A P P E N D I X IV UR-P1

SCHEDULE OF UNIT RATES

The prices and rates quoted in this Schedule of Unit Rates shall be used for
any variation to the Contract, whether additional or deduction to the quantities
to be installed.

The prices and rates shall be fixed for the duration of the Contract and shall
include for all fees, duties, taxes and other charges payable to the
Authorities for the supply, delivery, installation, testing and commissioning,
warranty for the stated Maintenance Period and all other requirements as per
the Specification, Drawings and Conditions of Contract.

......................................
Company Chop & Signature

P1496/1 – Piped Services Installation to Proposed Erection of A Block of 8 Storey


Hotel Development (132 Rooms) With 2 Basement Carparks, Sky Terrace
and A Rooftop Garden at TS19-00411V And TS19-00412P (PT)(SL)
at 189 Selegie Road (Rochor Planning Area)
PIPED SERVICES INSTALALTION
SCHEDULE OF UNIT RATE – CONTD UR-P2

1.00 To supply, install and commission the following pipework inclusive of


all jointing, supports, painting, provision of any opening and making good,
chasing in walls or floors, etc. as per Specification, per metre run.

The unit rate quoted shall include for all short lengths, wastages,
all fittings, e.g. tees, elbows or bends, reducers, couplings, flanges,
etc. to complete the pipework installations.

Ductile Iron Galvanised uPVC to


Size to BS 4772 Iron to BS uPVC to SS SS 141/BS
(mm) (Class K9) 1387/SS17 2131 BS 4514 3505

50

65

80

100

125

150

200

Note : * Price to be inclusive of all excavation, making good,


concrete bases, haunching, etc.

..............................
Company Chop & Signature

P1496/1 – Piped Services Installation to Proposed Erection of A Block of 8 Storey


Hotel Development (132 Rooms) With 2 Basement Carparks, Sky Terrace
and A Rooftop Garden at TS19-00411V And TS19-00412P (PT)(SL)
at 189 Selegie Road (Rochor Planning Area)
PIPED SERVICES INSTALLATION
SCHEDULE OF UNIT RATE - CONTD UR-P3

2.00 To supply, install and commission the following pipework inclusive


of all jointing, supports, painting, provision of any opening and
making good, chasing in walls or floors, etc. as per Specification,
per metre run.

The unit rate quoted shall include for all short lengths, wastages,
all fittings, e.g. tees, elbows or bends, reducers, couplings,
flanges, etc. to complete the pipework installations.

Ductile Iron Vitrified C I to Hubless


Size to BS 4772 Clay Pipe SS 33/BS Cast Iron
(mm) (Cement-Lined) (BS 65) 416 Pipe

50

65

80

100

125

150

200

Note : * Price to be inclusive of all excavation, making good,


concrete bases, haunching, etc.

.............................
Company Chop & Signature

P1496/1 – Piped Services Installation to Proposed Erection of A Block of 8 Storey


Hotel Development (132 Rooms) With 2 Basement Carparks, Sky Terrace
and A Rooftop Garden at TS19-00411V And TS19-00412P (PT)(SL)
at 189 Selegie Road (Rochor Planning Area)
PIPED SERVICES INSTALLATION
SCHEDULE OF UNIT RATE - CONTD UR-P4

3.00 To supply, install and commission the following pipework inclusive of


all jointing, supports, painting, provision of any opening and making
good, chasing in walls or floors, etc. as per Specification, per metre
run.

The unit rate quoted shall include for all short lengths, wastages,
all fittings, e.g. tees, elbows or bends, reducers, couplings,
flanges, etc. to complete the pipework installations.

Size Copper Copper to Copper to Stainless Copper Copper


(mm) to BS EN BS EN BS 2871 Steel to to to (PE)
1057 1057 (Chromed) BS 4127 (PPR) Pipe
(Table X) (Table Y) Pipe

15

20

25

32

40

50

65

75

80

100

150

............................
Company Chop & Signature
P1496/1 – Piped Services Installation to Proposed Erection of A Block of 8 Storey
Hotel Development (132 Rooms) With 2 Basement Carparks, Sky Terrace
and A Rooftop Garden at TS19-00411V And TS19-00412P (PT)(SL)
at 189 Selegie Road (Rochor Planning Area)
PIPED SERVICES INSTALLATION
SCHEDULE OF UNIT RATE - CONTD UR-P5

4.00 To supply and install the following valves inclusive of jointing,


painting, supports, etc. as per Specification.

