Doc. Ref.

: PP67-PE-GEN-00-DOR-MT-I-120
Peru Block 67 Field
Development Revision: 01 Rev Date : 28-Jul-2011

Status: IFP Class: 3


Civil Works – Concrete & Site
Preparation MTO Page 1 of 20

CIVIL WORKS – CONCRETE & SITE


PREPARATION MTO

01 IFP Issued for Procurement 28-Jul-11 F. Laloy V. Fort X. Grandiaud

Rev Status Revision Memo Date Written By Checked By Approved By

WARNING: This document as printed may not be the latest version. Please refer to the electronic file in the EDMS
/conversion/tmp/activity_task_scratch/757748457.doc
Doc. Ref.: PP67-PE-GEN-00-DOR-MT-I-120
Peru Block 67 Field
Development Revision: 01 Rev Date : 28-Jul-2011

Status: IFP Class: 3


Civil Works – Concrete & Site
Preparation MTO Page 2 of 20

INDEX

1 INTRODUCTION...................................................................................................................................... 4
2 SUMMARY OF QUANTITIES................................................................................................................... 4
2.1.1 Civil Reinforced Concrete.............................................................................................................................. 4
2.1.2 Earth Volumes............................................................................................................................................... 4
2.1.3 Geotextile...................................................................................................................................................... 5
2.1.4 Open Drain Pipes.......................................................................................................................................... 5
3 REFERENCE DOCUMENTS.................................................................................................................... 6
4 GENERAL ASSUMPTION........................................................................................................................ 7
4.1 Geotextiles....................................................................................................................................... 7
4.2 Steel Reinforcments........................................................................................................................ 7
4.3 Lean Concrete................................................................................................................................. 7
5 CPF CIVIL WORKS MTO......................................................................................................................... 8
5.1 Civil Reinforced Concrete................................................................................................................ 8
5.1.1 Concrete Slabs Foundations - Equipments...................................................................................................8
5.1.2 Concrete Slabs Foundations – Buildings, including Power Generation......................................................10
5.1.3 Tanks Foundation........................................................................................................................................ 10
5.1.4 Concrete Footings....................................................................................................................................... 10
5.1.5 Concrete Paving.......................................................................................................................................... 11
5.1.6 Basins.......................................................................................................................................................... 11
5.1.7 Miscellaneous Re-inforced Concrete Items.................................................................................................11
5.1.8 Lean Concrete............................................................................................................................................. 12
5.2 Steel Re-inforcements................................................................................................................... 12
5.3 Geotextile...................................................................................................................................... 13
6 CT CIVIL WORKS MTO......................................................................................................................... 14
6.1 Civil Reinforced Concrete.............................................................................................................. 14
6.1.1 Concrete Slabs Foundations - Equipments.................................................................................................14
6.1.2 Concrete Slabs Foundations – Buildings, including Power Generation......................................................14
6.1.3 Concrete Footings....................................................................................................................................... 14
6.1.4 Concrete Paving.......................................................................................................................................... 15
6.1.5 Vent Pit........................................................................................................................................................ 15
6.1.6 Miscellaneous Re-inforced Concrete Items.................................................................................................15
6.1.7 Lean Concrete............................................................................................................................................. 15
6.2 Steel Re-inforcements................................................................................................................... 15
6.3 Geotextile...................................................................................................................................... 16
7 PPI1 CIVIL WORKS MTO...................................................................................................................... 17
7.1 Civil Reinforced Concrete.............................................................................................................. 17
7.1.1 Concrete Slabs Foundations - Equipments.................................................................................................17
7.1.2 Trench......................................................................................................................................................... 17
7.1.3 Concrete Footings....................................................................................................................................... 17
7.1.4 Basins.......................................................................................................................................................... 17
7.1.5 Miscellaneous Re-inforced Concrete Items.................................................................................................18
7.1.6 Lean Concrete............................................................................................................................................. 18
7.2 Steel Re-inforcements................................................................................................................... 18
7.3 Geotextile...................................................................................................................................... 18
8 PPI3 CIVIL WORKS MTO...................................................................................................................... 19
8.1 Civil Reinforced Concrete.............................................................................................................. 19

WARNING: This document as printed may not be the latest version. Please refer to the electronic file in the EDMS
/conversion/tmp/activity_task_scratch/757748457.doc
Doc. Ref.: PP67-PE-GEN-00-DOR-MT-I-120
Peru Block 67 Field
Development Revision: 01 Rev Date : 28-Jul-2011

Status: IFP Class: 3


Civil Works – Concrete & Site
Preparation MTO Page 3 of 20

8.1.1 Concrete Slabs Foundations - Equipments.................................................................................................19


8.1.2 Trench......................................................................................................................................................... 19
8.1.3 Concrete Footings....................................................................................................................................... 19
8.1.4 Basins.......................................................................................................................................................... 19
8.1.5 Miscellaneous Re-inforced Concrete Items.................................................................................................19
8.1.6 Lean Concrete............................................................................................................................................. 20
8.2 Steel Re-inforcements................................................................................................................... 20
8.3 Geotextile...................................................................................................................................... 20

