel cu.m. 0.15 650.00 97.50
g. Cement bag 1.43 220.00 314.60
h. Concrete Saw (diamond blade 14") pc. 0.00015 8,000.00 1.20
i. Pipe Sleeve, 1" dia. l.m. 0.0078 34.33 0.27
j. Grease/Tar lit. 0.0014 300.00 0.42

Sub - Total for F 533.71


G. Direct Unit Cost (E + F) 639.72
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 57.57
I. Contractor's Profit (CP) 8% of G 51.18
J. Value Added Tax (VAT) 12% of (G + H + I) 89.82
K. Total Unit Cost (G + H + I + J) 838.29

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 311(1)a PCC Pavement (Plain) - Conventional Method, 150 mm. thk.
Unit of Measurement : sq.m.
Output per hour : 107.33

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Skilled Laborer 4 1 79.70 318.80
c. Laborer 12 1 61.44 737.28

Sub - Total for A 1,165.27


Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Transit Mixer (5 cu.m.) 4 1 1,279.00 5,116.00


b. Concrete Vibrator 2 1 148.88 297.76
c. Batching Plant (30 cu.m.) 1 1 1,208.03 1,208.03
d. Payloader (1.50 cu.m.), LX80-2C 1 1 1,733.00 1,733.00
e. Concrete Screeder (5.5 Hp) 1 1 545.00 545.00
f. Water Truck (1000 gal.) 1 1 1,065.00 1,065.00
g. Concrete Saw, Blade Ø 14" (7.5 Hp) 1 1 167.38 167.38
h. Bar Cutter, Single Phase, 25 mm. 1 0.10 219.75 21.98

Sub - Total for B 10,154.15


C. Total (A + B) 11,319.42
D. Output per hour = 107.33 sq.m.
E. Direct Unit Cost (C ÷ D) 105.46
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. Reinforcing Steel Bar kg. 0.33 40.00 13.20


b. Curing Compound lit. 0.29 28.00 8.12
c. Asphalt Sealant lit. 0.12 44.00 5.28
d. Forms l.m. 0.46 250.00 115.00
e. Sand cu.m. 0.0825 850.00 70.13
f. Gravel cu.m. 0.15 650.00 97.50
g. Cement bag 1.43 220.00 314.60
h. Concrete Saw (diamond blade 14") pc. 0.00015 8,000.00 1.20

Sub - Total for F 625.03


G. Direct Unit Cost (E + F) 730.49
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 65.74
I. Contractor's Profit (CP) 8% of G 58.44
J. Value Added Tax (VAT) 12% of (G + H + I) 102.56
K. Total Unit Cost (G + H + I + J) 957.23

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 311(1)a PCC Pavement (Plain) - Conventional Method, 200 mm. thk.
Unit of Measurement : sq.m.
Output per hour : 80.50

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Skilled Laborer 4 1 79.70 318.80
c. Laborer 12 1 61.44 737.28

Sub - Total for A 1,165.27


Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Transit Mixer (5 cu.m.) 4 1 1,279.00 5,116.00


b. Concrete Vibrator 2 1 148.88 297.76
c. Batching Plant (30 cu.m.) 1 1 1,208.03 1,208.03
d. Payloader (1.50 cu.m.), LX80-2C 1 1 1,733.00 1,733.00
e. Concrete Screeder (5.5 Hp) 1 1 545.00 545.00
f. Water Truck (1000 gal.) 1 1 1,065.00 1,065.00
g. Concrete Saw, Blade Ø 14" (7.5 Hp) 1 1 167.38 167.38
h. Bar Cutter, Single Phase 1 0.10 219.75 21.98
Minor Tools (5% of Labor) 58.26

Sub - Total for B 10,212.41


C. Total (A + B) 11,377.68
D. Output per hour = 80.500 sq.m.
E. Direct Unit Cost (C ÷ D) 141.34
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. Reinforcing Steel Bar kg. 0.39 40.00 15.60


b. Curing Compound lit. 0.29 28.00 8.12
c. Asphalt Sealant lit. 0.12 44.00 5.28
d. Steel Forms (Rental) l.m. 0.46 50.00 23.00
e. Sand cu.m. 0.110 850.00 93.50
f. Gravel cu.m. 0.20 650.00 130.00
g. Cement bag 1.90 220.00 418.00
h. Concrete Saw (diamond blade 14") pc. 0.00015 8,000.00 1.20
i. Pipe Sleeve, 1 1/2" dia. l.m. 0.0086 67.67 0.58
j. Grease/Tar lit. 0.0055 300.00 1.65

Sub - Total for F 696.93


G. Direct Unit Cost (E + F) 838.27
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 75.44
I. Contractor's Profit (CP) 8% of G 67.06
J. Value Added Tax (VAT) 12% of (G + H + I) 117.69
K. Total Unit Cost (G + H + I + J) 1,098.47

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 311(1)a PCC Pavement (Plain) - Conventional Method, 230 mm. thk.
Unit of Measurement : sq.m.
Output per hour : 70.00

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Skilled Laborer 4 1 79.70 318.80
c. Laborer 12 1 61.44 737.28

Sub - Total for A 1,165.27


Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Transit Mixer (5 cu.m.) 4 1 1,279.00 5,116.00


b. Concrete Vibrator 2 1 148.88 297.76
c. Batching Plant (30 cu.m.) 1 1 1,208.03 1,208.03
d. Payloader (1.50 cu.m.), LX80-2C 1 1 1,733.00 1,733.00
e. Concrete Screeder (5.5 Hp) 1 1 545.00 545.00
f. Water Truck (1000 gal.) 1 1 1,065.00 1,065.00
g. Concrete Saw, Blade Ø 14" (7.5 Hp) 1 1 167.38 167.38
h. Bar Cutter, Single Phase 1 0.10 219.75 21.98
Minor Tools (5% of Labor) 58.26

Sub - Total for B 10,212.41


C. Total (A + B) 11,377.68
D. Output per hour = 70.0000 sq.m.
E. Direct Unit Cost (C ÷ D) 162.54
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. Reinforcing Steel Bar kg. 0.43 40.00 17.20


b. Curing Compound lit. 0.29 28.00 8.12
c. Asphalt Sealant lit. 0.12 44.00 5.28
d. Steel Forms (Rental) l.m. 0.46 50.00 23.00
e. Sand cu.m. 0.1265 850.00 107.53
f. Gravel cu.m. 0.23 650.00 149.50
g. Cement bag 2.19 220.00 481.80
h. Concrete Saw (diamond blade 14") pc. 0.00015 8,000.00 1.20
i. Pipe Sleeve, 2" dia. l.m. 0.0071 97.00 0.69
j. Grease/Tar lit. 0.0022 300.00 0.66

Sub - Total for F 794.97


G. Direct Unit Cost (E + F) 957.51
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 86.18
I. Contractor's Profit (CP) 8% of G 76.60
J. Value Added Tax (VAT) 12% of (G + H + I) 134.43
K. Total Unit Cost (G + H + I + J) 1,254.72

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 311(1)a PCC Pavement (Plain) - Conventional Method, 250 mm. thk.
Unit of Measurement : sq.m.
Output per hour : 64.40

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Skilled Laborer 4 1 79.70 318.80
c. Laborer 12 1 61.44 737.28

Sub - Total for A 1,165.27


Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Transit Mixer (5 cu.m.) 4 1 1,279.00 5,116.00


b. Concrete Vibrator 2 1 148.88 297.76
c. Batching Plant (30 cu.m.) 1 1 1,208.03 1,208.03
d. Payloader (1.50 cu.m.), LX80-2C 1 1 1,733.00 1,733.00
e. Concrete Screeder (5.5 Hp) 1 1 545.00 545.00
f. Water Truck (1000 gal.) 1 1 1,065.00 1,065.00
g. Concrete Saw, Blade Ø 14" (7.5 Hp) 1 1 167.38 167.38
h. Bar Cutter, Single Phase 1 0.10 219.75 21.98
Minor Tools (5% of Labor) 58.26

Sub - Total for B 10,212.41


C. Total (A + B) 11,377.68
D. Output per hour = 64.400 sq.m.
E. Direct Unit Cost (C ÷ D) 176.67
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. Reinforcing Steel Bar kg. 0.45 40.00 18.00


b. Curing Compound lit. 0.29 28.00 8.12
c. Asphalt Sealant lit. 0.15 44.00 6.60
d. Steel Forms (Rental) l.m. 0.46 50.00 23.00
e. Sand cu.m. 0.1375 850.00 116.88
f. Gravel cu.m. 0.25 650.00 162.50
g. Cement bag 2.38 220.00 523.60
h. Concrete Saw (diamond blade 14") pc. 0.00015 8,000.00 1.20
i. Pipe Sleeve, 2" dia. l.m. 0.0078 97.00 0.76
j. Grease/Tar lit. 0.0025 300.00 0.75

Sub - Total for F 861.40


G. Direct Unit Cost (E + F) 1,038.07
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 93.43
I. Contractor's Profit (CP) 8% of G 83.05
J. Value Added Tax (VAT) 12% of (G + H + I) 145.75
K. Total Unit Cost (G + H + I + J) 1,360.29

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 311(1)a PCC Pavement (Plain) - Conventional Method, 280 mm. thk.
Unit of Measurement : sq.m.
Output per hour : 57.50

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Skilled Laborer 4 1 79.70 318.80
c. Laborer 12 1 61.44 737.28

Sub - Total for A 1,165.27


Name and Capacity No of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Transit Mixer (5 cu.m.) 4 1 1,279.00 5,116.00


b. Concrete Vibrator 2 1 148.88 297.76
c. Batching Plant (30 cu.m.) 1 1 1,208.03 1,208.03
d. Payloader (1.50 cu.m.), LX80-2C 1 1 1,733.00 1,733.00
e. Concrete Screeder (5.5 Hp) 1 1 545.00 545.00
f. Water Truck (1000 gal.) 1 1 1,065.00 1,065.00
g. Concrete Saw, Blade Ø 14" (7.5 Hp) 1 1 167.38 167.38
h. Bar Cutter, Single Phase 1 0.10 219.75 21.98
Minor Tools (5% of Labor) 58.26

Sub - Total for B 10,212.41


C. Total (A + B) 11,377.68
D. Output per hour = 57.500 sq.m.
E. Direct Unit Cost (C ÷ D) 197.87
Name and Specification Unit Quantity Unit Cost Amount
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. Reinforcing Steel Bar kg. 0.50 40.00 20.00


b. Curing Compound lit. 0.29 28.00 8.12
c. Asphalt Sealant lit. 0.17 44.00 7.48
d. Steel Forms (Rental) l.m. 0.46 50.00 23.00
e. Sand cu.m. 0.154 850.00 130.90
f. Gravel cu.m. 0.28 650.00 182.00
g. Cement bag 2.66 220.00 585.20
h. Concrete Saw (diamond blade 14") pc. 0.00015 8,000.00 1.20
i. Pipe Sleeve, 2" dia. l.m. 0.0078 97.00 0.76
j. Grease/Tar lit. 0.0077 300.00 2.31

Sub - Total for F 960.97


G. Direct Unit Cost (E + F) 1,158.84
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 104.30
I. Contractor's Profit (CP) 8% of G 92.71
J. Value Added Tax (VAT) 12% of (G + H + I) 162.70
K. Total Unit Cost (G + H + I + J) 1,518.54

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 311(1)a PCC Pavement (Plain) - Conventional Method, 300 mm. thk.
Unit of Measurement : sq.m.
Output per hour : 53.67

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Skilled Laborer 4 1 79.70 318.80
c. Laborer 12 1 61.44 737.28

Sub - Total for A 1,165.27


Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Transit Mixer (5 cu.m.) 4 1 1,279.00 5,116.00


b. Concrete Vibrator 2 1 148.88 297.76
c. Batching Plant (30 cu.m.) 1 1 1,208.03 1,208.03
d. Payloader (1.50 cu.m.), LX80-2C 1 1 1,733.00 1,733.00
e. Concrete Screeder (5.5 Hp) 1 1 545.00 545.00
f. Water Truck (1000 gal.) 1 1 1,065.00 1,065.00
g. Concrete Saw, Blade Ø 14" (7.5 Hp) 1 1 167.38 167.38
h. Bar Cutter, Single Phase 1 0.10 219.75 21.98
Minor Tools (5% of Labor) 58.26

Sub - Total for B 10,212.41


C. Total (A + B) 11,377.68
D. Output per hour = 53.67 sq.m.
E. Direct Unit Cost (C ÷ D) 211.99
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Reinforcing Steel Bar kg. 0.55 40.00 22.00


b. Curing Compound lit. 0.29 28.00 8.12
c. Asphalt Sealant lit. 0.18 44.00 7.92
d. Steel Forms (Rental) l.m. 0.46 50.00 23.00
e. Sand cu.m. 0.165 850.00 140.25
f. Gravel cu.m. 0.30 650.00 195.00
g. Cement bag 2.85 220.00 627.00
h. Concrete Saw (diamond blade 14") pc. 0.00015 8,000.00 1.20
i. Pipe Sleeve, 2" dia. l.m. 0.0094 97.00 0.91
j. Grease/Tar lit. 0.0093 300.00 2.79

Sub - Total for F 1,028.19


G. Direct Unit Cost (E + F) 1,240.19
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 111.62
I. Contractor's Profit (CP) 8% of G 99.21
J. Value Added Tax (VAT) 12% of (G + H + I) 174.12
K. Total Unit Cost (G + H + I + J) 1,625.14

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 311(1)b PCC Pavement (Plain) - Using Concrete Paver, 230 mm. thk.
Unit of Measurement : sq.m.
Output per hour : 90.00

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Skilled Laborer 4 1 79.70 318.80
c. Laborer 10 1 61.44 614.40

Sub - Total for A 1,042.39


Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Batching Plant (30 cu.m.) 1 1 1,208.03 1,208.03


b. Concrete Paver, GP-2000 Slipform 1 1 6,765.00 6,765.00
c. Transit Mixer (5 cu.m.) 4 1 1,279.00 5,116.00
d. Payloader (1.50 cu.m.), LX80-2C 1 1 1,733.00 1,733.00
e. Water Truck (1000 gal.) 1 1 1,065.00 1,065.00
f. Concrete Saw, Blade Ø 14" (7.5 Hp) 1 1 167.38 167.38
g. Concrete Vibrator 1 0.10 148.88 14.89
h. Bar Cutter, Single Phase 1 0.10 219.75 21.98

Sub - Total for B 16,091.27


C. Total (A + B) 17,133.66
D. Output per hour = 90.0000 sq.m.
E. Direct Unit Cost (C ÷ D) 190.37
Name and Specification Unit Quantity Unit Cost Amount

F. Materials
a. Reinforcing Steel Bar kg. 0.43 40.00 17.20
b. Curing Compound lit. 0.29 28.00 8.12
c. Asphalt Sealant lit. 0.12 44.00 5.28
d. Sand cu.m. 0.1265 850.00 107.53
e. Gravel cu.m. 0.23 650.00 149.50
f. Cement bag 2.19 220.00 481.80
g. Concrete Saw (diamond blade 14") pc. 0.00015 8,000.00 1.20
h. Pipe Sleeve, 2" dia. l.m. 0.0071 97.00 0.69
i. Grease/Tar lit. 0.0022 300.00 0.66

Sub - Total for F 771.97


G. Direct Unit Cost (E + F) 962.35
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 86.61
I. Contractor's Profit (CP) 8% of G 76.99
J. Value Added Tax (VAT) 12% of (G + H + I) 135.11
K. Total Unit Cost (G + H + I + J) 1,261.06

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 311(1)b PCC Pavement (Plain) - Using Concrete Paver, 250 mm. thk.
Unit of Measurement : sq.m.
Output per hour : 82.80

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Skilled Laborer 4 1 79.70 318.80
c. Laborer 10 1 61.44 614.40

Sub - Total for A 1,042.39


Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Batching Plant (30 cu.m.) 1 1 1,208.03 1,208.03


b. Concrete Paver, GP-2000 Slipform 1 1 6,765.00 6,765.00
c. Transit Mixer (5 cu.m.) 4 1 1,279.00 5,116.00
d. Payloader (1.50 cu.m.), LX80-2C 1 1 1,733.00 1,733.00
e. Water Truck (1000 gal.) 1 1 1,065.00 1,065.00
f. Concrete Saw, Blade Ø 14" (7.5 Hp) 1 1 167.38 167.38
g. Concrete Vibrator 1 0.10 148.88 14.89
h. Bar Cutter, Single Phase 1 0.10 219.75 21.98

Sub - Total for B 16,091.27


C. Total (A + B) 17,133.66
D. Output per hour = 82.800 sq.m.
E. Direct Unit Cost (C ÷ D) 206.93
Name and Specification Unit Quantity Unit Cost Amount

F. Materials
a. Reinforcing Steel Bar kg. 0.45 40.00 18.00
b. Curing Compound lit. 0.29 28.00 8.12
c. Asphalt Sealant lit. 0.15 44.00 6.60
d. Sand cu.m. 0.1375 850.00 116.88
e. Gravel cu.m. 0.25 650.00 162.50
f. Cement bag 2.38 220.00 523.60
g. Concrete Saw (diamond blade 14") pc. 0.00015 8,000.00 1.20
h. Pipe Sleeve, 2" dia. l.m. 0.0078 97.00 0.76
i. Grease/Tar lit. 0.0025 300.00 0.75

Sub - Total for F 838.40


G. Direct Unit Cost (E + F) 1,045.33
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 94.08
I. Contractor's Profit (CP) 8% of G 83.63
J. Value Added Tax (VAT) 12% of (G + H + I) 146.76
K. Total Unit Cost (G + H + I + J) 1,369.80

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 311(1)b PCC Pavement (Plain) - Using Concrete Paver, 280 mm. thk.
Unit of Measurement : sq.m.
Output per hour : 73.93

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Skilled Laborer 4 1 79.70 318.80
c. Laborer 10 1 61.44 614.40

Sub - Total for A 1,042.39


Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Batching Plant (30 cu.m.) 1 1 1,208.03 1,208.03


b. Concrete Paver, GP-2000 Slipform 1 1 6,765.00 6,765.00
c. Transit Mixer (5 cu.m.) 4 1 1,279.00 5,116.00
d. Payloader (1.50 cu.m.), LX80-2C 1 1 1,733.00 1,733.00
e. Water Truck (1000 gal.) 1 1 1,065.00 1,065.00
f. Concrete Saw, Blade Ø 14" (7.5 Hp) 1 1 167.38 167.38
g. Concrete Vibrator 1 0.10 148.88 14.89
h. Bar Cutter, Single Phase 1 0.10 219.75 21.98

Sub - Total for B 16,091.27


C. Total (A + B) 17,133.66
D. Output per hour = 73.93 sq.m.
E. Direct Unit Cost (C ÷ D) 231.76
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. Reinforcing Steel Bar kg. 0.50 40.00 20.00


b. Curing Compound lit. 0.29 28.00 8.12
c. Asphalt Sealant lit. 0.17 44.00 7.48
d. Sand cu.m. 0.154 850.00 130.90
e. Gravel cu.m. 0.28 650.00 182.00
f. Cement bag 2.66 220.00 585.20
g. Concrete Saw (diamond blade 14") pc. 0.00015 8,000.00 1.20
h. Pipe Sleeve, 2" dia. l.m. 0.0078 97.00 0.76
i. Grease/Tar lit. 0.0077 300.00 2.31

Sub - Total for F 937.97


G. Direct Unit Cost (E + F) 1,169.72
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 105.27
I. Contractor's Profit (CP) 8% of G 93.58
J. Value Added Tax (VAT) 12% of (G + H + I) 164.23
K. Total Unit Cost (G + H + I + J) 1,532.80

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 311(1)b PCC Pavement (Plain) - Using Concrete Paver, 300 mm. thk.
Unit of Measurement : sq.m.
Output per hour : 69.00

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Skilled Laborer 4 1 79.70 318.80
c. Laborer 10 1 61.44 614.40

Sub - Total for A 1,042.39


Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Batching Plant (30 cu.m.) 1 1 1,208.03 1,208.03


b. Concrete Paver, GP-2000 Slipform 1 1 6,765.00 6,765.00
c. Transit Mixer (5 cu.m.) 4 1 1,279.00 5,116.00
d. Payloader (1.50 cu.m.), LX80-2C 1 1 1,733.00 1,733.00
e. Water Truck (1000 gal.) 1 1 1,065.00 1,065.00
f. Concrete Saw, Blade Ø 14" (7.5 Hp) 1 1 167.38 167.38
g. Concrete Vibrator 1 0.10 148.88 14.89
h. Bar Cutter, Single Phase 1 0.10 219.75 21.98

Sub - Total for B 16,091.27


C. Total (A + B) 17,133.66
D. Output per hour = 69.0000 sq.m.
E. Direct Unit Cost (C ÷ D) 248.31
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. Reinforcing Steel Bar kg. 0.55 40.00 22.00


b. Curing Compound lit. 0.29 28.00 8.12
c. Asphalt Sealant lit. 0.18 44.00 7.92
d. Sand cu.m. 0.165 850.00 140.25
e. Gravel cu.m. 0.30 650.00 195.00
f. Cement bag 2.85 220.00 627.00
g. Concrete Saw (diamond blade 14") pc. 0.00015 8,000.00 1.20
h. Pipe Sleeve, 2" dia. l.m. 0.0094 97.00 0.91
i. Grease/Tar lit. 0.0093 300.00 2.79

Sub - Total for F 1,005.19


G. Direct Unit Cost (E + F) 1,253.51
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 112.82
I. Contractor's Profit (CP) 8% of G 100.28
J. Value Added Tax (VAT) 12% of (G + H + I) 175.99
K. Total Unit Cost (G + H + I + J) 1,642.59

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 311(2) PCC Pavement (Reinforced), 230 mm. thk.


Unit of Measurement : sq.m.
Output per hour : 15.22

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Skilled Laborer 4 1 79.70 318.80
c. Laborer 12 1 61.44 737.28
Fabrication/Installation
b. Skilled Laborer 2 1 79.70 159.40
c. Laborer 2 1 61.44 122.88

Sub - Total for A 1,447.55


Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Batching Plant (30 cu.m.) 1 0.75 1,208.03 906.02


b. Concrete Screeder (5.5 Hp) 1 1 545.00 545.00
c. Transit Mixer (5 cu.m.) 3 0.75 1,279.00 2,877.75
d. Payloader (1.50 cu.m.), LX80-2C 1 0.75 1,733.00 1,299.75
e. Water Truck (1000 gal.) 1 0.25 1,065.00 266.25
f. Concrete Vibrator 2 1 148.88 297.76
g. Bar Cutter, Single Phase 1 0.25 219.75 54.94
h. Bar Bender 1 0.25 351.50 87.88
Minor Tools (5% of Labor) 72.38

Sub - Total for B 6,407.72


C. Total (A + B) 7,855.27
D. Output per hour = 15.22 sq.m.
E. Direct Unit Cost (C ÷ D) 516.12
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. Reinforcing Steel Bar kg. 40.86 40.00 1,634.40


b. Curing Compound lit. 0.09 28.00 2.52
c. Asphalt Sealant lit. 0.02 44.00 0.88
d. Steel Forms (Rental) l.m. 0.23 250.00 57.50
e. Sand cu.m. 0.10 850.00 85.00
f. Gravel cu.m. 0.20 650.00 130.00
g. Cement bag 2.08 220.00 457.60
h. # 16 GI Tie Wire (2% of RSB) kg. 0.817 47.00 38.40

Sub - Total for F 2,406.30


G. Direct Unit Cost (E + F) 2,922.41
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 263.02
I. Contractor's Profit (CP) 8% of G 233.79
J. Value Added Tax (VAT) 12% of (G + H + I) 410.31
K. Total Unit Cost (G + H + I + J) 3,829.53
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 404c Reinforcing Steel Bar, Grade 40 (Minor Structures)


Unit of Measurement : kg.
Output per hour : 180.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Skilled Laborer 2 1 79.70 159.40
c. Laborer 8 1 61.44 491.52

Sub - Total for A 760.11


Name and Capacity No of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Bar Cutter 1 0.50 219.75 109.88


b. Bar Bender 1 0.50 351.50 175.75
c. Cargo Truck (10 T, 270 Hp) 1 0.15 1,102.00 165.30

Sub - Total for B 450.92


C. Total (A + B) 1,211.03
D. Output per hour = 180.00000 kg.
E. Direct Unit Cost (C ÷ D) 6.73
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Tie Wire (2% of RSB) kg. 0.021 47.00 0.99


b. Reinforcing Steel Bar, Grade 40 kg. 1.05 40.00 42.00
(w/ 5% Wastage)

Sub - Total for F 42.99


G. Direct Unit Cost (E + F) 49.71
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 4.47
I. Contractor's Profit (CP) 8% of G 3.98
J. Value Added Tax (VAT) 12% of (G + H + I) 6.98
K. Total Unit Cost (G + H + I + J) 65.15

DETAILED UNIT PRICE ANALYSIS (DUPA)


Item No./Description : 405 Structural Concrete Class A (Minor Structures)
Unit of Measurement : cu.m.
Output per hour : 1.40

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Skilled Laborer 4 1 79.70 318.80
c. Laborer 8 1 61.44 491.52

Installation/Removal of Formworks
a. Skilled Laborer 2 2 79.70 318.80
b. Laborer 4 2 61.44 491.52
Sub - Total for A 1,729.83
Name and Capacity No of Units No. of Hours Hourly Rate Amount
B. Equipment

a. One Bagger Mixer 1 1 172.00 172.00


b. Concrete Vibrator 1 1 148.88 148.88
c. Water Truck (1000 gal.) 1 0.10 1,065.00 106.50
Minor Tools (5% of Labor) 86.49

Sub - Total for B 513.87


C. Total (A + B) 2,243.70
D. Output per hour = 1.4000 cu.m.
E. Direct Unit Cost (C ÷ D) 1,602.64
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Lumber, Good - 4 uses bd.ft. * 70.0000 40.00 700.00


b. Marine Plywood (1/2" x 4' x 8') - 4 uses pc. * 1.600 700.00 280.00
c. Assorted CWN (1kg./100 bd.ft. of Lumber) kg. * 0.700 68.00 47.60
d. Cement bag 9.50 220.00 2,090.00
e. Sand cu.m. 0.50 850.00 425.00
f. Gravel cu.m. 1 650.00 650.00
Based on Box Culvert
Note:
*Quantities for lumber, plywood and CWN are dependent
on the type of minor structure.
The above-computed quantities are based on box
culvert.
Sub - Total for F 4,192.60
G. Direct Unit Cost (E + F) 5,795.24
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 521.57
I. Contractor's Profit (CP) 8% of G 463.62
J. Value Added Tax (VAT) 12% of (G + H + I) 813.65
K. Total Unit Cost (G + H + I + J) 7,594.09
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 500(1)a Pipe Culverts, 610mm dia. (24" Ø)


Unit of Measurement : l.m.
Output per hour : 2.25

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Skilled Laborer 2 1 79.70 159.40
c. Laborer 4 1 61.44 245.76

Sub - Total for A 514.35


Name and Capacity No of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Backhoe (0.80 cu.m.) 1 0.50 1,537.00 768.50


b. Plate Compactor (5 Hp) 1 0.50 123.00 61.50
Minor Tools (10 % of Labor) 51.44

Sub - Total for B 881.44


C. Total (A + B) 1,395.78
D. Output per hour = 2.25 l.m.
E. Direct Unit Cost (C ÷ D) 620.35
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Portland Cement bag 0.774 220.00 170.28


b. Sand cu.m. 0.044 850.00 37.40
c. R.C. Pipes (610 mm dia.) pc. 1 950.00 950.00
d. Sand Bedding/Selected Sandy Soil cu.m. 0.088 850.00 74.80

Sub - Total for F 1,232.48


G. Direct Unit Cost (E + F) 1,852.83
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 166.75
I. Contractor's Profit (CP) 8% of G 148.23
J. Value Added Tax (VAT) 12% of (G + H + I) 260.14
K. Total Unit Cost (G + H + I + J) 2,427.95

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 500(1)b Pipe Culverts, 760mm dia. (30" Ø)


Unit of Measurement : l.m.
Output per hour : 2.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor
a. Construction Foreman 1 1 109.19 109.19
b. Skilled Laborer 2 1 79.70 159.40
c. Laborer 4 1 61.44 245.76

Sub - Total for A 514.35


Name and Capacity No of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Backhoe (0.80 cu.m.) 1 0.50 1,537.00 768.50


b. Plate Compactor (5 Hp) 1 0.50 123.00 61.50
Minor Tools (10 % of Labor) 51.44

Sub - Total for B 881.44


C. Total (A + B) 1,395.78
D. Output per hour = 2.0000 l.m.
E. Direct Unit Cost (C ÷ D) 697.89
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Portland Cement bag 0.918 220.00 201.96


b. Sand cu.m. 0.052 850.00 44.20
c. R.C. Pipes (760 mm dia.) pc. 1 1,750.00 1,750.00
d. Sand Bedding/Selected Sandy Soil cu.m. 0.108 850.00 91.80

Sub - Total for F 2,087.96


G. Direct Unit Cost (E + F) 2,785.85
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 250.73
I. Contractor's Profit (CP) 8% of G 222.87
J. Value Added Tax (VAT) 12% of (G + H + I) 391.13
K. Total Unit Cost (G + H + I + J) 3,650.58

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 500(1)c Pipe Culverts, 910mm dia. (36" Ø)


Unit of Measurement : l.m.
Output per hour : 1.75

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Skilled Laborer 2 1 79.70 159.40
c. Laborer 4 1 61.44 245.76

Sub - Total for A 514.35


Name and Capacity No of Units No. of Hours Hourly Rate Amount
Name and Capacity No of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Backhoe (0.80 cu.m.) 1 0.50 1,537.00 768.50


b. Plate Compactor (5 Hp) 1 0.50 123.00 61.50
Minor Tools (10 % of Labor) 51.44

Sub - Total for B 881.44


C. Total (A + B) 1,395.78
D. Output per hour = 1.75 l.m.
E. Direct Unit Cost (C ÷ D) 797.59
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Portland Cement bag 1.080 220.00 237.60


b. Sand cu.m. 0.061 850.00 51.85
c. R.C. Pipes (910 mm dia.) pc. 1 2,170.00 2,170.00
d. Sand Bedding/Selected Sandy Soil cu.m. 0.128 850.00 108.80

Sub - Total for F 2,568.25


G. Direct Unit Cost (E + F) 3,365.84
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 302.93
I. Contractor's Profit (CP) 8% of G 269.27
J. Value Added Tax (VAT) 12% of (G + H + I) 472.56
K. Total Unit Cost (G + H + I + J) 4,410.60

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 500(1)d Pipe Culverts, 1070mm dia. (42" Ø)


Unit of Measurement : l.m.
Output per hour : 1.50

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Skilled Laborer 2 1 79.70 159.40
c. Laborer 4 1 61.44 245.76

Sub - Total for A 514.35


Name and Capacity No of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Backhoe (0.80 cu.m.) 1 0.50 1,537.00 768.50


b. Plate Compactor (5 Hp) 1 0.50 123.00 61.50
Minor Tools (10 % of Labor) 51.44
Sub - Total for B 881.44
C. Total (A + B) 1,395.78
D. Output per hour = 1.500 l.m.
E. Direct Unit Cost (C ÷ D) 930.52
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Portland Cement bag 1.242 250.00 310.50


b. Sand cu.m. 0.070 850.00 59.50
c. R.C. Pipes (1070 mm dia.) pc. 1 4,200.00 4,200.00
d. Sand Bedding/Selected Sandy Soil cu.m. 0.149 850.00 126.65

Sub - Total for F 4,696.65


G. Direct Unit Cost (E + F) 5,627.17
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 506.45
I. Contractor's Profit (CP) 8% of G 450.17
J. Value Added Tax (VAT) 12% of (G + H + I) 790.06
K. Total Unit Cost (G + H + I + J) 7,373.85

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 500(1)e Pipe Culverts, 1220mm dia. (48" Ø)


Unit of Measurement : l.m.
Output per hour : 1.25

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Skilled Laborer 2 1 79.70 159.40
c. Laborer 4 1 61.44 245.76

Sub - Total for A 514.35


Name and Capacity No of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Backhoe (0.80 cu.m.) 1 0.50 1,537.00 768.50


b. Plate Compactor (5 Hp) 1 0.50 123.00 61.50
Minor Tools (10 % of Labor) 51.44

Sub - Total for B 881.44


C. Total (A + B) 1,395.78
D. Output per hour = 1.25 l.m.
E. Direct Unit Cost (C ÷ D) 1,116.63
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Portland Cement bag 1.404 220.00 308.88


b. Sand cu.m. 0.080 850.00 68.00
c. R.C. Pipes (1220 mm dia.) pc. 1 3,800.00 3,800.00
d. Sand Bedding/Selected Sandy Soil cu.m. 0.170 850.00 144.50

Sub - Total for F 4,321.38


G. Direct Unit Cost (E + F) 5,438.01
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 489.42
I. Contractor's Profit (CP) 8% of G 435.04
J. Value Added Tax (VAT) 12% of (G + H + I) 763.50
K. Total Unit Cost (G + H + I + J) 7,125.97

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 500(1)f Pipe Culverts, 1520mm dia. (60" Ø)


Unit of Measurement : l.m.
Output per hour : 1.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Skilled Laborer 2 1 79.70 159.40
c. Laborer 4 1 61.44 245.76

Sub - Total for A 514.35


Name and Capacity No of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Backhoe (0.80 cu.m.) 1 0.50 1,537.00 768.50


b. Plate Compactor (5 Hp) 1 0.50 123.00 61.50
Minor Tools (10 % of Labor) 51.44

Sub - Total for B 881.44


C. Total (A + B) 1,395.78
D. Output per hour = 1.0000 l.m.
E. Direct Unit Cost (C ÷ D) 1,395.78
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Portland Cement bag 1.710 220.00 376.20


b. Sand cu.m. 0.097 850.00 82.45
c. R.C. Pipes (1520 mm dia.) pc. 1 6,175.00 6,175.00
d. Sand Bedding/Selected Sandy Soil cu.m. 0.210 850.00 178.50
Sub - Total for F 6,812.15
G. Direct Unit Cost (E + F) 8,207.94
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 738.71
I. Contractor's Profit (CP) 8% of G 656.63
J. Value Added Tax (VAT) 12% of (G + H + I) 1,152.39
K. Total Unit Cost (G + H + I + J) 10,755.68

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 501(1) Underdrain


Unit of Measurement : l.m.
Output per hour : 15.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Laborer 2 1 61.44 122.88

Sub - Total for A 232.07


Name and Capacity No of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Plate Compactor (5 Hp) 1 0.50 123.00 61.50


Minor Tools (10% of Labor) 23.21

Sub - Total for B 84.71


C. Total (A + B) 316.78
D. Output per hour = 15.0000 l.m.
E. Direct Unit Cost (C ÷ D) 21.12
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Coarse Aggregates (Granular Bedding) cu.m. 0.081 900.00 72.90


(w/ 15% Shrinkage Factor)
b. 150 mm. dia. Concrete Perforated Pipe pc. 1 230.00 230.00

Sub - Total for F 302.90


G. Direct Unit Cost (E + F) 324.02
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 29.16
I. Contractor's Profit (CP) 8% of G 25.92
J. Value Added Tax (VAT) 12% of (G + H + I) 45.49
K. Total Unit Cost (G + H + I + J) 424.59

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 501(2) Blind Drain


Unit of Measurement : l.m.
Output per hour : 6.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Skilled Laborer 1 1 79.70 79.70
c. Laborer 1 1 61.44 61.44

Sub - Total for A 250.33


Name and Capacity No of Units No. of Hours Hourly Rate Amount
B. Equipment

Minor Tools (10% of Labor) 25.03

Assumed 100 meter length


V = 0.15(0.30)(100) = 4.50 cu.m.
100/(2x8) = 6.25, say 6.00 l.m./hr

Sub - Total for B 25.03


C. Total (A + B) 275.36
D. Output per hour = 6.0000 l.m.
E. Direct Unit Cost (C ÷ D) 45.89
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. 150 mm. dia. Concrete Perforated Pipe pc. 1 230.00 230.00


b. G1/2 to G1 Washed Gravel cu.m. 0.026 650.00 16.90
c. Coarse Sand cu.m. 0.026 900.00 23.40

Sub - Total for F 270.30


G. Direct Unit Cost (E + F) 316.19
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 28.46
I. Contractor's Profit (CP) 8% of G 25.30
J. Value Added Tax (VAT) 12% of (G + H + I) 44.39
K. Total Unit Cost (G + H + I + J) 414.34

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 501(3) Granular Backfill filter material for Underdrains


Unit of Measurement : cu.m.
Output per hour : 1.25
Designation No. of Person No. of Hours Hourly Rate Amount
A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Laborer 4 1 61.44 245.76

Sub - Total for A 354.95


Name and Capacity No of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Plate Compactor (5 Hp) 1 1 123.00 123.00


Minor Tools (10% of Labor) 35.50

Sub - Total for B 158.50


C. Total (A + B) 513.44
D. Output per hour = 1.25 cu.m.
E. Direct Unit Cost (C ÷ D) 410.76
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Coarse Aggregates (Granular Backfill Materials) cu.m. 1.15 900.00 1,035.00


(w/ 15% Shrinkage Factor)

Sub - Total for F 1,035.00


G. Direct Unit Cost (E + F) 1,445.76
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 130.12
I. Contractor's Profit (CP) 8% of G 115.66
J. Value Added Tax (VAT) 12% of (G + H + I) 202.98
K. Total Unit Cost (G + H + I + J) 1,894.52

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 502(1)a Manhole (610 mm. dia. RCPC)


Unit of Measurement : ea.
Output : 1.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 8.90 109.19 971.79


b. Skilled Laborer 2 8.90 79.70 1,418.66
c. Laborer 4 8.90 61.44 2,187.26
Sub - Total for A 4,577.72
Name and Capacity No of Units No. of Hours Hourly Rate Amount
B. Equipment

a. One Bagger Mixer 1 2 172.00 344.00


b. Water Truck (1000 gal.) 1 0.15 1,065.00 159.75
c. Bar Cutter 1 0.30 219.75 65.93
d. Bar Bender 1 0.30 351.50 105.45
e. Concrete Vibrator 1 2 148.88 297.76
f. Welding Machine 1 0.15 391.00 58.65
Minor Tools (10% of Labor) 457.77

Sub - Total for B 1,489.31


C. Total (A + B) 6,067.02
D. Output = 1.0000 ea.
E. Direct Unit Cost (C ÷ D) 6,067.02
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Cement bag 23 220.00 5,060.00


b. Sand cu.m. 1.235 850.00 1,049.75
c. Gravel cu.m. 2.47 650.00 1,605.50
d. Reinforcing Steel Bar kg. 267.93 40.00 10,717.20
e. #16 G.I. Tie Wire (2% of RSB) kg. 5.359 47.00 251.87
f. 100 x 100 x 6mm Angle Bar kg. 48.98 48.00 2,350.94
g. Welding Rod (1 kg./2000 kg. of Steel) kg. 0.024 90.00 2.16
h. 1/4" Ordinary Plywood - 2 uses pc. 6.75 350.00 1,181.25
i. Coco Lumber - 2 uses bd.ft. 117.643 20.00 1,176.43
j. Assorted CWN (1 kg./100 bd.ft. of Lumber) kg. 1.176 68.00 79.97

Sub - Total for F 23,475.08


G. Direct Unit Cost (E + F) 29,542.10
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 2,658.79
I. Contractor's Profit (CP) 8% of G 2,363.37
J. Value Added Tax (VAT) 12% of (G + H + I) 4,147.71
K. Total Unit Cost (G + H + I + J) 38,711.96

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 502(1)b Manhole (760 mm. dia. RCPC)


