Professional Documents
Culture Documents
CHEMROAD - EN-Specification
CHEMROAD - EN-Specification
CHEM -road
SPECIFICATION FOR
SOIL-CEMENT POLYMER ROAD BASE
SCOPE
These specifications is for the contruction of new existing roads by in-situ stabilization
of road base layer with chem-road and Cement. Cover all the work in connection to the
stabilization of soil road base and include the scarifying of the in-situ soil road base.
Supply. Mix the road base with Cement. And the mixture of chem-road and water, compact
and cure the stabilization road base to the width and thickness shown on the drawing and to
the tolerances specified herein.
The contractor shall have good experience in work involving in-situ-stabilization and
recyeling of road. The work shall be supervised by a qualified and experienced stabilization
engineer.
MATERIAL
1.Soil
a. These materials are normally aggregates and soil. The aggregates and soil shall be
crushed rock, gravel, milled asphalt concrete, laterite, coarse sand, or combination of these
materials.
b. Soil classification when tasted in accordance with AASHTO T27-70 AASHTO T, 89
and AASHTO T90 should be A-1, a, A-1b, A-2 and A-3 group (AAHTO classification)
c. Maximum nominal size aggregates is limited to 50 mm.
d. Liquid Limit when tested in accordance with AASHTO T 89 should be less than 40
e. Plastic Index when tested in accordance with AASHTO T 90 should be less than 15
f. L.A Abrasion loss when tested in accordance with ASTM C 131 should be less than 60
2. Cement
The cement should be orntdinary sctting Portland cement complying with ASTM C
150. Cement delivered to the size should be fresh or tese to be fresh. The cement shall be
used within a reasonable period after delivery. Dry storage should be provide for cement that is not
used immediately upon delivery to the size.
3. Chem-road
The objectives of Chem-road soil cement stabilization are,
a. To minimize the damage to the road surface caused by cracking/settlement of
subgrade appearing as reflective cracking, rutting and pot hole.
b. To provide a waterproofing effects so as increase the durability of the road by
reducing the rate of saturation of the sub-base/base.
c. To provide a more flexible pavement wherein a reduction in stiffness can be
achieved without a decrease in strength.
d. To allow for pavement to rebound upon removal of load and there increase the
resistance against rutting.
1. Mixed Process
Homogeneously mixing cement to the soil
Uniformly spread the mixture of Chem-road and water
Homogeneously mixing the mixture of Chem-road and water to the dry soil –cement.
2. Degree of compaction
The minimum degree of field compaction with AASHTO T 191 should be 95 percent of the
maximum dry density determined in accordance with AASHTO T 180. The moisture content
of road base materials before compact should be at optimum moisture content when
determined according to AASHTO T 180.
3. Layer Thickness
The thickness of Chem-road soil cement stabilized road base is determined from Asphalt
Institute method or the multi – layer design method. The minimum layer Thickness should not
be less than 120 mm.
4. Field Compaction
Combination of different categories of the same plant will be permitted. In which case the
number of passes for each should be such proportion of the appropriate guide line number in
Table 1 as will together produce the same total compactive effort as any one operated singly.
5. Unconfined Compressive Strength
The Unconfined Compressive Strength of the Chem-road soil cement stabilized road base
should meet the design value. The minimum requirement is 1.7 mpa. Labortory samples
prepared in connection with the mixed design Proportion are make in cylindrical moulds to be
tested at 7 days age to determine the unconfined compressive strength in accordance with
AASHTO T 208
6. Flexural Strength
The Flexural Strengh is use to define by craking. The modulus of rupture test shall be
carried out according to AASHTO T 97. The modulus of rupture for Chem-road soil
cement stabilized road base should meet the design required value
7. Modulus of Elasticity
The Modulus of elasticity of Chem-road soil cement stabilized road base can be measured
statically by loading 150 mm. diameter cylinders fitted with extensometers or dynamically
using electrodynamic excitation on long became of 150 mm. square section. The resilient
modulus test for Chem-road soil cement stabilized road base material should by carried out
according to AASHOT T 274-82. The resilient modulus value should be meet the design value
following the design required value. The minimum modulus of elasticity is 10,000 kg./ cm.