Size Gate Solenoid Sluice Check Globe


(mm) Valve Valve Valve Valve Valve

15

20

25

32

40

50

65

75

100

150

200

...........................
Company Chop & Signature

P1496/1 – Piped Services Installation to Proposed Erection of A Block of 8 Storey


Hotel Development (132 Rooms) With 2 Basement Carparks, Sky Terrace
and A Rooftop Garden at TS19-00411V And TS19-00412P (PT)(SL)
at 189 Selegie Road (Rochor Planning Area)
PIPED SERVICES INSTALLATION
SCHEDULE OF UNIT RATE - CONTD UR-P6

5.00 To install the following sanitary fittings and equipments


(inclusive of all connections, necessary pipework and fittings,
etc.) as per specification.

.01 Wash basin c/w mixer $....... per unit

.02 Wash basin c/w delay action tap $....... per unit

.03 Long bath c/w mixer $....... per unit

.04 Shower roses c/w mixer $....... per unit

.05 Sink c/w mixer $....... per unit

.06 WCs squatting type c/w cistern $....... per unit

.07 WCs squatting type c/w flush valve $....... per unit

.08 WCs Pedestal type c/w cistern $....... per unit

.09 WCs Pedestal type c/w flush valve $....... per unit

.10 Slab urinal per 600mm length $....... per unit

.11 Wall hung urinal c/w cistern $....... per unit

.12 Wall hung urinal c/w flush valve $....... per unit

.13 Shower Tray $....... per unit

.14 Hair Dryer $....... per unit

.15 Hand Dryer $....... per unit

...........................
Company Chop & Signature

P1496/1 – Piped Services Installation to Proposed Erection of A Block of 8 Storey


Hotel Development (132 Rooms) With 2 Basement Carparks, Sky Terrace
and A Rooftop Garden at TS19-00411V And TS19-00412P (PT)(SL)
at 189 Selegie Road (Rochor Planning Area)
PIPED SERVICES INSTALLATION
SCHEDULE OF UNIT RATE - CONTD UR-P7

5.00 .16 Toilet Paper Holder $....... per unit

.17 Soap Holder $....... per unit

.18 Towel rail/ring $....... per unit

.19 Bib Tap $....... per unit

.20 Robe Hook $....... per unit

.21 Bath Towel Holder $....... per unit

.22 Others $....... per unit

6.00 To supply and install the following sanitary fittings (inclusive of all
connections necessary pipework and fittings) as per Specification.

.01 Floor Trap 300 x 300 $........ per unit


or Floor Drain
150 x 100 $........ per unit

100 x 100 $........ per unit

100 x 75 $........ per unit

75 x 75 $........ per unit

.02 Bidet Trap $........ per unit

.03 Urinal Trap $........ per unit

.04 Outlet Grating 300 x 300 $........ per unit


or waste outlet

150 x 150 $........ per unit

100 x 100 $........ per unit

75 x 75 $........ per unit

75 x 50 $........ per unit

50 X 50 $........ per unit

.05 Garage Gully Trap $........ per unit

..........................
Company Chop & Signature

P1496/1 – Piped Services Installation to Proposed Erection of A Block of 8 Storey


Hotel Development (132 Rooms) With 2 Basement Carparks, Sky Terrace
and A Rooftop Garden at TS19-00411V And TS19-00412P (PT)(SL)
at 189 Selegie Road (Rochor Planning Area)
PIPED SERVICES INSTALLATION
SCHEDULE OF UNIT RATE - CONTD UR-P8

7.00 .01 To supply and install inspection chamber/manhole (inclusive


of excavation, connection, cover, cleaning up, etc.)

Depth (mm) Cost Per Unit (S$)

750 - 900

901 - 1200

1201 - 1500

1501 - 2000

2001 - 2500

2501 - 3000

3001 - 3500

3501 - 4000

4001 - 4500

4501 - 5000

5001 - 5500

5501 - 6000

6001 - 6500

.02 To supply and install cover and frame (SS30) for inspection
chamber/manhole.

.1 Light Duty $........ per no.

.2 Medium Duty $........ per no.