WARNING: This document as printed may not be the latest version. Please refer to the electronic file in the EDMS
/conversion/tmp/activity_task_scratch/757748457.doc
Doc. Ref.: PP67-PE-GEN-00-DOR-MT-I-120
Peru Block 67 Field
Development Revision: 01 Rev Date : 28-Jul-2011

Status: IFP Class: 3


Civil Works – Concrete & Site
Preparation MTO Page 4 of 20

1 INTRODUCTION

The present document summarises the Material Take Off related to the civil works on the 4 sites to be
developed during the initial phases of the Perenco Peru Block 67 Field Development Project. These sites
are:
- Piraña Central Processing Facilities (CPF)
- Curaray Terminal
- Piraña Production pads PPi1 and PPi3

This MTO covers


- General Earthworks required for site preparation and (scrapping, backfilling and excavating)
- Civil concrete works
- Roads Construction
- UndergroundOpen Drain Pipes

Tis MTO does not cover


- CT Offloading Ramp
- CT River dredging
- Access Roads to the sites (PPi-1, PPi-3, CPF, CT)

The quantities indicated herein are basic engineering estimates only and do not include any
contingency.

Material Take Off for steel structures is covered in document ref. [x]. This steel structures MTO includes,
among other items, the piles that will be used for foundations.

2 SUMMARY OF QUANTITIES

2.1.1 Civil Reinforced Concrete


Structural Concrete Lean Concrete Steel
Volume Volume Reinforcement
(m3) (m3) (tonnes)
Location  Phase 0 Phase 1 Phase 0 Phase 1 Phase 0 Phase 1
Piraña CPF 6 810 630 384 59 681.0 63.0
Curaray Terminal 540 0 34 0 54.0 0
PPi 1 550 40 33 4 55 5
PPi 3 465 35 27 4 47 3.5
Total 8 365 705 478 67 837 72

2.1.2 Earth Volumes


Soft soil/ Organic Soil Re-usable Cut Material Backfilling Volume
Layer Volume (1) Volume
Location  (m3) (m3) (m3)
Piraña CPF 122 700 124 700 63 400
Curaray Terminal 48 200 0 178 700 (2)
PPi 1 39 500 500 26 300
PPi 3 21 600 26 900 5 400
Total 232 000 152 100 273 800
(1) : Not re-usable
(2) : Backfilling at CURARAY TERMINAL shall be performed using sand dredged from CURARAY River.

WARNING: This document as printed may not be the latest version. Please refer to the electronic file in the EDMS
/conversion/tmp/activity_task_scratch/757748457.doc
Doc. Ref.: PP67-PE-GEN-00-DOR-MT-I-120
Peru Block 67 Field
Development Revision: 01 Rev Date : 28-Jul-2011

Status: IFP Class: 3


Civil Works – Concrete & Site
Preparation MTO Page 5 of 20

2.1.3 Geotextile
Geoweb Geomembrane
2
Location  (m ) (m2)
Piraña CPF 8 430 10 370
Curaray Terminal 1690 2470
PPi 1 7430 1580
PPi 3 9 540 1 360
Total 27 090 15 780

2.1.4 Open Drain Pipes


Pipe Diameter (mm)
800 600 400 300 200 50
(m) (m) (m) (m) (m) (m)
Location Hazardous Non- Hazardous Non- Hazardous Non- Hazardous Non- Hazardous Non- Hazardous Non-
Hazardous Hazardous Hazardous Hazardous Hazardous Hazardous

Piraña 0 72 0 277 0 530 277 375 392 268 122 0
CPF
Curaray 0 0 0 0 0 0 110 160 0 15 38 0
Terminal

PPi 1 0 0 0 0 0 0 0 76 110 18 9 0
PPi 3 0 0 0 0 0 0 0 157 135 18 40 0
Total 0 72 0 277 0 530 387 768 637 319 209 0

Hazardous OD Pipes shall be GRP or HDPE material.


Non-Hazardous OD Pipes shall be Concrete or HDPE material.

Excavation in earth for open drain pipes (2m deep x 1m wide (mean) ):
CPF : 4650m3
CT : 650m3
PPi1 : 440m3
PPi3 : 720m3

WARNING: This document as printed may not be the latest version. Please refer to the electronic file in the EDMS
/conversion/tmp/activity_task_scratch/757748457.doc
Doc. Ref.: PP67-PE-GEN-00-DOR-MT-I-120
Peru Block 67 Field
Development Revision: 01 Rev Date : 28-Jul-2011

