Prodactivity Rates

Productivity Unit Of
Work Type Crew
Rate /Day Measure

PC Footings 1 Carpenter 1 Helper 15 M3

RC Footings 1 Carpenter 1 Helper 12 M3

RC Columns & Walls 1 Carpenter 1 Helper 2.5 M3

RC Slabs 1 Carpenter 1 Helper 5 M3

Steel Reinforcement FDN 1 Steel Fixer 1 Helper 12 M3

Steel Reinforcement Slabs 1 Steel Fixer 1 Helper 7 M3

Steel Reinforcement Columns 1 Steel Fixer 1 Helper 5 M3

Steel Reinforcement S.O.G. 1 Steel Fixer 1 Helper 90 M2

1 Mason 1 Helper 20 M2
Masonry Works
1 Mason 1 Helper 3 M3

Plaster Work ( 1st Stage ) 1 Plaster 1 Helper 80 M2

Plaster Work ( Final Stage ) 1 Plaster 1 Helper 30 M2

Plaster Work facades ( 1st Stage ) 1 Plaster 1 Helper 60 M2

Plaster Work facades ( 2nd Stage ) 1 Plaster 1 Helper 25 M2

Insulation Water Proof Bit 1 Insulation Labor 1 Helper 70 M2

Ceramic Works 1 Tiller 1 Helper 12 M2

Putty Works 1 Painter 1 Helper 50 M2

Painting Interior 1 Painter 1 Helper 100 M2

Facade Painting 1 painter 1 Helper 50 M2

Steel Handrails 1 Steel Handrail Tech. 1 Helper 20 M

Wooden Doors 1 Door Carpenter 1 Helper 1 NO

underground pipes 2 Plumber 4 Helper 25 M

Above Ground Pipes 1 Plumber 1 Helper 15 M

inspection Chambers & GullyTraps 1 Plumber 1 Helper 2 NO

Black Steel Pipes 1 Plumber 1 Helper 45 M

Fire Cabinets 1 Plumber 1 Helper 1 NO


Productivity Unit Of
Work Type Crew
Rate /Day Measure

Electrical Conduits 1 Electrical 1 Helper 10 NO

Electrical Wiring 1 Electrical 1 Helper 10 NO

Lighting Fixtures 1 Electrical 1 Helper 10 NO

Gypsum Board 1 Gypsum board Tech. 1 Helper 3.5 M2