Download as pdf or txt
Download as pdf or txt
You are on page 1of 7

Analysis Rate for 800 MM dia MS pipe sewer line work by trenchless technology

For Depth 4.5 - 6.0 Mtr

Ref. of Schedule of
rates for
construction
S.No. contracts employing Item Qty Unit Rate Amount
treachless
technology 2020,
Part. 3
1 2 3 4 5 6 7
1 Supply and installation of 800 mm dia M.S., pipe 14 MM
thick (As per IS:3589 and made from steel coafoming
to IS:2062) with 1000 micron thick Polyurethane
coating internally and externally and laid in gradient
by trechless technology Including excavation & filling
of pits, sapporting system for soil etc. complete.

A 1.3.2 (Page 20) Making of jacking and Recieving Pit(2 No.)

Confined Excavation of Shafts for pipe


jacking/ramming purpose in soil inclusive of H Beam
Strutting with MS Plate/Cubical wooden laggings and
maintaining the shaft dunng construction operation
and back filling the same with local sand after the
comolctron of work
For shafts of 6m X 5 m from 3m to 5m in all type of
1321 120 Cum 1800 216000
soil.
For shafts of 6m X 5 m from 5- 6 m depth in all type of
60 Cum 2400 144000
soil.
B 24 (Page 47) Installation of pipes
2.5 Installation of product pipe by Auger Boring method
including making of entry and exit pits, all rdated civil
works like excavation, shorng/strutting, etc. shielded
excavation through auger boring process, lowering of
pipe segments in the jacking pit, laying and jointing of
product pipeline though jacking process from the
jacking pit and after project completion &s per the
instructions of the Engincer-in-Charge all complete
except the cost of pipe.

2.5.3 For 800 mm dia in all type of soil (by adding 25% for
executing Auger Boring under water table as per Pg. 80 m 54427.5 4354200
67)
Add extra for depth beyond 5.0 m
C Cost of pipes
MR Cost of 800 mm MS pipe (14 mm) (rates are exclusive
of taxes, but including loading, transportation,
unloading) with 1000 micron PU coating internally and
80 m 25943.07 2075445
externally.
MR Supplying and installing MS. Barricading at site upto
minimum 2 meter height with proper signages and
traffic diversion including all labour material TAP etc 44 m 178.00 7832
complete in all respect upto satisfaction of engineer
incharge
1.2 (Page 19) Dewatering of Pit 300 hr 48.00 14400
TOTAL 6811877.44
G. Total 6811877.44
Rate per m= G.TOTAL/80 85148.47
Analysis Rate for 800 MM dia MS pipe sewer line work by trenchless technology
For Depth 4.5 - 6.0 Mtr

Ref. of Schedule of
rates for
construction
S.No. contracts employing Item No. L B H Quantity Unit
treachless
technology 2020,
Part. 3

1 2 3 4 5 6 7 8 9
1 Supply and installation of 800 mm dia M.S., pipe 14
MM thick (As per IS:3589 and made from steel
coafoming to IS:2062) with 1000 micron thick
Polyurethane coating internally and externally and
laid in gradient by trechless technology Including
excavation & filling of pits, sapporting system for
soil etc. complete.
A 1.3.2 (Page 20) Making of jacking and Recieving Pit(2 No.)
Confined Excavation of Shafts for pipe
jacking/ramming purpose in soil inclusive of H Beam
Strutting with MS Plate/Cubical wooden laggings and
maintaining the shaft dunng construction operation
and back filling the same with local sand after the
comolctron of work
For shafts of 6m X 5 m from 3m to 5m in all type of
1321 2 6 5 2 120.00 Cum
soil.
For shafts of 6m X 5 m from 5- 6 m depth in all type
2 6 5 1 60.00 Cum
of soil.
B 24 (Page 47) Installation of pipes
2.5 Installation of product pipe by Auger Boring method
including making of entry and exit pits, all rdated
civil works like excavation, shorng/strutting, etc.
shielded excavation through auger boring process,
lowering of pipe segments in the jacking pit, laying
and jointing of product pipeline though jacking
process from the jacking pit and after project
completion &s per the instructions of the Engincer-in-
Charge all complete except the cost of pipe.

