LIFTING PLAN DETAILS

Date:

Lifting Plan Details

Lifting Plan Title PSS Unloading Lifting Plan


Client/Project/Location STT DATA CENTRE - KOLKATTA -DC02
Date 16/05/2024
Load details/Crane details (Maximum SWL not to be exceeded)
Gross lift weight: 11 ton Crane Lifting Routine: Radius 6 Mtr
Crain Configuration mode: Yes Classification: Non-routine: yes SWL yes X

Safety Measures to be considered (Not exhaustive, thick as applicable)


Crane Set on level ground Load Visibility
Whether weight is verified √ √ √
Efficient means of rescue Rigging equipment inspected
√ Pick up and drop path identified √ √
Is the lift surrounding area Crane inspection checklist filled Suitable and adequate super
√ √ √
barricaded and ready for lifting operation vision
Toolbox talk required
Whether load is stable √ Route and Lay-down area clear √ √
Prevention of Person Lifting equipment/accessories
Center of Gravity √ √ √
becoming stuck/trapped certification
Communication between crane Tag lines require
Awkward Shape/Sharp Edges √ √ √
operator and signaler d
Lose objects removed from Packing Protection for Load and Accessories and equipment fit of
Load
√ equipment
√ purpose SWL

Efficient means of Escape
Trained personnel √ √ Correct PPE’s √
LIFTING OPERATION (Described in Steps)
1. Mobilization of lifting equipment and pre-check of lifting equipment’s and accessories.
2. Tool-box Talk shall be conducted on Rigging and lifting.
3. Crane hook lock will be ensured before lifting.
4. Ensure proper arrangement of Lifting gear for Mild Steel Column.
5. Arranging of equipment’s to lift the Mild Steel Column.

6. Riggers will allow carrying out the rigging activities such as sling fixing, removing etc.
7. The lifting process will be continued as per lifting plan.
8. After completion of lifting operation, the crane will be Dis-engaged from site.
- Weight of the LOAD =
- Crane block hook + gears =
---------------------------------------------
MAX. lift weight =
The lifting Load is not to exceed 75% of max crane rated capacity.
o GENERAL
LIFTING PLAN DETAILS

Date:

1. Whole operation is to be suspended in case of adverse weather like heavy rain, extreme wind.
Operation is to be stopped in any other unsafe condition or act as well.
2. Operation to be carried out preferably during the day.

Crane Capacity 27Ton.


Calculations
A = 6 mtr.

B = 8 mtr

C = 0.2 mt

D = 11 mt

Total Weight (C+D) = 11 + 0.2 = 11.2

Current % Crane Capacity

Hook Block + Material Weight


= __________________________ ×100
Safe Workload

= 11.2*100/18= 62.22%

Note: - Should not be more than 75 %

Sign of Site Engineer Signature of Safety Officer