Unit of Measurement : ea.
Output : 1.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 10.40 109.19 1,135.58


b. Skilled Laborer 2 10.40 79.70 1,657.76
c. Laborer 4 10.40 61.44 2,555.90

Sub - Total for A 5,349.24


Name and Capacity No of Units No. of Hours Hourly Rate Amount
B. Equipment

a. One Bagger Mixer 1 2.25 172.00 387.00


b. Water Truck (1000 gal.) 1 0.15 1,065.00 159.75
c. Bar Cutter 1 0.40 219.75 87.90
d. Bar Bender 1 0.40 351.50 140.60
e. Concrete Vibrator 1 2.25 148.88 334.98
f. Welding Machine 1 0.15 391.00 58.65
Minor Tools (10% of Labor) 534.92

Sub - Total for B 1,703.80


C. Total (A + B) 7,053.04
D. Output = 1.0000 ea.
E. Direct Unit Cost (C ÷ D) 7,053.04
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Cement bag 27 220.00 5,940.00


b. Sand cu.m. 1.467 850.00 1,246.95
c. Gravel cu.m. 2.934 650.00 1,907.10
d. Reinforcing Steel Bar kg. 288.721 40.00 11,548.84
e. #16 G.I. Tie Wire (2% of RSB) kg. 5.774 47.00 271.38
f. 100mm x 100mm x 6mm Angle Bar kg. 53.122 48.00 2,549.86
g. Welding Rod (1 kg./2000 kg. of Steel) kg. 0.027 90.00 2.43
h. 1/4" Ordinary Plywood - 2 uses pc. 7.86 350.00 1,375.50
i. Coco Lumber - 2 uses bd.ft. 120.135 20.00 1,201.35
j. Assorted CWN (1 kg./100 bd.ft. of Lumber) kg. 1.201 68.00 81.67

Sub - Total for F 26,125.07


G. Direct Unit Cost (E + F) 33,178.12
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 2,986.03
I. Contractor's Profit (CP) 8% of G 2,654.25
J. Value Added Tax (VAT) 12% of (G + H + I) 4,658.21
K. Total Unit Cost (G + H + I + J) 43,476.60

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 502(1)c Manhole (910 mm. dia. RCPC)


Unit of Measurement : ea.
Output : 1.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 11.20 109.19 1,222.93


b. Skilled Laborer 2 11.20 79.70 1,785.28
c. Laborer 4 11.20 61.44 2,752.51

Sub - Total for A 5,760.72


Name and Capacity No of Units No. of Hours Hourly Rate Amount
B. Equipment

a. One Bagger Mixer 1 2.42 172.00 416.24


b. Water Truck (1000 gal.) 1 0.16 1,065.00 170.40
c. Bar Cutter 1 0.50 219.75 109.88
d. Bar Bender 1 0.50 351.50 175.75
e. Concrete Vibrator 1 2.42 148.88 360.29
f. Welding Machine 1 0.16 391.00 62.56
Minor Tools (10% of Labor) 576.07 576.07

Sub - Total for B 1,871.19


C. Total (A + B) 7,631.91
D. Output = 1.0000 ea.
E. Direct Unit Cost (C ÷ D) 7,631.91
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Cement bag 29 220.00 6,380.00


b. Sand cu.m. 1.582 850.00 1,344.70
c. Gravel cu.m. 3.164 650.00 2,056.60
d. Reinforcing Steel Bar kg. 352.211 40.00 14,088.44
e. #16 G.I. Tie Wire (2% of RSB) kg. 7.044 47.00 331.07
f. 100 x 100 x 6mm Angle Bar kg. 57.078 48.00 2,739.74
g. Welding Rod (1 kg./2000 kg. of Steel) kg. 0.029 90.00 2.61
h. 1/4" Ordinary Plywood - 2 uses pc. 9.16 350.00 1,603.00
i. Coco Lumber - 2 uses bd.ft. 129.626 20.00 1,296.26
j. Assorted CWN (1 kg./100 bd.ft. of Lumber) kg. 1.296 68.00 88.13

Sub - Total for F 29,930.55


G. Direct Unit Cost (E + F) 37,562.46
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 3,380.62
I. Contractor's Profit (CP) 8% of G 3,005.00
J. Value Added Tax (VAT) 12% of (G + H + I) 5,273.77
K. Total Unit Cost (G + H + I + J) 49,221.84

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 502(1)d Manhole (1070 mm. dia. RCPC)


Unit of Measurement : ea.
Output : 1.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 13.30 109.19 1,452.23


b. Skilled Laborer 2 13.30 79.70 2,120.02
c. Laborer 4 13.30 61.44 3,268.61

Sub - Total for A 6,840.86


Name and Capacity No of Units No. of Hours Hourly Rate Amount
B. Equipment

a. One Bagger Mixer 1 2.83 172.00 486.76


b. Water Truck (1000 gal.) 1 0.19 1,065.00 202.35
c. Bar Cutter 1 0.52 219.75 114.27
d. Bar Bender 1 0.52 351.50 182.78
e. Concrete Vibrator 1 2.83 148.88 421.33
f. Welding Machine 1 0.19 391.00 74.29
Minor Tools (10% of Labor) 684.09 684.09

Sub - Total for B 2,165.87


C. Total (A + B) 9,006.72
D. Output = 1.0000 ea.
E. Direct Unit Cost (C ÷ D) 9,006.72
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Cement bag 34 220.00 7,480.00


b. Sand cu.m. 1.884 850.00 1,601.40
c. Gravel cu.m. 3.768 650.00 2,449.20
d. Reinforcing Steel Bar kg. 376.863 40.00 15,074.52
e. #16 G.I. Tie Wire (2% of RSB) kg. 7.537 47.00 354.24
f. 100 x 100 x 6mm Angle Bar kg. 62.729 48.00 3,010.99
g. Welding Rod (1 kg./2000 kg. of Steel) kg. 0.031 90.00 2.79
h. 1/4" Ordinary Plywood - 2 uses pc. 10.10 350.00 1,767.50
i. Coco Lumber - 2 uses bd.ft. 133.47 20.00 1,334.70
j. Assorted CWN (1 kg./100 bd.ft. of Lumber) kg. 1.335 68.00 90.78

Sub - Total for F 33,166.12


G. Direct Unit Cost (E + F) 42,172.84
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 3,795.56
I. Contractor's Profit (CP) 8% of G 3,373.83
J. Value Added Tax (VAT) 12% of (G + H + I) 5,921.07
K. Total Unit Cost (G + H + I + J) 55,263.29

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 502(1)e Manhole (1220 mm. dia. RCPC)


Unit of Measurement : ea.
Output : 1.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 15 109.19 1,637.85


b. Skilled Laborer 2 15 79.70 2,391.00
c. Laborer 4 15 61.44 3,686.40

Sub - Total for A 7,715.25


Name and Capacity No of Units No. of Hours Hourly Rate Amount
B. Equipment

a. One Bagger Mixer 1 3.60 172.00 619.20


b. Water Truck (1000 gal.) 1 0.24 1,065.00 255.60
c. Bar Cutter 1 0.73 219.75 160.42
d. Bar Bender 1 0.73 351.50 256.59
e. Concrete Vibrator 1 3.60 148.88 535.97
f. Welding Machine 1 0.24 391.00 93.84
Minor Tools (10% of Labor) 771.53 771.53

Sub - Total for B 2,693.15


C. Total (A + B) 10,408.40
D. Output = 1.0000 ea.
E. Direct Unit Cost (C ÷ D) 10,408.40
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Cement bag 43 220.00 9,460.00


b. Sand cu.m. 2.352 850.00 1,999.20
c. Gravel cu.m. 4.704 650.00 3,057.60
d. Reinforcing Steel Bar kg. 528.209 40.00 21,128.36
e. #16 G.I. Tie Wire (2% of RSB) kg. 10.564 47.00 496.51
f. 100mmx100mmx6mm Angle Bar kg. 72.525 48.00 3,481.20
g. Welding Rod (1 kg./2000 kg. of Steel) kg. 0.036 90.00 3.24
h. 1/4" Ordinary Plywood - 2 uses pc. 12.65 350.00 2,213.75
i. Coco Lumber - 2 uses bd.ft. 163.913 20.00 1,639.13
j. Assorted CWN (1 kg./100 bd.ft. of Lumber) kg. 1.639 68.00 111.45

Sub - Total for F 43,590.44


G. Direct Unit Cost (E + F) 53,998.84
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 4,859.90
I. Contractor's Profit (CP) 8% of G 4,319.91
J. Value Added Tax (VAT) 12% of (G + H + I) 7,581.44
K. Total Unit Cost (G + H + I + J) 70,760.07

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 502(2)a Inlet, Type I


Unit of Measurement : ea.
Output : 1.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 2 109.19 218.38


b. Skilled Laborer 2 2 79.70 318.80
c. Laborer 4 2 61.44 491.52

Sub - Total for A 1,028.70


Name and Capacity No of Units No. of Hours Hourly Rate Amount
B. Equipment

a. One Bagger Mixer 1 0.40 172.00 68.80


b. Water Truck (1000 gal.) 1 0.10 1,065.00 106.50
c. Bar Cutter 1 0.25 219.75 54.94
d. Welding Machine 1 0.25 391.00 97.75

Sub - Total for B 327.99


C. Total (A + B) 1,356.69
D. Output = 1.0000 ea.
E. Direct Unit Cost (C ÷ D) 1,356.69
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Cement bag 4.20 220.00 924.00


b. Sand cu.m. 0.188 850.00 159.80
c. Gravel cu.m. 0.377 650.00 245.05
d. Reinforcing Steel Bar kg. 16.224 40.00 648.96
e. #16 G.I. Tie Wire (2% of RSB) kg. 0.324 47.00 15.23
f. 1/4" thk. Ordinary Plywood - 2 uses pc. 1.26 350.00 220.50
g. Coco Lumber - 2 uses bd.ft. 22.775 20.00 227.75
h. Assorted CWN (1 kg./100 bd.ft. of Lumber) kg. 0.228 68.00 15.50
i. Inlet Frame Bars kg. 94.565 48.00 4,539.12
j. Welding Rod (1 kg./2000 kg. of Steel) kg. 0.047 90.00 4.23

Sub - Total for F 7,000.14


G. Direct Unit Cost (E + F) 8,356.83
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 752.11
I. Contractor's Profit (CP) 8% of G 668.55
J. Value Added Tax (VAT) 12% of (G + H + I) 1,173.30
K. Total Unit Cost (G + H + I + J) 10,950.79

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 502(2)b Inlet, Type I-A


Unit of Measurement : ea.
Output : 1.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 3 109.19 327.57


b. Skilled Laborer 2 3 79.70 478.20
c. Laborer 4 3 61.44 737.28

Sub - Total for A 1,543.05


Name and Capacity No of Units No. of Hours Hourly Rate Amount
B. Equipment

a. One Bagger Mixer 1 0.40 172.00 68.80


b. Water Truck (1000 gal.) 1 0.10 1,065.00 106.50
c. Bar Cutter 1 0.25 219.75 54.94
d. Welding Machine 1 0.25 391.00 97.75

Sub - Total for B 327.99


C. Total (A + B) 1,871.04
D. Output = 1.0000 ea.
E. Direct Unit Cost (C ÷ D) 1,871.04
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Cement bag 5.60 220.00 1,232.00


b. Sand cu.m. 0.249 850.00 211.65
c. Gravel cu.m. 0.498 650.00 323.70
d. Reinforcing Steel Bar kg. 16.224 40.00 648.96
e. #16 G.I. Tie Wire (2% of RSB) kg. 0.324 47.00 15.23
f. 1/4" thk. Ordinary Plywood - 2 uses pc. 1.44 350.00 252.00
g. Coco Lumber - 2 uses bd.ft. 31.32 20.00 313.20
h. Assorted CWN (1 kg./100 bd.ft. of Lumber) kg. 0.313 68.00 21.28
i. Inlet Frame Bars kg. 95.648 48.00 4,591.10
j. Welding Rod (1 kg./2000 kg. of Steel) kg. 0.048 90.00 4.32

Sub - Total for F 7,613.45


G. Direct Unit Cost (E + F) 9,484.48
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 853.60
I. Contractor's Profit (CP) 8% of G 758.76
J. Value Added Tax (VAT) 12% of (G + H + I) 1,331.62
K. Total Unit Cost (G + H + I + J) 12,428.47

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 502(3)a Catch Basin (Single Barrel 610 mm. dia. RCPC)
Unit of Measurement : ea.
Output : 1.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 6.50 109.19 709.74


b. Skilled Laborer 2 6.50 79.70 1,036.10
c. Laborer 4 6.50 61.44 1,597.44
Sub - Total for A 3,343.28
Name and Capacity No of Units No. of Hours Hourly Rate Amount
B. Equipment

a. One Bagger Mixer 1 2 172.00 344.00


b. Water Truck (1000 gal.) 1 2 1,065.00 2,130.00
c. Concrete Vibrator 1 2 148.88 297.76
d. Bar Cutter 1 0.50 219.75 109.88
e. Bar Bender 1 0.50 351.50 175.75
Minor Tools (10% of Labor) 334.33 334.33

Sub - Total for B 3,391.71


C. Total (A + B) 6,734.99
D. Output = 1.0000 ea.
E. Direct Unit Cost (C ÷ D) 6,734.99
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Portland Cement bag 17.70 220.00 3,894.00


b. Washed Sand cu.m. 0.79 850.00 671.50
c. Crushed Gravel cu.m. 1.57 650.00 1,020.50
d. 1/4" Ordinary Plywood - 2 uses pc. 7.43 350.00 1,300.25
e. Coco Lumber - 2 uses bd.ft. 78.31 20.00 783.10
f. 10 mm. dia. Reinforcing Steel Bar kg. 125.15 40.00 5,006.00
g. #16 GI Tie Wire (2% of RSB) kg. 2.503 47.00 117.64
h. Assorted CWN (1 kg./100 bd.ft. of Lumber) kg. 0.783 68.00 53.24

H = 1,860.00 mm.
C = 1,200.00 mm.
D = 1,200.00 mm.
Sub - Total for F 12,846.24
G. Direct Unit Cost (E + F) 19,581.22
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 1,762.31
I. Contractor's Profit (CP) 8% of G 1,566.50
J. Value Added Tax (VAT) 12% of (G + H + I) 2,749.20
K. Total Unit Cost (G + H + I + J) 25,659.23

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 502(3)a Catch Basin (Single Barrel 760 mm. dia. RCPC)
Unit of Measurement : ea.
Output : 1.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 6.50 109.19 709.74


b. Skilled Laborer 2 6.50 79.70 1,036.10
c. Laborer 4 6.50 61.44 1,597.44

Sub - Total for A 3,343.28


Name and Capacity No of Units No. of Hours Hourly Rate Amount
B. Equipment

a. One Bagger Mixer 1 2 172.00 344.00


b. Water Truck (1000 gal.) 1 2 1,065.00 2,130.00
c. Concrete Vibrator 1 2 148.88 297.76
d. Bar Cutter 1 0.50 219.75 109.88
e. Bar Bender 1 0.50 351.50 175.75
Minor Tools (10% of Labor) 334.33 334.33

Sub - Total for B 3,391.71


C. Total (A + B) 6,734.99
D. Output = 1.0000 ea.
E. Direct Unit Cost (C ÷ D) 6,734.99
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Portland Cement bag 20.15 220.00 4,433.00


b. Washed Sand cu.m. 0.90 850.00 765.00
c. Crushed Gravel cu.m. 1.79 650.00 1,163.50
d. 1/4" Ordinary Plywood - 2 uses pc. 9.48 350.00 1,659.00
e. Coco Lumber - 2 uses bd.ft. 89.19 20.00 891.90
f. 10 mm. dia. Reinforcing Steel Bar kg. 118.41 40.00 4,736.40
g. #16 GI Tie Wire (2% of RSB) kg. 2.368 47.00 111.30
h. Assorted CWN (1 kg./100 bd.ft. of Lumber) kg. 0.892 68.00 60.66

H = 2,100.00 mm.
C = 1,540.00 mm.
D = 1,240.00 mm.
Sub - Total for F 13,820.75
G. Direct Unit Cost (E + F) 20,555.74
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 1,850.02
I. Contractor's Profit (CP) 8% of G 1,644.46
J. Value Added Tax (VAT) 12% of (G + H + I) 2,886.03
K. Total Unit Cost (G + H + I + J) 26,936.24

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 502(3)a Catch Basin (Single Barrel 910 mm. dia. RCPC)
Unit of Measurement : ea.
Output : 1.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 7 109.19 764.33


b. Skilled Laborer 2 7 79.70 1,115.80
c. Laborer 4 7 61.44 1,720.32

Sub - Total for A 3,600.45


Name and Capacity No of Units No. of Hours Hourly Rate Amount
B. Equipment

a. One Bagger Mixer 1 2 172.00 344.00


b. Water Truck (1000 gal.) 1 2 1,065.00 2,130.00
c. Concrete Vibrator 1 2 148.88 297.76
d. Bar Cutter 1 0.50 219.75 109.88
e. Bar Bender 1 0.50 351.50 175.75
Minor Tools (10% of Labor) 360.05 360.05
Sub - Total for B 3,417.43
C. Total (A + B) 7,017.88
D. Output = 1.0000 ea.
E. Direct Unit Cost (C ÷ D) 7,017.88
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Portland Cement bag 25.04 220.00 5,508.80


b. Washed Sand cu.m. 1.11 850.00 943.50
c. Crushed Gravel cu.m. 2.23 650.00 1,449.50
d. 1/4" Ordinary Plywood - 2 uses pc. 10.14 350.00 1,774.50
e. Coco Lumber - 2 uses bd.ft. 99.64 20.00 996.40
f. 10 mm. dia. Reinforcing Steel Bar kg. 171.26 40.00 6,850.40
g. #16 GI Tie Wire (2% of RSB) kg. 3.425 47.00 160.98
h. Assorted CWN (1 kg./100 bd.ft. of Lumber) kg. 0.996 68.00 67.73

H = 2,210.00 mm.
C = 1,500.00 mm.
D = 1,500.00 mm.
Sub - Total for F 17,751.80
G. Direct Unit Cost (E + F) 24,769.68
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 2,229.27
I. Contractor's Profit (CP) 8% of G 1,981.57
J. Value Added Tax (VAT) 12% of (G + H + I) 3,477.66
K. Total Unit Cost (G + H + I + J) 32,458.19

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 502(3)a Catch Basin (Single Barrel 1070 mm. dia. RCPC)
Unit of Measurement : ea.
Output : 1.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 8 109.19 873.52


b. Skilled Laborer 2 8 79.70 1,275.20
c. Laborer 4 8 61.44 1,966.08

Sub - Total for A 4,114.80


Name and Capacity No of Units No. of Hours Hourly Rate Amount
B. Equipment

a. One Bagger Mixer 1 2 172.00 344.00


b. Water Truck (1000 gal.) 1 2 1,065.00 2,130.00
c. Concrete Vibrator 1 2 148.88 297.76
d. Bar Cutter 1 0.50 219.75 109.88
e. Bar Bender 1 0.50 351.50 175.75
Minor Tools (10% of Labor) 411.48 411.48

Sub - Total for B 3,468.87


C. Total (A + B) 7,583.67
D. Output = 1.0000 ea.
E. Direct Unit Cost (C ÷ D) 7,583.67
Name and Specification Unit Quantity Unit Cost Amount
F. Materials
a. Portland Cement bag 24.34 220.00 5,354.80
b. Washed Sand cu.m. 1.08 850.00 918.00
c. Crushed Gravel cu.m. 2.16 650.00 1,404.00
d. 1/4" Ordinary Plywood - 2 uses pc. 11.95 350.00 2,091.25
e. Coco Lumber - 2 uses bd.ft. 105.34 20.00 1,053.40
f. 10 mm. dia. Reinforcing Steel Bar kg. 189.05 40.00 7,562.00
g. #16 GI Tie Wire (2% of RSB) kg. 3.781 47.00 177.71
h. Assorted CWN (1 kg./100 bd.ft. of Lumber) kg. 1.053 68.00 71.60

H = 2,430.00 mm.
C = 1,770.00 mm.
D = 1,600.00 mm.
Sub - Total for F 18,632.76
G. Direct Unit Cost (E + F) 26,216.43
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 2,359.48
I. Contractor's Profit (CP) 8% of G 2,097.31
J. Value Added Tax (VAT) 12% of (G + H + I) 3,680.79
K. Total Unit Cost (G + H + I + J) 34,354.00

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 502(3)a Catch Basin (Single Barrel 1220 mm. dia. RCPC)
Unit of Measurement : ea.
Output : 1.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 8 109.19 873.52


b. Skilled Laborer 2 8 79.70 1,275.20
c. Laborer 4 8 61.44 1,966.08

Sub - Total for A 4,114.80


Name and Capacity No of Units No. of Hours Hourly Rate Amount
B. Equipment

a. One Bagger Mixer 1 2 172.00 344.00


b. Water Truck (1000 gal.) 1 2 1,065.00 2,130.00
c. Concrete Vibrator 1 2 148.88 297.76
d. Bar Cutter 1 0.50 219.75 109.88
e. Bar Bender 1 0.50 351.50 175.75
Minor Tools (10% of Labor) 411.48 411.48

Sub - Total for B 3,468.87


C. Total (A + B) 7,583.67
D. Output = 1.0000 ea.
E. Direct Unit Cost (C ÷ D) 7,583.67
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Portland Cement bag 32.45 220.00 7,139.00


b. Washed Sand cu.m. 1.44 850.00 1,224.00
c. Crushed Gravel cu.m. 2.88 650.00 1,872.00
d. 1/4" Ordinary Plywood - 2 uses pc. 12.84 350.00 2,247.00
e. Coco Lumber - 2 uses bd.ft. 121.27 20.00 1,212.70
f. 10 mm. dia. Reinforcing Steel Bar kg. 190.43 40.00 7,617.20
g. #16 GI Tie Wire (2% of RSB) kg. 3.809 47.00 179.02
h. Assorted CWN (1 kg./100 bd.ft. of Lumber) kg. 1.213 68.00 82.48

H = 2,580.00 mm.
C = 1,800.00 mm.
D = 1,600.00 mm.
Sub - Total for F 21,573.41
G. Direct Unit Cost (E + F) 29,157.07
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 2,624.14
I. Contractor's Profit (CP) 8% of G 2,332.57
J. Value Added Tax (VAT) 12% of (G + H + I) 4,093.65
K. Total Unit Cost (G + H + I + J) 38,207.43

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 502(3)b Catch Basin (Double Barrel 610 mm. dia. RCPC)
Unit of Measurement : ea.
Output : 1.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 5.25 109.19 573.25


b. Skilled Laborer 2 5.25 79.70 836.85
c. Laborer 4 5.25 61.44 1,290.24

Sub - Total for A 2,700.34


Name and Capacity No of Units No. of Hours Hourly Rate Amount
B. Equipment

a. One Bagger Mixer 1 2 172.00 344.00


b. Water Truck (1000 gal.) 1 2 1,065.00 2,130.00
c. Concrete Vibrator 1 2 148.88 297.76
d. Bar Cutter 1 0.50 219.75 109.88
e. Bar Bender 1 0.50 351.50 175.75
Minor Tools (10% of Labor) 270.03 270.03

Sub - Total for B 3,327.42


C. Total (A + B) 6,027.76
D. Output = 1.0000 ea.
E. Direct Unit Cost (C ÷ D) 6,027.76
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Portland Cement bag 16.87 220.00 3,711.40


b. Washed Sand cu.m. 0.75 850.00 637.50
c. Crushed Gravel cu.m. 1.50 650.00 975.00
d. 1/4" Ordinary Plywood - 2 uses pc. 11.23 350.00 1,965.25
e. Coco Lumber - 2 uses bd.ft. 99.42 20.00 994.20
f. 10 mm. dia. Reinforcing Steel Bar kg. 182.18 40.00 7,287.20
g. #16 GI Tie Wire (2% of RSB) kg. 3.644 47.00 171.27
h. Assorted CWN (1 kg./100 bd.ft. of Lumber) kg. 0.994 68.00 67.59

H = 1,860.00 mm.
C = 2,420.00 mm.
D = 1,200.00 mm.
Sub - Total for F 15,809.41
G. Direct Unit Cost (E + F) 21,837.17
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 1,965.34
I. Contractor's Profit (CP) 8% of G 1,746.97
J. Value Added Tax (VAT) 12% of (G + H + I) 3,065.94
K. Total Unit Cost (G + H + I + J) 28,615.42
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 502(3)b Catch Basin (Double Barrel 910 mm. dia. RCPC)
Unit of Measurement : ea.
Output : 1.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 8 109.19 873.52


b. Skilled Laborer 2 8 79.70 1,275.20
c. Laborer 4 8 61.44 1,966.08

Sub - Total for A 4,114.80


Name and Capacity No of Units No. of Hours Hourly Rate Amount
B. Equipment

a. One Bagger Mixer 1 2 172.00 344.00


b. Water Truck (1000 gal.) 1 2 1,065.00 2,130.00
c. Concrete Vibrator 1 2 148.88 297.76
d. Bar Cutter 1 0.50 219.75 109.88
e. Bar Bender 1 0.50 351.50 175.75
Minor Tools (10% of Labor) 411.48 411.48

Sub - Total for B 3,468.87


C. Total (A + B) 7,583.67
D. Output = 1.0000 ea.
E. Direct Unit Cost (C ÷ D) 7,583.67
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Portland Cement bag 42.63 220.00 9,378.60


b. Washed Sand cu.m. 1.89 850.00 1,606.50
c. Crushed Gravel cu.m. 3.79 650.00 2,463.50
d. 1/4" Ordinary Plywood - 2 uses pc. 16.84 350.00 2,947.00
e. Coco Lumber - 2 uses bd.ft. 149.42 20.00 1,494.20
f. 10 mm. dia. Reinforcing Steel Bar kg. 294.71 40.00 11,788.40
g. #16 GI Tie Wire (2% of RSB) kg. 5.894 47.00 277.02
h. Assorted CWN (1 kg./100 bd.ft. of Lumber) kg. 1.494 68.00 101.59

H = 2,210.00 mm.
C = 3,320.00 mm.
D = 1,500.00 mm.
Sub - Total for F 30,056.81
G. Direct Unit Cost (E + F) 37,640.48
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 3,387.64
I. Contractor's Profit (CP) 8% of G 3,011.24
J. Value Added Tax (VAT) 12% of (G + H + I) 5,284.72
K. Total Unit Cost (G + H + I + J) 49,324.08

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 502(3)b Catch Basin (Double Barrel 1220 mm. dia. RCPC)
Unit of Measurement : ea.
Output : 1.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor
a. Construction Foreman 1 8 109.19 873.52
b. Skilled Laborer 2 8 79.70 1,275.20
c. Laborer 4 8 61.44 1,966.08

Sub - Total for A 4,114.80


Name and Capacity No of Units No. of Hours Hourly Rate Amount
B. Equipment

a. One Bagger Mixer 1 2 172.00 344.00


b. Water Truck (1000 gal.) 1 2 1,065.00 2,130.00
c. Concrete Vibrator 1 2 148.88 297.76
d. Bar Cutter 1 0.50 219.75 109.88
e. Bar Bender 1 0.50 351.50 175.75
Minor Tools (10% of Labor) 411.48 411.48

Sub - Total for B 3,468.87


C. Total (A + B) 7,583.67
D. Output = 1.0000 ea.
E. Direct Unit Cost (C ÷ D) 7,583.67
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Portland Cement bag 60.18 220.00 13,239.60


b. Washed Sand cu.m. 2.67 850.00 2,269.50
c. Crushed Gravel cu.m. 5.35 650.00 3,477.50
d. 1/4" Ordinary Plywood - 2 uses pc. 23.86 350.00 4,175.50
e. Coco Lumber - 2 uses bd.ft. 193.89 20.00 1,938.90
f. 10 mm. dia. Reinforcing Steel Bar kg. 403.47 40.00 16,138.80
g. #16 GI Tie Wire (2% of RSB) kg. 8.069 47.00 379.24
h. Assorted CWN (1 kg./100 bd.ft. of Lumber) kg. 1.939 68.00 131.85

H = 2,580.00 mm.
C = 4,420.00 mm.
D = 1,600.00 mm.
Sub - Total for F 41,750.90
G. Direct Unit Cost (E + F) 49,334.56
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 4,440.11
I. Contractor's Profit (CP) 8% of G 3,946.76
J. Value Added Tax (VAT) 12% of (G + H + I) 6,926.57
K. Total Unit Cost (G + H + I + J) 64,648.01

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 502(4) Concrete Covers


Unit of Measurement : ea.
Output : 5.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Skilled Laborer 2 1 79.70 159.40
c. Laborer 4 1 61.44 245.76

Sub - Total for A 514.35


Name and Capacity No of Units No. of Hours Hourly Rate Amount
B. Equipment

a. One Bagger Mixer 1 0.50 172.00 86.00


b. Bar Cutter 1 0.50 219.75 109.88
c. Concrete Vibrator 1 0.50 148.88 74.44
d. Welding Machine (GasType) 1 0.25 391.00 97.75
e. Water Truck 1 0.05 1,065.00 53.25
Minor Tools (10% of Labor) 51.44 51.44

Sub - Total for B 472.75


C. Total (A + B) 987.10
D. Output = 5.0000 ea.
E. Direct Unit Cost (C ÷ D) 197.42
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

Dimension: 1.31m x 0.573m x 0.20m


a. Portland Cement bag 1.31 220.00 288.20
b. Sand cu.m. 0.06 850.00 51.00
c. Gravel cu.m. 0.12 650.00 78.00
d. Reinforcing Steel Bar kg. 44.38 40.00 1,775.20
e. #16 GI Tie Wire (2% of RSB) kg. 0.888 47.00 41.74
f. 6mm thk. Steel Plate kg. 35.48 48.00 1,703.04
g. 16mm thk. Steel Plate kg. 2.83 48.00 67.92
h. 1/2" Ordinary Plywood - 2 uses pc. 0.33 620.00 102.30
i. 16mm dia. U-bolt & Knot set 2.00 250.00 250.00
j. Welding Rod (1 kg./2000 kg. of Steel) kg. 0.019 90.00 0.86

Sub - Total for F 4,358.25


G. Direct Unit Cost (E + F) 4,555.67
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 410.01
I. Contractor's Profit (CP) 8% of G 364.45
J. Value Added Tax (VAT) 12% of (G + H + I) 639.62
K. Total Unit Cost (G + H + I + J) 5,969.75

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 502(5) Metal Frames and Gratings


Unit of Measurement : pair
Output : 1.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 0.50 109.19 54.60


b. Skilled Laborer 1 0.50 79.70 39.85
c. Laborer 1 0.50 61.44 30.72

Sub - Total for A 125.16


Name and Capacity No of Units No. of Hours Hourly Rate Amount
B. Equipment

Minor Tools (10% of Labor) 12.52 12.52


Sub - Total for B 12.52
C. Total (A + B) 137.68
D. Output = 1.0000 pair
E. Direct Unit Cost (C ÷ D) 137.68
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. 410mmx660mmx60mm, C.I. Cover with Frame set 1.00 4,700.00 4,700.00

Sub - Total for F 4,700.00


G. Direct Unit Cost (E + F) 4,837.68
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 435.39
I. Contractor's Profit (CP) 8% of G 387.01
J. Value Added Tax (VAT) 12% of (G + H + I) 679.21
K. Total Unit Cost (G + H + I + J) 6,339.30

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 502(6) Metal Frames and Covers (Circular)


Unit of Measurement : pair
Output : 1.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 0.50 109.19 54.60


b. Skilled Laborer 1 0.50 79.70 39.85
c. Laborer 1 0.50 61.44 30.72

Sub - Total for A 125.16


Name and Capacity No of Units No. of Hours Hourly Rate Amount
B. Equipment

Minor Tools (10% of Labor) 12.52 12.52

Sub - Total for B 12.52


C. Total (A + B) 137.68
D. Output = 1.0000 pair
E. Direct Unit Cost (C ÷ D) 137.68
Name and Specification Unit Quantity Unit Cost Amount
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. 580mm dia. C.I. Manhole Cover with Frame set 1.00 5,700.00 5,700.00

Sub - Total for F 5,700.00


G. Direct Unit Cost (E + F) 5,837.68
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 525.39
I. Contractor's Profit (CP) 8% of G 467.01
J. Value Added Tax (VAT) 12% of (G + H + I) 819.61
K. Total Unit Cost (G + H + I + J) 7,649.70

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 502(7) Adjusting Manhole, Type I-A (to be based on Item 103,404 & 405)
Unit of Measurement : ea.
Output : 1.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 5 109.19 545.95


b. Skilled Laborer 2 5 79.70 797.00
c. Laborer 4 5 61.44 1,228.80

Sub - Total for A 2,571.75


Name and Capacity No of Units No. of Hours Hourly Rate Amount
B. Equipment

a. One Bagger Mixer 1 1 172.00 172.00


b. Water Truck (1000 gal.) 1 0.10 1,065.00 106.50
c. Bar Cutter 1 0.25 219.75 54.94

Sub - Total for B 333.44


C. Total (A + B) 2,905.19
D. Output = 1.0000 ea.
E. Direct Unit Cost (C ÷ D) 2,905.19
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. Portland Cement bag 13 220.00 2,860.00


b. Sand cu.m. 0.568 850.00 482.80
c. Gravel cu.m. 1.136 650.00 738.40
d. Reinforcing Steel Bar kg. 141.12 40.00 5,644.80
e. #16 GI Tie Wire n(2% of RSB) kg. 2.822 47.00 132.63
f. 1/4" Ordinary Plywood -2 uses pc. 5 350.00 875.00
g. Coco Lumber - 2 uses bd.ft. 76.88 20.00 768.80
h. Assorted CWN (1 kg./100 bd.ft. of Lumber) kg. 0.769 68.00 52.29

Note: Assumed height of adjustment = 1 meter

G. Direct Unit Cost (E + F) 2,905.19


H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 261.47
I. Contractor's Profit (CP) 8% of G 232.42
J. Value Added Tax (VAT) 12% of (G + H + I) 407.89
K. Total Unit Cost (G + H + I + J) 3,806.96

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 502(8) Adjusting Inlets, Type I and I-A (to be based on Item 103, 404 & 405)
Unit of Measurement : ea.
Output : 1.00

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 2 109.19 218.38


b. Unskilled Laborer 2 2 61.44 245.76

Sub - Total for A 464.14


Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Jack Hammer 1 0.50 514.31 257.16


b. Compressor (103 Hp) 1 0.50 675.00 337.50
Minor Tools (10% of Labor) 46.41 46.41

Sub - Total for B 641.07


C. Total (A + B) 1,105.21
D. Output = 1.0000 ea.
E. Direct Unit Cost (C ÷ D) 1,105.21
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. Portland Cement bag 5 220.00 1,100.00


b. Sand cu.m. 0.195 850.00 165.75
c. Gravel cu.m. 0.391 650.00 254.15
d. Reinforcing Steel Bar kg. 17.606 40.00 704.24
e. #16 GI Tie Wire (2% of RSB) kg. 0.352 47.00 16.54
f. 1/4" Ordinary Plywood -2 uses pc. 0.77 350.00 134.75
g. Coco Lumber - 2 uses bd.ft. 20.733 20.00 207.33

h. Assorted CWN (1 kg./100 bd.ft. of Lumber) kg. 0.207 68.00 14.08

Note: Assumed height of adjustment = 0.50 meter

Sub - Total for F 2,596.84


G. Direct Unit Cost (E + F) 3,702.05
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 333.18
I. Contractor's Profit (CP) 8% of G 296.16
J. Value Added Tax (VAT) 12% of (G + H + I) 519.77
K. Total Unit Cost (G + H + I + J) 4,851.17

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 502(9)a Adjusting Catch Basin (Single Barrel, 610 mm. dia.) (to be based on Item 103, 404 & 405)
Unit of Measurement : ea.
Output : 1.00

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 5 109.19 545.95


b. Skilled Laborer 2 5 79.70 797.00
c. Laborer 4 5 61.44 1,228.80

Sub - Total for A 2,571.75


Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Jack Hammer 1 0.75 514.31 385.73


b. Compressor (103 Hp) 1 0.75 675.00 506.25
Minor Tools (10% of Labor) 257.18 257.18

Sub - Total for B 1,149.16


C. Total (A + B) 3,720.91
D. Output = 1.0000 ea.
E. Direct Unit Cost (C ÷ D) 3,720.91
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. Portland Cement bag 12 220.00 2,640.00


b. Sand cu.m. 0.52 850.00 442.00
c. Gravel cu.m. 1.04 650.00 676.00
d. Reinforcing Steel Bar kg. 58.428 40.00 2,337.12
e. #16 GI Tie Wire (2% of RSB) kg. 1.169 47.00 54.94
f. 1/4" Ordinary Plywood -2 uses pc. 6 350.00 1,050.00
g. Coco Lumber - 2 uses bd.ft. 54.67 20.00 546.70
h. Assorted CWN (1 kg./100 bd.ft. of Lumber) kg. 0.547 68.00 37.20

Note: Assumed height of adjustment = 1 meter

Sub - Total for F 7,783.96


G. Direct Unit Cost (E + F) 11,504.87
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 1,035.44
I. Contractor's Profit (CP) 8% of G 920.39
J. Value Added Tax (VAT) 12% of (G + H + I) 1,615.28
K. Total Unit Cost (G + H + I + J) 15,075.98

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 502(9)b Adjusting Catch Basin (Double Barrel, 610 mm. dia.) (to be based on Item 103, 404 & 405)
Unit of Measurement : ea.
Output : 1.00
Designation No. of Person No. of Hours Hourly Rate Amount
A. Labor

a. Construction Foreman 1 6 109.19 655.14


b. Skilled Laborer 2 6 79.70 956.40
c. Laborer 4 6 61.44 1,474.56

Sub - Total for A 3,086.10


Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Jack Hammer 1 1 514.31 514.31


b. Compressor (103 Hp) 1 1 675.00 675.00
Minor Tools (10% of Labor) 308.61 308.61

Sub - Total for B 1,497.92


C. Total (A + B) 4,584.02
D. Output = 1.0000 ea.
E. Direct Unit Cost (C ÷ D) 4,584.02
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. Portland Cement bag 17 220.00 3,740.00


b. Sand cu.m. 0.77 850.00 654.50
c. Gravel cu.m. 1.53 650.00 994.50
d. Reinfrocing Steel Bar kg. 79.659 40.00 3,186.36
e. #16 GI Tie Wire (2% of RSB) kg. 1.593 47.00 74.87
f. 1/4" Ordinary Plywood -2 uses pc. 8 350.00 1,400.00
g. Coco Lumber - 2 uses bd.ft. 67.33 20.00 673.30
h. Assorted CWN (1 kg./100 bd.ft. of RSB) kg. 0.673 68.00 45.76

Note: Assumed height of adjustment = 1 meter

Sub - Total for F 10,769.29


G. Direct Unit Cost (E + F) 15,353.31
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 1,381.80
I. Contractor's Profit (CP) 8% of G 1,228.27
J. Value Added Tax (VAT) 12% of (G + H + I) 2,155.61
K. Total Unit Cost (G + H + I + J) 20,118.98

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 503(a) Drainage Steel Grating with Frame (675mm x 975mm Sump Grating)
Unit of Measurement : set
Output per hour : 0.25

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Skilled Laborer 1 1 79.70 79.70
c. Laborer 1 1 61.44 61.44
Sub - Total for A 250.33
Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Bar Cutter 1 0.50 219.75 109.88


b. Welding Machine 1 1 391.00 391.00

Sub - Total for B 500.88


C. Total (A + B) 751.20
D. Output per hour = 0.25 set
E. Direct Unit Cost (C ÷ D) 3,004.82
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. 65mm x 5mm Flat Bar kg. 62.557 48.00 3,002.74


b. 6mm dia. x 975mm Twisted Cross Rod kg. 1.244 48.00 59.71
c. 75mm x 75mm x 9mm Angle Bar kg. 38.36 48.00 1,841.28
d. Welding Rod (1 kg./2000 kg. of Steel) kg. 0.051 90.00 4.59