.3 Heavy Duty $........ per no.

.............................
Company Chop & Signature

P1496/1 – Piped Services Installation to Proposed Erection of A Block of 8 Storey


Hotel Development (132 Rooms) With 2 Basement Carparks, Sky Terrace
and A Rooftop Garden at TS19-00411V And TS19-00412P (PT)(SL)
at 189 Selegie Road (Rochor Planning Area)
PIPED SERVICES INSTALLATION
SCHEDULE OF UNIT RATE - CONTD UR-P9

8.00 To supply and install (including excavation, joints, concreting,


etc.) for :

.01 Tumbling bay not exceeding 1.5m $........ per unit

.02 Backdrop not exceeding

.1 2m $........ per unit

.2 2.5m $........ per unit

.3 3.0m $........ per unit

.4 3.5m $........ per unit

9.00 100mm Bakau Piles (installed in position) as per Specification.

.01 1.8m long $........ per unit

.02 3.6m long $........ per unit

.03 5.4m long $........ per unit

.04 7.2m long $........ per unit

.05 9.0m long $........ per unit

.06 Per metre length additional $........ per unit


over 9.0m

........................
Company Chop & Signature

P1496/1 – Piped Services Installation to Proposed Erection of A Block of 8 Storey


Hotel Development (132 Rooms) With 2 Basement Carparks, Sky Terrace
and A Rooftop Garden at TS19-00411V And TS19-00412P (PT)(SL)
at 189 Selegie Road (Rochor Planning Area)
PIPED SERVICES INSTALLATION
SCHEDULE OF UNIT RATES - CONTD UR-P10

10.00 To supply and install the following :

Pilot
Operated Type Conventional Type

.01 Ball Float Valve

32 mm $............ $...............

50 mm $............ $..............

80 mm $............ $...............

100mm $............ $...............

150mm $............ $...............

.02 Pressure reducing valve

100mm $............

150mm $............

.03 Flush Valve

20 mm $............

25 mm $............

32 mm $............

.04 Flow Control Valve

20 mm $............

25 mm $............

32 mm $............

40 mm $............

50 mm $............

.05 Strainer

50 mm $............

65 mm $............

75 mm $............

100 mm $............

150 mm $............

................................
Company Chop & Signature

P1496/1 – Piped Services Installation to Proposed Erection of A Block of 8 Storey


Hotel Development (132 Rooms) With 2 Basement Carparks, Sky Terrace
and A Rooftop Garden at TS19-00411V And TS19-00412P (PT)(SL)
at 189 Selegie Road (Rochor Planning Area)
PIPED SERVICES INSTALLATION
SCHEDULE OF UNIT RATES - CONTD UR-P11

10.00 To supply and install the following :

.06 Flexible connection

25 mm $............

65 mm $............

80 mm $............

100 mm $............

150 mm $............

.07 Pressure Gauge $............

.08 Constant flow regulator

- 8 litre/min $............

- 12 litre/min $............

.09 20mm tap/hose-bib


c/w padlocked box $............

.10 Pressure reducing


valve c/w pressure $............
gauge

........................
Company Chop & Signature

P1496/1 – Piped Services Installation to Proposed Erection of A Block of 8 Storey


Hotel Development (132 Rooms) With 2 Basement Carparks, Sky Terrace
and A Rooftop Garden at TS19-00411V And TS19-00412P (PT)(SL)
at 189 Selegie Road (Rochor Planning Area)
PIPED SERVICES INSTALLATION
SCHEDULE OF UNIT RATES - CONTD UR-P12

11.00 .01 To supply, install and commission the following PVC insulated cables
in steel conduit c/w conduit, fittings and accessories, chasing (if
necessary) as per Specification per metre run.