Status: IFP Class: 3


Civil Works – Concrete & Site
Preparation MTO Page 6 of 20

3 REFERENCE DOCUMENTS

[1] General Earthwork Specification PP67-PE-GEN-00-DOR-SP-I-004


[2] CT - Site Preparation - Plan View PP67-PE-EXT-CT-DOR-DW-I-010
[3] CT - Site Preparation - Sections PP67-PE-EXT-CT-DOR-DW-I-020
[4] CT - Site Surface General Arrangement PP67-PE-EXT-CT-DOR-DW-I-030
[5] CT – Undergreound Networks PP67-PE-EXT-CT-DOR-DW-I-040
[6] CT – Typical Foundations PP67-PE-EXT-CT-DOR-DW-I-150
[7] CT – Quay Foundations PP67-PE-EXT-CT-DOR-DW-I-151
[8] CT – Accesses Foundations PP67-PE-EXT-CT-DOR-DW-I-152
[9] CT – Buildings Foundations PP67-PE-EXT-CT-DOR-DW-I-153
[10] Earthworks, Civil Works and Steel Structures – General Notes PP67-PE-GEN-00-DOR-DW-I-102
[11] Piraña – PPi1 – Site Preparation – Plan View PP67-PE-PIR-01-DOR-DW-I-010
[12] Piraña – PPi1 – Site Preparation – Sections PP67-PE-PIR-01-DOR-DW-I-020
[13] Piraña – PPi1 – Site Surface General Arrangement PP67-PE-PIR-01-DOR-DW-I-030
[14] Piraña – PPi1 – Hazardous and Non-Hazardous Open drains PP67-PE-PIR-01-DOR-DW-I-040
Underground Network Layout
[15] Piraña – PPi1 – Road Section Layout & Underground PP67-PE-PIR-01-DOR-DW-I-045
Networks
[16] Piraña – PPi3 – Site Preparation – Plan View PP67-PE-PIR-03-DOR-DW-I-010
[17] Piraña – PPi3 – Site Preparation – Sections PP67-PE-PIR-03-DOR-DW-I-020
[18] Piraña – PPi3 – Site Surface General Arrangement PP67-PE-PIR-03-DOR-DW-I-030
[19] Piraña – PPi3 – Hazardous and Non-Hazardous Open drains PP67-PE-PIR-03-DOR-DW-I-040
Underground Network Layout
[20] Piraña – CPF - PPi1 and PPI3 – API basin Principles PP67-PE-PIR-0X-DOR-DW-I-050
[21] Piraña – CPF – Site Preparation – Plan View PP67-PE-PIR-CF-DOR-DW-I-010
[22] Piraña – CPF – Site Preparation – Sections PP67-PE-PIR-CF-DOR-DW-I-020
[23] Piraña – CPF – Site Surface General Arrangement PP67-PE-PIR-CF-DOR-DW-I-030
[24] Piraña – CPF– Hazardous and Non-Hazardous Open drains PP67-PE-PIR-CF-DOR-DW-I-040
Underground Network Layout
[25] Piraña – CPF – Road Section Layout & Underground Networks PP67-PE-PIR-CF-DOR-DW-I-045
[26] Piraña – Diverter, API basin and Observation Basins Principles PP67-PE-PIR-CF-DOR-DW-I-050
[27] Piraña – CPF –Foundations Layout PP67-PE-PIR-CF-DOR-DW-I-130
[28] Piraña – CPF and Pads – Typical Equipment Foundations PP67-PE-PIR-CF-DOR-DW-I-140
[29] Piraña – CPF – Flare Foundations PP67-PE-PIR-CF-DOR-DW-I-141
[30] Piraña – CPF – Piperack Foundations PP67-PE-PIR-CF-DOR-DW-I-142
[31] Piraña – CPF – Typical Tank Foundations and Bund Wall PP67-PE-PIR-CF-DOR-DW-I-143
[32] Piraña – CPF –Buildings Foundations PP67-PE-PIR-CF-DOR-DW-I-144
[33] Piraña – CPF and pads – Pipe way Sleepers PP67-PE-PIR-CF-DOR-DW-I-145

WARNING: This document as printed may not be the latest version. Please refer to the electronic file in the EDMS
/conversion/tmp/activity_task_scratch/757748457.doc
Doc. Ref.: PP67-PE-GEN-00-DOR-MT-I-120
Peru Block 67 Field
Development Revision: 01 Rev Date : 28-Jul-2011

Status: IFP Class: 3


Civil Works – Concrete & Site
Preparation MTO Page 7 of 20

[34] Piraña – CPF –Telecom Mast Foundation PP67-PE-PIR-CF-DOR-DW-I-146


[35] Piraña – CPF – Piled Foundation PP67-PE-PIR-CF-DOR-DW-I-147
[36] Piraña – CPF –Diesel Storage Tank Retaining Wall PP67-PE-PIR-CF-DOR-DW-I-160
[37] Piraña – CPF – Road Crossings PP67-PE-PIR-CF-DOR-DW-I-161
[38] Steel Structure MTO PP67-PE-GEN-00-DOR-MT-Y-110

4 GENERAL ASSUMPTION

4.1 Geotextiles

Geotextiles will primarily be used in roads construction.


It shall be noted that the 2:1 slopes delimiting the various sites are considered to be stable. Hence geotextile
that may be used for stabilisation purposes do not appear in the present MTO.
A provision has however been added for stabilisation of 1:1 slopes on CPF (around diluent and crude
pumping stations) and of the outer wall of the diluent and crude storage bunds.

4.2 Steel Reinforcments

The amount of steel re-inforcement is estimated assuming an average rebar density of 100kg/concrete m3.

4.3 Lean Concrete

The lean concrete volume is calculated considering a thickness of 50mm under each concrete foundation.