Sub - Total for F 4,908.32


G. Direct Unit Cost (E + F) 7,913.14
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 712.18
I. Contractor's Profit (CP) 8% of G 633.05
J. Value Added Tax (VAT) 12% of (G + H + I) 1,111.00
K. Total Unit Cost (G + H + I + J) 10,369.38

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 503(b) Drainage Steel Grating with Frame (715mm x 2000mm Trench Grating)
Unit of Measurement : set
Output per hour : 0.125

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Skilled Laborer 1 1 79.70 79.70
c. Laborer 1 1 61.44 61.44

Sub - Total for A 250.33


Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Bar Cutter 1 0.50 219.75 109.88


b. Welding Machine 1 1 391.00 391.00
Sub - Total for B 500.88
C. Total (A + B) 751.20
D. Output per hour = 0.125 set
E. Direct Unit Cost (C ÷ D) 6,009.64
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. 65mm x 5mm Flat Bar kg. 127.066 48.00 6,099.17


b. 6mm dia. x 975mm Twisted Cross Rod kg. 3.174 48.00 152.35
c. 75mm x 75mm x 9mm Angle Bar kg. 41.64 48.00 1,998.72
d. Welding Rod (1 kg./2000 kg. of Steel) kg. 0.086 90.00 7.74

Sub - Total for F 8,257.98


G. Direct Unit Cost (E + F) 14,267.62
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 1,284.09
I. Contractor's Profit (CP) 8% of G 1,141.41
J. Value Added Tax (VAT) 12% of (G + H + I) 2,003.17
K. Total Unit Cost (G + H + I + J) 18,696.29

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 504(1)a Removing, Cleaning, Stockpilling Salvaged Culvert Pipe (24" dia) - 610 mm.
Unit of Measurement : l.m.
Output per hour : 3.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Skilled Laborer 2 1 79.70 159.40
c. Laborer 4 1 61.44 245.76

Sub - Total for A 514.35


Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Backhoe (0.80 cu.m.) 1 0.50 1,537.00 768.50


b. Boom Truck 1 0.50 961.20 480.60
c. Water Truck (1000 gal.) 1 0.25 1,065.00 266.25
Minor Tools (10% of Labor) 51.44 51.44
Sub - Total for B 1,566.78
C. Total (A + B) 2,081.13
D. Output per hour = 3.0000 l.m.
E. Direct Unit Cost (C ÷ D) 693.71
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

Sub - Total for F -


G. Direct Unit Cost (E + F) 693.71
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 62.43
I. Contractor's Profit (CP) 8% of G 55.50
J. Value Added Tax (VAT) 12% of (G + H + I) 97.40
K. Total Unit Cost (G + H + I + J) 909.04

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 504(1)b Removing, Cleaning, Stockpilling Salvaged Culvert Pipe (30" dia.) - 760 mm.
Unit of Measurement : l.m.
Output per hour : 2.50

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Skilled Laborer 2 1 79.70 159.40
c. Laborer 4 1 61.44 245.76

Sub - Total for A 514.35


Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Backhoe (0.80 cu.m.) 1 0.50 1,537.00 768.50


b. Boom Truck 1 0.50 961.20 480.60
c. Water Truck (1000 gal.) 1 0.25 1,065.00 266.25
Minor Tools (10% of Labor) 51.44 51.44

Sub - Total for B 1,566.78


C. Total (A + B) 2,081.13
D. Output per hour = 2.500 l.m.
E. Direct Unit Cost (C ÷ D) 832.45
Name and Specification Unit Quantity Unit Cost Amount

F. Materials
Sub - Total for F -
G. Direct Unit Cost (E + F) 832.45
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 74.92
I. Contractor's Profit (CP) 8% of G 66.60
J. Value Added Tax (VAT) 12% of (G + H + I) 116.88
K. Total Unit Cost (G + H + I + J) 1,090.85

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 504(1)c Removing, Cleaning, Stockpilling Salvaged Culvert Pipe (36" dia.) - 910 mm.
Unit of Measurement : l.m.
Output per hour : 2.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Skilled Laborer 2 1 79.70 159.40
c. Laborer 4 1 61.44 245.76

Sub - Total for A 514.35


Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Backhoe (0.80 cu.m.) 1 0.50 1,537.00 768.50


b. Boom Truck 1 0.50 961.20 480.60
c. Water Truck (1000 gal.) 1 0.25 1,065.00 266.25
Minor Tools (10% of Labor) 51.44 51.44

Sub - Total for B 1,566.78


C. Total (A + B) 2,081.13
D. Output per hour = 2.0000 l.m.
E. Direct Unit Cost (C ÷ D) 1,040.57
Name and Specification Unit Quantity Unit Cost Amount

F. Materials
Sub - Total for F -
G. Direct Unit Cost (E + F) 1,040.57
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 93.65
I. Contractor's Profit (CP) 8% of G 83.25
J. Value Added Tax (VAT) 12% of (G + H + I) 146.10
K. Total Unit Cost (G + H + I + J) 1,363.56

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 504(1)d Removing, Cleaning, Stockpilling Salvaged Culvert Pipe (42" dia.) - 1070 mm.
Unit of Measurement : l.m.
Output per hour : 2.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Skilled Laborer 2 1 79.70 159.40
c. Laborer 4 1 61.44 245.76

Sub - Total for A 514.35


Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Backhoe (0.80 cu.m.) 1 0.50 1,537.00 768.50


b. Boom Truck 1 0.50 961.20 480.60
c. Water Truck (1000 gal.) 1 0.25 1,065.00 266.25
Minor Tools (10% of Labor) 51.44 51.44

Sub - Total for B 1,566.78


C. Total (A + B) 2,081.13
D. Output per hour = 2.0000 l.m.
E. Direct Unit Cost (C ÷ D) 1,040.57
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

Sub - Total for F -


G. Direct Unit Cost (E + F) 1,040.57
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 93.65
I. Contractor's Profit (CP) 8% of G 83.25
J. Value Added Tax (VAT) 12% of (G + H + I) 146.10
K. Total Unit Cost (G + H + I + J) 1,363.56

DETAILED UNIT PRICE ANALYSIS (DUPA)


Item No./Description : 504(1)e Removing, Cleaning, Stockpilling Salvaged Culvert Pipe (48" dia.) - 1220 mm.
Unit of Measurement : l.m.
Output per hour : 1.50

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Skilled Laborer 2 1 79.70 159.40
c. Laborer 4 1 61.44 245.76

Sub - Total for A 514.35


Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Backhoe (0.80 cu.m.) 1 0.50 1,537.00 768.50


b. Boom Truck 1 0.50 961.20 480.60
c. Water Truck (1000 gal.) 1 0.25 1,065.00 266.25
Minor Tools (10% of Labor) 51.44 51.44

Sub - Total for B 1,566.78


C. Total (A + B) 2,081.13
D. Output per hour = 1.500 l.m.
E. Direct Unit Cost (C ÷ D) 1,387.42
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

Sub - Total for F -


G. Direct Unit Cost (E + F) 1,387.42
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 124.87
I. Contractor's Profit (CP) 8% of G 110.99
J. Value Added Tax (VAT) 12% of (G + H + I) 194.79
K. Total Unit Cost (G + H + I + J) 1,818.08

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 504(2)a Removing, Cleaning & Re-laying Salvaged Culvert Pipe (24" dia.) - 610 mm.
Unit of Measurement : l.m.
Output per hour : 1.50

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Skilled Laborer 2 1 79.70 159.40
c. Laborer 4 1 61.44 245.76

Sub - Total for A 514.35


Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Backhoe (0.80 cu.m.) 1 0.60 1,537.00 922.20


b. Plate Compactor (5 Hp) 1 0.60 123.00 73.80
c. Water Truck (1000 gal.) 1 0.15 1,065.00 159.75
Minor Tools (10 % of Labor) 51.44 51.44

Sub - Total for B 1,207.19


C. Total (A + B) 1,721.53
D. Output per hour = 1.500 l.m.
E. Direct Unit Cost (C ÷ D) 1,147.69
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. Portland Cement bag 0.774 220.00 170.28


b. Sand cu.m. 0.044 850.00 37.40
c. Sand Bedding cu.m. 0.088 850.00 74.80

Sub - Total for F 282.48


G. Direct Unit Cost (E + F) 1,430.17
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 128.72
I. Contractor's Profit (CP) 8% of G 114.41
J. Value Added Tax (VAT) 12% of (G + H + I) 200.80
K. Total Unit Cost (G + H + I + J) 1,874.09

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 504(2)b Removing, Cleaning & Re-laying Salvaged Culvert Pipe (30" dia.) - 760 mm.
Unit of Measurement : l.m.
Output per hour : 1.25

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Skilled Laborer 2 1 79.70 159.40
c. Laborer 4 1 61.44 245.76

Sub - Total for A 514.35


Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment
a. Backhoe (0.80 cu.m.) 1 0.60 1,537.00 922.20
b. Plate Compactor (5 Hp) 1 0.60 123.00 73.80
c. Water Truck (1000 gal.) 1 0.15 1,065.00 159.75
Minor Tools (10 % of Labor) 51.44 51.44

Sub - Total for B 1,207.19


C. Total (A + B) 1,721.53
D. Output per hour = 1.25 l.m.
E. Direct Unit Cost (C ÷ D) 1,377.23
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. Portland Cement bag 0.918 220.00 201.96


b. Sand cu.m. 0.052 850.00 44.20
c. Sand Bedding cu.m. 0.108 850.00 91.80

Sub - Total for F 337.96


G. Direct Unit Cost (E + F) 1,715.19
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 154.37
I. Contractor's Profit (CP) 8% of G 137.22
J. Value Added Tax (VAT) 12% of (G + H + I) 240.81
K. Total Unit Cost (G + H + I + J) 2,247.58

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 504(2)c Removing, Cleaning & Re-laying Salvaged Culvert Pipe (36" dia.) - 910 mm.
Unit of Measurement : l.m.
Output per hour : 1.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Skilled Laborer 2 1 79.70 159.40
c. Laborer 4 1 61.44 245.76

Sub - Total for A 514.35


Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Backhoe (0.80 cu.m.) 1 0.60 1,537.00 922.20


b. Plate Compactor (5 Hp) 1 0.60 123.00 73.80
c. Water Truck (1000 gal.) 1 0.15 1,065.00 159.75
Minor Tools (10 % of Labor) 51.44 51.44
Sub - Total for B 1,207.19
C. Total (A + B) 1,721.53
D. Output per hour = 1.00 l.m.
E. Direct Unit Cost (C ÷ D) 1,721.53
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. Portland Cement bag 1.080 220.00 237.60


b. Sand cu.m. 0.061 850.00 51.85
c. Sand Bedding cu.m. 0.128 850.00 108.80

Sub - Total for F 398.25


G. Direct Unit Cost (E + F) 2,119.79
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 190.78
I. Contractor's Profit (CP) 8% of G 169.58
J. Value Added Tax (VAT) 12% of (G + H + I) 297.62
K. Total Unit Cost (G + H + I + J) 2,777.77

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 504(2)d Removing, Cleaning and Re-laying Salvaged Culvert Pipe (42" dia.) - 1070 mm.
Unit of Measurement : l.m.
Output per hour : 1.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Skilled Laborer 2 1 79.70 159.40
c. Laborer 4 1 61.44 245.76

Sub - Total for A 514.35


Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Backhoe (0.80 cu.m.) 1 0.60 1,537.00 922.20


b. Plate Compactor (5 Hp) 1 0.60 123.00 73.80
c. Water Truck (1000 gal.) 1 0.15 1,065.00 159.75
Minor Tools (10 % of Labor) 51.44 51.44

Sub - Total for B 1,207.19


C. Total (A + B) 1,721.53
D. Output per hour = 1.00 l.m.
E. Direct Unit Cost (C ÷ D) 1,721.53
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Portland Cement bag 1.242 220.00 273.24


b. Sand cu.m. 0.070 850.00 59.50
c. Sand Bedding cu.m. 0.149 850.00 126.65

Sub - Total for F 459.39


G. Direct Unit Cost (E + F) 2,180.92
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 196.28
I. Contractor's Profit (CP) 8% of G 174.47
J. Value Added Tax (VAT) 12% of (G + H + I) 306.20
K. Total Unit Cost (G + H + I + J) 2,857.88

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 504(2)e Removing, Cleaning and Re-laying Salvaged Culvert Pipe (48" dia.) - 1220 mm.
Unit of Measurement : l.m.
Output per hour : 0.75

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Skilled Laborer 2 1 79.70 159.40
c. Laborer 4 1 61.44 245.76

Sub - Total for A 514.35


Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Backhoe (0.80 cu.m.) 1 0.60 1,537.00 922.20


b. Plate Compactor (5 Hp) 1 0.60 123.00 73.80
c. Water Truck (1000 gal.) 1 0.15 1,065.00 159.75
Minor Tools (10 % of Labor) 51.44 51.44

Sub - Total for B 1,207.19


C. Total (A + B) 1,721.53
D. Output per hour = 0.75 l.m.
E. Direct Unit Cost (C ÷ D) 2,295.38
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. Portland Cement bag 1.404 220.00 308.88


b. Sand cu.m. 0.080 850.00 68.00
c. Sand Bedding cu.m. 0.170 850.00 144.50
Sub - Total for F 521.38
G. Direct Unit Cost (E + F) 2,816.76
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 253.51
I. Contractor's Profit (CP) 8% of G 225.34
J. Value Added Tax (VAT) 12% of (G + H + I) 395.47
K. Total Unit Cost (G + H + I + J) 3,691.08

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 504(3)a Cleaning Culvert Pipe in place (610mm dia.) - Half Silted
Unit of Measurement : l.m.
Output per hour : 8.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Skilled Laborer 2 1 79.70 159.40
c. Laborer 4 1 61.44 245.76

Sub - Total for A 514.35


Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Cargo Truck (10 T) 1 1 1,102.00 1,102.00


b. Steel Wheel with Nylon Rope l.s. 300.00 300.00
c. Improvised Bamboo with Bucket l.s. 200.00 200.00
Minor Tools (10% of Labor) 51.44 51.44

Sub - Total for B 1,653.44


C. Total (A + B) 2,167.79
D. Output per hour = 8.0000 l.m.
E. Direct Unit Cost (C ÷ D) 270.97
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

Sub - Total for F -


G. Direct Unit Cost (E + F) 270.97
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 24.39
I. Contractor's Profit (CP) 8% of G 21.68
J. Value Added Tax (VAT) 12% of (G + H + I) 38.04
K. Total Unit Cost (G + H + I + J) 355.08
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 504(3)b Cleaning Culvert Pipe in place (760mm dia.) - Half Silted
Unit of Measurement : l.m.
Output per hour : 5.25

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Skilled Laborer 2 1 79.70 159.40
c. Laborer 4 1 61.44 245.76

Sub - Total for A 514.35


Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Cargo Truck (10 T) 1 1 1,102.00 1,102.00


b. Steel Wheel with Nylon Rope l.s. 300.00 300.00
c. Improvised Bamboo with Bucket l.s. 200.00 200.00
Minor Tools (10% of Labor) 51.44 51.44

Sub - Total for B 1,653.44


C. Total (A + B) 2,167.79
D. Output per hour = 5.25 l.m.
E. Direct Unit Cost (C ÷ D) 412.91
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

Sub - Total for F -


G. Direct Unit Cost (E + F) 412.91
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 37.16
I. Contractor's Profit (CP) 8% of G 33.03
J. Value Added Tax (VAT) 12% of (G + H + I) 57.97
K. Total Unit Cost (G + H + I + J) 541.08

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 504(3)c Cleaning Culvert Pipe in place (910mm dia.) - Half Silted
Unit of Measurement : l.m.
Output per hour : 3.75

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Skilled Laborer 2 1 79.70 159.40
c. Laborer 4 1 61.44 245.76

Sub - Total for A 514.35


Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Cargo Truck (10 T) 1 1 1,102.00 1,102.00


Minor Tools (10% of Labor) 51.44 51.44

Sub - Total for B 1,153.44


C. Total (A + B) 1,667.78
D. Output per hour = 3.75 l.m.
E. Direct Unit Cost (C ÷ D) 444.74
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

Sub - Total for F -


G. Direct Unit Cost (E + F) 444.74
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 40.03
I. Contractor's Profit (CP) 8% of G 35.58
J. Value Added Tax (VAT) 12% of (G + H + I) 62.44
K. Total Unit Cost (G + H + I + J) 582.79

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 504(3)d Cleaning Culvert Pipe in place (1070mm dia.) - Half Silted
Unit of Measurement : l.m.
Output per hour : 2.75

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Skilled Laborer 2 1 79.70 159.40
c. Laborer 4 1 61.44 245.76

Sub - Total for A 514.35


Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Cargo Truck (10 T) 1 1 1,102.00 1,102.00


Minor Tools (10% of Labor) 51.44 51.44

Sub - Total for B 1,153.44


C. Total (A + B) 1,667.78
D. Output per hour = 2.75 l.m.
E. Direct Unit Cost (C ÷ D) 606.47
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

Sub - Total for F -


G. Direct Unit Cost (E + F) 606.47
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 54.58
I. Contractor's Profit (CP) 8% of G 48.52
J. Value Added Tax (VAT) 12% of (G + H + I) 85.15
K. Total Unit Cost (G + H + I + J) 794.71

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 504(3)e Cleaning Culvert Pipe in place (1220mm dia.) - Half Silted
Unit of Measurement : l.m.
Output per hour : 2.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Skilled Laborer 2 1 79.70 159.40
c. Laborer 4 1 61.44 245.76

Sub - Total for A 514.35


Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Cargo Truck (10 T) 1 1 1,102.00 1,102.00


Minor Tools (10% of Labor) 51.44 51.44
Sub - Total for B 1,153.44
C. Total (A + B) 1,667.78
D. Output per hour = 2.0000 l.m.
E. Direct Unit Cost (C ÷ D) 833.89
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

Sub - Total for F -


G. Direct Unit Cost (E + F) 833.89
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 75.05
I. Contractor's Profit (CP) 8% of G 66.71
J. Value Added Tax (VAT) 12% of (G + H + I) 117.08
K. Total Unit Cost (G + H + I + J) 1,092.73

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 504(3)f Cleaning Culvert Pipe in place (1520mm dia.) - Half Silted
Unit of Measurement : l.m.
Output per hour : 1.50

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Skilled Laborer 2 1 79.70 159.40
c. Laborer 4 1 61.44 245.76

Sub - Total for A 514.35


Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Cargo Truck (10 T) 1 1 1,102.00 1,102.00


Minor Tools (10% of Labor) 51.44 51.44

Sub - Total for B 1,153.44


C. Total (A + B) 1,667.78
D. Output per hour = 1.500 l.m.
E. Direct Unit Cost (C ÷ D) 1,111.86
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

Sub - Total for F -


G. Direct Unit Cost (E + F) 1,111.86
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 100.07
I. Contractor's Profit (CP) 8% of G 88.95
J. Value Added Tax (VAT) 12% of (G + H + I) 156.10
K. Total Unit Cost (G + H + I + J) 1,456.98

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 504(4) Reconditioning Drainage Structures


Unit of Measurement : ea.
Output : 1.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 0.50 109.19 54.60


b. Skilled Laborer 1 0.50 79.70 39.85
c. Laborer 2 0.50 61.44 61.44

Sub - Total for A 155.89


Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Cargo Truck (10 T) 1 0.25 1,102.00 275.50


b. Bamboo with Bucket - 4 uses 1 1 200.00 50.00
Minor Tools (10% of Labor) 15.59 15.59

Sub - Total for B 341.09


C. Total (A + B) 496.97
D. Output = 1.000 ea.
E. Direct Unit Cost (C ÷ D) 496.97
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

* If some repair is needed, component materials required and


correcsponding man-hour will be added to DUPA
Sub - Total for F -
G. Direct Unit Cost (E + F) 496.97
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 44.73
I. Contractor's Profit (CP) 8% of G 39.76
J. Value Added Tax (VAT) 12% of (G + H + I) 69.78
K. Total Unit Cost (G + H + I + J) 651.23

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 505(1) Riprap (Class A)


Unit of Measurement : cu.m.
Output per hour : 1.50

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Skilled Laborer 2 1 79.70 159.40
c. Laborer 8 1 61.44 491.52

Sub - Total for A 760.11


Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

Minor Tools (5% of Labor) 38.01

Sub - Total for B 38.01


C. Total (A + B) 798.12
D. Output per hour = 1.50 cu.m.
E. Direct Unit Cost (C ÷ D) 532.08
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. Boulders (15 - 25 kg.) cu.m. 1.05 920.00 966.00


Miscellaneous (1% of Materials) 9.66

Sub - Total for F 975.66


G. Direct Unit Cost (E + F) 1,507.74
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 135.70
I. Contractor's Profit (CP) 8% of G 120.62
J. Value Added Tax (VAT) 12% of (G + H + I) 211.69
K. Total Unit Cost (G + H + I + J) 1,975.74

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 505(2) Riprap (Class B)


Unit of Measurement : cu.m.
Output per hour : 1.25

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Skilled Laborer 2 1 79.70 159.40
c. Laborer 4 1 61.44 245.76

Sub - Total for A 514.35


Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Backhoe (Wheel Type 0.28 cu.m.) 1 0.50 840.00 420.00


Minor Tools (5% of Labor) 25.72

Sub - Total for B 445.72


C. Total (A + B) 960.07
D. Output per hour = 1.25 cu.m.
E. Direct Unit Cost (C ÷ D) 768.05
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. Boulders (30 - 70 kg.) cu.m. 1.05 810.00 850.50


Miscellaneous (1% of Materials) 8.51

Sub - Total for F 859.01


G. Direct Unit Cost (E + F) 1,627.06
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 146.44
I. Contractor's Profit (CP) 8% of G 130.16
J. Value Added Tax (VAT) 12% of (G + H + I) 228.44
K. Total Unit Cost (G + H + I + J) 2,132.10

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 505(3) Riprap (Class C)


Unit of Measurement : cu.m.
Output per hour : 1.00
Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Skilled Laborer 2 1 79.70 159.40
c. Laborer 4 1 61.44 245.76

Sub - Total for A 514.35


Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

c. Backhoe (Wheel Type 0.28 cu.m.) 1 0.75 840.00 630.00


Minor Tools (5% of Labor) 25.72

Sub - Total for B 655.72


C. Total (A + B) 1,170.07
D. Output per hour = 1.000 cu.m.
E. Direct Unit Cost (C ÷ D) 1,170.07
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. Boulders (50 - 100 kg.) cu.m. 1.05 740.00 777.00


Miscellaneous (1% of Materials) 7.77

Sub - Total for F 784.77


G. Direct Unit Cost (E + F) 1,954.84
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 175.94
I. Contractor's Profit (CP) 8% of G 156.39
J. Value Added Tax (VAT) 12% of (G + H + I) 274.46
K. Total Unit Cost (G + H + I + J) 2,561.62

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 505(4) Riprap (Class D)


Unit of Measurement : cu.m.
Output per hour : 0.75

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Skilled Laborers 2 1 79.70 159.40
c. Laborers 4 1 61.44 245.76
Sub - Total for A 514.35
Name and Capacity No of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Backhoe (Wheel Type 0.28 cu.m.) 1 1.00 840.00 840.00


Minor Tools (5% of Labor) 25.72

Sub - Total for B 865.72


C. Total (A + B) 1,380.07
D. Output per hour = 0.75 cu.m.
E. Direct Unit Cost (C ÷ D) 1,840.09
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. Boulders (100 - 200 kg.) cu.m. 1.05 650.00 682.50


Miscellaneous (1% of Materials) 6.83

Sub - Total for F 689.33


G. Direct Unit Cost (E + F) 2,529.42
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 227.65
I. Contractor's Profit (CP) 8% of G 202.35
J. Value Added Tax (VAT) 12% of (G + H + I) 355.13
K. Total Unit Cost (G + H + I + J) 3,314.55
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 505(5) Grouted Riprap (Class A)


Unit of Measurement : cu.m.
Output per hour : 1.25

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Skilled Laborer 2 1 79.70 159.40
c. Laborer 8 1 61.44 491.52

Sub - Total for A 760.11


Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. One Bagger Mixer 1 1 172.00 172.00


b. Water Truck (1000 gal.) 1 0.05 1,065.00 53.25
Minor Tools (5% of Labor) 38.01

Sub - Total for B 263.26


C. Total (A + B) 1,023.37
D. Output per hour = 1.25 cu.m.
E. Direct Unit Cost (C ÷ D) 818.69
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. Cement bag 3.00 250.00 750.00


b. Sand cu.m. 0.25 850.00 212.50
c. Gravel Fill cu.m. 0.015 650.00 9.75
d. Weep Holes (PVC) l.m. 0.30 207.15 62.14
e. Filter Cloth sq.m. 0.015 370.00 5.55
f. Boulders (15 - 25 kg.) cu.m. 1.05 1,020.00 1,071.00
Miscellaneous (1% of Materials) 21.11

Sub - Total for F 2,132.05


G. Direct Unit Cost (E + F) 2,950.75
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 265.57
I. Contractor's Profit (CP) 8% of G 236.06
J. Value Added Tax (VAT) 12% of (G + H + I) 414.28
K. Total Unit Cost (G + H + I + J) 3,866.66

Prepared by: Checked by:

ALLISTER G. NACALABAN
Contractor Project Engineer
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 505(6) Grouted Riprap (Class B)


Unit of Measurement : cu.m.
Output per hour : 1.00

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Skilled Laborer 2 1 79.70 159.40
c. Laborer 8 1 61.44 491.52

Sub - Total for A 760.11


Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. One Bagger Mixer 1 1 172.00 172.00


b. Water Truck (1000 gal.) 1 0.05 1,065.00 53.25
c. Backhoe (Wheel Type 0.28 cu.m.) 1 0.50 840.00 420.00
Minor Tools (5% of Labor) 38.01

Sub - Total for B 683.26


C. Total (A + B) 1,443.37
D. Output per hour = 1.000 cu.m.
E. Direct Unit Cost (C ÷ D) 1,443.37
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. Cement bag 2.50 220.00 550.00


b. Sand cu.m. 0.21 850.00 178.50
c. Gravel Fill cu.m. 0.015 650.00 9.75
d. Weep Holes (PVC) l.m. 0.30 144.67 43.40
e. Filter Cloth sq.m. 0.015 275.00 4.13
f. Boulders (30 - 70 kg.) cu.m. 1.05 810.00 850.50
Miscellaneous (1% of Materials) 16.36

Sub - Total for F 1,652.64


G. Direct Unit Cost (E + F) 3,096.00
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 278.64
I. Contractor's Profit (CP) 8% of G 247.68
J. Value Added Tax (VAT) 12% of (G + H + I) 434.68
K. Total Unit Cost (G + H + I + J) 4,057.00

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 505(7) Grouted Riprap (Class C)


Unit of Measurement : cu.m.
Output per hour : 0.75

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor
a. Construction Foreman 1 1 109.19 109.19
b. Skilled Laborer 2 1 79.70 159.40
c. Laborer 8 1 61.44 491.52

Sub - Total for A 760.11


Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. One Bagger Mixer 1 1 172.00 172.00


b. Water Truck (1000 gal.) 1 0.05 1,065.00 53.25
Minor Tools (5% of Labor) 38.01

Sub - Total for B 263.26


C. Total (A + B) 1,023.37
D. Output per hour = 0.75 cu.m.
E. Direct Unit Cost (C ÷ D) 1,364.49
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. Cement bag 2.20 220.00 484.00


b. Sand cu.m. 0.18 850.00 153.00
c. Gravel Fill cu.m. 0.015 650.00 9.75
d. Weep Holes (PVC) l.m. 0.30 144.67 43.40
e. Filter Cloth sq.m. 0.015 275.00 4.13
f. Boulders (60 - 100 kg.) cu.m. 1.05 730.00 766.50
Miscellaneous (1% of Materials) 14.61

Sub - Total for F 1,475.38


G. Direct Unit Cost (E + F) 2,839.87
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 255.59
I. Contractor's Profit (CP) 8% of G 227.19
J. Value Added Tax (VAT) 12% of (G + H + I) 398.72
K. Total Unit Cost (G + H + I + J) 3,721.37

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 505(8) Grouted Riprap (Class D)


Unit of Measurement : cu.m.
Output per hour : 0.50

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Skilled Laborer 2 1 79.70 159.40
c. Laborer 8 1 61.44 491.52

Sub - Total for A 760.11


Name and Capacity No of Units No. of Hours Hourly Rate Amount
B. Equipment

a. One Bagger Mixer 1 1 172.00 172.00


b. Water Truck (1000 gal.) 1 0.05 1,065.00 53.25
Minor Tools (5% of Labor) 38.01

Sub - Total for B 263.26


C. Total (A + B) 1,023.37
D. Output per hour = 0.50 cu.m.
E. Direct Unit Cost (C ÷ D) 2,046.73
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. Cement bag 1.80 220.00 396.00


b. Sand cu.m. 0.15 850.00 127.50
c. Gravel Fill cu.m. 0.015 650.00 9.75
d. Weep Holes (PVC) l.m. 0.30 144.67 43.40
e. Filter Cloth sq.m. 0.015 275.00 4.13
f. Boulders (100 - 200 kg.) cu.m. 1.05 650.00 682.50
Miscellaneous (1% of Materials) 12.63

Sub - Total for F 1,275.91


G. Direct Unit Cost (E + F) 3,322.64
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 299.04
I. Contractor's Profit (CP) 8% of G 265.81
J. Value Added Tax (VAT) 12% of (G + H + I) 466.50
K. Total Unit Cost (G + H + I + J) 4,353.99

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 505(9) Filter Layer of Granular Material


Unit of Measurement : cu.m.
Output per hour : 1.00

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Skilled Laborer 1 1 79.70 79.70
c. Laborer 2 1 61.44 122.88

Sub - Total for A 311.77


Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

Minor Tools (10% of Labor) 31.18


Sub - Total for B 31.18
C. Total (A + B) 342.95
D. Output per hour = 1.0000 cu.m.
E. Direct Unit Cost (C ÷ D) 342.95
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. Granular Materials cu.m. 1.05 900.00 945.00

Sub - Total for F 945.00


G. Direct Unit Cost (E + F) 1,287.95
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 115.92
I. Contractor's Profit (CP) 8% of G 103.04
J. Value Added Tax (VAT) 12% of (G + H + I) 180.83
K. Total Unit Cost (G + H + I + J) 1,687.73

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 506 Stone Masonry


Unit of Measurement : cu.m.
Output per hour : 1.5625

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Skilled Laborer 2 1 79.70 159.40
c. Laborer 8 1 61.44 491.52

Sub - Total for A 760.11


Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. One Bagger Mixer 1 1 172.00 172.00


b. Water Truck (1000 gal.) 1 0.05 1,065.00 53.25
c. Backhoe (Wheel Type 0.28 cu.m.) 1 0.10 840.00 84.00
Minor Tools (10% Labor) 76.01

Sub - Total for B 385.26


C. Total (A + B) 1,145.37
D. Output per hour =1.5625 cu.m.
E. Direct Unit Cost (C ÷ D) 733.04
Name and Specification Unit Quantity Unit Cost Amount
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. Cement bag 5.50 220.00 1,210.00


b. Sand cu.m. 0.30 850.00 255.00
c. Gravel Fill cu.m. 0.02 650.00 13.00
d. Weep Holes (PVC) l.m. 0.30 144.67 43.40
e. Filter Cloth sq.m. 0.015 275.00 4.13
f. Boulders cu.m. 1.05 920.00 966.00
Miscellaneous (1% of Materials) 24.92

Sub - Total for F 2,516.44


G. Direct Unit Cost (E + F) 3,249.48
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 292.45
I. Contractor's Profit (CP) 8% of G 259.96
J. Value Added Tax (VAT) 12% of (G + H + I) 456.23
K. Total Unit Cost (G + H + I + J) 4,258.12

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 507 Rubble Concrete


Unit of Measurement : cu.m.
Output per hour : 1.40

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Skilled Laborer 2 1 79.70 159.40
c. Laborer 8 1 61.44 491.52

Sub - Total for A 760.11


Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. One Bagger Mixer 1 1 172.00 172.00


b. Water Truck (1000 gal.) 1 0.05 1,065.00 53.25
c. Backhoe (Wheel Type 0.28 cu.m.) 1 0.10 840.00 84.00
Minor Tools (10% Labor) 76.01

Sub - Total for B 385.26


C. Total (A + B) 1,145.37
D. Output per hour = 1.400 cu.m.
E. Direct Unit Cost (C ÷ D) 818.12
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. Cement bag 4.20 220.00 924.00


b. Sand cu.m. 0.2625 850.00 223.13
c. Gravel Fill cu.m. 0.02 650.00 13.00
d. Weep Holes (PVC) l.m. 0.30 144.67 43.40
e. Filter Cloth sq.m. 0.015 275.00 4.13
f. Boulders cu.m. 0.63 810.00 510.30
g. Gravel cu.m. 0.525 650.00 341.25
Miscellaneous (2% of Materials) 36.72
Note:
60% Boulder
50% Class "B" Concrete (w/ side forms only)

Sub - Total for F 2,095.92


G. Direct Unit Cost (E + F) 2,914.04
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 262.26
I. Contractor's Profit (CP) 8% of G 233.12
J. Value Added Tax (VAT) 12% of (G + H + I) 409.13
K. Total Unit Cost (G + H + I + J) 3,818.56

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 508 Hand Laid Rock Embankment


Unit of Measurement : cu.m.
Output per hour : 3.125

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Skilled Laborer 2 1 79.70 159.40
c. Laborer 8 1 61.44 491.52

Sub - Total for A 760.11


Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

Minor Tools (10% of Labor) 76.01

Sub - Total for B 76.01


C. Total (A + B) 836.12
D. Output per hour = 3.125 cu.m.
E. Direct Unit Cost (C ÷ D) 267.56
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. Boulders cu.m. 1.05 920.00 966.00

Sub - Total for F 966.00


G. Direct Unit Cost (E + F) 1,233.56
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 111.02
I. Contractor's Profit (CP) 8% of G 98.68
J. Value Added Tax (VAT) 12% of (G + H + I) 173.19
K. Total Unit Cost (G + H + I + J) 1,616.46

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 509(a) Timber Sheet Pile


Unit of Measurement : l.m.
Output per hour : 4.00

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Skilled Laborer 1 1 79.70 79.70
c. Laborer 2 1 61.44 122.88

Sub - Total for A 311.77


Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Crawler Crane (45 T) 1 1 1,772.00 1,772.00


b. Drop Hammer (15 T) 1 1 200.00 200.00
Minor Tools (10% of Labor) 31.18

Sub - Total for B 2,003.18


C. Total (A + B) 2,314.95
D. Output per hour = 4.0000 l.m.
E. Direct Unit Cost (C ÷ D) 578.74
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. Timber Sheet Piles, 3" x 12" x 3.28' bd.ft. 9.84 40.00 393.60
b. Coco Log - 2 uses m. 1.00 350.00 175.00
c. Lumber (Falsework) - 4 uses bd.ft. 16.00 40.00 160.00
d. Nail/Spike (1 kg./100 bd.ft. of Lumber) kg. 0.16 68.00 10.88

Sub - Total for F 739.48


G. Direct Unit Cost (E + F) 1,318.22
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 118.64
I. Contractor's Profit (CP) 8% of G 105.46
J. Value Added Tax (VAT) 12% of (G + H + I) 185.08
K. Total Unit Cost (G + H + I + J) 1,727.39

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 509(b)1 Steel Sheet Pile (Slope Protection)


Unit of Measurement : l.m.
Output per hour : 10.00

Designation No. of Person No. of Hours Hourly Rate Amount


Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Skilled Laborer 2 1 79.70 159.40
c. Laborer 4 1 61.44 245.76

Sub - Total for A 514.35


Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Crawler Crane (36 - 40 T) 1 1 1,729.00 1,729.00


b. Vibro Hammer (Hydraulic Operated) 1 1 1,800.00 1,800.00
c. Welding Machine (Gas Operated) 1 0.25 371.00 92.75
d. Cutting Outfit 1 0.25 45.45 11.36

Sub - Total for B 3,633.11


C. Total (A + B) 4,147.46
D. Output per hour = 10.0000 l.m.
E. Direct Unit Cost (C ÷ D) 414.75
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. Steel Sheet Piles (48 kg./l.m.) kg. 48.00 48.00 2,304.00


Miscellaneous (3% of Materials) 69.12

Sub - Total for F 2,373.12


G. Direct Unit Cost (E + F) 2,787.87
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 250.91
I. Contractor's Profit (CP) 8% of G 223.03
J. Value Added Tax (VAT) 12% of (G + H + I) 391.42
K. Total Unit Cost (G + H + I + J) 3,653.22

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 509(b)2 Steel Sheet Pile (for Cofferdaming)


Unit of Measurement : l.m.
Output per hour : 10.00

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Skilled Laborer 2 1 79.70 159.40
c. Laborer 4 1 61.44 245.76
Sub - Total for A 514.35
Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Crawler Crane (36 - 40 T) 1 1 1,729.00 1,729.00


b. Vibro Hammer (Hydraulic Operated) 1 1 1,800.00 1,800.00
c. Welding Machine 1 0.25 391.00 97.75
d. Cutting Outfit 1 0.25 45.45 11.36
e. Water Pump 1 1 -

Sub - Total for B 3,638.11


C. Total (A + B) 4,152.46
D. Output per hour = 10.0000 l.m.
E. Direct Unit Cost (C ÷ D) 415.25
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. Steel Sheet Piles (48 kg./l.m.) kg. 48.00 48.00 2,304.00


b. Structural Steel (Walling, Bracing, kg. 4.80 48.00 230.40
Diagonal etc.)

