Professional Documents
Culture Documents
Yang Et Al-2010-Mass Behaviour of Embedded Improved Soil Raft in An Excavation
Yang Et Al-2010-Mass Behaviour of Embedded Improved Soil Raft in An Excavation
Volume 164 Issue GE1 Geotechnical Engineering 164 February 2011 Issue GE1
Pages 11–25 doi: 10.1680/geng.9.00078
Mass behaviour of embedded improved Paper 900078
soil raft in an excavation Received 26/09/2009 Accepted 17/02/2010
Published online 06/01/2011
Yang, Tan and Leung Keywords: excavation/grouting/mathematical modelling
j
1 j
2 j
3
In deep excavation in soft soils, a layer of soil below formation level is often improved to stabilise the excavation.
The improvement, usually by deep cement mixing or jet-grout piling, will result in the construction of a raft of
overlapping short columns (termed an ‘embedded improved soil raft’). Soil investigation carried out will usually
provide information on vertical cores from such columns. But during excavation, the columns are loaded laterally by
the inward-moving retaining wall: thus the mobilised mass properties in the lateral direction are of importance in the
design. This paper examines the mechanisms of how mass properties are mobilised and their relation to the
elemental properties, the variation of properties within a column, and how the columns are arranged. The analysis
and the simulation of a reported field case history show that for soil-cement columns arranged just in contact with
each other, the mobilised mass stiffness is less than 28% of the elemental material stiffness. The analysis also shows
that the properties of the outer layer have a greater impact on the mass behaviour of the embedded improved soil
raft than those of the inner layer, and this ought to be considered in any site investigations.
Notation strutting cannot be used. To control the wall deflection and its
c cohesion yield stress associated ground movements effectively, one common approach
E Young’s modulus is to improve a layer of soft soils beneath the formation level. A
L overlap parameter common approach to improve the soft soil, as shown in Figure
n total number of samples 1(a), is to mix the in situ soft soils with cement, which can be
R column radius introduced into the ground either by the deep cement mixing
V coefficient of variance (DCM) method or the jet-grouted piling (JGP) method (Porbaha
Poisson’s ratio et al., 1999; Shibazaki, 2003). Both methods produce short soil-
normal stress cement columns that overlap with each other to form a continu-
f direct shear strength ously improved composite ground, which acts like a strut below
friction angle the formation level to help restrain the inward movement of the
ł dilation angle retaining wall. In this paper, this composite ground is termed the
embedded improved soil raft to emphasise that the improvement
1. Introduction is below the formation level, and is over a wide area rather than
Deep excavations in soft soils in urban areas often face serious in strips like a strut. Applications of such an embedded improved
challenges in the control of induced ground movement on nearby soil raft system to support deep excavation have been reported by
structures to limit its adverse impact (Tan and Shirlaw, 2000). many researchers (Hsi and Yu, 2005; O’Rourke and McGinn,
Typically, such deep excavations are supported by diaphragm 2006; O’Rourke and O’Donnell, 1997; Wong and Poh, 2000).
walls or sheet-pile walls. The imbalance caused by the removal of
soils will cause wall deflection, often with the maximum deflec- In construction, to monitor the quality of the embedded improved
tion occurring below the formation level, where conventional soil raft once constructed, vertically cored samples from indivi-
11
Geotechnical Engineering Mass behaviour of embedded improved
Volume 164 Issue GE1 soil raft in an excavation
Yang, Tan and Leung
sive strength and the Young’s modulus for design use. However,
Excavation in reality, when the improved soil raft is called upon to restrain
the retaining wall from moving in, the resistance comes from the
composite strength and stiffness in the horizontal direction, which
are affected by the imperfections and heterogeneity in the
horizontal direction, as well as by how the columns are arranged
and overlapped with each other. The mobilised properties of such
an embedded improved soil raft, used to stabilise an excavation,
is not going to be dependent on the elemental properties alone.
Once it is realised that the restraint comes from the composite
strength and stiffness in the horizontal direction, the non-
Soil raft uniformities in the horizontal direction, even within the same
improved soil column, become an important factor in the
estimation of the composite properties. This aspect, which to date
has seldom been discussed, is the focus of the present paper.