WARNING: This document as printed may not be the latest version. Please refer to the electronic file in the EDMS
/conversion/tmp/activity_task_scratch/757748457.doc
Doc. Ref.: PP67-PE-GEN-00-DOR-MT-I-120
Peru Block 67 Field
Development Revision: 01 Rev Date : 28-Jul-2011

Status: IFP Class: 3


Civil Works – Concrete & Site
Preparation MTO Page 8 of 20

5 CPF CIVIL WORKS MTO

5.1 Civil Reinforced Concrete

Notes relatives to section 5.1:


1. An “x” in the “Shaft” column indicates a foundation with shafts. In this case, the volume of the slab is
slightly larger than the product L x W x H.

5.1.1 Concrete Slabs Foundations - Equipments


Equipment Location Phase Dimensions Shaft Volume Notes
(LxWxH, m) (m3)
PI-U-101 FWKO Drum Train A Skid Process 0 8x16x0.9 x 116
Crude / Emulsion Heat Exchanger Train A
PI-U-102 Process 0 6x10.2x0.5
Skid 31
PI-U-103 Low Pressure Separator Train A Skid Process 0 7.5x16x0.9 x 109
PI-U-104 Raw Oil Pumps Skid Process 0 4.5x7x0.5 16
PI-U-105 Hot Oil Heater Train A Skid Process 0 5.5x9x0.7 35
PI-U-106 Produced Water Recirculation Pumps Skid Process 0 3.5x4.65x0.5 8
PI-U-107 Electrostatic Separator Skid Process 0 7x16x0.9 x 102
PI-U-108 Crude Oil Cooler Train A Skid Process 0 6x10.2x0.5 31
PI-U-200 FWKO Drum Train B Skid Process 1 8x16x0.9 x 116
Crude / Emulsion Heat Exchanger Train B x
PI-U-201 Process 1 6x10.2x0.5
Skid 31
PI-U-202 Hot Oil Heater Train B Skid Process 0 5.5x8.8x0.5 24
Pi-H-202 Centrifuge Spare Process 0 3.75x4x0.5 8
PI-U-203 Low Pressure Separator Train B Skid Process 1 4x8x0.7 x 23
PI-U-204 Centrifuge Inlet Filter Skid Process 0 3.5x10x0.5 18
PI-U-205 Crude Oil Cooler Train B Skid Process 0 6x10.2x0.5 31
PI-U-410 Water Skimmer Drum Phase 0 Skid Process 0 7x13.5x0.9 x 86
PI-U-411 Water Skimmer Drum Phase 1 Skid Process 1 7x13.5x0.9 x 86
PI-D-510 4x4x0.5 8
PI-U-420 Cooling Water System Skid Process 0 3.2x4.5x0.5 7
4x5x0.5 +
PI-U-990 Hot Oil System Skid Process 0
5x5x0.5 23
7x13.5x0.9 +
PI-U-991 Hot Oil Drain Drum & Pumps Skid Process 0
4x5x0.5 96
Sub-total Process Area 1001

Water
PI-U-401 Water Booster Pumps Skid Phase 0 0 5x7.2x0.5 18
Treatment
Water
PI-U-403 Water Booster Pumps Skid Phase 1 1 5x13.5x0.5 34
Treatment
Water
PI-U-402 Water Injection Pumps Skid Phase 0 0 10x11x0.5 55
Treatment
Water
PI-U-404 Water Injection Pumps Skid Phase 1 1 10x20x0.5 100
Treatment
Water
PI-U-405 Water Injection Filters Skid Phase 0 0 4x6x0.5 12
Treatment
Water
PI-U-406 Water Injection Filters Skid Phase 1 1 5x15x0.5 38
Treatment
Sub-total Water Treatment Area 257

WARNING: This document as printed may not be the latest version. Please refer to the electronic file in the EDMS
/conversion/tmp/activity_task_scratch/757748457.doc
Doc. Ref.: PP67-PE-GEN-00-DOR-MT-I-120
Peru Block 67 Field
Development Revision: 01 Rev Date : 28-Jul-2011

Status: IFP Class: 3


Civil Works – Concrete & Site
Preparation MTO Page 9 of 20

Equipment Location Phase Dimensions Shaft Volume Notes


(LxWxH, m) (m3)

PI-U-171 Crude Export Pumps Skid Crude Stor. 0 5.5x11x0.5 30


PI-U-172 Crude Transfer Pumps Skid Crude Stor. 0 4x6x0.5 12
Instrumentation Skid
PI-U-173 (Downstream Crude Export Pumps Skid PI- Crude Stor. 0 6.35x3x0.5 10
U-171)
PI-U-180 Reprocessing Pumps Skid Crude Stor. 0 5x7x0.5 18
PI-U-182 Reprocessing Heater Skid Crude Stor. 0 3.8x7.7x0.5 15
PI-D-150 A/B/C Storage Tanks Gas Boots Crude Stor. 0 3 x [1x2x0.9] 5
PI-U-950 Crude Stor. 0 2.5x7.5x0.5 9
Sub-total Crude Storage Area 99

Pig L/R
PI-U-100 Production Line Pig Receiver Skid 0 5.7x16.3x0.5 46
area
Pig L/R
PI-U-161 Diluent Pig Receiver Skid 0 4.4x13.2x0.5 29
area
Pig L/R
PI-U-170 Export Pig Launcher Skid 0 5.2x16.3x0.5 42
area
Sub-total Pigs L/R Area 117