Sub - Total for F 2,534.40


G. Direct Unit Cost (E + F) 2,949.65
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 265.47
I. Contractor's Profit (CP) 8% of G 235.97
J. Value Added Tax (VAT) 12% of (G + H + I) 414.13
K. Total Unit Cost (G + H + I + J) 3,865.22

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 509(c) Concrete Sheet Pile, furnished and driven


Unit of Measurement : l.m.
Output per hour : 1.20

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Skilled Laborer 4 1 79.70 318.80
c. Laborer 6 1 61.44 368.64
Formworks
b. Skilled Laborer 2 1 79.70 159.40
c. Laborer 4 1 61.44 245.76

Sub - Total for A 1,201.79


Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Crawler Crane (45 T) 1 0.10 1,772.00 177.20


b. One Bagger Mixer 1 0.40 172.00 68.80
c. Concrete Vibrator 1 0.15 148.88 22.33
d. Water Truck (1000 gal.) 1 0.03 1,065.00 31.95
e. Bar Cutter 1 0.03 219.75 6.59
f. Bar Bender 1 0.03 351.50 10.55
g. Drop Hammer 1 0.10 200.00 20.00
h. Jack Hammer 1 0.10 514.31 51.43
i. Air Compressor (103 Hp) 1 0.10 675.00 67.50
j. Plate Compactor (5 Hp) 1 0.03 123.00 3.69
Minor Tools (5% of Labor) 60.09

Sub - Total for B 520.13


C. Total (A + B) 1,721.92
D. Output per hour = 1.200 l.m.
E. Direct Unit Cost (C ÷ D) 1,434.93
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. Reinforcing Steel Bar kg. 28.11 40.00 1,124.40


b. Cement bag 1.44 220.00 316.80
c. Sand cu.m. 0.08 850.00 68.00
d. Gravel cu.m. 0.15 650.00 97.50
e. Marine Plywood, 1/2" x 4' x 8' pc. 0.15 700.00 105.00
f. Lumber, 2' x 2' bd.ft. 5.90 40.00 236.00
g. # 16 GI Tie Wire (2% of RSB) kg. 0.562 47.00 26.41
h. Assorted CWN (1 kg./100 bd.ft. of Lumber) kg. 0.059 68.00 4.01
Casting Bed
a. Ready Mix Concrete cu.m 0.030 2,840.00 85.20
b. Coco Lumber - 4 uses bd.ft. 1.500 20.00 7.50
c. Base Course cu.m 0.030 530.00 15.90
Sub - Total for F 2,086.73
G. Direct Unit Cost (E + F) 3,521.66
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 316.95
I. Contractor's Profit (CP) 8% of G 281.73
J. Value Added Tax (VAT) 12% of (G + H + I) 494.44
K. Total Unit Cost (G + H + I + J) 4,614.78

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 510(1) Bed Course Granular Material


Unit of Measurement : cu.m. in-place
Output per hour : 1.25

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Laborer 4 1 61.44 245.76

Sub - Total for A 354.95


Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Plate Compactor 1 1 123.00 123.00


Minor Tools (10% of Labor) 35.50

Sub - Total for B 158.50


C. Total (A + B) 513.44
D. Output per hour = 1.25 cu.m. in-place
E. Direct Unit Cost (C ÷ D) 410.76
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. Aggregate Subbase Course cu.m. 1.15 580.00 667.00


(w/ 15% Shrinkage Factor)

Sub - Total for F 667.00


G. Direct Unit Cost (E + F) 1,077.76
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 97.00
I. Contractor's Profit (CP) 8% of G 86.22
J. Value Added Tax (VAT) 12% of (G + H + I) 151.32
K. Total Unit Cost (G + H + I + J) 1,412.29

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 510(2) Concrete Slope Protection


Unit of Measurement : cu.m. in-place
Output per hour : 1.00

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Skilled Laborer 4 1 79.70 318.80
c. Laborer 8 1 61.44 491.52
Installation of Formworks & Rebars
a. Skilled Laborer 2 1 79.70 159.40
b. Laborer 4 1 61.44 245.76

Sub - Total for A 1,324.67


Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. One Bagger Mixer 1 1 172.00 172.00


b. Water Truck (1000 gal.) 1 0.05 1,065.00 53.25
c. Backhoe (Wheel Type 0.28 cu.m.) 1 0.10 840.00 84.00
d. Concrete Vibrator 1 0.05 148.88 7.44
e. Bar Cutter 1 0.05 219.75 10.99
f. Bar Bender 1 0.05 351.50 17.58
Minor Tools (10% Labor) 132.47

Sub - Total for B 477.72


C. Total (A + B) 1,802.39
D. Output per hour = 1.0000 cu.m. in-place
E. Direct Unit Cost (C ÷ D) 1,802.39
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. Cement bag 8.40 220.00 1,848.00


b. Sand cu.m. 0.50 850.00 425.00
c. Weep Holes (PVC) l.m. 0.21 144.67 30.38
d. Filter Cloth sq.m. 0.015 275.00 4.13
e. Gravel cu.m. 1 650.00 650.00
f. Granular Filter cu.m. 0.016 650.00 10.40
f. Reinforcing Steel Bar kg. * 26.03 40.00 1,041.20
g. Marine Plywood 1/2" x 4' x 8' - 4 uses pc. 0.48 700.00 84.00
h. Lumber - 4 uses bd.ft. 18.76 40.00 187.60
i. #16 GI Tie Wire (2% of RSB) kg. 0.521 47.00 24.49
j. Assorted CWN (1 kg./100 bd.ft. of Lumber) kg. 0.188 68.00 12.78
* Note: RSB quantity is variable based on approved plan.
Sub - Total for F 4,317.98
G. Direct Unit Cost (E + F) 6,120.37
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 550.83
I. Contractor's Profit (CP) 8% of G 489.63
J. Value Added Tax (VAT) 12% of (G + H + I) 859.30
K. Total Unit Cost (G + H + I + J) 8,020.13

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 511(1) Gabions


Unit of Measurement : cu.m.
Output per hour : 2.50

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Skilled Laborer 2 1 79.70 159.40
c. Laborer 8 1 61.44 491.52

Sub - Total for A 760.11


Name and Capacity No of Units No. of Hours Hourly Rate Amount
B. Equipment

Note: Exclude Excavation Works


Backhoe excluded, excavation should be separate as the
quantity is variable.

Sub - Total for B -


C. Total (A + B) 760.11
D. Output per hour = 2.500 cu.m.
E. Direct Unit Cost (C ÷ D) 304.04
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. Gabion Wire Mesh (1 x 1 x 2) pc. 0.50 2,900.00 1,450.00


(w/ complete accessories)
b. Boulders cu.m. 1.05 920.00 966.00

Sub - Total for F 2,416.00


G. Direct Unit Cost (E + F) 2,720.04
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 244.80
I. Contractor's Profit (CP) 8% of G 217.60
J. Value Added Tax (VAT) 12% of (G + H + I) 381.89
K. Total Unit Cost (G + H + I + J) 3,564.35

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 511(2) Mattresses


Unit of Measurement : cu.m.
Output per hour : 3.125

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Skilled Laborer 2 1 79.70 159.40
c. Laborer 8 1 61.44 491.52

Sub - Total for A 760.11


Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

Note: Exclude Excavation Works


Backhoe excluded, excavation should be separate as the
quantity is variable.

Sub - Total for B -


C. Total (A + B) 760.11
D. Output per hour = 3.125 cu.m.
E. Direct Unit Cost (C ÷ D) 243.24
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. Mattresses (6 x 2 x 0.3 ) pc. 0.28 5,000.00 1,400.00


(w/ complete accessories)
b. Boulders cu.m. 1.05 920.00 966.00

Sub - Total for F 2,366.00


G. Direct Unit Cost (E + F) 2,609.24
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 234.83
I. Contractor's Profit (CP) 8% of G 208.74
J. Value Added Tax (VAT) 12% of (G + H + I) 366.34
K. Total Unit Cost (G + H + I + J) 3,419.14

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 511(3) Filter Cloth


Unit of Measurement : sq.m.
Output per hour : 100.00

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Skilled Laborer 2 1 79.70 159.40
c. Laborer 8 1 61.44 491.52

Sub - Total for A 760.11


Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Cargo Truck (10 T) 1 0.25 1,102.00 275.50

Sub - Total for B 275.50


C. Total (A + B) 1,035.61
D. Output per hour = 100.0000 sq.m.
E. Direct Unit Cost (C ÷ D) 10.36
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. Filter Cloth sq.m. 1.05 275.00 288.75


Miscellaneous (5% of Materials) 14.44

Sub - Total for F 303.19


G. Direct Unit Cost (E + F) 313.54
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 28.22
I. Contractor's Profit (CP) 8% of G 25.08
J. Value Added Tax (VAT) 12% of (G + H + I) 44.02
K. Total Unit Cost (G + H + I + J) 410.87
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 600(1) Concrete Curb (Cast in place)


Unit of Measurement : l.m.
Output per hour : 17.50

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Skilled Laborer 4 1 79.70 318.80
c. Laborer 8 1 61.44 491.52

Sub - Total for A 919.51


Name and Capacity No of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Concrete Vibrator 1 1 148.88 148.88


b. One Bagger Mixer 1 1 172.00 172.00
c. Water Truck (1000 gal.) 1 0.05 1,065.00 53.25
Minor Tools (10% of Labor) 91.95 91.95

Sub - Total for B 466.08


C. Total (A + B) 1,385.59
D. Output per hour = 17.500 l.m.
E. Direct Unit Cost (C ÷ D) 79.18
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Cement bag 0.72 220.00 158.40


b. Sand cu.m. 0.04 850.00 34.00
c. Gravel cu.m. 0.08 650.00 52.00
d. Plywood Marine, 1/2" thk. x 4' x 8 - 4 uses pc. 0.28 700.00 49.00
e. Form Lumber - 4 uses bd.ft. 12.16 40.00 121.60
f. Assorted CWN (1 kg./100 bd.ft. of Lumber) kg. 0.12 68.00 8.16

Sub - Total for F 423.16


G. Direct Unit Cost (E + F) 502.34
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 45.21
I. Contractor's Profit (CP) 8% of G 40.19
J. Value Added Tax (VAT) 12% of (G + H + I) 70.53
K. Total Unit Cost (G + H + I + J) 658.26
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 600(2) Concrete Gutter (Cast in place)


Unit of Measurement : l.m.
Output per hour : 17.50

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Skilled Laborer 4 1 79.70 318.80
c. Laborer 8 1 61.44 491.52

Sub - Total for A 919.51


Name and Capacity No of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Concrete Vibrator 1 1 148.88 148.88


b. One Bagger Mixer 1 1 172.00 172.00
c. Water Truck (1000 gal.) 1 0.05 1,065.00 53.25
Minor Tools (10% of Labor) 91.95 91.95

Sub - Total for B 466.08


C. Total (A + B) 1,385.59
D. Output per hour = 17.500 l.m.
E. Direct Unit Cost (C ÷ D) 79.18
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Cement bag 0.70 220.00 154.00


b. Sand cu.m. 0.04 850.00 34.00
c. Gravel cu.m. 0.08 650.00 52.00
d. Good Lumber - 4 uses bd.ft. 6.56 40.00 65.60
e. Assorted CWN (1 kg./100 bd.ft. of Lumber) kg. 0.07 68.00 4.76

Sub - Total for F 310.36


G. Direct Unit Cost (E + F) 389.54
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 35.06
I. Contractor's Profit (CP) 8% of G 31.16
J. Value Added Tax (VAT) 12% of (G + H + I) 54.69
K. Total Unit Cost (G + H + I + J) 510.45

DETAILED UNIT PRICE ANALYSIS (DUPA)


Item No./Description : 600(3) Concrete Curb and Gutter, Type A (Cast in place) - National Road
Unit of Measurement : l.m.
Output per hour : 10.30

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Skilled Laborer 4 1 79.70 318.80
c. Laborer 8 1 61.44 491.52

Sub - Total for A 919.51


Name and Capacity No of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Concrete Vibrator 1 1 148.88 148.88


b. One Bagger Mixer 1 1 172.00 172.00
c. Water Truck (1000 gal.) 1 0.05 1,065.00 53.25
Minor Tools (10% of Labor) 91.95 91.95

Sub - Total for B 466.08


C. Total (A + B) 1,385.59
D. Output per hour = 10.300 l.m.
E. Direct Unit Cost (C ÷ D) 134.52
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Cement bag 1.29 220.00 283.80


b. Sand cu.m. 0.07 850.00 59.50
c. Gravel cu.m. 0.14 650.00 91.00
d. Plywood Marine, 1/2" thk. x 4' x 8 - 4 uses pc. 0.24 700.00 42.00
e. Form Lumber - 4 uses bd.ft. 11.47 40.00 114.70
f. Assorted CWN (1 kg./100 bd.ft. of Lumber) kg. 0.11 68.00 7.48
Miscellaneous (2% of Materials) 11.97 11.97

Sub - Total for F 610.45


G. Direct Unit Cost (E + F) 744.97
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 67.05
I. Contractor's Profit (CP) 8% of G 59.60
J. Value Added Tax (VAT) 12% of (G + H + I) 104.59
K. Total Unit Cost (G + H + I + J) 976.21

DETAILED UNIT PRICE ANALYSIS (DUPA)


Item No./Description : 600(4) Concrete Curb (Precast)
Unit of Measurement : pc.
Output per hour : 4.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Skilled Laborer 1 1 79.70 79.70
c. Laborer 1 1 61.44 61.44

Sub - Total for A 250.33


Name and Capacity No of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Boom Truck 1 0.50 961.20 480.60


Minor Tools (10% of Labor) 25.03 25.03

Sub - Total for B 505.63


C. Total (A + B) 755.96
D. Output per hour = 4.0000 pc.
E. Direct Unit Cost (C ÷ D) 188.99
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Fabricated Concrete Curb l.m. 1.00 690.00 690.00


Miscellaneous (5% of materials) 34.50 34.50

Sub - Total for F 724.50


G. Direct Unit Cost (E + F) 913.49
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 82.21
I. Contractor's Profit (CP) 8% of G 73.08
J. Value Added Tax (VAT) 12% of (G + H + I) 128.25
K. Total Unit Cost (G + H + I + J) 1,197.04

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 600(5) Concrete Gutter (Precast)


Unit of Measurement : pc.
Output per hour : 4.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Skilled Laborer 1 1 79.70 79.70
c. Laborer 1 1 61.44 61.44

Sub - Total for A 250.33


Name and Capacity No of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Boom Truck 1 0.50 961.20 480.60


Minor Tools (10% of Labor) 25.03 25.03

Sub - Total for B 505.63


C. Total (A + B) 755.96
D. Output per hour = 4.0000 pc.
E. Direct Unit Cost (C ÷ D) 188.99
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Fabricated Concrete Gutter l.m. 1.00 680.00 680.00


Miscellaneous (5% of materials) 34.00 34.00

Sub - Total for F 714.00


G. Direct Unit Cost (E + F) 902.99
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 81.27
I. Contractor's Profit (CP) 8% of G 72.24
J. Value Added Tax (VAT) 12% of (G + H + I) 126.78
K. Total Unit Cost (G + H + I + J) 1,183.28

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 600(6) Concrete Curb and Gutter (Precast)


Unit of Measurement : pc.
Output per hour : 3.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Skilled Laborer 1 1 79.70 79.70
c. Laborer 1 1 61.44 61.44

Sub - Total for A 250.33


Name and Capacity No of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Boom Truck 1 0.50 961.20 480.60


Minor Tools (10% of Labor) 25.03 25.03

Sub - Total for B 505.63


C. Total (A + B) 755.96
D. Output per hour = 3.0000 pc.
E. Direct Unit Cost (C ÷ D) 251.99
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Fabricated Concrete Curb and Gutter l.m. 1.00 1,750.00 1,750.00


Miscellaneous (5% of materials) 87.50 87.50

Sub - Total for F 1,837.50


G. Direct Unit Cost (E + F) 2,089.49
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 188.05
I. Contractor's Profit (CP) 8% of G 167.16
J. Value Added Tax (VAT) 12% of (G + H + I) 293.36
K. Total Unit Cost (G + H + I + J) 2,738.06

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 601 Sidewalk


Unit of Measurement : sq.m.
Output per hour : 161.00
Designation No. of Person No. of Hours Hourly Rate Amount
A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Skilled Laborer 4 1 79.70 318.80
c. Laborer 12 1 61.44 737.28

Sub - Total for A 1,165.27


Name and Capacity No of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Transit Mixer (5 cu.m.) 4 1 1,279.00 5,116.00


b. Concrete Vibrator 2 1 148.88 297.76
c. Batching Plant (30 cu.m.) 1 1 1,208.03 1,208.03
d. Payloader (1.50 cu.m.), LX80-2C 1 1 1,733.00 1,733.00
e. Concrete Screeder (5.5 Hp) 1 1 545.00 545.00
f. Water Truck (1000 gal.) 1 1 1,065.00 1,065.00
g. Concrete Saw, Blade Ø 14" (7.5 Hp) 1 1 167.38 167.38

Sub - Total for B 10,132.17


C. Total (A + B) 11,297.44
D. Output per hour = 161.0000 sq.m.
E. Direct Unit Cost (C ÷ D) 70.17
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Curing Compound lit. 0.29 28.00 8.12


b. Asphalt Sealant lit. 0.12 44.00 5.28
c. Forms l.m. 0.46 250.00 115.00
d. Sand cu.m. 0.055 850.00 46.75
e. Gravel cu.m. 0.10 650.00 65.00
f. Cement bag 0.95 220.00 209.00

Note : Bed Course excluded

Sub - Total for F 449.15


G. Direct Unit Cost (E + F) 519.32
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 46.74
I. Contractor's Profit (CP) 8% of G 41.55
J. Value Added Tax (VAT) 12% of (G + H + I) 72.91
K. Total Unit Cost (G + H + I + J) 680.52

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 602(1)a Right-of-Way Monument


Unit of Measurement : ea.
Output per hour : 2.00

Designation No. of Person No. of Hours Hourly Rate Amount


Designation No. of Person No. of Hours Hourly Rate Amount
A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Skilled Laborer 1 1 79.70 79.70
c. Laborer 2 1 61.44 122.88

Sub - Total for A 311.77


Name and Capacity No of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Concrete Vibrator 1 0.20 148.88 29.78


b. Cargo Truck (10 T) 1 0.05 1,102.00 55.10
Minor Tools (10% of Labor) 31.18 31.18

Sub - Total for B 116.05


C. Total (A + B) 427.82
D. Output per hour = 2.0000 ea.
E. Direct Unit Cost (C ÷ D) 213.91
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Concrete Class "A" cu.m. 0.03 3,538.78 106.16


b. Reinforcing Steel Bar, Grade 40 kg. 7.15 40.00 286.00
c. Plywood, 1/2" x 4' x 8' - 4 uses pc. 0.22 700.00 38.50
d. Form Lumber, Good - 4 uses bd.ft. 13.53 40.00 135.30
e. Reflectorized Paint, Marker lit. 0.10 475.00 47.50
f. # 16 Tie Wire (2% of RSB) kg. 0.14 47.00 6.58
g. Assorted CWN (1 kg./100 bd.ft. of Lumber) kg. 0.14 68.00 9.52

Sub - Total for F 629.56


G. Direct Unit Cost (E + F) 843.47
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 75.91
I. Contractor's Profit (CP) 8% of G 67.48
J. Value Added Tax (VAT) 12% of (G + H + I) 118.42
K. Total Unit Cost (G + H + I + J) 1,105.29

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 602(1)b Right-of-Way Monument (Precast)


Unit of Measurement : ea.
Output per hour : 4.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor
a. Construction Foreman 1 1 109.19 109.19
b. Skilled Laborer 1 1 79.70 79.70
c. Laborer 2 1 61.44 122.88

Sub - Total for A 311.77


Name and Capacity No of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Cargo Truck (10 T) 1 0.05 1,102.00 55.10


Minor Tools (10% of Labor) 31.18 31.18

Sub - Total for B 86.28


C. Total (A + B) 398.05
D. Output per hour = 4.0000 ea.
E. Direct Unit Cost (C ÷ D) 99.51
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Fabricated Right-of-Way Monument ea. 1 629.56 629.56


(delivered at site)

Sub - Total for F 629.56


G. Direct Unit Cost (E + F) 729.08
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 65.62
I. Contractor's Profit (CP) 8% of G 58.33
J. Value Added Tax (VAT) 12% of (G + H + I) 102.36
K. Total Unit Cost (G + H + I + J) 955.38

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 602(2)a Maintenance Marker Post


Unit of Measurement : ea.
Output per hour : 2.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor
a. Construction Foreman 1 1 109.19 109.19
b. Skilled Laborer 1 1 79.70 79.70
c. Laborer 2 1 61.44 122.88

Sub - Total for A 311.77


Name and Capacity No of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Concrete Vibrator 1 0.20 148.88 29.78


b. Cargo Truck (10 T) 1 0.05 1,102.00 55.10
Minor Tools (10% of Labor) 31.18 31.18

Sub - Total for B 116.05


C. Total (A + B) 427.82
D. Output per hour = 2.0000 ea.
E. Direct Unit Cost (C ÷ D) 213.91
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Concrete Class "A" cu.m. 0.03 3,400.00 102.00


b. Reinforcing Steel Bar, Grade 40 kg. 7.00 40.00 280.00
c. Plywood, 1/2" x 4' x 8' - 4 uses pc. 0.22 700.00 38.50
d. Form Lumber, Good - 4 uses bd.ft. 13.53 40.00 135.30
e. Reflectorized Paint, Marker lit. 0.10 475.00 47.50
f. # 16 Tie Wire (2% of RSB) kg. 0.14 47.00 6.58
g. Assorted CWN (1 kg./100 bd.ft. of Lumber) kg. 0.14 68.00 9.52

Sub - Total for F 619.40


G. Direct Unit Cost (E + F) 833.31
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 75.00
I. Contractor's Profit (CP) 8% of G 66.66
J. Value Added Tax (VAT) 12% of (G + H + I) 117.00
K. Total Unit Cost (G + H + I + J) 1,091.97

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 602(2)b Maintenance Marker Post (Precast)


Unit of Measurement : ea.
Output per hour : 4.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Skilled Laborer 1 1 79.70 79.70
c. Laborer 2 1 61.44 122.88

Sub - Total for A 311.77


Name and Capacity No of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Cargo Truck (10 T) 1 0.05 1,102.00 55.10


Minor Tools (10% of Labor) 31.18 31.18

Sub - Total for B 86.28


C. Total (A + B) 398.05
D. Output per hour = 4.0000 ea.
E. Direct Unit Cost (C ÷ D) 99.51
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Fabricated Maintenance Marker Post ea. 1 619.40 619.40


(delivered at site)

Sub - Total for F 619.40


G. Direct Unit Cost (E + F) 718.91
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 64.70
I. Contractor's Profit (CP) 8% of G 57.51
J. Value Added Tax (VAT) 12% of (G + H + I) 100.94
K. Total Unit Cost (G + H + I + J) 942.06

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 602(3)a Kilometer Post


Unit of Measurement : ea.
Output : 1.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1.50 109.19 163.79


b. Skilled Laborer 1 1.50 79.70 119.55
c. Laborer 2 1.50 61.44 184.32

Sub - Total for A 467.66


Name and Capacity No of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Cargo Truck (10 T) 1 0.75 1,102.00 826.50


b. Concrete Vibrator 1 0.05 148.88 7.44
Minor Tools (10% of Labor) 46.77 46.77

Sub - Total for B 880.71


C. Total (A + B) 1,348.36
D. Output = 1.0000 ea.
E. Direct Unit Cost (C ÷ D) 1,348.36
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Concrete Class "A" cu.m. 0.184 3,400.00 625.60


b. Reinforcing Steel Bar kg. 7.59 40.00 303.60
c. Plywood 1/2" x 4' x 8' - 2 uses pc. 0.604 700.00 211.40
d. Lumber - 2 uses bd.ft. 7.15 20.00 71.50
e. Reflectorized Paint, Marker lit. 0.20 475.00 95.00
f. # 16 Tie Wire (2% of RSB) kg. 0.15 47.00 7.05
g. Assorted CWN (1 kg./100 bd.ft. of Lumber) kg. 0.07 68.00 4.76

Sub - Total for F 1,318.91


G. Direct Unit Cost (E + F) 2,667.27
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 240.05
I. Contractor's Profit (CP) 8% of G 213.38
J. Value Added Tax (VAT) 12% of (G + H + I) 374.49
K. Total Unit Cost (G + H + I + J) 3,495.20

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 602(3)b Kilometer Post (Precast)


Unit of Measurement : ea.
Output : 2.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1.50 109.19 163.79


b. Skilled Laborer 1 1.50 79.70 119.55
c. Laborer 2 1.50 61.44 184.32
Sub - Total for A 467.66
Name and Capacity No of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Cargo Truck (10 T) 1 0.50 1,102.00 551.00


b. Concrete Vibrator 1 0.10 148.88 14.89
Minor Tools (10% of Labor) 46.77 46.77

Sub - Total for B 612.65


C. Total (A + B) 1,080.31
D. Output = 2.0000 ea.
E. Direct Unit Cost (C ÷ D) 540.15
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Fabricated Kilometer Post ea. 1 900.91 900.91


b. Concrete Class "A" cu.m. 0.095 3,400.00 323.00
c. Reflectorized Paint, Marker lit. 0.20 475.00 95.00

Sub - Total for F 1,318.91


G. Direct Unit Cost (E + F) 1,859.06
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 167.32
I. Contractor's Profit (CP) 8% of G 148.73
J. Value Added Tax (VAT) 12% of (G + H + I) 261.01
K. Total Unit Cost (G + H + I + J) 2,436.12

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 602(4) Guide Post


Unit of Measurement : ea.
Output per hour : 50.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Laborer 2 1 61.44 122.88
Sub - Total for A 232.07
Name and Capacity No of Units No. of Hours Hourly Rate Amount
B. Equipment

Minor Tools (10% of Labor) 23.21 23.21

Sub - Total for B 23.21


C. Total (A + B) 255.28
D. Output per hour = 50.0000 ea.
E. Direct Unit Cost (C ÷ D) 5.11
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Guide Post (Portable) ea. 1 1,240.00 1,240.00


b. Post Reflector ea. 1 85.00 85.00
Miscellaneous (5% of Materials) 66.25 66.25

Sub - Total for F 1,391.25


G. Direct Unit Cost (E + F) 1,396.36
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 125.67
I. Contractor's Profit (CP) 8% of G 111.71
J. Value Added Tax (VAT) 12% of (G + H + I) 196.05
K. Total Unit Cost (G + H + I + J) 1,829.78

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 603(1) Cable Wire Guardrail


Unit of Measurement : l.m.
Output per hour : 1.15

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Skilled Laborer 2 1 79.70 159.40
c. Laborer 8 1 61.44 491.52
Sub - Total for A 760.11
Name and Capacity No of Units No. of Hours Hourly Rate Amount
B. Equipment

a. One Bagger Mixer 1 1 172.00 172.00


b. Concrete Vibrator 1 1 148.88 148.88
c. Water Truck (1000 gal.) 1 0.10 1,065.00 106.50
d. Cargo Truck (5 T) 1 0.25 712.00 178.00
Minor Tools (10% of Labor)

Sub - Total for B 605.38


C. Total (A + B) 1,365.49
D. Output per hour = 1.15 l.m.
E. Direct Unit Cost (C ÷ D) 1,187.38
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Cement bag 4.18 220.00 919.60


b. Sand cu.m. 0.22 850.00 187.00
c. Gravel cu.m. 0.43 650.00 279.50
d. Guardrail Post set 0.27 1,800.00 486.00
e. Galvanized Wire Rope (1.21 kg./m) kg. 4.92 186.44 917.28
f. Check Rope set 0.22 750.00 165.00
g. Hook Bolt ea. 0.33 350.00 115.50
h. Anchor Bracket unit 0.11 1,200.00 132.00
i. Wire Mesh sq.m. 0.11 295.00 32.45
j. Tension Fittings set 0.65 1,000.00 650.00
Miscellaneous (5% of Materials)
* Tentative Canvass Price
Sub - Total for F 3,884.33
G. Direct Unit Cost (E + F) 5,071.72
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 456.45
I. Contractor's Profit (CP) 8% of G 405.74
J. Value Added Tax (VAT) 12% of (G + H + I) 712.07
K. Total Unit Cost (G + H + I + J) 6,645.98

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 603(3a) Metal Guardrails (Metal Beam) including Concrete Post
Unit of Measurement : 40 l.m.
Output per hour : 4.20

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 9.52380952381 109.19 1,039.90


b. Skilled Laborer 2 9.52380952381 79.70 1,518.10
c. Laborer 4 9.52380952381 61.44 2,340.57
Sub - Total for A 4,898.57
Name and Capacity No of Units No. of Hours Hourly Rate Amount
B. Equipment

a. One Bagger Mixer 1 4.76 172.00 819.05


b. Concrete Vibrator 1 4.76 148.88 708.95
c. Water Truck (1000 gal.) 1 0.48 1,065.00 507.14
d. Cargo Truck (10 T) 1 2.38 1,102.00 2,623.81
Minor Tools (5 % of Labor) 244.93 244.93

Sub - Total for B 4,903.88


C. Total (A + B) 9,802.45
D. Output per hour = 4.2000 l.m.
E. Direct Unit Cost (C ÷ D) 2,333.92
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Cement bag 13.20 220.00 2,904.00


b. Sand cu.m. 0.720 850.00 612.00
c. Gravel cu.m. 1.440 650.00 936.00
d. Metal Beam Guardrail l.m. 40 1,950.00 78,000.00
e. Plywood Marine, 1/2" thk. x 4' x 8' - 4 uses pc. 10.00 700.00 1,750.00
f. Lumber - 4 uses bd.ft. 320 40.00 3,200.00
g. Reinforcing Steel Bars, Grade 40 kg. 160 40.00 6,400.00
h. Tie Wire (2% of RSB) kg. 3.20 47.00 150.40
i. Assorted CWN (1 kg./100 bd.ft. of Lumber) kg. 3.20 68.00 217.60
j. Bolt, Nut & Washer 5/8" dia. x 9" pc. 20.00 28.00 560.00
k. Bolt, Nut & Washer 5/8" dia. x 1" pc. 80 21.00 1,680.00

Sub - Total for F 96,410.00


G. Direct Unit Cost (E + F) 98,743.92
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 8,886.95
I. Contractor's Profit (CP) 8% of G 7,899.51
J. Value Added Tax (VAT) 12% of (G + H + I) 13,863.65
K. Total Unit Cost (G + H + I + J) 129,394.03
L. Total Adjusted unit cost 3,234.85

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 603(3b) Guardrail (End Piece)


Unit of Measurement : ea.
Output per hour : 6.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Skilled Laborer 1 1 79.70 79.70
c. Laborer 2 1 61.44 122.88
Sub - Total for A 311.77
Name and Capacity No of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Cargo Truck (10 T) 1 1.00 1,102.00 1,102.00


Minor Tools (5% of Labor) 15.59 15.59

Sub - Total for B 1,117.59


C. Total (A + B) 1,429.36
D. Output per hour = 6.00000 ea.
E. Direct Unit Cost (C ÷ D) 238.23
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Metal Guradrail End Piece ea. 1.00 1,350.00 1,350.00

Sub - Total for F 1,350.00


G. Direct Unit Cost (E + F) 1,588.23
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 142.94
I. Contractor's Profit (CP) 8% of G 127.06
J. Value Added Tax (VAT) 12% of (G + H + I) 222.99
K. Total Unit Cost (G + H + I + J) 2,081.21

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 603(4) Guardrail (Timber)


Unit of Measurement : l.m.
Output per hour : 5.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Skilled Laborer 2 1 79.70 159.40
c. Laborer 4 1 61.44 245.76

Sub - Total for A 514.35


Name and Capacity No of Units No. of Hours Hourly Rate Amount
Name and Capacity No of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Cargo Truck (10 T) 1 0.50 1,102.00 551.00


Minor Tools (10% of Labor) 51.44 51.44

Sub - Total for B 602.44


C. Total (A + B) 1,116.78
D. Output per hour = 5.00000 l.m.
E. Direct Unit Cost (C ÷ D) 223.36
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Lumber, 8" x 8" x 5.5' Treated Post (Tanguile) bd.ft. 14.67 90.00 1,320.30
b. Lumber, 3" x 8" Plank (Tanguile) - Untreated bd.ft. 6.67 55.00 366.85
c. Carriage Bolt, 1/2"Ø x 12" pc. 1.60 350.00 560.00
Miscellaneous (5% of Materials) 112.36 112.36

Note: Exclude Excavation Works

Sub - Total for F 2,359.51


G. Direct Unit Cost (E + F) 2,582.86
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 232.46
I. Contractor's Profit (CP) 8% of G 206.63
J. Value Added Tax (VAT) 12% of (G + H + I) 362.63
K. Total Unit Cost (G + H + I + J) 3,384.59

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 604(1) Fencing (Barbed Wire)


Unit of Measurement : l.m.
Output per hour : 18.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Skilled Laborer 1 1 79.70 79.70
c. Laborer 2 1 61.44 122.88

Sub - Total for A 311.77


Name and Capacity No of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Welding Machine 1 0.10 391.00 39.10


Minor Tools (10% of Labor) 31.18 31.18

Sub - Total for B 70.28


C. Total (A + B) 382.05
D. Output per hour = 18.00000 l.m.
E. Direct Unit Cost (C ÷ D) 21.22
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. 3-Strand Galvanized Barbed Wire, Ga 12.5 l.m. 1 15.00 15.00


b. 50mmx50mmx6m Angle Bar kg. 0.52 48.00 24.96
c. Ga. 9 Twisted Wire Fastener pc. 0.67 81.15 54.37
Miscellaneous (2% of Materials, Welding Rod & etc.) 1.89 1.89

Sub - Total for F 96.22


G. Direct Unit Cost (E + F) 117.44
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 10.57
I. Contractor's Profit (CP) 8% of G 9.40
J. Value Added Tax (VAT) 12% of (G + H + I) 16.49
K. Total Unit Cost (G + H + I + J) 153.90

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 604(2) Fencing (Chain Link Fence)


Unit of Measurement : l.m.
Output per hour : 5.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Skilled Laborer 2 1 79.70 159.40
c. Laborer 8 1 61.44 491.52

Sub - Total for A 760.11


Name and Capacity No of Units No. of Hours Hourly Rate Amount
B. Equipment
a. One Bagger Mixer 1 1 172.00 172.00
b. Concrete Vibrator 1 0.50 148.88 74.44
c. Water Truck (1000 gal.) 1 0.10 1,065.00 106.50
d. Welding Machine 1 0.50 391.00 195.50
Minor Tools (10% of Labor) 76.01 76.01

Sub - Total for B 624.45


C. Total (A + B) 1,384.56
D. Output per hour = 5.00000 l.m.
E. Direct Unit Cost (C ÷ D) 276.91
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Cement bag 1.623 220.00 357.06


b. Sand cu.m. 0.085 850.00 72.25
c. Gravel, G1 cu.m. 0.171 650.00 111.15
d. Chainlink Fence, 4' l.m. 1 661.67 661.67
e. G.I. Pipe 2" dia. (corner or pull posts) pc. 0.03 1,500.00 45.00
f. G.I. Pipe 1 1/4" dia. (line post) pc. 0.12 1,140.00 136.80
g. G.I. Pipe 1 1/4" dia. (brace) pc. 0.50 1,140.00 570.00
h. Flat Bar, 3/16" x 3/4" (stretch bar) kg. 0.14 48.00 6.72
i. Plain Bar, 3/8" dia. (truss rod) kg. 0.30 40.00 12.00
j. Tension Wire, 0.177" dia. l.m. 2 134.44 268.89
Miscellaneous (5% of Materials) 112.08 112.08

Sub - Total for F 2,353.61


G. Direct Unit Cost (E + F) 2,630.53
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 236.75
I. Contractor's Profit (CP) 8% of G 210.44
J. Value Added Tax (VAT) 12% of (G + H + I) 369.33
K. Total Unit Cost (G + H + I + J) 3,447.04

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 604(3) Fencing (Post)


Unit of Measurement : ea.
Output : 1.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1.50 109.19 163.79


b. Skilled Laborer 2 1.50 79.70 239.10
c. Laborer 2 1.50 61.44 184.32

Sub - Total for A 587.20


Name and Capacity No of Units No. of Hours Hourly Rate Amount
B. Equipment
a. One Bagger Mixer 1 0.75 172.00 129.00
b. Bar Cutter 1 0.50 219.75 109.88
c. Bar Bender 1 0.50 351.50 175.75
d. Water Truck (1000 gal.) 1 0.05 1,065.00 53.25
Minor Tools (10% of Labor) 58.72 58.72

Sub - Total for B 526.60


C. Total (A + B) 1,113.80
D. Output = 1.00000 ea.
E. Direct Unit Cost (C ÷ D) 1,113.80
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Cement bag 2.105 220.00 463.10


b. Sand cu.m. 0.095 850.00 80.75
c. Gravel cu.m. 0.185 650.00 120.25
d. Reinforcing Steel Bar kg. 20.615 40.00 824.60
e. # 16 Tie Wire (2% of RSB) kg. 0.412 47.00 19.36
f. Plywood 1/4' x 4' x 8' - 2 uses pc. 0.760 350.00 133.00
g. Lumber - 2 uses bd.ft. 22.695 20.00 226.95
h. Assorted CWN (1 kg./100 bd.ft. of Lumber) kg. 0.227 68.00 15.44

Sub - Total for F 1,883.45


G. Direct Unit Cost (E + F) 2,997.25
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 269.75
I. Contractor's Profit (CP) 8% of G 239.78
J. Value Added Tax (VAT) 12% of (G + H + I) 420.81
K. Total Unit Cost (G + H + I + J) 3,927.60

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 604(4) Fencing (Gates) - (Height 3m. & Length 4.24m.)
Unit of Measurement : ea.
Output : 1.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 3 109.19 327.57


b. Skilled Laborer 1 3 79.70 239.10
c. Laborer 2 3 61.44 368.64

Sub - Total for A 935.31


Name and Capacity No of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Welding Machine 1 2 391.00 782.00


Minor Tools (10% of Labor) 93.53 93.53

Sub - Total for B 875.53


C. Total (A + B) 1,810.84
D. Output = 1.00000 ea.
E. Direct Unit Cost (C ÷ D) 1,810.84
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. 50 mm. Ø G.I. Pipe, Schedule 40 pc. 5 1,550.00 7,750.00


b. Cyclone Wire Galvanized 10' Gauge 10 l.m. 4.24 3,300.00 13,992.00
c. Aluminum Paint gal. 1.06 565.00 598.90
d. 6mm dia. Plain Bar kg. 1.607 40.00 64.28
e. Gate Lock/Hinge (12mm thk. Plate) kg. 9.743 48.00 467.66
b. Welding Rod (1 kg./2000 kg. of Steel) kg. 0.006 90.00 0.54

Sub - Total for F 22,873.38


G. Direct Unit Cost (E + F) 24,684.23
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 2,221.58
I. Contractor's Profit (CP) 8% of G 1,974.74
J. Value Added Tax (VAT) 12% of (G + H + I) 3,465.67
K. Total Unit Cost (G + H + I + J) 32,346.21

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 605(1) Danger/Warning Signs (60cm Triangle)


Unit of Measurement : ea.
Output per hour : 1.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Skilled Laborer 1 1 79.70 79.70
c. Laborer 2 1 61.44 122.88

Sub - Total for A 311.77


Name and Capacity No of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Cargo Truck (5 T) 1 0.25 712.00 178.00


Minor Tools (10 % of Labor) 31.18 31.18
Sub - Total for B 209.18
C. Total (A + B) 520.95
D. Output per hour = 1.00000 ea.
E. Direct Unit Cost (C ÷ D) 520.95
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Portland Cement bag 0.48 220.00 105.60


b. Sand cu.m. 0.025 850.00 21.25
c. Gravel cu.m. 0.050 650.00 32.50
d. Form Lumber, Good - 4 uses bd.ft. 8 40.00 80.00
e. 3"Ø G.I. Pipe m. 3.10 530.00 1,643.00
f. Plate kg. 2 48.00 96.00
g. Bolts, 5mm Ø pc. 12 10.00 120.00
h. Sign Face, 3mm thk. Aluminum Sheet pc. 1 2,800.00 2,800.00
i. Assorted CWN (1 kg./100 bd.ft. of Lumber) kg. 0.08 68.00 5.44

Sub - Total for F 4,903.79


G. Direct Unit Cost (E + F) 5,424.74
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 488.23
I. Contractor's Profit (CP) 8% of G 433.98
J. Value Added Tax (VAT) 12% of (G + H + I) 761.63
K. Total Unit Cost (G + H + I + J) 7,108.58

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 605(1) Danger/Warning Signs (90cm Triangle)


Unit of Measurement : ea.
Output per hour : 1.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Skilled Laborer 1 1 79.70 79.70
c. Laborer 2 1 61.44 122.88

Sub - Total for A 311.77


Name and Capacity No of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Cargo Truck (5 T) 1 0.25 712.00 178.00


Minor Tools (10 % of Labor) 31.18 31.18
Sub - Total for B 209.18
C. Total (A + B) 520.95
D. Output per hour = 1.00000 ea.
E. Direct Unit Cost (C ÷ D) 520.95
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Portland Cement bag 0.48 220.00 105.60


b. Sand cu.m. 0.025 850.00 21.25
c. Gravel cu.m. 0.050 650.00 32.50
d. Form Lumber, Good - 4 uses bd.ft. 8 40.00 80.00
e. 3"Ø G.I. Pipe m. 3.10 530.00 1,643.00
f. Plate kg. 2 48.00 96.00
g. Bolts, 5mm Ø pc. 12 10.00 120.00
h. Sign Face, 3mm thk. Aluminum Sheet pc. 1 4,200.00 4,200.00
i. Assorted CWN (1 kg./100 bd.ft. of Lumber) kg. 0.08 68.00 5.44