Contact critical
2. Variability in improved soil-cement
columns
Figure 2 shows the distribution of direct shear strengths of
samples cored from deep mixing columns at three locations at a
(a) site in Tokyo (Kawasaki et al., 1984). The direct shear strengths
were replotted, and the strength distribution along the column
radial direction is shown in Figure 3. It can be seen that,
generally, the outer layers have lower strength than the inner
layers. When these columns are arranged and subjected to loads
Embankment
that act on them horizontally, these variations will have an
Fill
important impact on the mobilised properties. In another site in
Singapore, a hybrid system called RAS-JET, which has jet open-
ings at the edges of mechanical mixing blades, is used to form
soil-cement columns in the ground. The soil-cement columns
Soil formed by the RAS-JET system have two distinct, concentric
layers in the radial direction: the inner layer formed by mechani-
Potential slip line cal mixing, and the outer one formed by jet grouting. The outer
jet-grouting layer is often stiffer than the inner mechanical mixing
layer. A typical unconfined compressive strength (UCS) profile of
Soil-cement column the RAS-JET soil-cement column is shown in Figure 4.
12
Geotechnical Engineering Mass behaviour of embedded improved
Volume 164 Issue GE1 soil raft in an excavation
Yang, Tan and Leung
(a)
9·1 9·9
25 8·7 8·3 10·6 9·9 11·1
A-13·2
10·3 14·9 14·0
n ⫽ 124 7·8 12·0 15·4 10·2 10·7
15·3
19·2
15·7
τf ⫽ 1262 kN/m2 10·3 12·6 9·8 8·3 11·9 14·9 12·9
11·5
20 11·3
σ ⫽ 279 kN/m2 12·6 14·9 11·4 11·5
Number of samples
10·5 9·6
8·0
13·1 12·4 2·9
A-14·2 11·7 14·4 5·8
11·7 9·1
15·8 12·6
20 n ⫽ 108 11·3 14·7 15·4 16·4 13·0 8·2
τf ⫽ 1267 kN/m2 16·3 12·6 13·6 11·0
10·9 10·3 16·6 14·1 16·0
σ ⫽ 396 kN/m2 14·7 9·1
Number of samples
13
Geotechnical Engineering Mass behaviour of embedded improved
Volume 164 Issue GE1 soil raft in an excavation
Yang, Tan and Leung
2·0
line cuts through the improved ground, such as from an embank-
ment loading, as shown in Figure 1(b). However, the mobilised
mechanics of an embedded improved soil raft during an excava-
tion (Figure 1(a)) are very different. The improved soil raft is
1·5
compressed horizontally as the excavation proceeds; it is also
Normalised strength
3
Well-mixed soil
0
0 0·35 0·70 1·05 1·40
(a)
Distance from column centre: m
Outer layer area ⫽ Inner layer area
Figure 4. Typical unconfined compressive strength profile of a
soil-cement column formed by RAS-JET at Nicoll Highway field
trial, Singapore
14
Geotechnical Engineering Mass behaviour of embedded improved
Volume 164 Issue GE1 soil raft in an excavation
Yang, Tan and Leung
two very stiff columns being pressed together. On the other hand, Soil-cement column
if a weighted average method based on area is used, there would
be no difference between the two cases. This simple example
demonstrates that if such an improved soil is used like a strut in
an excavation to restrain the inward movement of the retaining
wall, then an understanding of how an array of such columns In situ soil
behaves collectively when loaded laterally is important.