PI-U-920 Closed Drain Drum Skid CD & Flare 0 5x9.5x0.5 x 24


PI-U-921 Closed Drain Pumps Skid CD & Flare 0 5x6x0.5 15
PI-U-972 Flare KO Drum and Pumps Skid CD & Flare 0 5x16x0.50 40
PI-U-971 Flare Tip Ignition Panel CD & Flare 0 6x16x0.5 x 40
Sub-total CD & Flare Area 119

Diluent
PI-U-162 Diluent Pumps A , B & C Skid 0 6.5x9.2x0.5 30
Storage
Diluent Storage area 30

PI-U-900 Diesel Filters and Pumps Skid Utilities 0 4.25x5x0.5 11


PI-U-942 Potable Water Treatment Skid Utilities 0 7.5x9.5x0.5 36
PI-U-943 Potable Water Pumps Skid Utilities 0 5x5x0.5 13
PI-U-941 Utility Water Pump Skid Utilities 0 5x5x0.5 13
PI-FP-950 Foam Skid Utilities 0 2x3x0.5 3
PI-U950 Firewater Pump Utilities 0 8x8.5x0.5 34
PI-U-952 Jockey Pump Skid Utilities 0 5x5x0.5 13
PI-U-960 Chemical Injection Skid Utilities 0 3.5x12x0.5 21
PI-U-980 Nitrogen Generation Skid Utilities 0 3.5x12x0.5 21
PI-TR-942 Potable Water Storage Tank Utilities 0 Pi x2.5²x0.5 10
Sub-total Utilities Area 175

TOTAL 1798

WARNING: This document as printed may not be the latest version. Please refer to the electronic file in the EDMS
/conversion/tmp/activity_task_scratch/757748457.doc
Doc. Ref.: PP67-PE-GEN-00-DOR-MT-I-120
Peru Block 67 Field
Development Revision: 01 Rev Date : 28-Jul-2011

Status: IFP Class: 3


Civil Works – Concrete & Site
Preparation MTO Page 10 of 20

5.1.2 Concrete Slabs Foundations – Buildings, including Power Generation


Building/ Area Location Phase Dimensions Plots Volume (m3) Notes
PI-UG-1000 A/B/C/D (NPG)
+ E & I Shelter – Utilities Area Utilities 0 30x43.5x0.5 653
+ PI-UG-1001 (EDG)
PI-UG-1000 E/F Utilities 1 12.5x30x0.5 188
PI-U-800 Utilities 0 13x18x0.5 117
PI-U-800 Utilities 1 8x13x0.5 52
E & I Shelter – Process Area Process 0 5x19x0.9 x 85
E & I Shelter – Storage Area Storage 0 5x12.5x0.9 x 58
Administration and Control Building Utilities 0 10x14 x 44
Laboratory Utilities 0 6x10 x 11
Workshop Utilities 0 9x21x0.5 95
Gatehouses Utilities 0 2 x(2x6) x 7
Total 1310

5.1.3 Tanks Foundation


Equipment Location Phase Ext. Radius / Int. Volume (m3) Notes
Radius, Height
(m)
PI-TF-150 A/B/C Crude Storage Tanks Crude Storage 0 3 x Pi x [(9.3²-8.1²)x1.1] 216
PI-U-180 Slop Tank Crude Storage 0 Pi x (4.8² - 3.6²] x 1.1 36
PI-TF-161 A/B Imported Diluent Tanks Crude Storage 0 2 xPi x [(9.3²-8.1²)x1.1] 144
PI-TR-400 Water Skimmer Tank Utilities 0 Pi x [(8.3²-7.1²)x1.1] 64
PI-TR-901 Diesel Storage Tank Utilities 0 Pi x [(6.55²-5.35²)x1.1] 49
PI-TR-950 Firewater Storage Tank Utilities 0 Pi x [(9.3²-8.1²)x1.1] 72
Total 581

5.1.4 Concrete Footings


Item/ Equipment Location Phase Dimensions Volume (m3) Notes
PI-EA-420 Cooling water Air-Cooler Process 0 Piles
Manifold platform in front of Crude Storage
Crude 0 Piles
bund
Elevated Pipe Supports between Equipment
Process 0 9 items 23
and Piperack
Elevated Pipe Supports between Equipment Not taken
Process 1
and Piperack in account
Piperack Process 0 126
Sleepers All plants 0 119 items (section =0.77 m²) 169
Total 318

WARNING: This document as printed may not be the latest version. Please refer to the electronic file in the EDMS
/conversion/tmp/activity_task_scratch/757748457.doc
Doc. Ref.: PP67-PE-GEN-00-DOR-MT-I-120
Peru Block 67 Field
Development Revision: 01 Rev Date : 28-Jul-2011

Status: IFP Class: 3


Civil Works – Concrete & Site
Preparation MTO Page 11 of 20

5.1.5 Concrete Paving


Area Phase Area (m²) Volume (m3) Notes
Process 0 5600 840
Crude Storage Bund 0 3200 480
Area next Crude storage bund (manifold …) 0 780 117
Diluent Storage Bund 0 1900 285
Area next Diluent storage bund 0 120 18
Diesel Storage Bund 0 360 54
Utilities (Hot Oil) 0 300 45
Diluent reception 0 300 45
Total 1884