Sub - Total for F 6,303.79


G. Direct Unit Cost (E + F) 6,824.74
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 614.23
I. Contractor's Profit (CP) 8% of G 545.98
J. Value Added Tax (VAT) 12% of (G + H + I) 958.19
K. Total Unit Cost (G + H + I + J) 8,943.14

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 605(2) Regulatory Signs (60cm Triangle)


Unit of Measurement : ea.
Output per hour : 1.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Skilled Laborer 1 1 79.70 79.70
c. Laborer 2 1 61.44 122.88

Sub - Total for A 311.77


Name and Capacity No of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Cargo Truck (5 T) 1 0.25 712.00 178.00


Minor Tools (10 % of Labor) 31.18 31.18
Sub - Total for B 209.18
C. Total (A + B) 520.95
D. Output per hour = 1.00000 ea.
E. Direct Unit Cost (C ÷ D) 520.95
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Portland Cement bag 0.48 220.00 105.60


b. Sand cu.m. 0.025 850.00 21.25
c. Gravel cu.m. 0.050 650.00 32.50
d. Form Lumber, Good - 4 uses bd.ft. 8 40.00 80.00
e. 3"Ø G.I. Pipe m. 3.10 530.00 1,643.00
f. Plate kg. 2 48.00 96.00
g. Bolts, 5mm Ø pc. 12 10.00 120.00
h. Sign Face, 3mm thk. Aluminum Sheet pc. 1 2,800.00 2,800.00
i. Assorted CWN (1 kg./100 bd.ft. of Lumber) kg. 0.08 68.00 5.44

Sub - Total for F 4,903.79


G. Direct Unit Cost (E + F) 5,424.74
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 488.23
I. Contractor's Profit (CP) 8% of G 433.98
J. Value Added Tax (VAT) 12% of (G + H + I) 761.63
K. Total Unit Cost (G + H + I + J) 7,108.58
9.52381
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : SPL 3 Tree Planting


Unit of Measurement : pc.
Output per hour : 60.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Laborer 10 1 61.44 614.40

Sub - Total for A 723.59


Name and Capacity No of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Cargo Truck (5 T) 1 0.25 712.00 178.00


b. Water Truck (1000 gal.) 1 0.25 1,065.00 266.25
Minor Tools (10% of Labor) 72.36 72.36

Sub - Total for B 516.61


C. Total (A + B) 1,240.20
D. Output per hour = 60.0000 pc.
E. Direct Unit Cost (C ÷ D) 20.67
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Saplings pc. 1 50.00 50.00


b. Coco Lumber bd.ft. 8 20.00 160.00
c. Assorted CWN (1 kg./100 bd.ft.) kg. 0.08 68.00 5.44
d. Fertilizers kg. 0.10 50.00 5.00

Sub - Total for F 220.44


G. Direct Unit Cost (E + F) 241.11
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 21.70
I. Contractor's Profit (CP) 8% of G 19.29
J. Value Added Tax (VAT) 12% of (G + H + I) 33.85
K. Total Unit Cost (G + H + I + J) 315.95
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : SPL 3 Tree Planting


Unit of Measurement : pc.
Output per hour : 60.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Laborer 10 1 61.44 614.40

Sub - Total for A 723.59


Name and Capacity No of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Cargo Truck (5 T) 1 0.25 712.00 178.00


b. Water Truck (1000 gal.) 1 0.25 1,065.00 266.25
Minor Tools (10% of Labor) 72.36 72.36

Sub - Total for B 516.61


C. Total (A + B) 1,240.20
D. Output per hour = 60.0000 pc.
E. Direct Unit Cost (C ÷ D) 20.67
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Saplings pc. 1 50.00 50.00


b. Fertilizers kg. 0.10 26.00 2.60

Sub - Total for F 52.60


G. Direct Unit Cost (E + F) 73.27
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 6.59
I. Contractor's Profit (CP) 8% of G 5.86
J. Value Added Tax (VAT) 12% of (G + H + I) 10.29
K. Total Unit Cost (G + H + I + J) 96.01

DETAILED UNIT PRICE ANALYSIS (DUPA)


Item No./Description : SPL 2 Crack and Seat
Unit of Measurement : sq.m.
Output per hour : 35.00

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Skilled Laborer 1 1 79.70 79.70
c. Laborer 2 1 61.44 122.88

Sub - Total for A 311.77


Name and Capacity No of Units No. of Hours Rental Rate Amount

B. Equipment

a. Backhoe w/ Breaker (0.80 cu.m.) 1 1.00 2,074.95 2,074.95


b. Vibratory Roller (10 m.t.), SP56 1 0.75 1,507.00 1,130.25

Sub - Total for B 3,205.20


C. Total (A + B) 3,516.97
D. Output per hour = 35.0000 sq.m.
E. Direct Unit Cost (C ÷ D) 100.48
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

Sub - Total for F -


G. Direct Unit Cost (E + F) 100.48
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 9.04
I. Contractor's Profit (CP) 8% of G 8.04
J. Value Added Tax (VAT) 12% of (G + H + I) 14.11
K. Total Unit Cost (G + H + I + J) 131.68

DETAILED UNIT PRICE ANALYSIS (DUPA)


Item No./Description : SPL 2 Crack and Seat
Unit of Measurement : sq.m.
Output per hour : 30.00

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Skilled Laborer 1 1 79.70 79.70
c. Laborer 2 1 61.44 122.88

Sub - Total for A 311.77


Name and Capacity No of Units No. of Hours Rental Rate Amount

B. Equipment

a. Arrow Master D 500 1 1.00 1,485.84 1,485.84


(Additional 35% for Oil and Lubricants)
b. Vibratory Roller (10 m.t.), SP56 1 0.75 1,507.00 1,130.25

Sub - Total for B 2,616.09


C. Total (A + B) 2,927.86
D. Output per hour = 30.0000 sq.m.
E. Direct Unit Cost (C ÷ D) 97.60
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

Sub - Total for F -


G. Direct Unit Cost (E + F) 97.60
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 8.78
I. Contractor's Profit (CP) 8% of G 7.81
J. Value Added Tax (VAT) 12% of (G + H + I) 13.70
K. Total Unit Cost (G + H + I + J) 127.89
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 100(1) Clearing & Grubbing (with Stripping)


Unit of Measurement : sq.m.
Output per hour : 500.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Laborer 2 1 61.44 122.88

Sub - Total for A 232.07


Name and Capacity No of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Dump Truck (10 cu.m.) 2 1 1,352.00 2,704.00


b. Payloader (1.50 cu.m.) 1 1 1,733.00 1,733.00
c. Bulldozer (155 Hp), D65A-8 1 1 2,299.00 2,299.00

(Hauling Distance - within five (5) kilometers)

Sub - Total for B 6,736.00


C. Total (A + B) 6,968.07
D. Output per hour = 500.0000 sq.m.
E. Direct Unit Cost (C ÷ D) 13.94
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

Sub - Total for F -


G. Direct Unit Cost (E + F) 13.94
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 1.25
I. Contractor's Profit (CP) 8% of G 1.11
J. Value Added Tax (VAT) 12% of (G + H + I) 1.96
K. Total Unit Cost (G + H + I + J) 18.26
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 101(3)a1 Removal of Existing Concrete Pavement (0.23m thk.)


Unit of Measurement : sq.m.
Output per hour : 40.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Laborer 2 1 61.44 122.88

Sub - Total for A 232.07


Name and Capacity No of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Backhoe w/ Pavement Breaker (0.80 cu.m.) 1 1 2,074.95 2,074.95


b. Payloader (1.50 cu.m.), LX80-2C 1 1 1,733.00 1,733.00
c. Dump Truck (10 cu.m.) 1 1 1,352.00 1,352.00
Minor Tools (10% of Labor) 23.21

* Disposal area (within five (5) km)

Sub - Total for B 5,183.16


C. Total (A + B) 5,415.23
D. Output per hour = 40.00 sq.m.
E. Direct Unit Cost (C ÷ D) 135.38
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

Sub - Total for F -


G. Direct Unit Cost (E + F) 135.38
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 12.18
I. Contractor's Profit (CP) 8% of G 10.83
J. Value Added Tax (VAT) 12% of (G + H + I) 19.01
K. Total Unit Cost (G + H + I + J) 177.40

DETAILED UNIT PRICE ANALYSIS (DUPA)


Item No./Description : 101(3)a2 Removal of Existing PCC Pavement, 0.23m thk. (for Reblocking at intermittent section)
Unit of Measurement : sq.m.
Output per hour : 30.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Laborer 2 1 61.44 122.88

Sub - Total for A 232.07


Name and Capacity No of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Backhoe w/ Pavement Breaker (0.80 cu.m.) 1 1 2,074.95 2,074.95


b. Payloader (1.50 cu.m.), LX80-2C 1 1 1,733.00 1,733.00
c. Dump Truck (10 cu.m.) 1 1 1,352.00 1,352.00
d. Concrete Saw, Blade Ø 14" (7.5 Hp) 1 0.50 167.38 167.38
Minor Tools (10% of Labor) 23.21

* Disposal area (within five (5) km)

Sub - Total for B 5,350.54


C. Total (A + B) 5,582.61
D. Output per hour = 30.00000 sq.m.
E. Direct Unit Cost (C ÷ D) 186.09
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Concrete Saw (diamond blade 14") pc. 0.00015 8,000.00 1.20

Sub - Total for F 1.20


G. Direct Unit Cost (E + F) 187.29
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 16.86
I. Contractor's Profit (CP) 8% of G 14.98
J. Value Added Tax (VAT) 12% of (G + H + I) 26.30
K. Total Unit Cost (G + H + I + J) 245.42

DETAILED UNIT PRICE ANALYSIS (DUPA)


Item No./Description : 101(3)b Removal of Existing Asphalt Pavement (100mm thk.)
Unit of Measurement : sq.m.
Output per hour : 60.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Laborer 2 1 61.44 122.88

Sub - Total for A 232.07


Name and Capacity No of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Motorized Road Grader w/ Scarifier, G710A 1 1 2,173.00 2,173.00


b. Payloader (1.50 cu.m.), LX80-2C 1 1 1,733.00 1,733.00
c. Dump Truck (10 cu.m.) 1 1 1,352.00 1,352.00
Minor Tools (10% of Labor) 23.21

* Disposal area (within five (5) km)

Sub - Total for B 5,281.21


C. Total (A + B) 5,513.28
D. Output per hour = 60.00000 sq.m.
E. Direct Unit Cost (C ÷ D) 91.89
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

Sub - Total for F -


G. Direct Unit Cost (E + F) 91.89
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 8.27
I. Contractor's Profit (CP) 8% of G 7.35
J. Value Added Tax (VAT) 12% of (G + H + I) 12.90
K. Total Unit Cost (G + H + I + J) 120.41

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 101(4)c Removal of Sidewalk


Unit of Measurement : sq.m.
Output per hour : 60.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Laborer 2 1 61.44 122.88

Sub - Total for A 232.07


Name and Capacity No of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Backhoe w/ Pavement Breaker (0.80 cu.m.) 1 0.50 2,074.95 1,037.48


b. Backhoe (0.80 cu.m.) 1 0.50 1,537.00 768.50
c. Dump Truck (10 cu.m.) 1 1 1,352.00 1,352.00

* Disposal area (within five (5) km)

Sub - Total for B 3,157.98


C. Total (A + B) 3,390.05
D. Output per hour = 60.00000 sq.m.
E. Direct Unit Cost (C ÷ D) 56.50
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

Sub - Total for F -


G. Direct Unit Cost (E + F) 56.50
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 5.09
I. Contractor's Profit (CP) 8% of G 4.52
J. Value Added Tax (VAT) 12% of (G + H + I) 7.93
K. Total Unit Cost (G + H + I + J) 74.04

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 101(4)a Removal of Curb


Unit of Measurement : l.m.
Output per hour : 50.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Laborer 2 1 61.44 122.88

Sub - Total for A 232.07


Name and Capacity No of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Backhoe w/ Breaker (0.80 cu.m.) 1 0.50 2,074.95 1,037.48


b. Backhoe (0.80 cu.m.) 1 0.50 1,537.00 768.50
c. Dump Truck (10 cu.m.) 1 1 1,352.00 1,352.00

* Disposal area (within five (5) km)

Sub - Total for B 3,157.98


C. Total (A + B) 3,390.05
D. Output per hour = 50.00000 l.m.
E. Direct Unit Cost (C ÷ D) 67.80
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

Sub - Total for F -


G. Direct Unit Cost (E + F) 67.80
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 6.10
I. Contractor's Profit (CP) 8% of G 5.42
J. Value Added Tax (VAT) 12% of (G + H + I) 9.52
K. Total Unit Cost (G + H + I + J) 88.85

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 101(4)b Removal of Curb & Gutter


Unit of Measurement : l.m.
Output per hour : 30.00
Designation No. of Person No. of Hours Hourly Rate Amount
A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Laborer 2 1 61.44 122.88

Sub - Total for A 232.07


Name and Capacity No of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Backhoe w/ Breaker (0.80 cu.m.) 1 0.50 2,074.95 1,037.48


b. Backhoe (0.80 cu.m.) 1 0.50 1,537.00 768.50
c. Dump Truck (10 cu.m.) 1 1 1,352.00 1,352.00

* Disposal area (within five (5) km)

Sub - Total for B 3,157.98


C. Total (A + B) 3,390.05
D. Output per hour = 30.00000 l.m.
E. Direct Unit Cost (C ÷ D) 113.00
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

Sub - Total for F -


G. Direct Unit Cost (E + F) 113.00
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 10.17
I. Contractor's Profit (CP) 8% of G 9.04
J. Value Added Tax (VAT) 12% of (G + H + I) 15.87
K. Total Unit Cost (G + H + I + J) 148.08

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 102(1) Roadway Excavation (Unsuitable)


Unit of Measurement : cu.m.
Output per hour : 20.00

Designation No. of Person No. of Hours Hourly Rate Amount


Designation No. of Person No. of Hours Hourly Rate Amount
A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Laborer 3 1 61.44 184.32

Sub - Total for A 293.51


Name and Capacity No of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Dump Truck (10 cu.m.) 2 1 1,352.00 2,704.00


b. Backhoe (0.80 cu.m.) 1 1 1,537.00 1,537.00
c. Payloader (1.50 cu.m.) at disposal site 1 0.10 1,733.00 173.30
Minor Tools (10% of Labor) 29.35

* Disposal area (within five (5) km)

Sub - Total for B 4,443.65


C. Total (A + B) 4,737.16
D. Output per hour = 20.0000 cu.m.
E. Direct Unit Cost (C ÷ D) 236.86
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

Sub - Total for F -


G. Direct Unit Cost (E + F) 236.86
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 21.32
I. Contractor's Profit (CP) 8% of G 18.95
J. Value Added Tax (VAT) 12% of (G + H + I) 33.25
K. Total Unit Cost (G + H + I + J) 310.38

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 102(2)a Roadway Excavation (Surplus Common)


Unit of Measurement : cu.m.
Output per hour : 60.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor
a. Construction Foreman 1 1 109.19 109.19
b. Laborer 2 1 61.44 122.88

Sub - Total for A 232.07


Name and Capacity No of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Bulldozer (155 Hp), D65A-8 1 1 2,299.00 2,299.00


b. Payloader (1.50 cu.m.) 1 1.00 1,733.00 1,733.00
c. Payloader (1.50 cu.m.) - at disposal area 1 0.25 1,733.00 433.25
d. Dump Truck (10 cu.m.) 2 1 1,352.00 2,704.00

(Hauling Distance - within five (5) kilometers)

Sub - Total for B 7,169.25


C. Total (A + B) 7,401.32
D. Output per hour = 60.0000 cu.m.
E. Direct Unit Cost (C ÷ D) 123.36
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

Sub - Total for F -


G. Direct Unit Cost (E + F) 123.36
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 11.10
I. Contractor's Profit (CP) 8% of G 9.87
J. Value Added Tax (VAT) 12% of (G + H + I) 17.32
K. Total Unit Cost (G + H + I + J) 161.64

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 102(2)b Roadway Excavation (Surplus Common)


Unit of Measurement : cu.m.
Output per hour : 80.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor
a. Construction Foreman 1 1 109.19 109.19
b. Laborer 2 1 61.44 122.88

Sub - Total for A 232.07


Name and Capacity No of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Bulldozer (155 Hp), D65A-8 1 1 2,299.00 2,299.00


b. Payloader (1.50 cu.m.) 1 1.00 1,733.00 1,733.00
c. Payloader (1.50 cu.m.) - at disposal area 1 0.30 1,733.00 519.90
d. Dump Truck (10 cu.m.) 3 1 1,352.00 4,056.00
e. Backhoe (0.80 cu.m.) 1 1 1,537.00 1,537.00

(Hauling Distance - within five (5) kilometers)

Sub - Total for B 10,144.90


C. Total (A + B) 10,376.97
D. Output per hour = 80.0000 cu.m.
E. Direct Unit Cost (C ÷ D) 129.71
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

Sub - Total for F -


G. Direct Unit Cost (E + F) 129.71
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 11.67
I. Contractor's Profit (CP) 8% of G 10.38
J. Value Added Tax (VAT) 12% of (G + H + I) 18.21
K. Total Unit Cost (G + H + I + J) 169.97

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 102(3)a Roadway Excavation (Surplus Soft Rock)


Unit of Measurement : cu.m.
Output per hour : 56.00 with Backhoe

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Laborer 2 1 61.44 122.88

Sub - Total for A 232.07


Name and Capacity No of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Bulldozer w/ Ripper (155 Hp), D65A-8 1 1 2,758.80 2,758.80


b. Payloader (1.50 cu.m.) 1 1 1,733.00 1,733.00
c. Payloader (1.50 cu.m.) at disposal area 1 0.25 1,733.00 433.25
d. Dump Truck (10 cu.m.) 3 1 1,352.00 4,056.00
e. Backhoe (0.80 cu.m.) w/ attachment 1 1 2,074.95 2,074.95

(Hauling Distance - within five (5) kilometers)

Sub - Total for B 11,056.00


C. Total (A + B) 11,288.07
D. Output per hour = 56.0000 cu.m.
E. Direct Unit Cost (C ÷ D) 201.57
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

Sub - Total for F -


G. Direct Unit Cost (E + F) 201.57
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 18.14
I. Contractor's Profit (CP) 8% of G 16.13
J. Value Added Tax (VAT) 12% of (G + H + I) 28.30
K. Total Unit Cost (G + H + I + J) 264.14

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 102(3)b Roadway Excavation (Surplus Soft Rock)


Unit of Measurement : cu.m.
Output per hour : 42.00 w/out Backhoe

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Laborer 2 1 61.44 122.88
Sub - Total for A 232.07
Name and Capacity No of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Bulldozer w/ Ripper (155 Hp), D65A-8 1 1 2,758.80 2,758.80


b. Payloader (1.50 cu.m.) 1 1 1,733.00 1,733.00
c. Payloader (1.50 cu.m.) at disposal area 1 0.20 1,733.00 346.60
d. Dump Truck (10 cu.m.) 3 1 1,352.00 4,056.00

(Hauling Distance - within five (5) kilometers)

Sub - Total for B 8,894.40


C. Total (A + B) 9,126.47
D. Output per hour = 42.0000 cu.m.
E. Direct Unit Cost (C ÷ D) 217.30
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

Sub - Total for F -


G. Direct Unit Cost (E + F) 217.30
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 19.56
I. Contractor's Profit (CP) 8% of G 17.38
J. Value Added Tax (VAT) 12% of (G + H + I) 30.51
K. Total Unit Cost (G + H + I + J) 284.75

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 102(3)c Roadway Excavation (Surplus Hard Rock) - Blasting


Unit of Measurement : cu.m.
Output per hour : 10.00

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor
a. Construction Foreman (Drilling) 1 1 109.19 109.19
b. Skilled Laborer 2 1 79.70 159.40
c. Laborer 4 1 61.44 245.76
a. Construction Foreman (Blasting) 1 1 109.19 109.19
b. Skilled Laborer 1 1 79.70 79.70
c. Laborer 2 1 61.44 122.88
a. Construction Foreman (Disposal) 1 1 109.19 109.19
b Laborer 2 1 61.44 122.88
Sub - Total for A 1,058.19
Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Backhoe (0.80 cu.m.) 1 0.25 1,537.00 384.25


b. Payloader (1.50 cu.m.) 1 0.25 1,733.00 433.25
c. Payloader (1.50 cu.m.) at disposal area 1 0.05 1,733.00 86.65
d. Dump Truck (10 cu.m.) 1 1 1,352.00 1,352.00
e. Pneumatic Drilling Machine 2 1 514.31 1,028.62
f. Compressor 1 1 358.00 358.00
(Hauling Distance - within five (5) kilometers)

Sub - Total for B 3,642.77


C. Total (A + B) 4,700.96
D. Output per hour = 10.0000 cu.m.
E. Direct Unit Cost (C ÷ D) 470.10
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. Dynamite kg. 0.40 280.00 112.00


b. Detonation Cord m. 2.00 80.00 160.00
c. Detonator pc. 0.15 260.00 39.00
d. Ammonium Sulfate kg. 0.20 75.00 15.00
e. Blasting Cap pc. 0.30 45.00 13.50
f. Safety Fuse m. 0.10 40.00 4.00

Sub - Total for F 343.50


G. Direct Unit Cost (E + F) 813.60
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 73.22
I. Contractor's Profit (CP) 8% of G 65.09
J. Value Added Tax (VAT) 12% of (G + H + I) 114.23
K. Total Unit Cost (G + H + I + J) 1,066.14

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 103(1)a Structure Excavation (Common Soil)


Unit of Measurement : cu.m.
Output per hour : 20.00

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Laborer 3 1 61.44 184.32
Sub - Total for A 293.51
Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Dump Truck (10 cu.m.) 2 1 1,352.00 2,704.00


b. Backhoe (0.80 cu.m.) 1 1 1,537.00 1,537.00
Minor Tools (10% of Labor) 29.35

Sub - Total for B 4,270.35


C. Total (A + B) 4,563.86
D. Output per hour = 20.0000 cu.m.
E. Direct Unit Cost (C ÷ D) 228.19
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

Sub - Total for F -


G. Direct Unit Cost (E + F) 228.19
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 20.54
I. Contractor's Profit (CP) 8% of G 18.26
J. Value Added Tax (VAT) 12% of (G + H + I) 32.04
K. Total Unit Cost (G + H + I + J) 299.02

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 103(1)b Structure Excavation (Soft Rock)


Unit of Measurement : cu.m.
Output per hour : 14.00

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Laborer 3 1 61.44 184.32
Sub - Total for A 293.51
Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Dump Truck (10 cu.m.) 2 1 1,352.00 2,704.00


b. Backhoe (0.80 cu.m.) 1 0.50 1,537.00 768.50
c. Backhoe w/ Breaker (0.80 cu.m.) 1 0.50 2,074.95 1,037.48
Minor Tools (10% of Labor) 29.35

Sub - Total for B 4,539.33


C. Total (A + B) 4,832.84
D. Output per hour = 14.0000 cu.m.
E. Direct Unit Cost (C ÷ D) 345.20
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

Sub - Total for F -


G. Direct Unit Cost (E + F) 345.20
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 31.07
I. Contractor's Profit (CP) 8% of G 27.62
J. Value Added Tax (VAT) 12% of (G + H + I) 48.47
K. Total Unit Cost (G + H + I + J) 452.35

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 103(1)c Structure Excavation (Solid Rock)


Unit of Measurement : cu.m.
Output per hour : 4.00

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Laborer 3 1 61.44 184.32
Sub - Total for A 293.51
Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Dump Truck (10 cu.m.) 1 1 1,352.00 1,352.00


b. Backhoe (0.80 cu.m.) 1 0.50 1,537.00 768.50
c. Backhoe w/ Breaker (0.80 cu.m.) 1 0.50 2,074.95 1,037.48
Minor Tools (10% of Labor) 29.35

Sub - Total for B 3,187.33


C. Total (A + B) 3,480.84
D. Output per hour = 4.0000 cu.m.
E. Direct Unit Cost (C ÷ D) 870.21
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

Sub - Total for F -


G. Direct Unit Cost (E + F) 870.21
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 78.32
I. Contractor's Profit (CP) 8% of G 69.62
J. Value Added Tax (VAT) 12% of (G + H + I) 122.18
K. Total Unit Cost (G + H + I + J) 1,140.32

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 103(2)a Bridge Excavation (Common Soil)


Unit of Measurement : cu.m.
Output per hour : 20.00

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Skilled Laborer 1 1 79.70 79.70
c. Laborer 2 1 61.44 122.88
Sub - Total for A 311.77
Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

b. Backhoe (0.80 cu.m.) 1 1 1,537.00 1,537.00


b. Dump Truck (10 cu.m.) 2 1 1,352.00 2,704.00
Minor Tools (10% of Labor) 31.18

Sub - Total for B 4,272.18


C. Total (A + B) 4,583.95
D. Output per hour = 20.0000 cu.m.
E. Direct Unit Cost (C ÷ D) 229.20
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

Sub - Total for F -


G. Direct Unit Cost (E + F) 229.20
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 20.63
I. Contractor's Profit (CP) 8% of G 18.34
J. Value Added Tax (VAT) 12% of (G + H + I) 32.18
K. Total Unit Cost (G + H + I + J) 300.34

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 103(2)b Bridge Excavation (Soft Rock)


Unit of Measurement : cu.m.
Output per hour : 14.00

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Skilled Laborer 1 1 79.70 79.70
c. Laborer 2 1 61.44 122.88

Sub - Total for A 311.77


Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Backhoe (0.80 cu.m.) 1 0.50 1,537.00 768.50


b. Backhoe w/ Breaker (0.80 cu.m.) 1 0.50 2,074.95 1,037.48
c. Dump Truck (10 cu.m.) 2 1 1,352.00 2,704.00
Minor Tools (10% of Labor) 31.18

Sub - Total for B 4,541.15


C. Total (A + B) 4,852.92
D. Output per hour = 14.0000 cu.m.
E. Direct Unit Cost (C ÷ D) 346.64
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

Sub - Total for F -


G. Direct Unit Cost (E + F) 346.64
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 31.20
I. Contractor's Profit (CP) 8% of G 27.73
J. Value Added Tax (VAT) 12% of (G + H + I) 48.67
K. Total Unit Cost (G + H + I + J) 454.23

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 103(2)c Bridge Excavation (Solid Rock)


Unit of Measurement : cu.m.
Output per hour : 4.00

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Skilled Laborer 1 1 79.70 79.70
c. Laborer 2 1 61.44 122.88

Sub - Total for A 311.77


Name and Capacity No of Units No. of Hours Hourly Rate Amount
Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Backhoe (0.80 cu.m.) 1 0.50 1,537.00 768.50


b. Backhoe w/ Breaker (0.80 cu.m.) 1 0.50 2,074.95 1,037.48
c. Dump Truck (10 cu.m.) 1 1 1,352.00 1,352.00
Minor Tools (10% of Labor) 31.18

Sub - Total for B 3,189.15


C. Total (A + B) 3,500.92
D. Output per hour = 4.0000 cu.m.
E. Direct Unit Cost (C ÷ D) 875.23
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

Sub - Total for F -


G. Direct Unit Cost (E + F) 875.23
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 78.77
I. Contractor's Profit (CP) 8% of G 70.02
J. Value Added Tax (VAT) 12% of (G + H + I) 122.88
K. Total Unit Cost (G + H + I + J) 1,146.90

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 103(3) Foundation Fill


Unit of Measurement : cu.m.
Output per hour : 1.25

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Laborer 4 1 61.44 245.76

Sub - Total for A 354.95


Name and Capacity No of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Plate Compactor 1 1 123.00 123.00


b. Water Truck (1000 gal.) 1 0.01 1,065.00 10.65
Minor Tools (10% of Labor) 35.50

Sub - Total for B 169.15


C. Total (A + B) 524.10
D. Output per hour = 1.25 cu.m.
E. Direct Unit Cost (C ÷ D) 419.28
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. Filling Materials cu.m. 1.15 465.00 534.75

Sub - Total for F 534.75


G. Direct Unit Cost (E + F) 954.03
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 85.86
I. Contractor's Profit (CP) 8% of G 76.32
J. Value Added Tax (VAT) 12% of (G + H + I) 133.95
K. Total Unit Cost (G + H + I + J) 1,250.16

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 103(4) Excavation ordered below Plan Elevation


Unit of Measurement : cu.m.
Output per hour : 20.00

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Laborer 3 1 61.44 184.32

Sub - Total for A 293.51


Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment
a. Dump Truck (10 cu.m.) 2 1 1,352.00 2,704.00
b. Backhoe (0.80 cu.m.) 1 1 1,537.00 1,537.00
Minor Tools (10% of Labor) 29.35

Sub - Total for B 4,270.35


C. Total (A + B) 4,563.86
D. Output per hour = 20.0000 cu.m.
E. Direct Unit Cost (C ÷ D) 228.19
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

Sub - Total for F -


G. Direct Unit Cost (E + F) 228.19
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 20.54
I. Contractor's Profit (CP) 8% of G 18.26
J. Value Added Tax (VAT) 12% of (G + H + I) 32.04
K. Total Unit Cost (G + H + I + J) 299.02

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 103(5)a Shoring and other related works (assumed footing area = 15 sq.m.)
Unit of Measurement : sq.m.
Output per hour : 1.25

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Skilled Laborer 2 1 79.70 159.40
c. Laborer 4 1 61.44 245.76

Sub - Total for A 514.35


Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment
a. Crawler Crane (45 T) 1 1 1,772.00 1,772.00
b. Vibro Hammer (Hydraulic Operated) 1 1 3,069.00 3,069.00
c. Welding Machine 1 0.25 391.00 97.75
d. Cutting Outfit 1 0.25 45.45 11.36

Sub - Total for B 4,950.11


C. Total (A + B) 5,464.46
D. Output per hour = 1.25 sq.m.
E. Direct Unit Cost (C ÷ D) 4,371.57
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. Steel Sheet Piles KSP-II (FY36) kg. 384.00 71.90 27,609.60


40 pcs. - 400mm x 3m
b. Welding Rod (1 kg./2000 kg. of Steel) kg. 0.192 90.00 17.28
c. Oxy/Acetylene (1 set/5000 kg. of Steel) set 0.077 2,500.00 192.50
Miscellaneous (10% of Materials) 2,781.94

Area = 3m x 5m = 15 sq.m.
Perimeter = (3+5)2 =16 /0.40 = 40 pcs.
40 pcs. x 3m/pc. x 48kg/m. = 5,760 kg.

Sub - Total for F 30,601.32


G. Direct Unit Cost (E + F) 34,972.89
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 3,147.56
I. Contractor's Profit (CP) 8% of G 2,797.83
J. Value Added Tax (VAT) 12% of (G + H + I) 4,910.19
K. Total Unit Cost (G + H + I + J) 45,828.47

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 103(5)b Shoring and other related works (assumed footing area = 15 sq.m.)
Unit of Measurement : sq.m.
Output per hour : 0.80

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Skilled Laborer 2 1 79.70 159.40
c. Laborer 4 1 61.44 245.76

Sub - Total for A 514.35


Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Crawler Crane (45 T) 1 1 1,772.00 1,772.00


b. Drop Hammer 1 1 200.00 200.00

Sub - Total for B 1,972.00


C. Total (A + B) 2,486.35
D. Output per hour = 0.80 sq.m.
E. Direct Unit Cost (C ÷ D) 3,107.94
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. Coco Log 0.325m dia. x 3m. bd.ft. 351.30 20.00 7,026.00


b. Wheeler & Squarehole bd.ft. 8.889 40.00 355.56
(10pcs.x 2"x8"x10')/12 = 133.33 bd.ft.
c. Assorted CWN (1 kg./100 bd.ft. of Lumber) kg. 0.089 68.00 6.05
Miscellaneous (10% of Materials) 738.76

Area = 3m x 5m = 15 sq.m.
Perimeter = (3+5)2 =16 /0.325 = 49.23 pcs., say 50 pcs.
50 pcs. x 3m/pc. x 35.13bd.ft./m. = 5,269.50 bd.ft.

Sub - Total for F 8,126.37


G. Direct Unit Cost (E + F) 11,234.31
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 1,011.09
I. Contractor's Profit (CP) 8% of G 898.74
J. Value Added Tax (VAT) 12% of (G + H + I) 1,577.30
K. Total Unit Cost (G + H + I + J) 14,721.44

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 103(5)c Shoring and other related works (assumed slope protection length = 20 l.m.)
Unit of Measurement : l.m.
Output per hour : 10.00

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Skilled Laborer 2 1 79.70 159.40
c. Laborer 4 1 61.44 245.76

Sub - Total for A 514.35


Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Crawler Crane (45 T) 1 1 1,772.00 1,772.00


b. Vibro Hammer (Hydraulic Operated) 1 1 3,069.00 3,069.00
c. Welding Machine 1 0.50 391.00 195.50
d. Cutting Outfit 1 0.50 45.45 22.73

Sub - Total for B 5,059.23


C. Total (A + B) 5,573.58
D. Output per hour = 10.000 l.m.
E. Direct Unit Cost (C ÷ D) 557.36
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. Steel Sheet Piles KSP-II (FY36) kg. 48.00 71.90 3,451.20


50 pcs. - 400mm x 3m
b. Welding Rod (1 kg./2000 kg. of Steel) kg. 0.024 90.00 2.16
c. Oxy/Acetylene (1 set/5000 kg. of Steel) set 0.010 2,500.00 25.00
Miscellaneous (10% of Materials) 347.84

20 l.m./0.40 = 50 pcs.
50 pcs. x 3m/pc. x 48kg/m. = 7,200.00 kg.

Sub - Total for F 3,826.20


G. Direct Unit Cost (E + F) 4,383.55
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 394.52
I. Contractor's Profit (CP) 8% of G 350.68
J. Value Added Tax (VAT) 12% of (G + H + I) 615.45
K. Total Unit Cost (G + H + I + J) 5,744.21

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 103(5)d Shoring and other related works (assumed slope protection length = 20 l.m.)
Unit of Measurement : l.m.
Output per hour : 8.00

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Skilled Laborer 2 1 79.70 159.40
c. Laborer 4 1 61.44 245.76

Sub - Total for A 514.35


Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Crawler Crane (45 T) 1 1 1,772.00 1,772.00


b. Drop Hammer 1 1 200.00 200.00
Sub - Total for B 1,972.00
C. Total (A + B) 2,486.35
D. Output per hour = 8.000 l.m.
E. Direct Unit Cost (C ÷ D) 310.79
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. Coco Log 0.325m dia. x 3m. bd.ft. 35.13 20.00 702.60


b. Wheeler & Squarehole bd.ft. 0.717 40.00 28.68
(10pcs.x 2"x8"x10')/12 = 133.33 bd.ft.
c. Assorted CWN (1 kg./100 bd.ft. of Lumber) kg. 0.007 68.00 0.48
Miscellaneous (10% of Materials) 73.18

20 l.m./0.325 = 61.54 pcs., say 62 pcs.


62 pcs. x 3m/pc. x 35.13bd.ft./m. = 6,534.18 bd.ft.