2.5.3 For 800 mm dia in all type of soil (by adding 25% for
executing Auger Boring under water table as per Pg. 1 80 - - 80 M
67)
C Cost of pipes
MR Cost of 800 mm MS pipe (14 mm) (rates are
exclusive of taxes, but including loading,
1 80 - - 80 M
transportation, unloading) with 1000 micron PU
coating internally and externally.
MR Supplying and installing MS. Barricading at site upto
minimum 2 meter heith with proper signages and
traffic diversion including all labour material TAP etc 2 22 - - 44 M
complete in all respect upto satisfaction of engineer
incharge
1.2 (Page 19) Dewatering of Pit 1 300 - - 300 Hr
Analysis Rate for 800 MM dia MS pipe sewer line work by trenchless technology
For Depth 6.0 - 7.5 Mtr
Ref. of
Schedule
S.No. of rates Item Qty Unit Rate Amount
for
constructi
1 on
2 3 4 5 6 7
1 Supply and installation of 800 mm dia M.S., pipe 14
MM thick (As per IS:3589 and made from steel
coafoming to IS:2062) with 1000 micron thick
Polyurethane coating internally and externally and
laid in gradient by trechless technology Including
excavation & filling of pits, sapporting system for soil
etc. complete.
A 1.3.2 (Page 20)Making of jacking and Recieving Pit(2 No.)
Confined Excavation of Shafts for pipe
jacking/ramming purpose in soil inclusive of H Beam
Strutting with MS Plate/Cubical wooden laggings and
maintaining the shaft dunng construction operation
and back filling the same with local sand after the
comolctron of work
1321 For shafts of 6m X 5 m from m in all type of soil. 120 Cum 1800 216000
For shafts of 6m X 5 m from 5- 6 m depth in all type of
150 Cum 2400 360000
soil.
B 24 (Page 47) Installation of pipes
2.5 Installation of product pipe by Auger Boring method
including making of entry and exit pits, all rdated civil
works like excavation, shorng/strutting, etc. shielded
excavation through auger boring process, lowering of
pipe segments in the jacking pit, laying and jointing
of product pipeline though jacking process from the
jacking pit and after project completion &s per the
instructions of the Engincer-in-Charge all complete
except the cost of pipe.

2.5.3 For 800 mm dia in all type of soil (by adding 25% for
executing Auger Boring under water table as per Pg. 80 m 54427.5 4354200
67)
Add extra for depth beyond 5.0 m
C Cost of pipes
MR Cost of 800 mm MS pipe (14 mm) (rates are exclusive
of taxes, but including loading, transportation,
unloading) with 1000 micron PU coating internally
80 m 25943.07 2075445
and externally.
MR Supplying and installing MS. Barricading at site upto
minimum 2 meter heith with proper signages and
traffic diversion including all labour material TAP etc 44 m 178.00 7832
complete in all respect upto satisfaction of engineer
incharge
1.2 (Page 19)Dewatering of Pit 500 hr 48.00 24000
TOTAL 7037477.44
G. Total 7037477.44
Rate per m= G.TOTAL/80 87968.47
Analysis Rate for 800 MM dia MS pipe sewer line work by trenchless technology
For Depth 6.0 - 7.5 Mtr
Ref. of Schedule
of rates for
construction
contracts
S.No. employing
Item No. L B H Quantity Unit
treachless
technology 2020,
Part. 3
3
1 2 4 5 6 7 8 9
1 Supply and installation of 800 mm dia M.S., pipe 14 MM
thick (As per IS:3589 and made from steel coafoming to
IS:2062) with 1000 micron thick Polyurethane coating
internally and externally and laid in gradient by trechless
technology Including excavation & filling of pits,
sapporting system for soil etc. complete.
A 1.3.2 (Page 20) Making of jacking and Recieving Pit(2 No.)