5.1.6 Basins
Basin Location Phase Basin Dimensions Volume (m3) Notes
(L*l*h)
PI-V-911 Overflow Diverter Basins 0 5 x 6.3 x 4.5 36
PI-TP-911 API Basin Basins 0 7.8 x 20 x 3.9 117
PI-TP-912 Observation Basin Basins 0 25.8 x 68 x 5.15 915
Total 1068

5.1.7 Miscellaneous Re-inforced Concrete Items


Item/ Equipment Location Phase Dimensions Volume (m3) Notes
Bund Wall for Diesel Storage Tank Utilities 0 4x (l=22m; h=2.15) 85
Telecom Mast Foundation Utilities 0 8x9x1 72
Lighting Poles Foundation All plant 0 59 items 35
Open drainage System Manholes All plant 0 81 items (variable dim) 144
Concrete Culvert Pig L/R (-) 75
Not taken in
Road Crossings 3x()
account
Gutter for Electrical Cables in Powergen Area Utilities 0 Length = 62m 25
Open Drain Gutter in Process Area 0 Length = 82m 24
Fence poles foundation 0 123 items / 0.3x0.3x0.5 6 (1)
PI-FM 11 items / 1x3x0.5 17
Total 483
(1) : Assumption : Total Fence length : 1224m, 1 pole every 10 m.

WARNING: This document as printed may not be the latest version. Please refer to the electronic file in the EDMS
/conversion/tmp/activity_task_scratch/757748457.doc
Doc. Ref.: PP67-PE-GEN-00-DOR-MT-I-120
Peru Block 67 Field
Development Revision: 01 Rev Date : 28-Jul-2011

Status: IFP Class: 3


Civil Works – Concrete & Site
Preparation MTO Page 12 of 20

5.1.8 Lean Concrete


Item Location Phase Cumulated Surface (m²) Volume (m3) Notes
Equipment in Process Area (Phase 0) Process 0 1072 53.6
Rest in Process Area Process 0 177 8.85
Equipment in Process Area (Phase 1) Process 1 425 21.3
Equipment in Crude Storage Area Crude Storage 0 236 11.8
Rest in Crude Storage Area Crude Storage 0 474 23.7
Equipment in Diesel Storage Area Diluent Storage & Reception 0 300 15
Rest in Diesel Storage Area Diluent Storage & reception 0 197 9.9
Equipment in Utilities Area (Phase 0) Utilities 0 2180 109
Rest in Utilities area Utilities 0 642 32.1
Equipment in Utilities Area (Phase 1) Utilities 1 747 37.4
Equipment in Basins Area Basins 0 1945 97.3
Equipment in CD and Flare Area CD & Flare 0 267 13.4
Open drainage System Manholes All plants 0 117 5.85
Total 439

5.2 Steel Re-inforcements

Item Location Volume (m3) Steel weight (tonnes)


Equipment Sub-total Process Area 1001 100
Sub-total Water Treatment 257
Equipment 26
Area
Sub-total Crude Storage 99
Equipment 10
Area
Equipment Sub-total Pigs L/R Area 117 12
Equipment Sub-total CD & Flare Area 119 12
Equipment Diluent Storage Area 30 3
Equipment Sub-total Utilities Area 175 18
Building All plants 1310 131
Tanks All plants 581 58
Footings All plants 318 32
Paving All plants 1884 188
Basins All plants 1068 107
Miscellaneous Re-inforced Concrete Items All plants 483 48
Total 7442 745

WARNING: This document as printed may not be the latest version. Please refer to the electronic file in the EDMS
/conversion/tmp/activity_task_scratch/757748457.doc
Doc. Ref.: PP67-PE-GEN-00-DOR-MT-I-120
Peru Block 67 Field
Development Revision: 01 Rev Date : 28-Jul-2011

Status: IFP Class: 3


Civil Works – Concrete & Site
Preparation MTO Page 13 of 20

5.3 Geotextile

Item Location Dimension Surface geoweb (m²) Surface geomembrane (m²)


Road Process 247.5x6 1485 1485
Road Process 115x3 345 345
Road Utilities 115x3 345 345
Road Utilities 367.5x6 2205 2205
Road Crude Storage 235x4 940 940
Road Crude Storgae 120x6 720 720
Road Diluent storage 290x4 1160 1160
Road Diluent storage 120x6 720 720
Road Diluent Reception 85x6 510 510
Bund Diluent Storage 3.5x200 700
Bund Crude Storage 3.5x240 840
Slope (1:1) Diluent Pumps 2.75x25 +1.4x65 160
Slope (1:1) Crude Slipping / Reprocessing Pumps 2.75x70 +1.4x35 240
Total 8430 10 370

WARNING: This document as printed may not be the latest version. Please refer to the electronic file in the EDMS
/conversion/tmp/activity_task_scratch/757748457.doc
Doc. Ref.: PP67-PE-GEN-00-DOR-MT-I-120
Peru Block 67 Field
Development Revision: 01 Rev Date : 28-Jul-2011