Sub - Total for F 804.93


G. Direct Unit Cost (E + F) 1,115.73
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 100.42
I. Contractor's Profit (CP) 8% of G 89.26
J. Value Added Tax (VAT) 12% of (G + H + I) 156.65
K. Total Unit Cost (G + H + I + J) 1,462.05

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 103(6) Pipe Culvert and Drain Excavation


Unit of Measurement : cu.m.
Output per hour : 20.00

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Laborer 3 1 61.44 184.32

Sub - Total for A 293.51


Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Dump Truck (10 cu.m.) 2 1 1,352.00 2,704.00


b. Backhoe (0.80 cu.m.) 1 1 1,537.00 1,537.00
Minor Tools (10% of Labor) 29.35
Sub - Total for B 4,270.35
C. Total (A + B) 4,563.86
D. Output per hour = 20.00000 cu.m.
E. Direct Unit Cost (C ÷ D) 228.19
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

Sub - Total for F -


G. Direct Unit Cost (E + F) 228.19
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 20.54
I. Contractor's Profit (CP) 8% of G 18.26
J. Value Added Tax (VAT) 12% of (G + H + I) 32.04
K. Total Unit Cost (G + H + I + J) 299.02

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 104(1)a Embankment (from Borrow)


Unit of Measurement : cu.m.
Output per hour : 50.00

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Laborer 2 1 61.44 122.88

Sub - Total for A 232.07


Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Motorized Road Grader, G710A 1 1 2,173.00 2,173.00


b. Vibratory Roller (10 m.t.), SP56 1 1 1,507.00 1,507.00
c. Water Truck (1000 gal.) 1 0.25 1,065.00 266.25
Sub - Total for B 3,946.25
C. Total (A + B) 4,178.32
D. Output per hour = 50.00000 cu.m.
E. Direct Unit Cost (C ÷ D) 83.57
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. Common Borrow (w/ 25% Shrinkage Factor) cu.m. 1.25 400.00 500.00

Sub - Total for F 500.00


G. Direct Unit Cost (E + F) 583.57
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 52.52
I. Contractor's Profit (CP) 8% of G 46.69
J. Value Added Tax (VAT) 12% of (G + H + I) 81.93
K. Total Unit Cost (G + H + I + J) 764.71

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 104(1)b Embankment from Roadway Excavation


Unit of Measurement : cu.m.
Output per hour : 50.00

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor
For Excavation Work:
a. Construction Foreman 1 0.83 109.19 90.63
b. Laborer 2 0.83 61.44 101.99

Spreading and Compaction:


a. Construction Foreman 1 1 109.19 109.19
b. Laborer 2 1 61.44 122.88

Sub - Total for A 424.69


Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment
For Excavation Work:
a. Bulldozer (155 Hp), D65A-8 1 0.83 2,299.00 1,908.17
b. Payloader (1.50 cu.m.) 1 0.83 1,733.00 1,438.39
c. Dump Truck (10 cu.m.) 2 0.83 1,352.00 2,244.32

Spreading and Compaction


a. Motorized Road Grader, G710A 1 1 2,173.00 2,173.00
b. Vibratory Roller (10 m.t.), SP56 1 1 1,507.00 1,507.00
c. Water Truck (1000 gal.) 1 0.25 1,065.00 266.25

Sub - Total for B 9,537.13


C. Total (A + B) 9,961.82
D. Output per hour = 50.00000 cu.m.
E. Direct Unit Cost (C ÷ D) 199.24
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

Sub - Total for F -


G. Direct Unit Cost (E + F) 199.24
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 17.93
I. Contractor's Profit (CP) 8% of G 15.94
J. Value Added Tax (VAT) 12% of (G + H + I) 27.97
K. Total Unit Cost (G + H + I + J) 261.08

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 104(2) Selected Borrow for topping , case 1


Unit of Measurement : cu.m.
Output per hour : 50.00

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Laborer 2 1 61.44 122.88

Sub - Total for A 232.07


Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Motorized Road Grader, G710A 1 1 2,173.00 2,173.00


b. Vibratory Roller (10 m.t.) 1 1 1,507.00 1,507.00
c. Water Truck (1000 gal.) 1 0.25 1,065.00 266.25
Sub - Total for B 3,946.25
C. Total (A + B) 4,178.32
D. Output per hour = 50.00000 cu.m.
E. Direct Unit Cost (C ÷ D) 83.57
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. Selected Borrow (w/ 25% Shrinkage Factor) cu.m. 1.25 420.00 525.00

Sub - Total for F 525.00


G. Direct Unit Cost (E + F) 608.57
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 54.77
I. Contractor's Profit (CP) 8% of G 48.69
J. Value Added Tax (VAT) 12% of (G + H + I) 85.44
K. Total Unit Cost (G + H + I + J) 797.47

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 104(3) Selected Borrow for topping , case 2


Unit of Measurement : cu.m.
Output per hour : 50.00

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Laborer 2 1 61.44 122.88

Sub - Total for A 232.07


Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Motorized Road Grader, G710A 1 1 2,173.00 2,173.00


b. Vibratory Roller (10 m.t.) 1 1 1,507.00 1,507.00
c. Water Truck (1000 gal.) 1 0.25 1,065.00 266.25
Sub - Total for B 3,946.25
C. Total (A + B) 4,178.32
D. Output per hour = 50.00000 cu.m.
E. Direct Unit Cost (C ÷ D) 83.57
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. Selected Borrow (w/ 25% Shrinkage Factor) cu.m. 1.25 420.00 525.00

Sub - Total for F 525.00


G. Direct Unit Cost (E + F) 608.57
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 54.77
I. Contractor's Profit (CP) 8% of G 48.69
J. Value Added Tax (VAT) 12% of (G + H + I) 85.44
K. Total Unit Cost (G + H + I + J) 797.47

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 104(4) Earth Berm


Unit of Measurement : cu.m.
Output per hour : 1.25

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Laborer 4 1 61.44 245.76

Sub - Total for A 354.95


Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Plate Compactor 1 1 123.00 123.00


b. Water Truck (1000 gal.) 1 0.01 1,065.00 10.65
Minor Tools (10% of Labor) 35.50
Sub - Total for B 169.15
C. Total (A + B) 524.10
D. Output per hour = 1.25 cu.m.
E. Direct Unit Cost (C ÷ D) 419.28
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. Filling Materials cu.m. 1.25 420.00 525.00

Sub - Total for F 525.00


G. Direct Unit Cost (E + F) 944.28
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 84.98
I. Contractor's Profit (CP) 8% of G 75.54
J. Value Added Tax (VAT) 12% of (G + H + I) 132.58
K. Total Unit Cost (G + H + I + J) 1,237.38

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 105(1) Subgrade Preparation (Common Excavation)


Unit of Measurement : sq.m.
Output per hour : 300.00

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Laborer 2 1 61.44 122.88

Sub - Total for A 232.07


Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Motorized Road Grader, G710A 1 1 2,173.00 2,173.00


b. Vibratory Roller (10 m.t.), SP56 1 1 1,507.00 1,507.00
c. Water Truck (1000 gal.) 1 0.25 1,065.00 266.25
Sub - Total for B 3,946.25
C. Total (A + B) 4,178.32
D. Output per hour = 300.00000 sq.m.
E. Direct Unit Cost (C ÷ D) 13.93
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

Sub - Total for F -


G. Direct Unit Cost (E + F) 13.93
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 1.25
I. Contractor's Profit (CP) 8% of G 1.11
J. Value Added Tax (VAT) 12% of (G + H + I) 1.96
K. Total Unit Cost (G + H + I + J) 18.25

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 105(2) Subgrade Preparation (Existing Pavement)


Unit of Measurement : sq.m.
Output per hour : 300.00

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Laborer 2 1 61.44 122.88

Sub - Total for A 232.07


Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Motorized Road Grader, G710A 1 1 2,173.00 2,173.00


b. Vibratory Roller (10 m.t.), SP56 1 1 1,507.00 1,507.00
c. Water Truck (1000 gal.) 1 0.25 1,065.00 266.25
Sub - Total for B 3,946.25
C. Total (A + B) 4,178.32
D. Output per hour = 300.00000 sq.m.
E. Direct Unit Cost (C ÷ D) 13.93
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

Sub - Total for F -


G. Direct Unit Cost (E + F) 13.93
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 1.25
I. Contractor's Profit (CP) 8% of G 1.11
J. Value Added Tax (VAT) 12% of (G + H + I) 1.96
K. Total Unit Cost (G + H + I + J) 18.25

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 105(3) Subgrade Preparation (Unsuitable Excavation)


Unit of Measurement : sq.m.
Output per hour : 300.00

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Laborer 2 1 61.44 122.88

Sub - Total for A 232.07


Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Motorized Road Grader, G710A 1 1 2,173.00 2,173.00


b. Vibratory Roller (10 m.t.), SP56 1 1 1,507.00 1,507.00
c. Water Truck (1000 gal.) 1 0.25 1,065.00 266.25
Sub - Total for B 3,946.25
C. Total (A + B) 4,178.32
D. Output per hour = 300.00000 sq.m.
E. Direct Unit Cost (C ÷ D) 13.93
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

Sub - Total for F -


G. Direct Unit Cost (E + F) 13.93
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 1.25
I. Contractor's Profit (CP) 8% of G 1.11
J. Value Added Tax (VAT) 12% of (G + H + I) 1.96
K. Total Unit Cost (G + H + I + J) 18.25
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 200 Aggregate Subbase Course


Unit of Measurement : cu.m
Output per hour : 50.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Laborers 2 1 61.44 122.88

Sub - Total for A 232.07


Name and Capacity No of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Motorized Road Grader, G710A 1 1 2,173.00 2,173.00


b. Vibratory Roller (10 m.t.), SP56 1 1 1,507.00 1,507.00
c. Water Truck (1000 gal.) 1 0.25 1,065.00 266.25

Sub - Total for B 3,946.25


C. Total (A + B) 4,178.32
D. Output per hour = 50.0000 cu.m.
E. Direct Unit Cost (C ÷ D) 83.57
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Aggregate Subbase Course cu.m. 1.15 580.00 667.00


(w/ 15% Shrinkage Factor)

Sub - Total for F 667.00


G. Direct Unit Cost (E + F) 750.57
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 67.55
I. Contractor's Profit (CP) 8% of G 60.05
J. Value Added Tax (VAT) 12% of (G + H + I) 105.38
K. Total Unit Cost (G + H + I + J) 983.54
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 200(1) Aggregate Subbase Course (for Intermittent Reblocking)


Unit of Measurement : cu.m
Output per hour : 40.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Laborers 2 1 61.44 122.88

Sub - Total for A 232.07


Name and Capacity No of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Motorized Road Grader, G710A 1 1 2,173.00 2,173.00


b. Vibratory Roller (10 m.t.), SP56 1 1 1,507.00 1,507.00
c. Plate Compactor 1 0.25 123.00 30.75
d. Water Truck (1000 gal.) 1 0.25 1,065.00 266.25

Sub - Total for B 3,977.00


C. Total (A + B) 4,209.07
D. Output per hour = 40.0000 cu.m.
E. Direct Unit Cost (C ÷ D) 105.23
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Aggregate Subbase Course cu.m. 1.15 580.00 667.00


(w/ 15% Shrinkage Factor)

Sub - Total for F 667.00


G. Direct Unit Cost (E + F) 772.23
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 69.50
I. Contractor's Profit (CP) 8% of G 61.78
J. Value Added Tax (VAT) 12% of (G + H + I) 108.42
K. Total Unit Cost (G + H + I + J) 1,011.93

DETAILED UNIT PRICE ANALYSIS (DUPA)


Item No./Description : 201 Aggregate Base Course
Unit of Measurement : cu.m
Output per hour : 50.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Laborers 2 1 61.44 122.88

Sub - Total for A 232.07


Name and Capacity No of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Motorized Road Grader, G710A 1 1 2,173.00 2,173.00


b. Vibratory Roller (10 m.t.), SP56 1 1 1,507.00 1,507.00
c. Water Truck (1000 gal.) 1 0.25 1,065.00 266.25

Sub - Total for B 3,946.25


C. Total (A + B) 4,178.32
D. Output per hour = 50.0000 cu.m.
E. Direct Unit Cost (C ÷ D) 83.57
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Aggregate Base Course cu.m. 1.15 650.00 747.50


(w/ 15% Shrinkage Factor)

Sub - Total for F 747.50


G. Direct Unit Cost (E + F) 831.07
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 74.80
I. Contractor's Profit (CP) 8% of G 66.49
J. Value Added Tax (VAT) 12% of (G + H + I) 116.68
K. Total Unit Cost (G + H + I + J) 1,089.03

DETAILED UNIT PRICE ANALYSIS (DUPA)


Item No./Description : 201(1) Aggregate Base Course (for Reblocking)
Unit of Measurement : cu.m
Output per hour : 40.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Laborers 2 1 61.44 122.88

Sub - Total for A 232.07


Name and Capacity No of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Motorized Road Grader, G710A 1 1 2,173.00 2,173.00


b. Vibratory Roller (10 m.t.), SP56 1 1 1,507.00 1,507.00
c. Plate Compactor 1 0.25 123.00 30.75
d. Water Truck (1000 gal.) 1 0.25 1,065.00 266.25

Sub - Total for B 3,977.00


C. Total (A + B) 4,209.07
D. Output per hour = 40.0000 cu.m.
E. Direct Unit Cost (C ÷ D) 105.23
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Aggregate Base Course cu.m. 1.15 650.00 747.50


(w/ 15% Shrinkage Factor)

Sub - Total for F 747.50


G. Direct Unit Cost (E + F) 852.73
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 76.75
I. Contractor's Profit (CP) 8% of G 68.22
J. Value Added Tax (VAT) 12% of (G + H + I) 119.72
K. Total Unit Cost (G + H + I + J) 1,117.41

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 202 Crushed Aggregate Base Course


Unit of Measurement : cu.m
Output per hour : 50.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Laborers 2 1 61.44 122.88

Sub - Total for A 232.07


Name and Capacity No of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Motorized Road Grader, G710A 1 1 2,173.00 2,173.00


b. Vibratory Roller (10 m.t.), SP56 1 1 1,507.00 1,507.00
c. Water Truck (1000 gal.) 1 0.25 1,065.00 266.25

Sub - Total for B 3,946.25


C. Total (A + B) 4,178.32
D. Output per hour = 50.0000 cu.m.
E. Direct Unit Cost (C ÷ D) 83.57
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Crushed Aggregate Base Course cu.m. 1.15 700.00 805.00


(w/ 15% Shrinkage Factor)

Sub - Total for F 805.00


G. Direct Unit Cost (E + F) 888.57
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 79.97
I. Contractor's Profit (CP) 8% of G 71.09
J. Value Added Tax (VAT) 12% of (G + H + I) 124.75
K. Total Unit Cost (G + H + I + J) 1,164.38

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 202(1) Crushed Aggregate Base Course (for Reblocking)


Unit of Measurement : cu.m
Output per hour : 50.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Laborers 2 1 61.44 122.88

Sub - Total for A 232.07


Name and Capacity No of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Motorized Road Grader, G710A 1 1 2,173.00 2,173.00


b. Vibratory Roller (10 m.t.), SP56 1 1 1,507.00 1,507.00
c. Plate Compactor 1 0.25 123.00 30.75
d. Water Truck (1000 gal.) 1 0.25 1,065.00 266.25

Sub - Total for B 3,977.00


C. Total (A + B) 4,209.07
D. Output per hour = 50.0000 cu.m.
E. Direct Unit Cost (C ÷ D) 84.18
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Crushed Aggregate Base Course cu.m. 1.15 700.00 805.00


(w/ 15% Shrinkage Factor)

Sub - Total for F 805.00


G. Direct Unit Cost (E + F) 889.18
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 80.03
I. Contractor's Profit (CP) 8% of G 71.13
J. Value Added Tax (VAT) 12% of (G + H + I) 124.84
K. Total Unit Cost (G + H + I + J) 1,165.18
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 301(1) Bituminous Prime Coat (MC Cut-back Asphalt)


Unit of Measurement : m.t.
Output per hour : 0.30

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Laborer 3 1 61.44 184.32

Sub - Total for A 293.51


Name and Capacity No of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Asphalt Distributor, 10 ft. wide (5 tons) 1 1 936.00 936.00


b. Power Broom (20 m. wide) 1 1 130.54 130.54

Sub - Total for B 1,066.54


C. Total (A + B) 1,360.05
D. Output per hour = 0.300 m.t.
E. Direct Unit Cost (C ÷ D) 4,533.50
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. MC 70 Cut-back Asphalt m.t. 1.05 40,300.00 42,315.00


(w/ 5% wastage)

Sub - Total for F 42,315.00


G. Direct Unit Cost (E + F) 46,848.50
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 4,216.37
I. Contractor's Profit (CP) 8% of G 3,747.88
J. Value Added Tax (VAT) 12% of (G + H + I) 6,577.53
K. Total Unit Cost (G + H + I + J) 61,390.27
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 301(2) Bituminous Prime Coat (RC Cut-back Asphalt)


Unit of Measurement : m.t.
Output per hour : 0.30

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Laborer 3 1 61.44 184.32

Sub - Total for A 293.51


Name and Capacity No of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Asphalt Distributor, 10 ft. wide (5 tons) 1 1 936.00 936.00


b. Power Broom (20 m. wide) 1 1 130.54 130.54

Sub - Total for B 1,066.54


C. Total (A + B) 1,360.05
D. Output per hour = 0.300 m.t.
E. Direct Unit Cost (C ÷ D) 4,533.50
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. RC 70 Cut-back Asphalt m.t. 1.05 41,575.00 43,653.75


(w/ 5% wastage)

Sub - Total for F 43,653.75


G. Direct Unit Cost (E + F) 48,187.25
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 4,336.85
I. Contractor's Profit (CP) 8% of G 3,854.98
J. Value Added Tax (VAT) 12% of (G + H + I) 6,765.49
K. Total Unit Cost (G + H + I + J) 63,144.57

DETAILED UNIT PRICE ANALYSIS (DUPA)


Item No./Description : 302(1) Bituminous Tack Coat (RC Cut-back Asphalt)
Unit of Measurement : m.t.
Output per hour : 0.30

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Laborer 3 1 61.44 184.32

Sub - Total for A 293.51


Name and Capacity No of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Asphalt Distributor, 10 ft. wide (5 tons) 1 1 936.00 936.00


b. Power Broom (20 m. wide) 1 1 130.54 130.54

Sub - Total for B 1,066.54


C. Total (A + B) 1,360.05
D. Output per hour = 0.300 m.t.
E. Direct Unit Cost (C ÷ D) 4,533.50
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. RC 70 Cut-back Asphalt m.t. 1.05 41,575.00 43,653.75


(w/ 5% wastage)

Sub - Total for F 43,653.75


G. Direct Unit Cost (E + F) 48,187.25
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 4,336.85
I. Contractor's Profit (CP) 8% of G 3,854.98
J. Value Added Tax (VAT) 12% of (G + H + I) 6,765.49
K. Total Unit Cost (G + H + I + J) 63,144.57

DETAILED UNIT PRICE ANALYSIS (DUPA)


Item No./Description : 302(2) Bituminous Tack Coat (Emulsified Asphalt)
Unit of Measurement : m.t.
Output per hour : 0.30

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Laborer 3 1 61.44 184.32

Sub - Total for A 293.51


Name and Capacity No of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Asphalt Distributor, 10 ft. wide (5 tons) 1 1 936.00 936.00


b. Power Broom (20 m. wide) 1 1 130.54 130.54

Sub - Total for B 1,066.54


C. Total (A + B) 1,360.05
D. Output per hour = 0.300 m.t.
E. Direct Unit Cost (C ÷ D) 4,533.50
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Emulsified Asphalt SS-1 m.t. 1.05 44,000.00 46,200.00


(w/ 5% wastage)

Sub - Total for F 46,200.00


G. Direct Unit Cost (E + F) 50,733.50
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 4,566.01
I. Contractor's Profit (CP) 8% of G 4,058.68
J. Value Added Tax (VAT) 12% of (G + H + I) 7,122.98
K. Total Unit Cost (G + H + I + J) 66,481.18

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 303(1) Bituminous Seal Coat (Cover Aggregate)


Unit of Measurement : m.t.
Output per hour : 16.00 (10 m³)

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Laborer 20 1 61.44 1,228.80

Sub - Total for A 1,337.99


Name and Capacity No of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Tandem Steel Roller (10.1 m.t.), CC421 1 1 1,652.00 1,652.00


b. Water Truck (1000 gal.) 1 0.25 1,065.00 266.25

Sub - Total for B 1,918.25


C. Total (A + B) 3,256.24
D. Output per hour = 16.0000 m.t.
E. Direct Unit Cost (C ÷ D) 203.52
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Cover Aggregate m.t. 1.15 406.25 467.19


(w/ 15% Shrinkage Factor)

Note: 1.60 m.t./cu.m.


using unit wt. of 1,600 kg./m³

Sub - Total for F 467.19


G. Direct Unit Cost (E + F) 670.70
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 60.36
I. Contractor's Profit (CP) 8% of G 53.66
J. Value Added Tax (VAT) 12% of (G + H + I) 94.17
K. Total Unit Cost (G + H + I + J) 878.89

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 303(2) Bituminous Seal Coat (MC Cut-back Asphalt)


Unit of Measurement : m.t.
Output per hour : 0.30

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Laborer 3 1 61.44 184.32

Sub - Total for A 293.51


Name and Capacity No of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Asphalt Distributor, 10 ft. wide (5 tons) 1 1 936.00 936.00


b. Power Broom (20 m. wide) 1 1 130.54 130.54

Sub - Total for B 1,066.54


C. Total (A + B) 1,360.05
D. Output per hour = 0.300 m.t.
E. Direct Unit Cost (C ÷ D) 4,533.50
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. MC Cut-back Asphalt m.t. 1.05 40,300.00 42,315.00


(w/ 5% Wastage)

Sub - Total for F 42,315.00


G. Direct Unit Cost (E + F) 46,848.50
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 4,216.37
I. Contractor's Profit (CP) 8% of G 3,747.88
J. Value Added Tax (VAT) 12% of (G + H + I) 6,577.53
K. Total Unit Cost (G + H + I + J) 61,390.27

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 303(3) Bituminous Seal Coat (RC Cut-back Asphalt)


Unit of Measurement : m.t.
Output per hour : 0.30
Designation No. of Person No. of Hours Hourly Rate Amount
A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Laborer 3 1 61.44 184.32

Sub - Total for A 293.51


Name and Capacity No of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Asphalt Distributor, 10 ft. wide (5 tons) 1 1 936.00 936.00


b. Power Broom (20 m. wide) 1 1 130.54 130.54

Sub - Total for B 1,066.54


C. Total (A + B) 1,360.05
D. Output per hour = 0.300 m.t.
E. Direct Unit Cost (C ÷ D) 4,533.50
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. RC 70 Cut-back Asphalt m.t. 1.05 41,575.00 43,653.75


(w/ 5% Wastage)

Sub - Total for F 43,653.75


G. Direct Unit Cost (E + F) 48,187.25
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 4,336.85
I. Contractor's Profit (CP) 8% of G 3,854.98
J. Value Added Tax (VAT) 12% of (G + H + I) 6,765.49
K. Total Unit Cost (G + H + I + J) 63,144.57

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 303(4) Bituminous Seal Coat (Asphalt Cement Penetration Grade 120-150)
Unit of Measurement : m.t.
Output per hour : 0.30

Designation No. of Person No. of Hours Hourly Rate Amount


Designation No. of Person No. of Hours Hourly Rate Amount
A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Laborer 3 1 61.44 184.32

Sub - Total for A 293.51


Name and Capacity No of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Asphalt Distributor, 10 ft. wide (5 tons) 1 1 936.00 936.00


b. Power Broom (20 m. wide) 1 1 130.54 130.54

Sub - Total for B 1,066.54


C. Total (A + B) 1,360.05
D. Output per hour = 0.300 m.t.
E. Direct Unit Cost (C ÷ D) 4,533.50
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Asphalt Cement Penetration Grade 120-150 m.t. 1.05 50,775.00 53,313.75


(w/ 5% Wastage)

Sub - Total for F 53,313.75


G. Direct Unit Cost (E + F) 57,847.25
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 5,206.25
I. Contractor's Profit (CP) 8% of G 4,627.78
J. Value Added Tax (VAT) 12% of (G + H + I) 8,121.75
K. Total Unit Cost (G + H + I + J) 75,803.04

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 304(1) Bituminous Surface Treatment (Aggregate Grading)


Unit of Measurement : m.t.
Output per hour : 16.00 (10 m³)

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor
a. Construction Foreman 1 1 109.19 109.19
b. Laborer 20 1 61.44 1,228.80

Sub - Total for A 1,337.99


Name and Capacity No of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Vibratory Roller (10 m.t.), SP56 1 1 1,507.00 1,507.00


b. Water Truck (1000 gal.) 1 0.25 1,065.00 266.25

Sub - Total for B 1,773.25


C. Total (A + B) 3,111.24
D. Output per hour = 16.0000 m.t.
E. Direct Unit Cost (C ÷ D) 194.45
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Aggregates m.t. 1.15 406.25 467.19


(w/ 15% Shrinkage Factor)

Sub - Total for F 467.19


G. Direct Unit Cost (E + F) 661.64
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 59.55
I. Contractor's Profit (CP) 8% of G 52.93
J. Value Added Tax (VAT) 12% of (G + H + I) 92.89
K. Total Unit Cost (G + H + I + J) 867.01

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 304(2) Bituminous Surface Treatment (Asphalt Cement Penetration Grade 120-150)
Unit of Measurement : m.t.
Output per hour : 0.30

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor
a. Construction Foreman 1 1 109.19 109.19
b. Laborer 3 1 61.44 184.32

Sub - Total for A 293.51


Name and Capacity No of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Asphalt Distributor, 10 ft. wide (5 tons) 1 1 936.00 936.00


b. Power Broom (20 m. wide) 1 1 130.54 130.54

Sub - Total for B 1,066.54


C. Total (A + B) 1,360.05
D. Output per hour = 0.300 m.t.
E. Direct Unit Cost (C ÷ D) 4,533.50
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Asphalt Cement Penetration Grade 120-150 m.t. 1.05 50,775.00 53,313.75


(w/ 5% Wastage)

Sub - Total for F 53,313.75


G. Direct Unit Cost (E + F) 57,847.25
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 5,206.25
I. Contractor's Profit (CP) 8% of G 4,627.78
J. Value Added Tax (VAT) 12% of (G + H + I) 8,121.75
K. Total Unit Cost (G + H + I + J) 75,803.04

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 304(3) Bituminous Surface Treatment (MC Cut-back Asphalt)


Unit of Measurement : m.t.
Output per hour : 0.30

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Laborer 3 1 61.44 184.32

Sub - Total for A 293.51


Name and Capacity No of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Asphalt Distributor, 10 ft. wide (5 tons) 1 1 936.00 936.00


b. Power Broom (20 m. wide) 1 1 130.54 130.54

Sub - Total for B 1,066.54


C. Total (A + B) 1,360.05
D. Output per hour = 0.300 m.t.
E. Direct Unit Cost (C ÷ D) 4,533.50
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. MC Cut-back Asphalt m.t. 1.05 40,300.00 42,315.00


(w/ 5% Wastage)

Sub - Total for F 42,315.00


G. Direct Unit Cost (E + F) 46,848.50
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 4,216.37
I. Contractor's Profit (CP) 8% of G 3,747.88
J. Value Added Tax (VAT) 12% of (G + H + I) 6,577.53
K. Total Unit Cost (G + H + I + J) 61,390.27

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 304(4) Bituminous Surface Treatment (RC Cut-back Asphalt)


Unit of Measurement : m.t.
Output per hour : 0.30

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Laborer 3 1 61.44 184.32
Sub - Total for A 293.51
Name and Capacity No of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Asphalt Distributor, 10 ft. wide (5 tons) 1 1 936.00 936.00


b. Power Broom (20 m. wide) 1 1 130.54 130.54

Sub - Total for B 1,066.54


C. Total (A + B) 1,360.05
D. Output per hour = 0.300 m.t.
E. Direct Unit Cost (C ÷ D) 4,533.50
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. RC 70 Cut-back Asphalt m.t. 1.05 41,575.00 43,653.75


(w/ 5% Wastage)

Sub - Total for F 43,653.75


G. Direct Unit Cost (E + F) 48,187.25
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 4,336.85
I. Contractor's Profit (CP) 8% of G 3,854.98
J. Value Added Tax (VAT) 12% of (G + H + I) 6,765.49
K. Total Unit Cost (G + H + I + J) 63,144.57

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 304(5) Bituminous Surface Treatment (Emulsified Asphalt)


Unit of Measurement : m.t.
Output per hour : 0.30

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Laborer 3 1 61.44 184.32
Sub - Total for A 293.51
Name and Capacity No of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Asphalt Distributor, 10 ft. wide (5 tons) 1 1 936.00 936.00


b. Power Broom (20 m. wide) 1 1 130.54 130.54

Sub - Total for B 1,066.54


C. Total (A + B) 1,360.05
D. Output per hour = 0.300 m.t.
E. Direct Unit Cost (C ÷ D) 4,533.50
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Emulsified Asphalt SS-1 m.t. 1.05 44,000.00 46,200.00


(w/ 5% wastage)

Sub - Total for F 46,200.00


G. Direct Unit Cost (E + F) 50,733.50
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 4,566.01
I. Contractor's Profit (CP) 8% of G 4,058.68
J. Value Added Tax (VAT) 12% of (G + H + I) 7,122.98
K. Total Unit Cost (G + H + I + J) 66,481.18

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 307 Bituminous Plant Mix Surface Course-General (50 mm. thick)
Unit of Measurement : sq.m.
Output per hour : 171.30

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Skilled Laborer 6 1 79.70 478.20
c. Laborer 12 1 61.44 737.28
Sub - Total for A 1,324.67
Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Asphalt Paver (80 Hp), NF220BIIVDM 1 1 1,833.00 1,833.00


b. Pneumatic Tire Roller (10 m.t.) 1 1 553.00 553.00
c. Tandem Steel Roller (10.1 m.t.), CC421 1 1 1,652.00 1,652.00
d. Dump Truck (10 cu.m.) 2 1 1,352.00 2,704.00
e. Asphalt Batch Plant ( 60-80 TPH) 1 1 1,214.73 1,214.73
f. Water Truck (1000 gal.) 1 1 1,065.00 1,065.00
g. Payloader (1.50 cu.m.), LX80-2C 1 1 1,733.00 1,733.00
Minor Tools (10% of Labor) 132.47

Sub - Total for B 10,887.20


C. Total (A + B) 12,211.87
D. Output per hour = 171.300 sq.m.
E. Direct Unit Cost (C ÷ D) 71.29
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. Bituminous Material (8%) m.t 0.00981 44,000.00 431.64


b. Aggregates (93%) cu.m. 0.0488 650.00 31.72
c. Mineral Filler (7%) bag 0.13 240.56 31.27
(w/ 5% wastage)

0.065(2.335)(0.05)(1.05) = 0.00797

Sub - Total for F 494.63


G. Direct Unit Cost (E + F) 565.92
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 50.93
I. Contractor's Profit (CP) 8% of G 45.27
J. Value Added Tax (VAT) 12% of (G + H + I) 79.46
K. Total Unit Cost (G + H + I + J) 741.58

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 310(a1) Bituminous Concrete Surface Course - 30mm thick, Premix Hot Asphalt
Unit of Measurement : sq.m.
Output per hour : 285.51

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Skilled Laborer 4 1 79.70 318.80
c. Laborer 8 1 61.44 491.52
Sub - Total for A 919.51
Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Asphalt Paver (80 Hp) 1 1 1,833.00 1,833.00


b. Pneumatic Tire Roller (10 m.t.) 1 1 553.00 553.00
c. Tandem Steel Roller (10.1 m.t.), CC421 1 1 1,652.00 1,652.00
d. Water Truck (1000 gal.) 1 1 1,065.00 1,065.00
Minor Tools (10% of Labor) 91.95

Sub - Total for B 5,194.95


C. Total (A + B) 6,114.46
D. Output per hour = 285.51 sq.m.
E. Direct Unit Cost (C ÷ D) 21.42
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. Bituminous Concrete Surface Course m.t. 0.074 4,500.00 333.00


thickness = 30 mm. (w/ 5% wastage)

0.03(2.335)(1.05) = 0.074

Sub - Total for F 333.00


G. Direct Unit Cost (E + F) 354.42
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 31.90
I. Contractor's Profit (CP) 8% of G 28.35
J. Value Added Tax (VAT) 12% of (G + H + I) 49.76
K. Total Unit Cost (G + H + I + J) 464.43

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 310(a2) Bituminous Concrete Surface Course - 40mm thick, Premix Hot Asphalt
Unit of Measurement : sq.m.
Output per hour : 214.13

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Skilled Laborer 4 1 79.70 318.80
c. Laborer 8 1 61.44 491.52
Sub - Total for A 919.51
Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Asphalt Paver (80 Hp) 1 1 1,833.00 1,833.00


b. Pneumatic Tire Roller (10 m.t.) 1 1 553.00 553.00
c. Tandem Steel Roller (10.1 m.t.), CC421 1 1 1,652.00 1,652.00
d. Water Truck (1000 gal.) 1 1 1,065.00 1,065.00
Minor Tools (10% of Labor) 91.95

Sub - Total for B 5,194.95


C. Total (A + B) 6,114.46
D. Output per hour = 214.13 sq.m.
E. Direct Unit Cost (C ÷ D) 28.55
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. Bituminous Concrete Surface Course m.t. 0.098 4,500.00 441.00


thickness = 40 mm. (w/ 5% wastage)

0.04(2.335)(1.05) = 0.098

Sub - Total for F 441.00


G. Direct Unit Cost (E + F) 469.55
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 42.26
I. Contractor's Profit (CP) 8% of G 37.56
J. Value Added Tax (VAT) 12% of (G + H + I) 65.93
K. Total Unit Cost (G + H + I + J) 615.30

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 310(a3) Bituminous Concrete Surface Course - 50mm thick, Premix Hot Asphalt
Unit of Measurement : sq.m.
Output per hour : 171.30

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Skilled Laborer 4 1 79.70 318.80
c. Laborer 8 1 61.44 491.52
Sub - Total for A 919.51
Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Asphalt Paver (80 Hp) 1 1 1,833.00 1,833.00


b. Pneumatic Tire Roller (10 m.t.) 1 1 553.00 553.00
c. Tandem Steel Roller (10.1 m.t.), CC421 1 1 1,652.00 1,652.00
d. Water Truck (1000 gal.) 1 1 1,065.00 1,065.00
Minor Tools (10% of Labor) 91.95

Sub - Total for B 5,194.95


C. Total (A + B) 6,114.46
D. Output per hour = 171.300 sq.m.
E. Direct Unit Cost (C ÷ D) 35.69
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. Bituminous Concrete Surface Course m.t. 0.123 4,500.00 553.50


thickness = 50 mm. (w/ 5% wastage)

0.05(2.335)(1.05) = 0.123

Sub - Total for F 553.50


G. Direct Unit Cost (E + F) 589.19
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 53.03
I. Contractor's Profit (CP) 8% of G 47.14
J. Value Added Tax (VAT) 12% of (G + H + I) 82.72
K. Total Unit Cost (G + H + I + J) 772.08

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 310(b1) Bituminous Concrete Surface Course (30 mm. thick)-w/Asphalt Batching Plant
Unit of Measurement : sq.m.
Output per hour : 285.51

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Skilled Laborer 6 1 79.70 478.20
c. Laborer 12 1 61.44 737.28

Sub - Total for A 1,324.67


Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Asphalt Paver (80 Hp), NF220BIIVDM 1 1 1,833.00 1,833.00


b. Pneumatic Tire Roller (10 m.t.) 1 1 553.00 553.00
c. Tandem Steel Roller (10.1 m.t.), CC421 1 1 1,652.00 1,652.00
d. Dump Truck (10 cu.m.) 2 1 1,352.00 2,704.00
e. Asphalt Batch Plant ( 60-80 TPH) 1 1 1,214.73 1,214.73
f. Water Truck (1000 gal.) 1 1 1,065.00 1,065.00
g. Payloader (1.50 cu.m.), LX80-2C 1 1 1,733.00 1,733.00
Minor Tools (10% of Labor) 132.47

Sub - Total for B 10,887.20


C. Total (A + B) 12,211.87
D. Output per hour = 285.51 sq.m.
E. Direct Unit Cost (C ÷ D) 42.77
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. Asphalt Cement (8%) m.t 0.00588 50,775.00 298.56


b. Aggregates (93%) cu.m. 0.0488 650.00 31.72
c. Mineral Filler (7%) bag 0.13 240.56 31.27
(w/ 5% wastage)

0.08(2.335)(0.03)(1.05) = 0.00588

Sub - Total for F 361.55


G. Direct Unit Cost (E + F) 404.32
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 36.39
I. Contractor's Profit (CP) 8% of G 32.35
J. Value Added Tax (VAT) 12% of (G + H + I) 56.77
K. Total Unit Cost (G + H + I + J) 529.82

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 310(b2) Bituminous Concrete Surface Course (40 mm. thick)-w/Asphalt Batching Plant
Unit of Measurement : sq.m.
Output per hour : 214.13

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Skilled Laborer 6 1 79.70 478.20
c. Laborer 12 1 61.44 737.28

Sub - Total for A 1,324.67


Name and Capacity No of Units No. of Hours Hourly Rate Amount
Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Asphalt Paver (80 Hp), NF220BIIVDM 1 1 1,833.00 1,833.00


b. Pneumatic Tire Roller (10 m.t.) 1 1 553.00 553.00
c. Tandem Steel Roller (10.1 m.t.), CC421 1 1 1,652.00 1,652.00
d. Dump Truck (10 cu.m.) 2 1 1,352.00 2,704.00
e. Asphalt Batch Plant ( 60-80 TPH) 1 1 1,214.73 1,214.73
f. Water Truck (1000 gal.) 1 1 1,065.00 1,065.00
g. Payloader (1.50 cu.m.), LX80-2C 1 1 1,733.00 1,733.00
Minor Tools (10% of Labor) 132.47

Sub - Total for B 10,887.20


C. Total (A + B) 12,211.87
D. Output per hour = 214.13 sq.m.
E. Direct Unit Cost (C ÷ D) 57.03
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. Asphalt Cement (8%) m.t 0.00785 50,775.00 398.58


b. Aggregates (93%) cu.m. 0.0488 650.00 31.72
c. Mineral Filler (7%) bag 0.13 240.56 31.27
(w/ 5% wastage)

0.08(2.335)(0.04)(1.05) = 0.00785

Sub - Total for F 461.58


G. Direct Unit Cost (E + F) 518.61
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 46.67
I. Contractor's Profit (CP) 8% of G 41.49
J. Value Added Tax (VAT) 12% of (G + H + I) 72.81
K. Total Unit Cost (G + H + I + J) 679.58

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 310(b3) Bituminous Concrete Surface Course (50 mm. thick)-w/Asphalt Batching Plant
Unit of Measurement : sq.m.
Output per hour : 171.30

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Skilled Laborer 6 1 79.70 478.20
c. Laborer 12 1 61.44 737.28

Sub - Total for A 1,324.67


Name and Capacity No of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Asphalt Paver (80 Hp), NF220BIIVDM 1 1 1,833.00 1,833.00


b. Pneumatic Tire Roller (10 m.t.) 1 1 553.00 553.00
c. Tandem Steel Roller (10.1 m.t.), CC421 1 1 1,652.00 1,652.00
d. Dump Truck (10 cu.m.) 2 1 1,352.00 2,704.00
e. Asphalt Batch Plant ( 60-80 TPH) 1 1 1,214.73 1,214.73
f. Water Truck (1000 gal.) 1 1 1,065.00 1,065.00
g. Payloader (1.50 cu.m.), LX80-2C 1 1 1,733.00 1,733.00
Minor Tools (10% of Labor) 132.47

Sub - Total for B 10,887.20


C. Total (A + B) 12,211.87
D. Output per hour = 171.300 sq.m.
E. Direct Unit Cost (C ÷ D) 71.29
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. Asphalt Cement (8%) m.t 0.00981 50,775.00 498.10


b. Aggregates (93%) cu.m. 0.0488 650.00 31.72
c. Mineral Filler (7%) bag 0.13 240.56 31.27
(w/ 5% wastage)

0.065(2.335)(0.05)(1.05) = 0.00797

Sub - Total for F 561.10


G. Direct Unit Cost (E + F) 632.38
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 56.91
I. Contractor's Profit (CP) 8% of G 50.59
J. Value Added Tax (VAT) 12% of (G + H + I) 88.79
K. Total Unit Cost (G + H + I + J) 828.68

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 311(1)a PCC Pavement (Plain) - Conventional Method, 150 mm. thk.
Unit of Measurement : sq.m.
Output per hour : 107.33

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Skilled Laborer 4 1 79.70 318.80
c. Laborer 12 1 61.44 737.28

Sub - Total for A 1,165.27


Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment
a. Transit Mixer (5 cu.m.) 4 1 1,279.00 5,116.00
b. Concrete Vibrator 2 1 148.88 297.76
c. Batching Plant (30 cu.m.) 1 1 1,208.03 1,208.03
d. Payloader (1.50 cu.m.), LX80-2C 1 1 1,733.00 1,733.00
e. Concrete Screeder (5.5 Hp) 1 1 545.00 545.00
f. Water Truck (1000 gal.) 1 1 1,065.00 1,065.00
g. Concrete Saw, Blade Ø 14" (7.5 Hp) 1 1 167.38 167.38
h. Bar Cutter, Single Phase 1 0.10 219.75 21.98
Minor Tools (5% of Labor) 58.26

Sub - Total for B 10,212.41


C. Total (A + B) 11,377.68
D. Output per hour = 107.33 sq.m.
E. Direct Unit Cost (C ÷ D) 106.01
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. Reinforcing Steel Bar kg. 0.33 40.00 13.20


b. Curing Compound lit. 0.29 28.00 8.12
c. Asphalt Sealant lit. 0.12 44.00 5.28
d. Steel Forms (Rental) l.m. 0.46 50.00 23.00
e. Sand cu.m. 0.0825 850.00 70.13
f. Gravel cu.m. 0.15 650.00 97.50
g. Cement bag 1.43 220.00 314.60
h. Concrete Saw (diamond blade 14") pc. 0.00015 8,000.00 1.20
i. Pipe Sleeve, 1" dia. l.m. 0.0078 34.33 0.27
j. Grease/Tar lit. 0.0014 300.00 0.42

Sub - Total for F 533.71


G. Direct Unit Cost (E + F) 639.72
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 57.57
I. Contractor's Profit (CP) 8% of G 51.18
J. Value Added Tax (VAT) 12% of (G + H + I) 89.82
K. Total Unit Cost (G + H + I + J) 838.29

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 311(1)a PCC Pavement (Plain) - Conventional Method, 200 mm. thk.
Unit of Measurement : sq.m.
Output per hour : 80.50

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Skilled Laborer 4 1 79.70 318.80
c. Laborer 12 1 61.44 737.28

Sub - Total for A 1,165.27


Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment
a. Transit Mixer (5 cu.m.) 4 1 1,279.00 5,116.00
b. Concrete Vibrator 2 1 148.88 297.76
c. Batching Plant (30 cu.m.) 1 1 1,208.03 1,208.03
d. Payloader (1.50 cu.m.), LX80-2C 1 1 1,733.00 1,733.00
e. Concrete Screeder (5.5 Hp) 1 1 545.00 545.00
f. Water Truck (1000 gal.) 1 1 1,065.00 1,065.00
g. Concrete Saw, Blade Ø 14" (7.5 Hp) 1 1 167.38 167.38
h. Bar Cutter, Single Phase 1 0.10 219.75 21.98
Minor Tools (5% of Labor) 58.26

Sub - Total for B 10,212.41


C. Total (A + B) 11,377.68
D. Output per hour = 80.500 sq.m.
E. Direct Unit Cost (C ÷ D) 141.34
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. Reinforcing Steel Bar kg. 0.39 40.00 15.60


b. Curing Compound lit. 0.29 28.00 8.12
c. Asphalt Sealant lit. 0.12 44.00 5.28
d. Steel Forms (Rental) l.m. 0.46 50.00 23.00
e. Sand cu.m. 0.110 850.00 93.50
f. Gravel cu.m. 0.20 650.00 130.00
g. Cement bag 1.90 220.00 418.00
h. Concrete Saw (diamond blade 14") pc. 0.00015 8,000.00 1.20
i. Pipe Sleeve, 1 1/2" dia. l.m. 0.0086 67.67 0.58
j. Grease/Tar lit. 0.0055 300.00 1.65