Cable Type of Type of Circuit


Size Cables Wiring
(mm) Method SPN TP TPN

PVC c/w Surface


e.c.c.
Concealed
1.5
PVC/PVC Surface
c/w
e.c.c. Concealed

PVC c/w Surface


e.c.c.
Concealed
2.5
PVC/PVC Surface
c/w
e.c.c. Concealed

PVC c/w Surface


e.c.c.
Concealed
4.0
PVC/PVC Surface
c/w
e.c.c. Concealed

PVC c/w Surface


e.c.c.
Concealed
6.0
PVC/PVC Surface
c/w
e.c.c. Concealed

.............................
Company Chop & Signature

P1496/1 – Piped Services Installation to Proposed Erection of A Block of 8 Storey


Hotel Development (132 Rooms) With 2 Basement Carparks, Sky Terrace
and A Rooftop Garden at TS19-00411V And TS19-00412P (PT)(SL)
at 189 Selegie Road (Rochor Planning Area)
PIPED SERVICES INSTALLATION
SCHEDULE OF UNIT RATES - CONTD UR-P13

11.00 .02 To supply, install and commission the following PVC insulated cables
in steel conduit c/w conduit, fittings and accessories, chasing (if
necessary) as per Specification per metre run - Contd

Cable Type of Type of Circuit


Size Cables Wiring
(mm) Method SPN TP TPN

PVC c/w Surface


e.c.c.
Concealed
10
PVC/PVC Surface
c/w
e.c.c. Concealed

PVC c/w Surface


e.c.c.
Concealed
16
PVC/PVC Surface
c/w
e.c.c. Concealed

PVC c/w Surface


e.c.c.
Concealed
25
PVC/PVC Surface
c/w
e.c.c. Concealed

PVC c/w Surface


e.c.c.
Concealed
35
PVC/PVC Surface
c/w
e.c.c. Concealed

Concealed

.............................
Company Chop & Signature

P1496/1 – Piped Services Installation to Proposed Erection of A Block of 8 Storey


Hotel Development (132 Rooms) With 2 Basement Carparks, Sky Terrace
and A Rooftop Garden at TS19-00411V And TS19-00412P (PT)(SL)
at 189 Selegie Road (Rochor Planning Area)
PIPED SERVICES INSTALLATION
SCHEDULE OF UNIT RATES - CONTD UR-P14

12.00 To supply and install the following sizes of water heater inclusive
of all connections, valves, necessary pipeworks fittings, bracket,
vacuum breaker, wiring, etc. as per specification.

Supply Install

.01 23 litres $...... per unit $....... per unit

.02 38 litres $...... per unit $....... per unit

.03 56 litres $...... per unit $....... per unit

.04 76 litres $...... per unit $....... per unit

13.00 To supply labour employed for day work authorized by Client/Architect/


M&E Engineer in writing.

Type Hour/Rate

.01 Unskilled Labour $............

.02 Semi-Skilled Labour $............

.03 Skilled Labour $............

.04 Overseer working with the men $............

14.00 To supply and install the following sizes of Gas water heater inclusive
of all connection, valves, necessary pipeworks fittings, bracket, wiring
control panel, etc. as per specification.

.01 10 litres per min $............

.02 20 litres per min $............

.03 24 litres per min $............

.04 26 litre per min $............

.05 32 litres per min $............

............................
Company Chop & Signature

P1496/1 – Piped Services Installation to Proposed Erection of A Block of 8 Storey


Hotel Development (132 Rooms) With 2 Basement Carparks, Sky Terrace
and A Rooftop Garden at TS19-00411V And TS19-00412P (PT)(SL)
at 189 Selegie Road (Rochor Planning Area)
PIPED SERVICES INSTALLATION
SCHEDULE OF UNIT RATES - CONTD UR-P15

15.00 To supply, install and commission the following pipework inclusive of


all jointing, supports & hangers, and painting, provision of any opening,
chasing in walls or floors and making good, etc. as per Specification
per metre run :

The unit rate quoted shall include for all short lengths, all fittings,
e.g. tees, elbows or bends, reducers, couplings, flanges, etc.to
complete the pipework installation.

Galvd. Steel Steel to Steel to


Size To BS 1387 BS 1387 BS 3601 API
(mm) (Heavy Grade) Schedule
40
Med Heavy Med Heavy Galvd Black
Grade Grade Grade Grade Steel

20

25

32

40

50

65

80

100

150

200

Note :

* Price to be inclusive of all excavation, making good


concrete bases and haunching, etc.

............................
Company Chop & Signature

P1496/1 – Piped Services Installation to Proposed Erection of A Block of 8 Storey


Hotel Development (132 Rooms) With 2 Basement Carparks, Sky Terrace
and A Rooftop Garden at TS19-00411V And TS19-00412P (PT)(SL)
at 189 Selegie Road (Rochor Planning Area)

You might also like