Status: IFP Class: 3


Civil Works – Concrete & Site
Preparation MTO Page 14 of 20

6 CT CIVIL WORKS MTO

6.1 Civil Reinforced Concrete

6.1.1 Concrete Slabs Foundations - Equipments


Equipment Dimensions Volume (m3) Notes
CT-KC-930 A/B Air compressor 4x4.5x0.5 9
CT-M-163 Diluent Metering Unit 3x3x0.5 4
CT-M-173 Crude Metering Unit 3x6x0.5 9
CT-PA-161ABC Diluent export pump 6x10x0.5 30
CT-PA-942A/B Potable Water Pump 3x4x0.5 6
CT-PL-160 Diluent Pig Launcher 3.5x9.5x0.5 17
CT-PR-171 Crude Oil Pig Receiver 3.5x13.5x0.5 24
CT-TR-942 Potable water tank 2x2x0.5 2
CT-U-172 Instrumentation skid 4.5x9x0.5 20
CT-U-932 A/B Instrument air dryers With ct-kc-930
CT-U-942 Potable water treatment 4.5x4.5x0.5 10
CT-U-960 Chemical injection skid 4x5x0.5 10
CT-V-933 Instrument air receiver 2.5x4.7x0.5 6
CT-VF-941 Utility water filter 0.4x0.4x0.5 0
CT-SH-201 MCC 9x12x0.5 54
Total 201

Notes:

6.1.2 Concrete Slabs Foundations – Buildings, including Power Generation


Building/ Area Dimensions Plots Volume (m3) Notes
Mess Catering 2.5x10 x 6
Administration and Control Building 2x(2.5x10) x 12
Laboratory 2.5x5 x 4
Gatehouses 2x6 x 4
CT-UG-100 A/B Main power generator 5.5x7x0.5 19
CT-UG-101 Emergency diesel generator 3.5x5.5x0.5 10
Total 55

Notes:

6.1.3 Concrete Footings


Item/ Equipment Dimensions Volume (m3) Notes
Sleepers 77 items (section =0.77 m²) 92
Total 92

WARNING: This document as printed may not be the latest version. Please refer to the electronic file in the EDMS
/conversion/tmp/activity_task_scratch/757748457.doc
Doc. Ref.: PP67-PE-GEN-00-DOR-MT-I-120
Peru Block 67 Field
Development Revision: 01 Rev Date : 28-Jul-2011

Status: IFP Class: 3


Civil Works – Concrete & Site
Preparation MTO Page 15 of 20

6.1.4 Concrete Paving


Area Dimensions Volume (m3) Notes
Ct-PL-160 32 5
CT-U-172 50 7.5
CT-PA-942 70 10.5
CT-U-942 16 2.5
Buildings 170 25.5
Power Generator Area 290 43.5
Crane 110 16.5
Total 111

6.1.5 Vent Pit


Equipment Basin Dimensions Volume (m3) Notes
(L*l*h)
Vent Pit 2x2x2 3
Total 3

6.1.6 Miscellaneous Re-inforced Concrete Items


Item/ Equipment Dimensions Volume (m3) Notes
Telecom Mast Foundation 8x9x1 72
Open drainage System Manholes 7 items (variable dim) 5
Fence poles foundation 46 items / 0.3x0.3x0.5 2 (1)
Total 79
Assumption : Total Fence length : 460m, 1 pole every 10 m.

6.1.7 Lean Concrete


Equipment Cumulated Surface Volume (m3) Notes
Equipment 460 23
Rest 220 11
Total 34

6.2 Steel Re-inforcements

Item Volume (m3) Steel weight (tonnes)


Equipment 201 20
Concrete Slabs Foundations – Buildings, including Power 54 5
Generation
Footings 92 9
Paving 111 11
Vent pit 3 0
Miscellaneous Re-inforced Concrete items 79 8
Total 540 54

WARNING: This document as printed may not be the latest version. Please refer to the electronic file in the EDMS
/conversion/tmp/activity_task_scratch/757748457.doc
Doc. Ref.: PP67-PE-GEN-00-DOR-MT-I-120
Peru Block 67 Field
Development Revision: 01 Rev Date : 28-Jul-2011

Status: IFP Class: 3


Civil Works – Concrete & Site
Preparation MTO Page 16 of 20

6.3 Geotextile

Item Location Dimension (m) Surface for geoweb(m²) Surface for geomembrane(m²)
Road 28x3 84 84
Road 324x4 1296 1296
Road 25x6 150 150
Parking 10*16 160 160
Ditch 650x1.2 780
Total 1690 2470

WARNING: This document as printed may not be the latest version. Please refer to the electronic file in the EDMS
/conversion/tmp/activity_task_scratch/757748457.doc
Doc. Ref.: PP67-PE-GEN-00-DOR-MT-I-120
Peru Block 67 Field
Development Revision: 01 Rev Date : 28-Jul-2011