Sub - Total for F 696.93


G. Direct Unit Cost (E + F) 838.27
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 75.44
I. Contractor's Profit (CP) 8% of G 67.06
J. Value Added Tax (VAT) 12% of (G + H + I) 117.69
K. Total Unit Cost (G + H + I + J) 1,098.47

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 311(1)a PCC Pavement (Plain) - Conventional Method, 230 mm. thk.
Unit of Measurement : sq.m.
Output per hour : 70.00

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Skilled Laborer 4 1 79.70 318.80
c. Laborer 12 1 61.44 737.28

Sub - Total for A 1,165.27


Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Transit Mixer (5 cu.m.) 4 1 1,279.00 5,116.00


b. Concrete Vibrator 2 1 148.88 297.76
c. Batching Plant (30 cu.m.) 1 1 1,208.03 1,208.03
d. Payloader (1.50 cu.m.), LX80-2C 1 1 1,733.00 1,733.00
e. Concrete Screeder (5.5 Hp) 1 1 545.00 545.00
f. Water Truck (1000 gal.) 1 1 1,065.00 1,065.00
g. Concrete Saw, Blade Ø 14" (7.5 Hp) 1 1 167.38 167.38
h. Bar Cutter, Single Phase 1 0.10 219.75 21.98
Minor Tools (5% of Labor) 58.26

Sub - Total for B 10,212.41


C. Total (A + B) 11,377.68
D. Output per hour = 70.0000 sq.m.
E. Direct Unit Cost (C ÷ D) 162.54
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. Reinforcing Steel Bar kg. 0.43 40.00 17.20


b. Curing Compound lit. 0.29 28.00 8.12
c. Asphalt Sealant lit. 0.12 44.00 5.28
d. Steel Forms (Rental) l.m. 0.46 50.00 23.00
e. Sand cu.m. 0.1265 850.00 107.53
f. Gravel cu.m. 0.23 650.00 149.50
g. Cement bag 2.19 220.00 481.80
h. Concrete Saw (diamond blade 14") pc. 0.00015 8,000.00 1.20
i. Pipe Sleeve, 2" dia. l.m. 0.0071 97.00 0.69
j. Grease/Tar lit. 0.0022 300.00 0.66

Sub - Total for F 794.97


G. Direct Unit Cost (E + F) 957.51
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 86.18
I. Contractor's Profit (CP) 8% of G 76.60
J. Value Added Tax (VAT) 12% of (G + H + I) 134.43
K. Total Unit Cost (G + H + I + J) 1,254.72

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 311(1)a PCC Pavement (Plain) - Conventional Method, 250 mm. thk.
Unit of Measurement : sq.m.
Output per hour : 64.40

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Skilled Laborer 4 1 79.70 318.80
c. Laborer 12 1 61.44 737.28

Sub - Total for A 1,165.27


Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Transit Mixer (5 cu.m.) 4 1 1,279.00 5,116.00


b. Concrete Vibrator 2 1 148.88 297.76
c. Batching Plant (30 cu.m.) 1 1 1,208.03 1,208.03
d. Payloader (1.50 cu.m.), LX80-2C 1 1 1,733.00 1,733.00
e. Concrete Screeder (5.5 Hp) 1 1 545.00 545.00
f. Water Truck (1000 gal.) 1 1 1,065.00 1,065.00
g. Concrete Saw, Blade Ø 14" (7.5 Hp) 1 1 167.38 167.38
h. Bar Cutter, Single Phase 1 0.10 219.75 21.98
Minor Tools (5% of Labor) 58.26

Sub - Total for B 10,212.41


C. Total (A + B) 11,377.68
D. Output per hour = 64.400 sq.m.
E. Direct Unit Cost (C ÷ D) 176.67
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. Reinforcing Steel Bar kg. 0.45 40.00 18.00


b. Curing Compound lit. 0.29 28.00 8.12
c. Asphalt Sealant lit. 0.15 44.00 6.60
d. Steel Forms (Rental) l.m. 0.46 50.00 23.00
e. Sand cu.m. 0.1375 850.00 116.88
f. Gravel cu.m. 0.25 650.00 162.50
g. Cement bag 2.38 220.00 523.60
h. Concrete Saw (diamond blade 14") pc. 0.00015 8,000.00 1.20
i. Pipe Sleeve, 2" dia. l.m. 0.0078 97.00 0.76
j. Grease/Tar lit. 0.0025 300.00 0.75

Sub - Total for F 861.40


G. Direct Unit Cost (E + F) 1,038.07
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 93.43
I. Contractor's Profit (CP) 8% of G 83.05
J. Value Added Tax (VAT) 12% of (G + H + I) 145.75
K. Total Unit Cost (G + H + I + J) 1,360.29

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 311(1)a PCC Pavement (Plain) - Conventional Method, 280 mm. thk.
Unit of Measurement : sq.m.
Output per hour : 57.50

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Skilled Laborer 4 1 79.70 318.80
c. Laborer 12 1 61.44 737.28

Sub - Total for A 1,165.27


Name and Capacity No of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Transit Mixer (5 cu.m.) 4 1 1,279.00 5,116.00


b. Concrete Vibrator 2 1 148.88 297.76
c. Batching Plant (30 cu.m.) 1 1 1,208.03 1,208.03
d. Payloader (1.50 cu.m.), LX80-2C 1 1 1,733.00 1,733.00
e. Concrete Screeder (5.5 Hp) 1 1 545.00 545.00
f. Water Truck (1000 gal.) 1 1 1,065.00 1,065.00
g. Concrete Saw, Blade Ø 14" (7.5 Hp) 1 1 167.38 167.38
h. Bar Cutter, Single Phase 1 0.10 219.75 21.98
Minor Tools (5% of Labor) 58.26

Sub - Total for B 10,212.41


C. Total (A + B) 11,377.68
D. Output per hour = 57.500 sq.m.
E. Direct Unit Cost (C ÷ D) 197.87
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. Reinforcing Steel Bar kg. 0.50 40.00 20.00


b. Curing Compound lit. 0.29 28.00 8.12
c. Asphalt Sealant lit. 0.17 44.00 7.48
d. Steel Forms (Rental) l.m. 0.46 50.00 23.00
e. Sand cu.m. 0.154 850.00 130.90
f. Gravel cu.m. 0.28 650.00 182.00
g. Cement bag 2.66 220.00 585.20
h. Concrete Saw (diamond blade 14") pc. 0.00015 8,000.00 1.20
i. Pipe Sleeve, 2" dia. l.m. 0.0078 97.00 0.76
j. Grease/Tar lit. 0.0077 300.00 2.31

Sub - Total for F 960.97


G. Direct Unit Cost (E + F) 1,158.84
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 104.30
I. Contractor's Profit (CP) 8% of G 92.71
J. Value Added Tax (VAT) 12% of (G + H + I) 162.70
K. Total Unit Cost (G + H + I + J) 1,518.54

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 311(1)a PCC Pavement (Plain) - Conventional Method, 300 mm. thk.
Unit of Measurement : sq.m.
Output per hour : 53.67

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Skilled Laborer 4 1 79.70 318.80
c. Laborer 12 1 61.44 737.28

Sub - Total for A 1,165.27


Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Transit Mixer (5 cu.m.) 4 1 1,279.00 5,116.00


b. Concrete Vibrator 2 1 148.88 297.76
c. Batching Plant (30 cu.m.) 1 1 1,208.03 1,208.03
d. Payloader (1.50 cu.m.), LX80-2C 1 1 1,733.00 1,733.00
e. Concrete Screeder (5.5 Hp) 1 1 545.00 545.00
f. Water Truck (1000 gal.) 1 1 1,065.00 1,065.00
g. Concrete Saw, Blade Ø 14" (7.5 Hp) 1 1 167.38 167.38
h. Bar Cutter, Single Phase 1 0.10 219.75 21.98
Minor Tools (5% of Labor) 58.26

Sub - Total for B 10,212.41


C. Total (A + B) 11,377.68
D. Output per hour = 53.67 sq.m.
E. Direct Unit Cost (C ÷ D) 211.99
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. Reinforcing Steel Bar kg. 0.55 40.00 22.00


b. Curing Compound lit. 0.29 28.00 8.12
c. Asphalt Sealant lit. 0.18 44.00 7.92
d. Steel Forms (Rental) l.m. 0.46 50.00 23.00
e. Sand cu.m. 0.165 850.00 140.25
f. Gravel cu.m. 0.30 650.00 195.00
g. Cement bag 2.85 220.00 627.00
h. Concrete Saw (diamond blade 14") pc. 0.00015 8,000.00 1.20
i. Pipe Sleeve, 2" dia. l.m. 0.0094 97.00 0.91
j. Grease/Tar lit. 0.0093 300.00 2.79

Sub - Total for F 1,028.19


G. Direct Unit Cost (E + F) 1,240.19
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 111.62
I. Contractor's Profit (CP) 8% of G 99.21
J. Value Added Tax (VAT) 12% of (G + H + I) 174.12
K. Total Unit Cost (G + H + I + J) 1,625.14

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 311(1)b PCC Pavement (Plain) - Using Concrete Paver, 230 mm. thk.
Unit of Measurement : sq.m.
Output per hour : 90.00

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Skilled Laborer 4 1 79.70 318.80
c. Laborer 10 1 61.44 614.40

Sub - Total for A 1,042.39


Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Batching Plant (30 cu.m.) 1 1 1,208.03 1,208.03


b. Concrete Paver, GP-2000 Slipform 1 1 6,765.00 6,765.00
c. Transit Mixer (5 cu.m.) 4 1 1,279.00 5,116.00
d. Payloader (1.50 cu.m.), LX80-2C 1 1 1,733.00 1,733.00
e. Water Truck (1000 gal.) 1 1 1,065.00 1,065.00
f. Concrete Saw, Blade Ø 14" (7.5 Hp) 1 1 167.38 167.38
g. Concrete Vibrator 1 0.10 148.88 14.89
h. Bar Cutter, Single Phase 1 0.10 219.75 21.98

Sub - Total for B 16,091.27


C. Total (A + B) 17,133.66
D. Output per hour = 90.0000 sq.m.
E. Direct Unit Cost (C ÷ D) 190.37
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. Reinforcing Steel Bar kg. 0.43 40.00 17.20


b. Curing Compound lit. 0.29 28.00 8.12
c. Asphalt Sealant lit. 0.12 44.00 5.28
d. Sand cu.m. 0.1265 850.00 107.53
e. Gravel cu.m. 0.23 650.00 149.50
f. Cement bag 2.19 220.00 481.80
g. Concrete Saw (diamond blade 14") pc. 0.00015 8,000.00 1.20
h. Pipe Sleeve, 2" dia. l.m. 0.0071 97.00 0.69
i. Grease/Tar lit. 0.0022 300.00 0.66

Sub - Total for F 771.97


G. Direct Unit Cost (E + F) 962.35
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 86.61
I. Contractor's Profit (CP) 8% of G 76.99
J. Value Added Tax (VAT) 12% of (G + H + I) 135.11
K. Total Unit Cost (G + H + I + J) 1,261.06

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 311(1)b PCC Pavement (Plain) - Using Concrete Paver, 250 mm. thk.
Unit of Measurement : sq.m.
Output per hour : 82.80

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Skilled Laborer 4 1 79.70 318.80
c. Laborer 10 1 61.44 614.40

Sub - Total for A 1,042.39


Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Batching Plant (30 cu.m.) 1 1 1,208.03 1,208.03


b. Concrete Paver, GP-2000 Slipform 1 1 6,765.00 6,765.00
c. Transit Mixer (5 cu.m.) 4 1 1,279.00 5,116.00
d. Payloader (1.50 cu.m.), LX80-2C 1 1 1,733.00 1,733.00
e. Water Truck (1000 gal.) 1 1 1,065.00 1,065.00
f. Concrete Saw, Blade Ø 14" (7.5 Hp) 1 1 167.38 167.38
g. Concrete Vibrator 1 0.10 148.88 14.89
h. Bar Cutter, Single Phase 1 0.10 219.75 21.98

Sub - Total for B 16,091.27


C. Total (A + B) 17,133.66
D. Output per hour = 82.800 sq.m.
E. Direct Unit Cost (C ÷ D) 206.93
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. Reinforcing Steel Bar kg. 0.45 40.00 18.00


b. Curing Compound lit. 0.29 28.00 8.12
c. Asphalt Sealant lit. 0.15 44.00 6.60
d. Sand cu.m. 0.1375 850.00 116.88
e. Gravel cu.m. 0.25 650.00 162.50
f. Cement bag 2.38 220.00 523.60
g. Concrete Saw (diamond blade 14") pc. 0.00015 8,000.00 1.20
h. Pipe Sleeve, 2" dia. l.m. 0.0078 97.00 0.76
i. Grease/Tar lit. 0.0025 300.00 0.75

Sub - Total for F 838.40


G. Direct Unit Cost (E + F) 1,045.33
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 94.08
I. Contractor's Profit (CP) 8% of G 83.63
J. Value Added Tax (VAT) 12% of (G + H + I) 146.76
K. Total Unit Cost (G + H + I + J) 1,369.80

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 311(1)b PCC Pavement (Plain) - Using Concrete Paver, 280 mm. thk.
Unit of Measurement : sq.m.
Output per hour : 73.93

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Skilled Laborer 4 1 79.70 318.80
c. Laborer 10 1 61.44 614.40

Sub - Total for A 1,042.39


Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Batching Plant (30 cu.m.) 1 1 1,208.03 1,208.03


b. Concrete Paver, GP-2000 Slipform 1 1 6,765.00 6,765.00
c. Transit Mixer (5 cu.m.) 4 1 1,279.00 5,116.00
d. Payloader (1.50 cu.m.), LX80-2C 1 1 1,733.00 1,733.00
e. Water Truck (1000 gal.) 1 1 1,065.00 1,065.00
f. Concrete Saw, Blade Ø 14" (7.5 Hp) 1 1 167.38 167.38
g. Concrete Vibrator 1 0.10 148.88 14.89
h. Bar Cutter, Single Phase 1 0.10 219.75 21.98

Sub - Total for B 16,091.27


C. Total (A + B) 17,133.66
D. Output per hour = 73.93 sq.m.
E. Direct Unit Cost (C ÷ D) 231.76
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. Reinforcing Steel Bar kg. 0.50 40.00 20.00


b. Curing Compound lit. 0.29 28.00 8.12
c. Asphalt Sealant lit. 0.17 44.00 7.48
d. Sand cu.m. 0.154 850.00 130.90
e. Gravel cu.m. 0.28 650.00 182.00
f. Cement bag 2.66 220.00 585.20
g. Concrete Saw (diamond blade 14") pc. 0.00015 8,000.00 1.20
h. Pipe Sleeve, 2" dia. l.m. 0.0078 97.00 0.76
i. Grease/Tar lit. 0.0077 300.00 2.31

Sub - Total for F 937.97


G. Direct Unit Cost (E + F) 1,169.72
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 105.27
I. Contractor's Profit (CP) 8% of G 93.58
J. Value Added Tax (VAT) 12% of (G + H + I) 164.23
K. Total Unit Cost (G + H + I + J) 1,532.80

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 311(1)b PCC Pavement (Plain) - Using Concrete Paver, 300 mm. thk.
Unit of Measurement : sq.m.
Output per hour : 69.00

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Skilled Laborer 4 1 79.70 318.80
c. Laborer 10 1 61.44 614.40

Sub - Total for A 1,042.39


Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Batching Plant (30 cu.m.) 1 1 1,208.03 1,208.03


b. Concrete Paver, GP-2000 Slipform 1 1 6,765.00 6,765.00
c. Transit Mixer (5 cu.m.) 4 1 1,279.00 5,116.00
d. Payloader (1.50 cu.m.), LX80-2C 1 1 1,733.00 1,733.00
e. Water Truck (1000 gal.) 1 1 1,065.00 1,065.00
f. Concrete Saw, Blade Ø 14" (7.5 Hp) 1 1 167.38 167.38
g. Concrete Vibrator 1 0.10 148.88 14.89
h. Bar Cutter, Single Phase 1 0.10 219.75 21.98
Sub - Total for B 16,091.27
C. Total (A + B) 17,133.66
D. Output per hour = 69.0000 sq.m.
E. Direct Unit Cost (C ÷ D) 248.31
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. Reinforcing Steel Bar kg. 0.55 40.00 22.00


b. Curing Compound lit. 0.29 28.00 8.12
c. Asphalt Sealant lit. 0.18 44.00 7.92
d. Sand cu.m. 0.165 850.00 140.25
e. Gravel cu.m. 0.30 650.00 195.00
f. Cement bag 2.85 220.00 627.00
g. Concrete Saw (diamond blade 14") pc. 0.00015 8,000.00 1.20
h. Pipe Sleeve, 2" dia. l.m. 0.0094 97.00 0.91
i. Grease/Tar lit. 0.0093 300.00 2.79

Sub - Total for F 1,005.19


G. Direct Unit Cost (E + F) 1,253.51
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 112.82
I. Contractor's Profit (CP) 8% of G 100.28
J. Value Added Tax (VAT) 12% of (G + H + I) 175.99
K. Total Unit Cost (G + H + I + J) 1,642.59

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 311(2) PCC Pavement (Reinforced), 230 mm. thk.


Unit of Measurement : sq.m.
Output per hour : 15.22

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Skilled Laborer 4 1 79.70 318.80
c. Laborer 12 1 61.44 737.28
Fabrication/Installation
b. Skilled Laborer 2 1 79.70 159.40
c. Laborer 2 1 61.44 122.88

Sub - Total for A 1,447.55


Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Batching Plant (30 cu.m.) 1 0.75 1,208.03 906.02


b. Concrete Screeder (5.5 Hp) 1 1 545.00 545.00
c. Transit Mixer (5 cu.m.) 3 0.75 1,279.00 2,877.75
d. Payloader (1.50 cu.m.), LX80-2C 1 0.75 1,733.00 1,299.75
e. Water Truck (1000 gal.) 1 0.25 1,065.00 266.25
f. Concrete Vibrator 2 1 148.88 297.76
g. Bar Cutter, Single Phase 1 0.25 219.75 54.94
h. Bar Bender 1 0.25 351.50 87.88
Minor Tools (5% of Labor) 72.38
Sub - Total for B 6,407.72
C. Total (A + B) 7,855.27
D. Output per hour = 15.22 sq.m.
E. Direct Unit Cost (C ÷ D) 516.12
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. Reinforcing Steel Bar kg. 40.86 40.00 1,634.40


b. Curing Compound lit. 0.09 28.00 2.52
c. Asphalt Sealant lit. 0.02 44.00 0.88
d. Steel Forms (Rental) l.m. 0.23 250.00 57.50
e. Sand cu.m. 0.10 850.00 85.00
f. Gravel cu.m. 0.20 650.00 130.00
g. Cement bag 2.08 220.00 457.60
h. # 16 GI Tie Wire (2% of RSB) kg. 0.817 47.00 38.40

Sub - Total for F 2,406.30


G. Direct Unit Cost (E + F) 2,922.41
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 263.02
I. Contractor's Profit (CP) 8% of G 233.79
J. Value Added Tax (VAT) 12% of (G + H + I) 410.31
K. Total Unit Cost (G + H + I + J) 3,829.53
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 404c Reinforcing Steel Bar, Grade 40 (Minor Structures)


Unit of Measurement : kg.
Output per hour : 180.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Skilled Laborer 2 1 79.70 159.40
c. Laborer 8 1 61.44 491.52

Sub - Total for A 760.11


Name and Capacity No of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Bar Cutter 1 0.50 219.75 109.88


b. Bar Bender 1 0.50 351.50 175.75
c. Cargo Truck (10 T, 270 Hp) 1 0.15 1,102.00 165.30

Sub - Total for B 450.92


C. Total (A + B) 1,211.03
D. Output per hour = 180.00000 kg.
E. Direct Unit Cost (C ÷ D) 6.73
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Tie Wire (2% of RSB) kg. 0.021 47.00 0.99


b. Reinforcing Steel Bar, Grade 40 kg. 1.05 40.00 42.00
(w/ 5% Wastage)

Sub - Total for F 42.99


G. Direct Unit Cost (E + F) 49.71
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 4.47
I. Contractor's Profit (CP) 8% of G 3.98
J. Value Added Tax (VAT) 12% of (G + H + I) 6.98
K. Total Unit Cost (G + H + I + J) 65.15
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 405 Structural Concrete Class A (Minor Structures)


Unit of Measurement : cu.m.
Output per hour : 1.40

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Skilled Laborer 4 1 79.70 318.80
c. Laborer 8 1 61.44 491.52

Installation/Removal of Formworks
a. Skilled Laborer 2 2 79.70 318.80
b. Laborer 4 2 61.44 491.52
Sub - Total for A 1,729.83
Name and Capacity No of Units No. of Hours Hourly Rate Amount
B. Equipment

a. One Bagger Mixer 1 1 172.00 172.00


b. Concrete Vibrator 1 1 148.88 148.88
c. Water Truck (1000 gal.) 1 0.10 1,065.00 106.50
Minor Tools (5% of Labor) 86.49

Sub - Total for B 513.87


C. Total (A + B) 2,243.70
D. Output per hour = 1.4000 cu.m.
E. Direct Unit Cost (C ÷ D) 1,602.64
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Lumber, Good - 4 uses bd.ft. * 70.0000 40.00 700.00


b. Marine Plywood (1/2" x 4' x 8') - 4 uses pc. * 1.600 700.00 280.00
c. Assorted CWN (1kg./100 bd.ft. of Lumber) kg. * 0.700 68.00 47.60
d. Cement bag 9.50 220.00 2,090.00
e. Sand cu.m. 0.50 850.00 425.00
f. Gravel cu.m. 1 650.00 650.00
Based on Box Culvert
Note:
*Quantities for lumber, plywood and CWN are dependent
on the type of minor structure.
The above-computed quantities are based on box
culvert.
Sub - Total for F 4,192.60
G. Direct Unit Cost (E + F) 5,795.24
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 521.57
I. Contractor's Profit (CP) 8% of G 463.62
J. Value Added Tax (VAT) 12% of (G + H + I) 813.65
K. Total Unit Cost (G + H + I + J) 7,594.09
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 500(1)a Pipe Culverts, 610mm dia. (24" Ø)


Unit of Measurement : l.m.
Output per hour : 2.25

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Skilled Laborer 2 1 79.70 159.40
c. Laborer 4 1 61.44 245.76

Sub - Total for A 514.35


Name and Capacity No of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Backhoe (0.80 cu.m.) 1 0.50 1,537.00 768.50


b. Plate Compactor (5 Hp) 1 0.50 123.00 61.50
Minor Tools (10 % of Labor) 51.44

Sub - Total for B 881.44


C. Total (A + B) 1,395.78
D. Output per hour = 2.25 l.m.
E. Direct Unit Cost (C ÷ D) 620.35
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Portland Cement bag 0.774 220.00 170.28


b. Sand cu.m. 0.044 850.00 37.40
c. R.C. Pipes (610 mm dia.) pc. 1 950.00 950.00
d. Sand Bedding/Selected Sandy Soil cu.m. 0.088 850.00 74.80

Sub - Total for F 1,232.48


G. Direct Unit Cost (E + F) 1,852.83
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 166.75
I. Contractor's Profit (CP) 8% of G 148.23
J. Value Added Tax (VAT) 12% of (G + H + I) 260.14
K. Total Unit Cost (G + H + I + J) 2,427.95

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 500(1)c Pipe Culverts, 910mm dia. (36" Ø)


Unit of Measurement : l.m.
Output per hour : 1.75

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Skilled Laborer 2 1 79.70 159.40
c. Laborer 4 1 61.44 245.76

Sub - Total for A 514.35


Name and Capacity No of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Backhoe (0.80 cu.m.) 1 0.50 1,537.00 768.50


b. Plate Compactor (5 Hp) 1 0.50 123.00 61.50
Minor Tools (10 % of Labor) 51.44

Sub - Total for B 881.44


C. Total (A + B) 1,395.78
D. Output per hour = 1.75 l.m.
E. Direct Unit Cost (C ÷ D) 797.59
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Portland Cement bag 1.080 220.00 237.60


b. Sand cu.m. 0.061 850.00 51.85
c. R.C. Pipes (910 mm dia.) pc. 1 2,170.00 2,170.00
d. Sand Bedding/Selected Sandy Soil cu.m. 0.128 850.00 108.80

Sub - Total for F 2,568.25


G. Direct Unit Cost (E + F) 3,365.84
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 302.93
I. Contractor's Profit (CP) 8% of G 269.27
J. Value Added Tax (VAT) 12% of (G + H + I) 472.56
K. Total Unit Cost (G + H + I + J) 4,410.60

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 500(1)d Pipe Culverts, 1070mm dia. (42" Ø)


Unit of Measurement : l.m.
Output per hour : 1.50

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor
a. Construction Foreman 1 1 109.19 109.19
b. Skilled Laborer 2 1 79.70 159.40
c. Laborer 4 1 61.44 245.76

Sub - Total for A 514.35


Name and Capacity No of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Backhoe (0.80 cu.m.) 1 0.50 1,537.00 768.50


b. Plate Compactor (5 Hp) 1 0.50 123.00 61.50
Minor Tools (10 % of Labor) 51.44

Sub - Total for B 881.44


C. Total (A + B) 1,395.78
D. Output per hour = 1.500 l.m.
E. Direct Unit Cost (C ÷ D) 930.52
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Portland Cement bag 1.242 220.00 273.24


b. Sand cu.m. 0.070 850.00 59.50
c. R.C. Pipes (1070 mm dia.) pc. 1 2,900.00 2,900.00
d. Sand Bedding/Selected Sandy Soil cu.m. 0.149 850.00 126.65

Sub - Total for F 3,359.39


G. Direct Unit Cost (E + F) 4,289.91
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 386.09
I. Contractor's Profit (CP) 8% of G 343.19
J. Value Added Tax (VAT) 12% of (G + H + I) 602.30
K. Total Unit Cost (G + H + I + J) 5,621.50

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 500(1)e Pipe Culverts, 1220mm dia. (48" Ø)


Unit of Measurement : l.m.
Output per hour : 1.25

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Skilled Laborer 2 1 79.70 159.40
c. Laborer 4 1 61.44 245.76
Sub - Total for A 514.35
Name and Capacity No of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Backhoe (0.80 cu.m.) 1 0.50 1,537.00 768.50


b. Plate Compactor (5 Hp) 1 0.50 123.00 61.50
Minor Tools (10 % of Labor) 51.44

Sub - Total for B 881.44


C. Total (A + B) 1,395.78
D. Output per hour = 1.25 l.m.
E. Direct Unit Cost (C ÷ D) 1,116.63
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Portland Cement bag 1.404 220.00 308.88


b. Sand cu.m. 0.080 850.00 68.00
c. R.C. Pipes (1220 mm dia.) pc. 1 3,800.00 3,800.00
d. Sand Bedding/Selected Sandy Soil cu.m. 0.170 850.00 144.50

Sub - Total for F 4,321.38


G. Direct Unit Cost (E + F) 5,438.01
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 489.42
I. Contractor's Profit (CP) 8% of G 435.04
J. Value Added Tax (VAT) 12% of (G + H + I) 763.50
K. Total Unit Cost (G + H + I + J) 7,125.97

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 500(1)f Pipe Culverts, 1520mm dia. (60" Ø)


Unit of Measurement : l.m.
Output per hour : 1.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Skilled Laborer 2 1 79.70 159.40
c. Laborer 4 1 61.44 245.76

Sub - Total for A 514.35


Name and Capacity No of Units No. of Hours Hourly Rate Amount
Name and Capacity No of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Backhoe (0.80 cu.m.) 1 0.50 1,537.00 768.50


b. Plate Compactor (5 Hp) 1 0.50 123.00 61.50
Minor Tools (10 % of Labor) 51.44

Sub - Total for B 881.44


C. Total (A + B) 1,395.78
D. Output per hour = 1.0000 l.m.
E. Direct Unit Cost (C ÷ D) 1,395.78
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Portland Cement bag 1.710 220.00 376.20


b. Sand cu.m. 0.097 850.00 82.45
c. R.C. Pipes (1520 mm dia.) pc. 1 6,175.00 6,175.00
d. Sand Bedding/Selected Sandy Soil cu.m. 0.210 850.00 178.50

Sub - Total for F 6,812.15


G. Direct Unit Cost (E + F) 8,207.94
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 738.71
I. Contractor's Profit (CP) 8% of G 656.63
J. Value Added Tax (VAT) 12% of (G + H + I) 1,152.39
K. Total Unit Cost (G + H + I + J) 10,755.68

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 502(1)a Manhole (610 mm. dia. RCPC)


Unit of Measurement : ea.
Output : 1.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 8.90 109.19 971.79


b. Skilled Laborer 2 8.90 79.70 1,418.66
c. Laborer 4 8.90 61.44 2,187.26

Sub - Total for A 4,577.72


Name and Capacity No of Units No. of Hours Hourly Rate Amount
B. Equipment

a. One Bagger Mixer 1 2 172.00 344.00


b. Water Truck (1000 gal.) 1 0.15 1,065.00 159.75
c. Bar Cutter 1 0.30 219.75 65.93
d. Bar Bender 1 0.30 351.50 105.45
e. Concrete Vibrator 1 2 148.88 297.76
f. Welding Machine 1 0.15 391.00 58.65
Minor Tools (10% of Labor) 457.77

Sub - Total for B 1,489.31


C. Total (A + B) 6,067.02
D. Output = 1.0000 ea.
E. Direct Unit Cost (C ÷ D) 6,067.02
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Cement bag 23 220.00 5,060.00


b. Sand cu.m. 1.235 850.00 1,049.75
c. Gravel cu.m. 2.47 650.00 1,605.50
d. Reinforcing Steel Bar kg. 267.93 40.00 10,717.20
e. #16 G.I. Tie Wire (2% of RSB) kg. 5.359 47.00 251.87
f. 100 x 100 x 6mm Angle Bar kg. 48.98 48.00 2,350.94
g. Welding Rod (1 kg./2000 kg. of Steel) kg. 0.024 90.00 2.16
h. 1/4" Ordinary Plywood - 2 uses pc. 6.75 350.00 1,181.25
i. Coco Lumber - 2 uses bd.ft. 117.643 20.00 1,176.43
j. Assorted CWN (1 kg./100 bd.ft. of Lumber) kg. 1.176 68.00 79.97

Sub - Total for F 23,475.08


G. Direct Unit Cost (E + F) 29,542.10
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 2,658.79
I. Contractor's Profit (CP) 8% of G 2,363.37
J. Value Added Tax (VAT) 12% of (G + H + I) 4,147.71
K. Total Unit Cost (G + H + I + J) 38,711.96

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 502(1)c Manhole (910 mm. dia. RCPC)


Unit of Measurement : ea.
Output : 1.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 11.20 109.19 1,222.93


b. Skilled Laborer 2 11.20 79.70 1,785.28
c. Laborer 4 11.20 61.44 2,752.51

Sub - Total for A 5,760.72


Name and Capacity No of Units No. of Hours Hourly Rate Amount
B. Equipment

a. One Bagger Mixer 1 2.42 172.00 416.24


b. Water Truck (1000 gal.) 1 0.16 1,065.00 170.40
c. Bar Cutter 1 0.50 219.75 109.88
d. Bar Bender 1 0.50 351.50 175.75
e. Concrete Vibrator 1 2.42 148.88 360.29
f. Welding Machine 1 0.16 391.00 62.56
Minor Tools (10% of Labor) 576.07 576.07
Sub - Total for B 1,871.19
C. Total (A + B) 7,631.91
D. Output = 1.0000 ea.
E. Direct Unit Cost (C ÷ D) 7,631.91
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Cement bag 29 220.00 6,380.00


b. Sand cu.m. 1.582 850.00 1,344.70
c. Gravel cu.m. 3.164 650.00 2,056.60
d. Reinforcing Steel Bar kg. 352.211 40.00 14,088.44
e. #16 G.I. Tie Wire (2% of RSB) kg. 7.044 47.00 331.07
f. 100 x 100 x 6mm Angle Bar kg. 57.078 48.00 2,739.74
g. Welding Rod (1 kg./2000 kg. of Steel) kg. 0.029 90.00 2.61
h. 1/4" Ordinary Plywood - 2 uses pc. 9.16 350.00 1,603.00
i. Coco Lumber - 2 uses bd.ft. 129.626 20.00 1,296.26
j. Assorted CWN (1 kg./100 bd.ft. of Lumber) kg. 1.296 68.00 88.13

Sub - Total for F 29,930.55


G. Direct Unit Cost (E + F) 37,562.46
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 3,380.62
I. Contractor's Profit (CP) 8% of G 3,005.00
J. Value Added Tax (VAT) 12% of (G + H + I) 5,273.77
K. Total Unit Cost (G + H + I + J) 49,221.84

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 502(1)d Manhole (1070 mm. dia. RCPC)


Unit of Measurement : ea.
Output : 1.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 13.30 109.19 1,452.23


b. Skilled Laborer 2 13.30 79.70 2,120.02
c. Laborer 4 13.30 61.44 3,268.61

Sub - Total for A 6,840.86


Name and Capacity No of Units No. of Hours Hourly Rate Amount
B. Equipment

a. One Bagger Mixer 1 2.83 172.00 486.76


b. Water Truck (1000 gal.) 1 0.19 1,065.00 202.35
c. Bar Cutter 1 0.52 219.75 114.27
d. Bar Bender 1 0.52 351.50 182.78
e. Concrete Vibrator 1 2.83 148.88 421.33
f. Welding Machine 1 0.19 391.00 74.29
Minor Tools (10% of Labor) 684.09 684.09
Sub - Total for B 2,165.87
C. Total (A + B) 9,006.72
D. Output = 1.0000 ea.
E. Direct Unit Cost (C ÷ D) 9,006.72
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Cement bag 34 220.00 7,480.00


b. Sand cu.m. 1.884 850.00 1,601.40
c. Gravel cu.m. 3.768 650.00 2,449.20
d. Reinforcing Steel Bar kg. 376.863 40.00 15,074.52
e. #16 G.I. Tie Wire (2% of RSB) kg. 7.537 47.00 354.24
f. 100 x 100 x 6mm Angle Bar kg. 62.729 48.00 3,010.99
g. Welding Rod (1 kg./2000 kg. of Steel) kg. 0.031 90.00 2.79
h. 1/4" Ordinary Plywood - 2 uses pc. 10.10 350.00 1,767.50
i. Coco Lumber - 2 uses bd.ft. 133.47 20.00 1,334.70
j. Assorted CWN (1 kg./100 bd.ft. of Lumber) kg. 1.335 68.00 90.78

Sub - Total for F 33,166.12


G. Direct Unit Cost (E + F) 42,172.84
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 3,795.56
I. Contractor's Profit (CP) 8% of G 3,373.83
J. Value Added Tax (VAT) 12% of (G + H + I) 5,921.07
K. Total Unit Cost (G + H + I + J) 55,263.29

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 502(1)e Manhole (1220 mm. dia. RCPC)


Unit of Measurement : ea.
Output : 1.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 15 109.19 1,637.85


b. Skilled Laborer 2 15 79.70 2,391.00
c. Laborer 4 15 61.44 3,686.40

Sub - Total for A 7,715.25


Name and Capacity No of Units No. of Hours Hourly Rate Amount
B. Equipment

a. One Bagger Mixer 1 3.60 172.00 619.20


b. Water Truck (1000 gal.) 1 0.24 1,065.00 255.60
c. Bar Cutter 1 0.73 219.75 160.42
d. Bar Bender 1 0.73 351.50 256.59
e. Concrete Vibrator 1 3.60 148.88 535.97
f. Welding Machine 1 0.24 391.00 93.84
Minor Tools (10% of Labor) 771.53 771.53

Sub - Total for B 2,693.15


C. Total (A + B) 10,408.40
D. Output = 1.0000 ea.
E. Direct Unit Cost (C ÷ D) 10,408.40
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Cement bag 43 220.00 9,460.00


b. Sand cu.m. 2.352 850.00 1,999.20
c. Gravel cu.m. 4.704 650.00 3,057.60
d. Reinforcing Steel Bar kg. 528.209 40.00 21,128.36
e. #16 G.I. Tie Wire (2% of RSB) kg. 10.564 47.00 496.51
f. 100mmx100mmx6mm Angle Bar kg. 72.525 48.00 3,481.20
g. Welding Rod (1 kg./2000 kg. of Steel) kg. 0.036 90.00 3.24
h. 1/4" Ordinary Plywood - 2 uses pc. 12.65 350.00 2,213.75
i. Coco Lumber - 2 uses bd.ft. 163.913 20.00 1,639.13
j. Assorted CWN (1 kg./100 bd.ft. of Lumber) kg. 1.639 68.00 111.45

Sub - Total for F 43,590.44


G. Direct Unit Cost (E + F) 53,998.84
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 4,859.90
I. Contractor's Profit (CP) 8% of G 4,319.91
J. Value Added Tax (VAT) 12% of (G + H + I) 7,581.44
K. Total Unit Cost (G + H + I + J) 70,760.07

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 502(4) Concrete Covers


Unit of Measurement : ea.
Output : 5.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Skilled Laborer 2 1 79.70 159.40
c. Laborer 4 1 61.44 245.76

Sub - Total for A 514.35


Name and Capacity No of Units No. of Hours Hourly Rate Amount
B. Equipment

a. One Bagger Mixer 1 0.50 172.00 86.00


b. Bar Cutter 1 0.50 219.75 109.88
c. Concrete Vibrator 1 0.50 148.88 74.44
d. Welding Machine (GasType) 1 0.25 391.00 97.75
e. Water Truck 1 0.05 1,065.00 53.25
Minor Tools (10% of Labor) 51.44 51.44

Sub - Total for B 472.75


C. Total (A + B) 987.10
D. Output = 5.0000 ea.
E. Direct Unit Cost (C ÷ D) 197.42
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

Dimension: 1.31m x 0.573m x 0.20m


a. Portland Cement bag 1.31 220.00 288.20
b. Sand cu.m. 0.06 850.00 51.00
c. Gravel cu.m. 0.12 650.00 78.00
d. Reinforcing Steel Bar kg. 44.38 40.00 1,775.20
e. #16 GI Tie Wire (2% of RSB) kg. 0.888 47.00 41.74
f. 6mm thk. Steel Plate kg. 35.48 48.00 1,703.04
g. 16mm thk. Steel Plate kg. 2.83 48.00 67.92
h. 1/2" Ordinary Plywood - 2 uses pc. 0.33 620.00 102.30
i. 16mm dia. U-bolt & Knot set 2.00 250.00 250.00
j. Welding Rod (1 kg./2000 kg. of Steel) kg. 0.019 90.00 0.86

Sub - Total for F 4,358.25


G. Direct Unit Cost (E + F) 4,555.67
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 410.01
I. Contractor's Profit (CP) 8% of G 364.45
J. Value Added Tax (VAT) 12% of (G + H + I) 639.62
K. Total Unit Cost (G + H + I + J) 5,969.75

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 504(3)a Cleaning Culvert Pipe in place (610mm dia.) - Half Silted
Unit of Measurement : l.m.
Output per hour : 8.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Skilled Laborer 2 1 79.70 159.40
c. Laborer 4 1 61.44 245.76

Sub - Total for A 514.35


Name and Capacity No of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Cargo Truck (10 T) 1 1 1,102.00 1,102.00


b. Steel Wheel with Nylon Rope l.s. 300.00 300.00
c. Improvised Bamboo with Bucket l.s. 200.00 200.00
Minor Tools (10% of Labor) 51.44 51.44

Sub - Total for B 1,653.44


C. Total (A + B) 2,167.79
D. Output per hour = 8.0000 l.m.
E. Direct Unit Cost (C ÷ D) 270.97
Name and Specification Unit Quantity Unit Cost Amount