Confined Excavation of Shafts for pipe jacking/ramming


purpose in soil inclusive of H Beam Strutting with MS
Plate/Cubical wooden laggings and maintaining the shaft
dunng construction operation and back filling the same
with local sand after the comolctron of work
For shafts of 6m X 5 m from 3 m to 5 m in all type of soil.
1.3.2.1 2 6 5 2 120.00 Cum
For shafts of 6m X 5 m from 5- 7.5 m depth in all type of
2 6 5 2.50 150.00 Cum
soil.
B 24 (Page 47) Installation of pipes
2.5 Installation of product pipe by Auger Boring method
including making of entry and exit pits, all rdated civil
works like excavation, shorng/strutting, etc. shielded
excavation through auger boring process, lowering of
pipe segments in the jacking pit, laying and jointing of
product pipeline though jacking process from the jacking
pit and after project completion &s per the instructions of
the Engincer-in-Charge all complete except the cost of
pipe.
2.5.3 For 800 mm dia in all type of soil (by adding 25% for
executing Auger Boring under water table as per Pg. 67) 1 80 - - 80 M
C Cost of pipes
MR Cost of 800 mm MS pipe (14 mm) (rates are exclusive of
taxes, but including loading, transportation, unloading)
1 80 - - 80 M
with 1000 micron PU coating internally and externally.

MR
Supplying and installing MS. Barricading at site upto
minimum 2 meter heith with proper signages and traffic
2 22 - - 44 M
diversion including all labour material TAP etc complete in
all respect upto satisfaction of engineer incharge
1.2 (Page 19) Dewatering of Pit 1 500 - - 500 Hrs
Analysis Rate for 800 MM dia MS pipe sewer line work by trenchless technology
For Depth 7.5 - 9.0 Mtr
Ref. of
Schedule
S.No. of rates Item Qty Unit Rate Amount
for
constructi
1 on
2 3 4 5 6 7
1 Supply and installation of 800 mm dia M.S., pipe 14
MM thick (As per IS:3589 and made from steel
coafoming to IS:2062) with 1000 micron thick
Polyurethane coating internally and externally and
laid in gradient by trechless technology Including
excavation & filling of pits, sapporting system for soil
etc. complete.
A 1.3.2 (Page 20)Making of jacking and Recieving Pit(2 No.)
Confined Excavation of Shafts for pipe
jacking/ramming purpose in soil inclusive of H Beam
Strutting with MS Plate/Cubical wooden laggings and
maintaining the shaft dunng construction operation
and back filling the same with local sand after the
comolctron of work
1321 For shafts of 6m X 5 m from m in all type of soil. 120 Cum 1800 216000
For shafts of 6m X 5 m from 5- 6 m depth in all type of
240 Cum 2400 576000
soil.
B 24 (Page 47) Installation of pipes
2.5 Installation of product pipe by Auger Boring method
including making of entry and exit pits, all rdated civil
works like excavation, shorng/strutting, etc. shielded
excavation through auger boring process, lowering of
pipe segments in the jacking pit, laying and jointing
of product pipeline though jacking process from the
jacking pit and after project completion &s per the
instructions of the Engincer-in-Charge all complete
except the cost of pipe.