CONSTRUCTION REQUIREMENT
1. The Chem-road soil cement stabilized road base material should be kept moist at
optimum moisture content before compact
2. The cement spray, mixing, level correction, and compaction should by carried out
within two hours to avoid the destruction of initial hardening bonds of cement.
3. The cement stabilized road base material should be kept moist for 7 days at least or
covered with prime coat. It is recommend not be to use heavy trucks for curing or
prime coat spraying during the first 7 days to avoid early loading of Chem-road
soil cement stabilized road base or using manual lightweight equipment. Therefore,
the spray of bituminous prime coat should be carried out either immediately after
the final compaction, or be carried out later when the strength of the Chem-road
soil cement stabilized road base is sufficient stand against spray turck axle loads.
4. If the curing of the Chem-road soil cement stabilized road base would be carried out by
spray of water, the water spray should be carried out using manual or lightweight
equipment especially during the first 7 days.
5. For new road, lightweight passenger cars should be allowed to pass on the cement
stabilized road base only 7 days after construction of the stabilized layer or as required
design for other types roads.
A sample of quality plan for construction of Chem-road soil cement stabilized road
base layer is shown in Table 2. A comprehensive laboratory and field-testing program
for design purpose should be carried out prior to the commencement of construction.
The testing program results should be used to determine the target and frequency of
tests for each property of Chem-road soil cement stabilized road base. These properties
should fulfill the design requirement.
Product Specification of polymer Chem-roadTM
Description :
Polymer SBR is a soil-cement additive, the polymers based mixture of latex and
cellulose dispersed in water. It is specifically formulated to stabilized the insitu soils with the
cement and water. Polymer SBR mix used as an additive to modify Portland cement
mixtures. The mix of Polymer SBR and Portland cement together bind the soil particles to
from a polymer concrete- like material. It allows concrete work to be made with out course
aggregate but to be used with insitu soil as a filler.
Benefits :
Improves cohesion between the soil aggregates and the cement paste, increases
fracture toughness and cracking resistance, modifies porosity and water penetration. In road
construction work, improves stability of material, provides water retention and Increases
workability. Non-toxic and environment friendly product.
Note : Chem-roadTM indicates a trademark of the International Polymer for Soil stabilized.
Chem-road TM
APPLICABILITY
Chem-Road dust may be applied to any site especially critical in arid areas where exposed soil is more
likely to be transported in to receiving water bodies by runoff and wind action. Chem-Road dust can also
be applied to any industrial activities that generate large quantity of dust, particularly if this dust could be
transported to a nearby water body
Chem-road TM
Soil Cement Polymer Road Base
Technical Characteristic
1. STRENGHT CHARATERISTIC
Unconfined compressive Strength : 17.5 – 40 kg./cm.2
(7 Days and Soaked water for 2 hours)
Flexural Strength (28 day) : 9–2 kg./cm.2
Elastic Modulus : 30,000-70,000 kg./cm.2
Soaked CBR : <250%
Poisson Ratio : 0.1 - 0.3
3. DURABILITY
I Slake Durability Index (ASTM D 4644-87) more than 75%
I No Pot-hole, no rutting depth and minimizes cracking.
I High Stiffness with no brittle.
I Minimizes subgrade pressure and has low deflection under loads.
I Bridges over weak spots in the subgrade.
4. OTHER PROPERTIES
I Dry Density : 1,700 - 2,300 kg./cm.3
I Water Absorption : <2.5%
I Coefficient of permcability: >10-8 cm./sec.
5. COMPACTION
Degree of compaction not less than 95% (Modified Proctor Density)
6. DESIGN CRITERLA
Unconfined Compressive Strength (7 day curing and soaked water for 2 house before testing)
not less than 17.5 kg./cm.2