15
Geotechnical Engineering Mass behaviour of embedded improved
Volume 164 Issue GE1 soil raft in an excavation
Yang, Tan and Leung
6000
Linear elastic
4000
Stress: kPa
3000
2000
1000
500
Figure 9. The normal stress is normalised by its value at the
centre of the contact area, and the distance from the contact
centre is normalised by the length of the contact path. The
400 normal stress is at a maximum at the centre of the contact area,
and drops to zero at the edge of the contact area. The analytical
solution (Johnson, 1985) to the Hertz contact problem is also
300 shown in this figure, and the near-perfect agreement between the
Stiffness: MPa
Strain: %
perfectly plastic
0·6
0·4
to move vertically. Compressive loading from the neighbouring Analytical solutions
column was modelled by prescribing uniform displacements at 0·2 Numerical results
the top boundary to press the column against a rigid body (HKS,
2003). As noted before, the material model used is an isotropic 0
0 0·2 0·4 0·6 0·8 1·0
linearly elastic model. At the start of the analysis, the bottom was
Normalised distance from contact centre
in point contact with the rigid base, which was fixed in all
degrees of freedom. Intuitively, we expect that as the load is Figure 9. Solutions to Hertz contact problem: numerical
applied, the area of contact will grow from a point to a patch. compared with analytical
The normal stress distribution over the contact area is shown in
16
Geotechnical Engineering Mass behaviour of embedded improved
Volume 164 Issue GE1 soil raft in an excavation
Yang, Tan and Leung
0·40
when the columns are mobilised as a whole to resist the lateral
0·35 loading, the properties of the outer layers are more important. To
Normalised mass stiffness
Figure 11. Von Mises stress contours for Hertz contact problem
17
Geotechnical Engineering Mass behaviour of embedded improved
Volume 164 Issue GE1 soil raft in an excavation
Yang, Tan and Leung
500
Material parameter Stiffer Less stiff
layer layer
200
In a more realistic simulation, a failure criterion ought to be behaviour of the dashed line in Figure 13. So the mass stiffness is
introduced. In this case, the Mohr–Coulomb failure criterion is about 23% of the elemental material stiffness when it starts to
coupled with the elastic model to simulate this failure behaviour. drop as the system is further loaded.
Once the failure criterion is introduced into the elemental
material model, part of each column will undergo yielding once 5.2 Simulation of a reported case history
the shear stresses within the columns reach the elemental material In a deep excavation in Tokyo (Nakagawa et al., 1996), soil-
strength. These yielded parts, if sufficiently large, dominate the cement columns are arranged just in contact with each other to
mass behaviour, and will drastically reduce the mass stiffness form an improved soil layer to stabilise the excavation. The
even though a bigger area has been mobilised, as shown by the authors found that the improved soil layer was much less effective
18
Geotechnical Engineering Mass behaviour of embedded improved
Volume 164 Issue GE1 soil raft in an excavation
Yang, Tan and Leung
0·004 stiffness
H/δ
K⬘h/K h
H/δ
0·50 1·0
0·003
K⬘h/K h
0·001
0 0
0 0·25 0·50 0·75 1·00
D /DB
0
0 0·5 1·0 1·5 2·0
Figure 14. Correlation of depth of excavation with displacement,
Mass strain: %
and K value (reprinted with permission of Taylor & Francis from
0·40 Nakagawa et al., 1996)
19
Geotechnical Engineering Mass behaviour of embedded improved
Volume 164 Issue GE1 soil raft in an excavation
Yang, Tan and Leung
Abaqus model. This special treatment allows lateral forces to be situ soft soils and those of the improved soils based on Nakagawa
transmitted to the nearby soil-cement columns, and at the same et al.’s (1996) reported K values.
time accounts for the interaction with the surrounding soils, albeit
with small inaccuracies introduced. Similar treatment is applied The normalised mass stiffness from the simulation is shown in
to the corner at the right-hand side in Figure 15 to simulate the Figure 16. The mobilised mass stiffness is about 28% of the
constraining effects of the neighbouring row of soil-cement elemental properties of the soil-cement columns, slightly higher
columns. The model is loaded up to 0.33% mass strain, which is than the mobilised mass stiffness of one row of soil-cement
comparable to the mobilised level in the field (Nakagawa et al., columns just in contact with each other, because of the confining
1996). Compared with the model in the previous section, the effects of the surrounding soils and the adjacent columns. This
model as shown in Figure 6(b) will take into account the mobilised mass stiffness is still considerably lower than the
confining effects of the surrounding soils and the adjacent soil- elemental material stiffness. At least a 70% reduction is expected
cement columns. The material properties used for the improved due to such a geometric arrangement alone, in which the uniform
soils and the in situ soils are shown in Table 2. This set of deep cement mixing columns are arranged just in contact with
parameters largely reflects the typical material properties of in each other in a grid in soft soils. Though this is a simple three-
dimensional model of a representative unit, its ability to account
for a large part of the reduction of the mobilised lateral stiffness
from the elemental stiffness of the soil-cement columns is clearly
Material parameter Improved soil In situ soil demonstrated. The soil-cement columns arranged in such a
fashion are able to mobilise only very limited zones near the
Young’s modulus, E: MPa 396 60
contact point when they are laterally loaded. A large portion of
Poisson’s ratio, 0.495 0.495
the column experiences low mobilised stresses, as shown in the
Cohesion yield stress, c: kPa 1980 30
shear stress contours in Figure 15.