2.5.3 For 800 mm dia in all type of soil (by adding 25% for
executing Auger Boring under water table as per Pg. 80 m 54427.5 4354200
67)
Add extra for depth beyond 5.0 m
C Cost of pipes
MR Cost of 800 mm MS pipe (14 mm) (rates are exclusive
of taxes, but including loading, transportation,
unloading) with 1000 micron PU coating internally
80 m 25943.07 2075445
and externally.
MR Supplying and installing MS. Barricading at site upto
minimum 2 meter heith with proper signages and
traffic diversion including all labour material TAP etc 44 m 178.00 7832
complete in all respect upto satisfaction of engineer
incharge
1.2 (Page 19)Dewatering of Pit 750 hr 48.00 36000
TOTAL 7265477.44
G. Total 7265477.44
Rate per m= G.TOTAL/80 90818.47
Analysis Rate for 800 MM dia MS pipe sewer line work by trenchless technology
For Depth 7.5 - 9.0 Mtr
Ref. of
Schedule of
rates for
construction
S.No. contracts
Item No. L B H Quantity Unit
employing
treachless
technology
1 2 3 4 5 6 7 8 9
1 Supply and installation of 800 mm dia M.S., pipe 14 MM
thick (As per IS:3589 and made from steel coafoming to
IS:2062) with 1000 micron thick Polyurethane coating
internally and externally and laid in gradient by trechless
technology Including excavation & filling of pits,
sapporting system for soil etc. complete.
A 1.3.2 (Page 20)Making of jacking and Recieving Pit(2 No.)

Confined Excavation of Shafts for pipe jacking/ramming


purpose in soil inclusive of H Beam Strutting with MS
Plate/Cubical wooden laggings and maintaining the
shaft dunng construction operation and back filling the
same with local sand after the comolctron of work
For shafts of 6m X 5 m from 3 m to 5 m in all type of soil.
1321 2 6 5 2 120.00 Cum
For shafts of 6m X 5 m from 5- 7.5 m depth in all type of
2 6 5 4.00 240.00 Cum
soil.
B 24 (Page 47) Installation of pipes
2.5 Installation of product pipe by Auger Boring method
including making of entry and exit pits, all rdated civil
works like excavation, shorng/strutting, etc. shielded
excavation through auger boring process, lowering of
pipe segments in the jacking pit, laying and jointing of
product pipeline though jacking process from the
jacking pit and after project completion &s per the
instructions of the Engincer-in-Charge all complete
except the cost of pipe.
2.5.3
For 800 mm dia in all type of soil (by adding 25% for 1 80 - - 80 M
executing Auger Boring under water table as per Pg. 67)
C Cost of pipes
MR Cost of 800 mm MS pipe (14 mm) (rates are exclusive of
taxes, but including loading, transportation, unloading)
1 80 - - 80 M
with 1000 micron PU coating internally and externally.

MR
Supplying and installing MS. Barricading at site upto
minimum 2 meter heith with proper signages and traffic 2 22 - - 44 M
diversion including all labour material TAP etc complete
in all respect upto satisfaction of engineer incharge
1.2 (Page 19)Dewatering of Pit 1 750 - - 750 Hrs
Skeleton of Rate (Rs./Kg.) for MS Specials (Bend & Tee) proposed to be used in 800 mm dia Sewer
laying work

Sl. Item of Work Qty. Unit Rate Amount


C1 C2 C3 C4 C5 C6
A Fabrication of MS pipe 800mm dia (14 mm thick, in
length 6 m for convenient carting purpose) on applying
rolling, welding processes on 12 mm thick MS plate. It
will be used for making specials at the site according to
its refquirement.
(i) Weight of MS plate material used for making 6 m length, 14
mm thick MS pipe
6m x 244.91 kg./m 1469.5 Kg 65.00 95515.86
(ii) Carting, loading, unloading of MS plate from godown to 1469.5 Kg 6.04 8875.63
rolling mill.
(iii) Rolling & welding of MS plate for making MS pipe Kg
including wastage @ 2 % 1469.47 14.00 20572.65
(iv) PU coating on both side (inner + outer) surfaces 1000
Micron min thickness
Surface area (outer) = π DL

3.14 x 0.828x 6
15.60 Sqm. 250.00 3899.88
Surface area (inner) = π DL

3.14 x 0.80x 6
15.07 Sqm. 250.00 3768.00
(v) carting of ms pipe 6 meter length from store to site
1469.47 kg 6.04 8875.63

141507.64
Contractor Profit @ 10%
14150.76

155658.41
Rate (Rs./m)
155658.41
25943.07
6.00
Says Rs. 25943

Project Engineer

You might also like