F. Materials
Sub - Total for F -
G. Direct Unit Cost (E + F) 270.97
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 24.39
I. Contractor's Profit (CP) 8% of G 21.68
J. Value Added Tax (VAT) 12% of (G + H + I) 38.04
K. Total Unit Cost (G + H + I + J) 355.08

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 504(3)c Cleaning Culvert Pipe in place (910mm dia.) - Half Silted
Unit of Measurement : l.m.
Output per hour : 3.75

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Skilled Laborer 2 1 79.70 159.40
c. Laborer 4 1 61.44 245.76

Sub - Total for A 514.35


Name and Capacity No of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Cargo Truck (10 T) 1 1 1,102.00 1,102.00


Minor Tools (10% of Labor) 51.44 51.44

Sub - Total for B 1,153.44


C. Total (A + B) 1,667.78
D. Output per hour = 3.75 l.m.
E. Direct Unit Cost (C ÷ D) 444.74
Name and Specification Unit Quantity Unit Cost Amount

F. Materials
Sub - Total for F -
G. Direct Unit Cost (E + F) 444.74
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 40.03
I. Contractor's Profit (CP) 8% of G 35.58
J. Value Added Tax (VAT) 12% of (G + H + I) 62.44
K. Total Unit Cost (G + H + I + J) 582.79

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 504(3)d Cleaning Culvert Pipe in place (1070mm dia.) - Half Silted
Unit of Measurement : l.m.
Output per hour : 2.75

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Skilled Laborer 2 1 79.70 159.40
c. Laborer 4 1 61.44 245.76

Sub - Total for A 514.35


Name and Capacity No of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Cargo Truck (10 T) 1 1 1,102.00 1,102.00


Minor Tools (10% of Labor) 51.44 51.44

Sub - Total for B 1,153.44


C. Total (A + B) 1,667.78
D. Output per hour = 2.75 l.m.
E. Direct Unit Cost (C ÷ D) 606.47
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

Sub - Total for F -


G. Direct Unit Cost (E + F) 606.47
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 54.58
I. Contractor's Profit (CP) 8% of G 48.52
J. Value Added Tax (VAT) 12% of (G + H + I) 85.15
K. Total Unit Cost (G + H + I + J) 794.71

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 504(3)e Cleaning Culvert Pipe in place (1220mm dia.) - Half Silted
Unit of Measurement : l.m.
Output per hour : 2.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Skilled Laborer 2 1 79.70 159.40
c. Laborer 4 1 61.44 245.76

Sub - Total for A 514.35


Name and Capacity No of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Cargo Truck (10 T) 1 1 1,102.00 1,102.00


Minor Tools (10% of Labor) 51.44 51.44

Sub - Total for B 1,153.44


C. Total (A + B) 1,667.78
D. Output per hour = 2.0000 l.m.
E. Direct Unit Cost (C ÷ D) 833.89
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

Sub - Total for F -


G. Direct Unit Cost (E + F) 833.89
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 75.05
I. Contractor's Profit (CP) 8% of G 66.71
J. Value Added Tax (VAT) 12% of (G + H + I) 117.08
K. Total Unit Cost (G + H + I + J) 1,092.73

DETAILED UNIT PRICE ANALYSIS (DUPA)


Item No./Description : 504(3)f Cleaning Culvert Pipe in place (1520mm dia.) - Half Silted
Unit of Measurement : l.m.
Output per hour : 1.50

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Skilled Laborer 2 1 79.70 159.40
c. Laborer 4 1 61.44 245.76

Sub - Total for A 514.35


Name and Capacity No of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Cargo Truck (10 T) 1 1 1,102.00 1,102.00


Minor Tools (10% of Labor) 51.44 51.44

Sub - Total for B 1,153.44


C. Total (A + B) 1,667.78
D. Output per hour = 1.500 l.m.
E. Direct Unit Cost (C ÷ D) 1,111.86
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

Sub - Total for F -


G. Direct Unit Cost (E + F) 1,111.86
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 100.07
I. Contractor's Profit (CP) 8% of G 88.95
J. Value Added Tax (VAT) 12% of (G + H + I) 156.10
K. Total Unit Cost (G + H + I + J) 1,456.98

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 504(4) Reconditioning Drainage Structures


Unit of Measurement : ea.
Output : 1.00
Designation No. of Person No. of Hours Hourly Rate Amount
A. Labor

a. Construction Foreman 1 0.50 109.19 54.60


b. Skilled Laborer 1 0.50 79.70 39.85
c. Laborer 2 0.50 61.44 61.44

Sub - Total for A 155.89


Name and Capacity No of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Cargo Truck (10 T) 1 0.25 1,102.00 275.50


b. Bamboo with Bucket - 4 uses 1 1 200.00 50.00
Minor Tools (10% of Labor) 15.59 15.59

Sub - Total for B 341.09


C. Total (A + B) 496.97
D. Output = 1.000 ea.
E. Direct Unit Cost (C ÷ D) 496.97
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

* If some repair is needed, component materials required and


correcsponding man-hour will be added to DUPA
Sub - Total for F -
G. Direct Unit Cost (E + F) 496.97
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 44.73
I. Contractor's Profit (CP) 8% of G 39.76
J. Value Added Tax (VAT) 12% of (G + H + I) 69.78
K. Total Unit Cost (G + H + I + J) 651.23
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 505(5) Grouted Riprap (Class A)


Unit of Measurement : cu.m.
Output per hour : 1.25

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Skilled Laborer 2 1 79.70 159.40
c. Laborer 8 1 61.44 491.52

Sub - Total for A 760.11


Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. One Bagger Mixer 1 1 172.00 172.00


b. Water Truck (1000 gal.) 1 0.05 1,065.00 53.25
Minor Tools (5% of Labor) 38.01

Sub - Total for B 263.26


C. Total (A + B) 1,023.37
D. Output per hour = 1.25 cu.m.
E. Direct Unit Cost (C ÷ D) 818.69
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. Cement bag 3.00 250.00 750.00


b. Sand cu.m. 0.25 850.00 212.50
c. Gravel Fill cu.m. 0.015 650.00 9.75
d. Weep Holes (PVC) l.m. 0.30 207.15 62.15
e. Filter Cloth sq.m. 0.015 370.00 5.55
f. Boulders (15 - 25 kg.) cu.m. 1.05 1,020.00 1,071.00
Miscellaneous (1% of Materials) 21.11

Sub - Total for F 2,132.06


G. Direct Unit Cost (E + F) 2,950.75
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 265.57
I. Contractor's Profit (CP) 8% of G 236.06
J. Value Added Tax (VAT) 12% of (G + H + I) 414.29
K. Total Unit Cost (G + H + I + J) 3,866.66
Prepared by: Checked by:

ALLISTER G. NACALABAN
Contractor Project Engineer
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 506 Stone Masonry


Unit of Measurement : cu.m.
Output per hour : 1.5625

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Skilled Laborer 2 1 79.70 159.40
c. Laborer 8 1 61.44 491.52

Sub - Total for A 760.11


Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. One Bagger Mixer 1 1 172.00 172.00


b. Water Truck (1000 gal.) 1 0.05 1,065.00 53.25
c. Backhoe (Wheel Type 0.28 cu.m.) 1 0.10 840.00 84.00
Minor Tools (10% Labor) 76.01

Sub - Total for B 385.26


C. Total (A + B) 1,145.37
D. Output per hour =1.5625 cu.m.
E. Direct Unit Cost (C ÷ D) 733.04
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. Cement bag 5.50 220.00 1,210.00


b. Sand cu.m. 0.30 850.00 255.00
c. Gravel Fill cu.m. 0.02 650.00 13.00
d. Weep Holes (PVC) l.m. 0.30 144.67 43.40
e. Filter Cloth sq.m. 0.015 275.00 4.13
f. Boulders cu.m. 1.05 920.00 966.00
Miscellaneous (1% of Materials) 24.92

Sub - Total for F 2,516.44


G. Direct Unit Cost (E + F) 3,249.48
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 292.45
I. Contractor's Profit (CP) 8% of G 259.96
J. Value Added Tax (VAT) 12% of (G + H + I) 456.23
K. Total Unit Cost (G + H + I + J) 4,258.12

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 507 Rubble Concrete


Unit of Measurement : cu.m.
Output per hour : 1.40

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Skilled Laborer 2 1 79.70 159.40
c. Laborer 8 1 61.44 491.52

Sub - Total for A 760.11


Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. One Bagger Mixer 1 1 172.00 172.00


b. Water Truck (1000 gal.) 1 0.05 1,065.00 53.25
c. Backhoe (Wheel Type 0.28 cu.m.) 1 0.10 840.00 84.00
Minor Tools (10% Labor) 76.01

Sub - Total for B 385.26


C. Total (A + B) 1,145.37
D. Output per hour = 1.400 cu.m.
E. Direct Unit Cost (C ÷ D) 818.12
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. Cement bag 4.20 220.00 924.00


b. Sand cu.m. 0.2625 850.00 223.13
c. Gravel Fill cu.m. 0.02 650.00 13.00
d. Weep Holes (PVC) l.m. 0.30 144.67 43.40
e. Filter Cloth sq.m. 0.015 275.00 4.13
f. Boulders cu.m. 0.63 810.00 510.30
g. Gravel cu.m. 0.525 650.00 341.25
Miscellaneous (2% of Materials) 36.72
Note:
60% Boulder
50% Class "B" Concrete (w/ side forms only)

Sub - Total for F 2,095.92


G. Direct Unit Cost (E + F) 2,914.04
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 262.26
I. Contractor's Profit (CP) 8% of G 233.12
J. Value Added Tax (VAT) 12% of (G + H + I) 409.13
K. Total Unit Cost (G + H + I + J) 3,818.56

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 508 Hand Laid Rock Embankment


Unit of Measurement : cu.m.
Output per hour : 3.125

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Skilled Laborer 2 1 79.70 159.40
c. Laborer 8 1 61.44 491.52

Sub - Total for A 760.11


Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

Minor Tools (10% of Labor) 76.01

Sub - Total for B 76.01


C. Total (A + B) 836.12
D. Output per hour = 3.125 cu.m.
E. Direct Unit Cost (C ÷ D) 267.56
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. Boulders cu.m. 1.05 920.00 966.00

Sub - Total for F 966.00


G. Direct Unit Cost (E + F) 1,233.56
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 111.02
I. Contractor's Profit (CP) 8% of G 98.68
J. Value Added Tax (VAT) 12% of (G + H + I) 173.19
K. Total Unit Cost (G + H + I + J) 1,616.46

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 509(b)1 Steel Sheet Pile (Slope Protection)


Unit of Measurement : l.m.
Output per hour : 10.00

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Skilled Laborer 2 1 79.70 159.40
c. Laborer 4 1 61.44 245.76
Sub - Total for A 514.35
Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Crawler Crane (36 - 40 T) 1 1 1,729.00 1,729.00


b. Vibro Hammer (Hydraulic Operated) 1 1 1,800.00 1,800.00
c. Welding Machine (Gas Operated) 1 0.25 371.00 92.75
d. Cutting Outfit 1 0.25 45.45 11.36

Sub - Total for B 3,633.11


C. Total (A + B) 4,147.46
D. Output per hour = 10.0000 l.m.
E. Direct Unit Cost (C ÷ D) 414.75
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. Steel Sheet Piles (48 kg./l.m.) kg. 48.00 48.00 2,304.00


Miscellaneous (3% of Materials) 69.12

Sub - Total for F 2,373.12


G. Direct Unit Cost (E + F) 2,787.87
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 250.91
I. Contractor's Profit (CP) 8% of G 223.03
J. Value Added Tax (VAT) 12% of (G + H + I) 391.42
K. Total Unit Cost (G + H + I + J) 3,653.22

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 509(b)2 Steel Sheet Pile (for Cofferdaming)


Unit of Measurement : l.m.
Output per hour : 10.00

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Skilled Laborer 2 1 79.70 159.40
c. Laborer 4 1 61.44 245.76

Sub - Total for A 514.35


Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Crawler Crane (36 - 40 T) 1 1 1,729.00 1,729.00


b. Vibro Hammer (Hydraulic Operated) 1 1 1,800.00 1,800.00
c. Welding Machine 1 0.25 391.00 97.75
d. Cutting Outfit 1 0.25 45.45 11.36
e. Water Pump 1 1 -

Sub - Total for B 3,638.11


C. Total (A + B) 4,152.46
D. Output per hour = 10.0000 l.m.
E. Direct Unit Cost (C ÷ D) 415.25
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. Steel Sheet Piles (48 kg./l.m.) kg. 48.00 48.00 2,304.00


b. Structural Steel (Walling, Bracing, kg. 4.80 48.00 230.40
Diagonal etc.)

Sub - Total for F 2,534.40


G. Direct Unit Cost (E + F) 2,949.65
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 265.47
I. Contractor's Profit (CP) 8% of G 235.97
J. Value Added Tax (VAT) 12% of (G + H + I) 414.13
K. Total Unit Cost (G + H + I + J) 3,865.22

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 509(c) Concrete Sheet Pile, furnished and driven


Unit of Measurement : l.m.
Output per hour : 1.20

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Skilled Laborer 4 1 79.70 318.80
c. Laborer 6 1 61.44 368.64
Formworks
b. Skilled Laborer 2 1 79.70 159.40
c. Laborer 4 1 61.44 245.76

Sub - Total for A 1,201.79


Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Crawler Crane (45 T) 1 0.10 1,772.00 177.20


b. One Bagger Mixer 1 0.40 172.00 68.80
c. Concrete Vibrator 1 0.15 148.88 22.33
d. Water Truck (1000 gal.) 1 0.03 1,065.00 31.95
e. Bar Cutter 1 0.03 219.75 6.59
f. Bar Bender 1 0.03 351.50 10.55
g. Drop Hammer 1 0.10 200.00 20.00
h. Jack Hammer 1 0.10 514.31 51.43
i. Air Compressor (103 Hp) 1 0.10 675.00 67.50
j. Plate Compactor (5 Hp) 1 0.03 123.00 3.69
Minor Tools (5% of Labor) 60.09

Sub - Total for B 520.13


C. Total (A + B) 1,721.92
D. Output per hour = 1.200 l.m.
E. Direct Unit Cost (C ÷ D) 1,434.93
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. Reinforcing Steel Bar kg. 28.11 40.00 1,124.40


b. Cement bag 1.44 220.00 316.80
c. Sand cu.m. 0.08 850.00 68.00
d. Gravel cu.m. 0.15 650.00 97.50
e. Marine Plywood, 1/2" x 4' x 8' pc. 0.15 700.00 105.00
f. Lumber, 2' x 2' bd.ft. 5.90 40.00 236.00
g. # 16 GI Tie Wire (2% of RSB) kg. 0.562 47.00 26.41
h. Assorted CWN (1 kg./100 bd.ft. of Lumber) kg. 0.059 68.00 4.01
Casting Bed
a. Ready Mix Concrete cu.m 0.030 2,840.00 85.20
b. Coco Lumber - 4 uses bd.ft. 1.500 20.00 7.50
c. Base Course cu.m 0.030 530.00 15.90
Sub - Total for F 2,086.73
G. Direct Unit Cost (E + F) 3,521.66
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 316.95
I. Contractor's Profit (CP) 8% of G 281.73
J. Value Added Tax (VAT) 12% of (G + H + I) 494.44
K. Total Unit Cost (G + H + I + J) 4,614.78

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 510(1) Bed Course Granular Material


Unit of Measurement : cu.m. in-place
Output per hour : 1.25

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Laborer 4 1 61.44 245.76

Sub - Total for A 354.95


Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Plate Compactor 1 1 123.00 123.00


Minor Tools (10% of Labor) 35.50
Sub - Total for B 158.50
C. Total (A + B) 513.44
D. Output per hour = 1.25 cu.m. in-place
E. Direct Unit Cost (C ÷ D) 410.76
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. Aggregate Subbase Course cu.m. 1.15 580.00 667.00


(w/ 15% Shrinkage Factor)

Sub - Total for F 667.00


G. Direct Unit Cost (E + F) 1,077.76
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 97.00
I. Contractor's Profit (CP) 8% of G 86.22
J. Value Added Tax (VAT) 12% of (G + H + I) 151.32
K. Total Unit Cost (G + H + I + J) 1,412.29

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 510(2) Concrete Slope Protection


Unit of Measurement : cu.m. in-place
Output per hour : 1.00

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Skilled Laborer 4 1 79.70 318.80
c. Laborer 8 1 61.44 491.52
Installation of Formworks & Rebars
a. Skilled Laborer 2 1 79.70 159.40
b. Laborer 4 1 61.44 245.76

Sub - Total for A 1,324.67


Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. One Bagger Mixer 1 1 172.00 172.00


b. Water Truck (1000 gal.) 1 0.05 1,065.00 53.25
c. Backhoe (Wheel Type 0.28 cu.m.) 1 0.10 840.00 84.00
d. Concrete Vibrator 1 0.05 148.88 7.44
e. Bar Cutter 1 0.05 219.75 10.99
f. Bar Bender 1 0.05 351.50 17.58
Minor Tools (10% Labor) 132.47
Sub - Total for B 477.72
C. Total (A + B) 1,802.39
D. Output per hour = 1.0000 cu.m. in-place
E. Direct Unit Cost (C ÷ D) 1,802.39
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. Cement bag 8.40 220.00 1,848.00


b. Sand cu.m. 0.50 850.00 425.00
c. Weep Holes (PVC) l.m. 0.21 144.67 30.38
d. Filter Cloth sq.m. 0.015 275.00 4.13
e. Gravel cu.m. 1 650.00 650.00
f. Granular Filter cu.m. 0.016 650.00 10.40
f. Reinforcing Steel Bar kg. * 26.03 40.00 1,041.20
g. Marine Plywood 1/2" x 4' x 8' - 4 uses pc. 0.48 700.00 84.00
h. Lumber - 4 uses bd.ft. 18.76 40.00 187.60
i. #16 GI Tie Wire (2% of RSB) kg. 0.521 47.00 24.49
j. Assorted CWN (1 kg./100 bd.ft. of Lumber) kg. 0.188 68.00 12.78
* Note: RSB quantity is variable based on approved plan.
Sub - Total for F 4,317.98
G. Direct Unit Cost (E + F) 6,120.37
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 550.83
I. Contractor's Profit (CP) 8% of G 489.63
J. Value Added Tax (VAT) 12% of (G + H + I) 859.30
K. Total Unit Cost (G + H + I + J) 8,020.13

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 511(1) Gabions


Unit of Measurement : cu.m.
Output per hour : 2.50

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Skilled Laborer 2 1 79.70 159.40
c. Laborer 8 1 61.44 491.52

Sub - Total for A 760.11


Name and Capacity No of Units No. of Hours Hourly Rate Amount
B. Equipment

Note: Exclude Excavation Works


Backhoe excluded, excavation should be separate as the
quantity is variable.

Sub - Total for B -


C. Total (A + B) 760.11
D. Output per hour = 2.500 cu.m.
E. Direct Unit Cost (C ÷ D) 304.04
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. Gabion Wire Mesh (1 x 1 x 2) pc. 0.50 2,900.00 1,450.00


(w/ complete accessories)
b. Boulders cu.m. 1.05 920.00 966.00

Sub - Total for F 2,416.00


G. Direct Unit Cost (E + F) 2,720.04
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 244.80
I. Contractor's Profit (CP) 8% of G 217.60
J. Value Added Tax (VAT) 12% of (G + H + I) 381.89
K. Total Unit Cost (G + H + I + J) 3,564.35

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 511(2) Mattresses


Unit of Measurement : cu.m.
Output per hour : 3.125

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Skilled Laborer 2 1 79.70 159.40
c. Laborer 8 1 61.44 491.52

Sub - Total for A 760.11


Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

Note: Exclude Excavation Works


Backhoe excluded, excavation should be separate as the
quantity is variable.

Sub - Total for B -


C. Total (A + B) 760.11
D. Output per hour = 3.125 cu.m.
E. Direct Unit Cost (C ÷ D) 243.24
Name and Specification Unit Quantity Unit Cost Amount

F. Materials
a. Mattresses (6 x 2 x 0.3 ) pc. 0.28 5,000.00 1,400.00
(w/ complete accessories)
b. Boulders cu.m. 1.05 920.00 966.00

Sub - Total for F 2,366.00


G. Direct Unit Cost (E + F) 2,609.24
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 234.83
I. Contractor's Profit (CP) 8% of G 208.74
J. Value Added Tax (VAT) 12% of (G + H + I) 366.34
K. Total Unit Cost (G + H + I + J) 3,419.14

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 511(3) Filter Cloth


Unit of Measurement : sq.m.
Output per hour : 100.00

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Skilled Laborer 2 1 79.70 159.40
c. Laborer 8 1 61.44 491.52

Sub - Total for A 760.11


Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Cargo Truck (10 T) 1 0.25 1,102.00 275.50

Sub - Total for B 275.50


C. Total (A + B) 1,035.61
D. Output per hour = 100.0000 sq.m.
E. Direct Unit Cost (C ÷ D) 10.36
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. Filter Cloth sq.m. 1.05 275.00 288.75


Miscellaneous (5% of Materials) 14.44
Sub - Total for F 303.19
G. Direct Unit Cost (E + F) 313.54
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 28.22
I. Contractor's Profit (CP) 8% of G 25.08
J. Value Added Tax (VAT) 12% of (G + H + I) 44.02
K. Total Unit Cost (G + H + I + J) 410.87
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 606(1) Pavement Marking (Premix Reflectorized)


Unit of Measurement : sq.m.
Output per hour : 10.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Skilled Laborer 1 1 79.70 79.70
c. Laborer 2 1 61.44 122.88

Sub - Total for A 311.77


Name and Capacity No of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Cargo Truck (5 T) 1 0.05 712.00 35.60


Minor Tools (5% of Labor) 15.59 15.59

Sub - Total for B 51.19


C. Total (A + B) 362.96
D. Output per hour = 10.00000 sq.m.
E. Direct Unit Cost (C ÷ D) 36.30
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Pavement Markings (White) lit. 1.00 450.00 450.00


Miscellaneous (5% of above) 22.50

0.33 lit./sq.m. (1.05) = 1.0398, say 1.00 lit./sq.m.

Sub - Total for F 472.50


G. Direct Unit Cost (E + F) 508.80
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 45.79
I. Contractor's Profit (CP) 8% of G 40.70
J. Value Added Tax (VAT) 12% of (G + H + I) 71.43
K. Total Unit Cost (G + H + I + J) 666.73
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 606(2)a Pavement Markings (Reflectorized Thermoplastic) - White


Unit of Measurement : sq.m.
Output per hour : 10.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Skilled Laborer 1 1 79.70 79.70
c. Laborer 2 1 61.44 122.88

Sub - Total for A 311.77


Name and Capacity No of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Cargo Truck (5 T) 1 0.05 712.00 35.60


Minor Tools (10% of Labor) 31.18 31.18

Sub - Total for B 66.78


C. Total (A + B) 378.55
D. Output per hour = 10.00000 sq.m.
E. Direct Unit Cost (C ÷ D) 37.85
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Reflectorized Traffic Paint (White) lit. 1.00 450.00 450.00


Miscellaneous (5% of above) 22.50 22.50

0.33 lit./sq.m. (1.05) = 1.0398, say 1.00 lit./sq.m.

Sub - Total for F 472.50


G. Direct Unit Cost (E + F) 510.35
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 45.93
I. Contractor's Profit (CP) 8% of G 40.83
J. Value Added Tax (VAT) 12% of (G + H + I) 71.65
K. Total Unit Cost (G + H + I + J) 668.77

DETAILED UNIT PRICE ANALYSIS (DUPA)


Item No./Description : 606(2)b Pavement Markings (Reflectorized Thermoplastic) - Yellow
Unit of Measurement : sq.m.
Output per hour : 10.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Skilled Laborer 1 1 79.70 79.70
c. Laborer 2 1 61.44 122.88

Sub - Total for A 311.77


Name and Capacity No of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Cargo Truck (5 T) 1 0.05 712.00 35.60


Minor Tools (10% of Labor) 31.18 31.18

Sub - Total for B 66.78


C. Total (A + B) 378.55
D. Output per hour = 10.00000 sq.m.
E. Direct Unit Cost (C ÷ D) 37.85
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Reflectorized Traffic Paint (Yellow) lit. 1.00 475.00 475.00


Miscellaneous (5% of above) 23.75 23.75

0.33 lit./sq.m. (1.05) = 1.0398, say 1.00 lit./sq.m.

Sub - Total for F 498.75


G. Direct Unit Cost (E + F) 536.60
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 48.29
I. Contractor's Profit (CP) 8% of G 42.93
J. Value Added Tax (VAT) 12% of (G + H + I) 75.34
K. Total Unit Cost (G + H + I + J) 703.17

DETAILED UNIT PRICE ANALYSIS (DUPA)


Item No./Description : 607 Reflective Pavement Studs (4" RPM)
Unit of Measurement : ea.
Output per hour : 10.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Laborer 3 1 61.44 184.32

Sub - Total for A 293.51


Name and Capacity No of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Drill, CP-8 with attachment 1 1 201.25 201.25


b. Cargo Truck (5 T) 1 0.25 712.00 178.00
c. Compressor (20 Hp) 1 1 189.00 189.00
Minor Tools (5% of Labor) 14.68 14.68

Sub - Total for B 582.93


C. Total (A + B) 876.44
D. Output per hour = 10.00000 ea.
E. Direct Unit Cost (C ÷ D) 87.64
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Reflective Stud Catcheye Raised Surface pc. 1 3,465.00 3,465.00


100mm x 100mm (type depends on the req.)
b. Concrete Epoxy A & B lit. 0.012 1,200.00 14.40

Sub - Total for F 3,479.40


G. Direct Unit Cost (E + F) 3,567.04
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 321.03
I. Contractor's Profit (CP) 8% of G 285.36
J. Value Added Tax (VAT) 12% of (G + H + I) 500.81
K. Total Unit Cost (G + H + I + J) 4,674.25

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 612(1) Reflectorized Thermoplastic Pavement Markings (White)


Unit of Measurement : sq.m.
Output per hour : 25.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Skilled Laborer 2 1 79.70 159.40
c. Laborer 6 1 61.44 368.64

Sub - Total for A 637.23


Name and Capacity No of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Cargo Truck/Delivery Truck (5 T) 1 1 712.00 712.00


b. Applicator Machine 1 1 93.75 93.75
c. Kneading Machine 1 1 187.50 187.50
Minor Tools (10 % of Labor) 63.72 63.72

Sub - Total for B 1,056.97


C. Total (A + B) 1,694.20
D. Output per hour = 25.00000 sq.m.
E. Direct Unit Cost (C ÷ D) 67.77
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Thermoplastic Paint (White) bag 0.325 1,565.00 508.63


b. Glass Beads bag 0.033 650.00 21.45
c. Primer liter 0.120 160.00 19.20
d. LPG (50 kg.) cyl. 0.004 3,800.00 15.20
e. LPG (12 kg.) cyl. 0.002 735.00 1.47
f. Calsumine kg. 0.125 3.00 0.38
Miscellaneous (5% of Materials) 28.32 28.32

Sub - Total for F 594.64


G. Direct Unit Cost (E + F) 662.40
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 59.62
I. Contractor's Profit (CP) 8% of G 52.99
J. Value Added Tax (VAT) 12% of (G + H + I) 93.00
K. Total Unit Cost (G + H + I + J) 868.01

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 612(2) Reflectorized Thermoplastic Pavement Markings (Yellow)


Unit of Measurement : sq.m.
Output per hour : 25.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Skilled Laborer 2 1 79.70 159.40
c. Laborer 6 1 61.44 368.64

Sub - Total for A 637.23


Name and Capacity No of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Cargo Truck/Delivery Truck (5 T) 1 1 712.00 712.00


b. Applicator Machine 1 1 93.75 93.75
c. Kneading Machine 1 1 187.50 187.50
Minor Tools (10 % of Labor) 63.72 63.72

Sub - Total for B 1,056.97


C. Total (A + B) 1,694.20
D. Output per hour = 25.00000 sq.m.
E. Direct Unit Cost (C ÷ D) 67.77
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Thermoplastic Paint (Yellow)) bag 0.325 1,780.00 578.50


b. Glass Beads bag 0.033 650.00 21.45
c. Primer liter 0.120 175.00 21.00
d. LPG (50 kg.) cyl. 0.004 3,800.00 15.20
e. LPG (12 kg.) cyl. 0.002 735.00 1.47
f. Calsumine kg. 0.125 3.00 0.38
Miscellaneous (5% of Materials) 31.90 31.90

Sub - Total for F 669.89


G. Direct Unit Cost (E + F) 737.66
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 66.39
I. Contractor's Profit (CP) 8% of G 59.01
J. Value Added Tax (VAT) 12% of (G + H + I) 103.57
K. Total Unit Cost (G + H + I + J) 966.63

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 613 Concrete Joint Sealant (Hot Poured Elastic and Cold-Applied Types)
Unit of Measurement : kg.
Output per hour : 20.00
.
Designation No. of Person No. of Hours Hourly Rate Amount
A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Laborer 6 1 61.44 368.64

Sub - Total for A 477.83


Name and Capacity No of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Asphalt Kettle/Drum 1 1 10.00 10.00


Minor Tools (5% of Labor) 23.89 23.89

Sub - Total for B 33.89


C. Total (A + B) 511.72
D. Output per hour = 20.0000 kg.
E. Direct Unit Cost (C ÷ D) 25.59
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Blown Asphalt kg. 1.05 250.00 262.50


Miscellaneous (5% of Materials) 13.13 13.13

Sub - Total for F 275.63


G. Direct Unit Cost (E + F) 301.21
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 27.11
I. Contractor's Profit (CP) 8% of G 24.10
J. Value Added Tax (VAT) 12% of (G + H + I) 42.29
K. Total Unit Cost (G + H + I + J) 394.71

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 622(1)a Bio-Engineering Solutions (Coco-net)


Unit of Measurement : sq.m.
Output per hour : 50.00

Designation No. of Person No. of Hours Hourly Rate Amount


Designation No. of Person No. of Hours Hourly Rate Amount
A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Laborer 8 1 61.44 491.52

Sub - Total for A 600.71


Name and Capacity No of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Water Truck (1000 gal.) 1 0.25 1,065.00 266.25


Minor Tools (10% of Labor) 60.07 60.07

Sub - Total for B 326.32


C. Total (A + B) 927.03
D. Output per hour = 50.0000 sq.m.
E. Direct Unit Cost (C ÷ D) 18.54
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Erosion Control Net CGN 400 w/ 5 % wastage sq.m. 1.05 110.00 115.50
(Price includes bamboo pegs)

Sub - Total for F 115.50


G. Direct Unit Cost (E + F) 134.04
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 12.06
I. Contractor's Profit (CP) 8% of G 10.72
J. Value Added Tax (VAT) 12% of (G + H + I) 18.82
K. Total Unit Cost (G + H + I + J) 175.65

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 622(1)b Bio-Engineering Solutions (Coco-net)


Unit of Measurement : sq.m.
Output per hour : 50.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor
a. Construction Foreman 1 1 109.19 109.19
b. Laborer 8 1 61.44 491.52

Sub - Total for A 600.71


Name and Capacity No of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Water Truck (1000 gal.) 1 0.25 1,065.00 266.25


Minor Tools (10% of Labor) 60.07 60.07

Sub - Total for B 326.32


C. Total (A + B) 927.03
D. Output per hour = 50.0000 sq.m.
E. Direct Unit Cost (C ÷ D) 18.54
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Erosion Control Net CGN 700 w/ 5 % wastage sq.m. 1.05 156.00 163.80
(Price includes bamboo pegs)

Sub - Total for F 163.80


G. Direct Unit Cost (E + F) 182.34
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 16.41
I. Contractor's Profit (CP) 8% of G 14.59
J. Value Added Tax (VAT) 12% of (G + H + I) 25.60
K. Total Unit Cost (G + H + I + J) 238.94

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 622(2)a Bio-Engineering Solutions (Coco-logs/Fascine)


Unit of Measurement : l.m.
Output per hour : 15.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor
a. Construction Foreman 1 1 109.19 109.19
b. Laborer 8 1 61.44 491.52

Sub - Total for A 600.71


Name and Capacity No of Units No. of Hours Hourly Rate Amount
B. Equipment

Minor Tools (10% of Labor) 60.07 60.07

Sub - Total for B 60.07


C. Total (A + B) 660.78
D. Output per hour = 15.0000 l.m.
E. Direct Unit Cost (C ÷ D) 44.05
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Coco Fiber Roll (CGR 200) l.m. 1.05 388.00 407.40


(Price includes nylon ropes and live stakes)

Sub - Total for F 407.40


G. Direct Unit Cost (E + F) 451.45
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 40.63
I. Contractor's Profit (CP) 8% of G 36.12
J. Value Added Tax (VAT) 12% of (G + H + I) 63.38
K. Total Unit Cost (G + H + I + J) 591.58

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 622(2)b Bio-Engineering Solutions (Coco-logs/Fascine)


Unit of Measurement : l.m.
Output per hour : 15.00

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Laborer 8 1 61.44 491.52

Sub - Total for A 600.71


Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

Minor Tools (10% of Labor) 60.07 60.07

Sub - Total for B 60.07


C. Total (A + B) 660.78
D. Output per hour = 15.0000 l.m.
E. Direct Unit Cost (C ÷ D) 44.05
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. Coco Fiber Roll (CGR 300) l.m. 1.05 509.00 534.45


(Price includes nylon ropes and live stakes)

Sub - Total for F 534.45


G. Direct Unit Cost (E + F) 578.50
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 52.07
I. Contractor's Profit (CP) 8% of G 46.28
J. Value Added Tax (VAT) 12% of (G + H + I) 81.22
K. Total Unit Cost (G + H + I + J) 758.07

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 622(3)a Bio-Engineering Solutions (Vegetation)


Unit of Measurement : sq.m.
Output per hour : 62.50

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Laborer 2 1 61.44 122.88
Sub - Total for A 232.07
Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Hydroseeding Machine 1 1 952.00 952.00


b. Water Truck (1000 gal.) 1 1 1,065.00 1,065.00
(including maintenance time)

Sub - Total for B 2,017.00


C. Total (A + B) 2,249.07
D. Output per hour = 62.500 sq.m.
E. Direct Unit Cost (C ÷ D) 35.99
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. Grass Cover sq.m. 1.05 45.00 47.25


(Price includes grass seeds, mulch, cocopeat
& binding agent for hydroseeding)

Sub - Total for F 47.25


G. Direct Unit Cost (E + F) 83.24
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 7.49
I. Contractor's Profit (CP) 8% of G 6.66
J. Value Added Tax (VAT) 12% of (G + H + I) 11.69
K. Total Unit Cost (G + H + I + J) 109.07

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 622(3)b Bio-Engineering Solutions (Vegetation)


Unit of Measurement : sq.m.
Output per hour : 35.00

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Laborer 8 1 61.44 491.52
Sub - Total for A 600.71
Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Water Truck (1000 gal.) 1 0.50 1,065.00 532.50


Minor Tools (10% of Labor) 60.07 60.07

Sub - Total for B 592.57


C. Total (A + B) 1,193.28
D. Output per hour = 35.0000 sq.m.
E. Direct Unit Cost (C ÷ D) 34.09
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. Vetiver Grass System sq.m. 1.05 70.00 73.50


(Price includes cocopeat fertilizer)

Sub - Total for F 73.50


G. Direct Unit Cost (E + F) 107.59
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 9.68
I. Contractor's Profit (CP) 8% of G 8.61
J. Value Added Tax (VAT) 12% of (G + H + I) 15.11
K. Total Unit Cost (G + H + I + J) 140.99
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : SPL 3 Tree Planting


Unit of Measurement : pc.
Output per hour : 60.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Laborer 10 1 61.44 614.40

Sub - Total for A 723.59


Name and Capacity No of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Cargo Truck (5 T) 1 0.25 712.00 178.00


b. Water Truck (1000 gal.) 1 0.25 1,065.00 266.25
Minor Tools (10% of Labor) 72.36 72.36

Sub - Total for B 516.61


C. Total (A + B) 1,240.20
D. Output per hour = 60.0000 pc.
E. Direct Unit Cost (C ÷ D) 20.67
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Saplings pc. 1 50.00 50.00


b. Coco Lumber bd.ft. 8 20.00 160.00
c. Assorted CWN (1 kg./100 bd.ft.) kg. 0.08 68.00 5.44
d. Fertilizers kg. 0.10 50.00 5.00

Sub - Total for F 220.44


G. Direct Unit Cost (E + F) 241.11
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 21.70
I. Contractor's Profit (CP) 8% of G 19.29
J. Value Added Tax (VAT) 12% of (G + H + I) 33.85
K. Total Unit Cost (G + H + I + J) 315.95
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : SPL 3 Tree Planting


Unit of Measurement : pc.
Output per hour : 60.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Laborer 10 1 61.44 614.40

Sub - Total for A 723.59


Name and Capacity No of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Cargo Truck (5 T) 1 0.25 712.00 178.00


b. Water Truck (1000 gal.) 1 0.25 1,065.00 266.25
Minor Tools (10% of Labor) 72.36 72.36

Sub - Total for B 516.61


C. Total (A + B) 1,240.20
D. Output per hour = 60.0000 pc.
E. Direct Unit Cost (C ÷ D) 20.67
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Saplings pc. 1 50.00 50.00


b. Fertilizers kg. 0.10 26.00 2.60

Sub - Total for F 52.60


G. Direct Unit Cost (E + F) 73.27
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 6.59
I. Contractor's Profit (CP) 8% of G 5.86
J. Value Added Tax (VAT) 12% of (G + H + I) 10.29
K. Total Unit Cost (G + H + I + J) 96.01

DETAILED UNIT PRICE ANALYSIS (DUPA)


Item No./Description : SPL 2 Crack and Seat
Unit of Measurement : sq.m.
Output per hour : 35.00

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Skilled Laborer 1 1 79.70 79.70
c. Laborer 2 1 61.44 122.88

Sub - Total for A 311.77


Name and Capacity No of Units No. of Hours Rental Rate Amount

B. Equipment

a. Backhoe w/ Breaker (0.80 cu.m.) 1 1.00 2,074.95 2,074.95


b. Vibratory Roller (10 m.t.), SP56 1 0.75 1,507.00 1,130.25

Sub - Total for B 3,205.20


C. Total (A + B) 3,516.97
D. Output per hour = 35.0000 sq.m.
E. Direct Unit Cost (C ÷ D) 100.48
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

Sub - Total for F -


G. Direct Unit Cost (E + F) 100.48
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 9.04
I. Contractor's Profit (CP) 8% of G 8.04
J. Value Added Tax (VAT) 12% of (G + H + I) 14.11
K. Total Unit Cost (G + H + I + J) 131.68

DETAILED UNIT PRICE ANALYSIS (DUPA)


Item No./Description : SPL 2 Crack and Seat
Unit of Measurement : sq.m.
Output per hour : 30.00

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Skilled Laborer 1 1 79.70 79.70
c. Laborer 2 1 61.44 122.88

Sub - Total for A 311.77


Name and Capacity No of Units No. of Hours Rental Rate Amount

B. Equipment

a. Arrow Master D 500 1 1.00 1,485.84 1,485.84


(Additional 35% for Oil and Lubricants)
b. Vibratory Roller (10 m.t.), SP56 1 0.75 1,507.00 1,130.25

Sub - Total for B 2,616.09


C. Total (A + B) 2,927.86
D. Output per hour = 30.0000 sq.m.
E. Direct Unit Cost (C ÷ D) 97.60
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

Sub - Total for F -


G. Direct Unit Cost (E + F) 97.60
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 8.78
I. Contractor's Profit (CP) 8% of G 7.81
J. Value Added Tax (VAT) 12% of (G + H + I) 13.70
K. Total Unit Cost (G + H + I + J) 127.89

You might also like