Friction angle, : degrees 0 0
Dilation angle, ł: degrees 0 0
As discussed earlier in this paper, soil-cement columns that are
Table 2. Material properties for the simulation of Nakagawa et formed in the field are often not uniform, and tend to show
al.’s (1996) case layered properties. A parametric study is then performed to assess
the effects of layering on the mobilised mass stiffness in the
20
Geotechnical Engineering Mass behaviour of embedded improved
Volume 164 Issue GE1 soil raft in an excavation
Yang, Tan and Leung
1·8 Outer layer: ⫻4 half the distance between the centres of two adjacent columns
1·6 Outer layer: ⫻2 (Figure 6(c)), is introduced to facilitate discussion. A smaller L
Normalised mass stiffness
Uniform columns value means a larger amount of overlap. The columns would be
1·4 Outer layer: ⫻1/2
in point contact if L equalled the column radius R. For the
1·2 Outer layer: ⫻1/4
triangular grid shown in Figure 6(d), L is (ˇ3/2)R, which gives L
1·0 ¼ 0.779 m for R ¼ 0.9 m.
0·8
0·6 Figure 17 shows that, compared with columns arranged to just
touch each other, when the columns are arranged to partly overlap
0·4
each other in a row, the mobilised mass stiffness at a very early
0·2
stage increases much more significantly. For example, the mass
0 stiffness is about 55% of the elemental material stiffness when
0 0·05 0·10 0·15 0·20 0·25 0·30 0·35 0·40
Mass strain: %
the overlap parameter L is 0.850 m. This set of results confirms
the importance of ensuring that such improved soil columns must
Figure 16. Mobilised mass stiffness of the improved soil layer be constructed to have adequate overlapping. To highlight this
(after Nakagawa et al., 1996) difference, Figure 18 compares the stress contours for the case of
columns that are just touching each other with the case where the
columns are overlapping. An examination of the von Mises stress
reported case history. The parametric study here is not a back- contours at 0.02% mass strain (Figure 18) shows that the stresses
analysis of the field case but a further assessment of the impact for the point contact case (just touching each other) are
of layering on the mobilised mass stiffness after taking into concentrated mainly near the contact point, whereas for the
account the geometric arrangement of soil-cement columns in an overlap case this is spread to a much wider area.
embedded improved soil raft. In the parametric study, the deep
cement mixing columns were assumed to have two concentric Obviously the next question is how the mobilised stiffness relates
layers that were of the same cross-sectional areas. The strength to the amount of overlap, as increased overlap would imply a
and the stiffness of the outer layers were varied from a quarter to higher cost of construction. Intuitively, the mass property of these
four times the initial values while those of the inner layers were overlapping columns should approach the elemental property as
kept unchanged. Such a range of properties in different layers the overlap becomes increasingly large. Since the mass stiffness
covers the possible variations as reported by Kawasaki et al. varies with the mass strain, its value at 0.8% mass strain was
(1984) and the Nicoll Highway field trial. The mobilised mass extracted and plotted in Figure 19 for comparison, and this figure
stiffness obtained from the parametric study is normalised to the shows that the mass stiffness approaches the elemental material
stiffness of the inner layer as shown in Figure 16. If the outer stiffness as the overlap parameter L decreases or the amount of
layer is stiffer, as in the Nicoll Highway field trial case, the overlap increases. An important point to note is that even with a
mobilised mass stiffness can reach about 55% of the inner layer very small overlap, for example L ¼ 0.897 m, the initial mass
stiffness. On the other hand, if the outer layer is less stiff, as stiffness is nearly twice that for the case where there is no
reported by Kawasaki et al. (1984), the mobilised mass stiffness overlap, just a point contact. Thus a small overlap is shown to
can be as low as 12% of the inner layer stiffness, a further have a large impact on the stress distribution within the column,
reduction from the mobilised mass stiffness of the uniform soil-
cement case. When reasonable variations of material properties in 1·0
different layers are considered in the model, the mobilised mass Overlap parameter, L ⫽ 0·850 m
0·9
Overlap parameter, L ⫽ 0·880 m
stiffness can range from about 55% to about 12% of the
Normalised mass stiffness
21
Geotechnical Engineering Mass behaviour of embedded improved
Volume 164 Issue GE1 soil raft in an excavation
Yang, Tan and Leung
Figure 18. Von Mises stress contours at 0.02% mass strain: left,
very small overlap case; right, point contact case
in the outer layer that are different from those of the inner layer.
It is therefore necessary to examine the effects of such material
0·8
layering on the overlapping soil-cement columns. Figure 20
0·6 shows the results for one row of overlapping columns with two
layers having equal cross-sectional areas but different stiffnesses.
0·4 The overlap parameter L is 0.897 m. Similar to the mass behav-
Elemental stiffness
Normalised mass stiffness iour shown in Figure 12, the mass stiffness is higher when the
0·2 outer layer is assigned the stiffer material. A stiffer outer layer
also helps maintain the initial mass stiffness until a larger mass
0 strain is mobilised, which is a very important contribution to the
0·90 0·85 0·80 0·75 0·70 0·65 0·60
control of wall deflections and associated ground movements in
Overlap parameter, L: m
deep excavation.
Figure 19. Mass stiffness at 0.8% mass strain against the overlap
parameter L (for R ¼ 0.9 m) Parametric studies were carried out to evaluate the effect of the
ratio of stiffness of the outer layer to that of the inner layer on
the initial mass stiffness for different degrees of overlap. For each
overlap parameter the stiffness ratio is varied from 0.125 to 8, a
as a larger area is mobilised right from the start of loading. To range that covers the reported variation from the field (Kawasaki
achieve 80% of the elemental material stiffness, the overlap et al., 1984). The soil-cement columns are assumed to have equal
parameter L should be less than 0.75 m for one row of uniform cross-sectional areas. The results are shown in Figure 21. The
soil-cement columns with radius of 0.9 m. If a line is drawn vertical axis shows the initial mass stiffness normalised by the
between the centres of two connecting soil-cement columns, 30% elemental stiffness of the inner layer. Generally, increasing the
of the column radius must overlap another column along that degree of overlap helps make the composite system stiffer; and
line. this effect is more evident when the stiffness ratio increases. In
other words, even if sufficient overlap in the field is ensured, the
What Figure 19 also shows is that, once the uniform soil-cement benefit from overlapping can still be offset if the outer layer is
columns are overlapped to some extent, the mass stiffness weaker than the inner layer. It is therefore important to improve
becomes less sensitive to the degree of overlap. However, as this the workmanship in the field to ensure good control of the
figure also shows, a certain reduction from the elemental proper- positions of the soil-cement columns. It is also important to core
ties is required to take into account the effect of overlapping if and test samples that are located in the outer layer.
the test results of the elemental cores are to represent the mass
behaviour. Common overlapping used in practice would typically 5.4 Multiple overlapping columns
imply that the mobilised stiffness will see a reduction of at least In this section, soil-cement columns overlapping in an equilateral
30% from the elemental stiffness. triangular grid as shown in Figure 6(d) are studied. Two
22
Geotechnical Engineering Mass behaviour of embedded improved
Volume 164 Issue GE1 soil raft in an excavation
Yang, Tan and Leung
500 2·0
Inner 75 MPa; outer 300 MPa Overlap parameter, L ⫽ 0·779 m
L ⫽ 0·850 m
Inner 300 MPa; outer 75 MPa L ⫽ 0·880 m
1·5 L ⫽ 0·897 m
400 L ⫽ 0·900 m
Emax /Einner
1·0
Mass stress: kPa
300
0·5
200
0
0·125 0·25 0·5 1 2 4 8
Eouter /Einner
100
Figure 21. Normalised initial mass stiffness for one row of
overlapping columns
0
0 0·5 1·0 1·5 2·0
Mass strain: % 10
Volume ratio: outer layer 90%
Volume ratio: outer layer 70%
50 8 Volume ratio: outer layer 50%
Volume ratio: outer layer 30%
Volume ratio: outer layer 10%
Emass /Einner
6
40
4
Mass stiffness: MPa
30 2
0
20 0·125 0·25 0·5 1 2 4 8
Eouter /Einner
23
Geotechnical Engineering Mass behaviour of embedded improved
Volume 164 Issue GE1 soil raft in an excavation
Yang, Tan and Leung
5
Normalised to outer layer stiffness columns. Overlapping the uniform soil-cement columns in a row
Normalised to inner layer stiffness helps to improve the mobilised initial mass stiffness of the soil
Normalised initial mass stiffness
24
Geotechnical Engineering Mass behaviour of embedded improved
Volume 164 Issue GE1 soil raft in an excavation
Yang, Tan and Leung
Geotechnical and Geoenvironmental Engineering 123(6): and Ground Treatment (Johnsen LF, Bruce DA and Byle MJ
516–524. (eds)). American Society of Civil Engineers, Reston, VA,
Ou CY, Wu TS and Hsieh HS (1996) Analysis of deep excavation USA, Geotechnical Special Publication No. 120, Vol. 1, pp.
with column type of ground improvement in soft clay. 198–217.
Journal of Geotechnical and Geoenvironmental Engineering Shirlaw JN (2003) Jet grouting soft clays for tunnelling and deep
122(9): 709–716. excavations: design and construction issues. In Grouting and
Pickles AR and Henderson TO (2005) Some thoughts on the use Ground Treatment (Johnsen LF, Bruce DA and Byle MJ
of numerical modelling in geotechnical design practice. (eds)). American Society of Civil Engineers, Reston, VA,
Proceedings of Underground Singapore 2005: Special Session USA, Geotechnical Special Publication No. 120, Vol. 1, pp.
Numerical Analysis in Geotechnical Engineering, Singapore, 257–268.
11 pp. Tan TS and Shirlaw JN (2000) Braced excavation: excavation in
Porbaha A (2000) State of the art in deep mixing technology. general. In Proceedings of the 3rd International Symposium
Part IV: Design considerations. Ground Improvement 4(3): on Geotechnical Aspects of Underground Construction in Soft
111–125. Ground, Tokyo (Kusakabe O, Fujita K and Miyazaki Y (eds)).
Porbaha A (2002) State of the art in quality assessment of deep Balkema, Rotterdam, the Netherlands, pp. 53–62.
mixing technology. Ground Improvement 6(3): 95–120, doi: Tanaka H (1993) Behavior of braced excavations stabilized
10.1680/grim.2002.6.3.95. by deep mixing method. Soils and Foundations 33(2): 105–
Porbaha A, Asada H and Fatemi MJ (1999) Deep mixing 115.
technology for deep excavation. In Proceedings of the 3rd Wen DZ (2005) Use of jet grouting in deep excavations. In
National Conference on Geo-Engineering for Underground Ground Improvement – Case Histories (Indraratna B and Jian
Facilities, Urbana-Champaign (Fernandez G and Bauer RA C (eds)). Elsevier, Amsterdam, pp. 357–370.
(eds)). American Society of Civil Engineers, Reston, VA, Wong IH and Poh TY (2000) Effects of jet grouting on adjacent
USA, pp. 1048–1059. ground and structures. Journal of Geotechnical and
Shibazaki M (2003) State of practice of jet grouting. In Grouting Geoenvironmental Engineering 126(3): 247–256.
25