Status: IFP Class: 3


Civil Works – Concrete & Site
Preparation MTO Page 17 of 20

7 PPI1 CIVIL WORKS MTO

7.1 Civil Reinforced Concrete

7.1.1 Concrete Slabs Foundations - Equipments


Equipment Phase Dimensions Volume Notes
(m3)
P1-IW-01 Injection wells 0 17 Special foundation
P1-IW-2/3 Injection wells 1 41 Special foundation
P-PW-1/2/3/4/5 Production wells 0 85 Special foundation
P1-U-001 Manifold 0 6x11x0.5 33
P1-U-003 Water injection skid 0 7.5x9.5x0.5 36
P1-U-960 Chemical injection skid 0 3x4x0.5 6
P1-UA-930 Air compressor package 0 4.5x8x0.5 18
P1-V-933 Instrument air receiver 0 With-UA-930
HL-LV Voltage 0 4.5x11.5x0.5 26
HL-LV-Instrumentation 0 4.5x9.5x0.5 21
HL-LV-Transformers 0 2.5x4.5x0.5 6
Transfo & VSD 0 7.5x15x0.5 56
Total 345

7.1.2 Trench
Phase Dimensions Volume (m3) Notes
Concrete Slab 0 7x78x0.2 109

Excavation in earth :675m3

7.1.3 Concrete Footings


Item/ Equipment Phase Dimensions Volume (m3) Notes
Sleepers 0 77 items (section =0.77 m²) 84

7.1.4 Basins
Equipment Phase Basin Dimensions (L*l*h) Volume (m3) Notes
P1-TP-911 API Basin 0 2.1 x 8.5 x 4 20
Vent Pit 0 5x5x1.7 15
Total 35

WARNING: This document as printed may not be the latest version. Please refer to the electronic file in the EDMS
/conversion/tmp/activity_task_scratch/757748457.doc
Doc. Ref.: PP67-PE-GEN-00-DOR-MT-I-120
Peru Block 67 Field
Development Revision: 01 Rev Date : 28-Jul-2011

Status: IFP Class: 3


Civil Works – Concrete & Site
Preparation MTO Page 18 of 20

7.1.5 Miscellaneous Re-inforced Concrete Items


Item/ Equipment Phase Dimensions Volume (m3) Notes
Open drainage System Manholes 0 10 items (variable dim) 12
Fence poles foundation 0 75 items / 0.3x0.3x0.5 3 (1)
Total 15
Assumption : Total Fence length : 746m, 1 pole every 10 m.

7.1.6 Lean Concrete

Equipment Phase Cumulated Surface Volume (m3) Notes


Equipment 0 476 24
Equipment 1 70 3.5
Rest 0 175 9
Total 36.5

7.2 Steel Re-inforcements

Item Volume (m3) Steel weight (tonnes)


Equipment 345 35
Trench 109 11
Footings 84 8
Basins 35 4
Miscellaneous Re-inforced Concrete items 15 2
Total 588 60

7.3 Geotextile

Item Location Dimension Surface for geoweb (m²) Surface for geomembrane (m²)
Road 358x4 1432 1432
Parking 10*15 150 150
Drilling area 5850
Total 7432 1582

WARNING: This document as printed may not be the latest version. Please refer to the electronic file in the EDMS
/conversion/tmp/activity_task_scratch/757748457.doc
Doc. Ref.: PP67-PE-GEN-00-DOR-MT-I-120
Peru Block 67 Field
Development Revision: 01 Rev Date : 28-Jul-2011

Status: IFP Class: 3


Civil Works – Concrete & Site
Preparation MTO Page 19 of 20

8 PPI3 CIVIL WORKS MTO

8.1 Civil Reinforced Concrete

8.1.1 Concrete Slabs Foundations - Equipments


Equipment Phase Dimensions Volume Notes
(m3)
P3-PW-01/2/3/4/5/6 Production wells 0 102 Special foundation
P3-PW-7 Production wells 1 34 Special foundation
P3-PL-100 Crude Oil Pig Launcher 0 4.5x11x0.5 25
P1-U-001 Manifold 0 6x11x0.5 33
P1-U-960 Chemical injection skid 0 3x4x0.5 6
P1-UA-930 Air compressor package 0 4.5x8x0.5 18
P1-V-933 Instrument air receiver 0 With-UA-930
HL-LV Voltage 0 4.5x11.5x0.5 26
HL-LV-Instrumentation 0 4.5x9.5x0.5 21
HL-LV-Transformers 0 2.5x4.5x0.5 6
Transfo & VSD 0 7.5x15x0.5 56
Total 327

8.1.2 Trench
Phase Dimensions Volume (m3) Notes
Concrete Slab 0 7x52x0.2 73

Excavation in earth : 450 m3

8.1.3 Concrete Footings


Item/ Equipment Phase Dimensions Volume (m3) Notes
Sleepers 0 53 items (section =0.77 m²) 50

8.1.4 Basins
Equipment Phase Basin Dimensions (L*l*h) Volume (m3) Notes
P1-TP-911 API Basin 0 2.1 x 8.5 x 4 20
Vent Pit 0 5x5x1.7 15
Total 35

8.1.5 Miscellaneous Re-inforced Concrete Items


Item/ Equipment Phase Dimensions Volume (m3) Notes
Open drainage System Manholes 0 9 items (variable dim) 10
Fence poles foundation 0 79 items / 0.3x0.3x0.5 4 (1)
Total 14
Assumption : Total Fence length : 782m, 1 pole every 10 m.

WARNING: This document as printed may not be the latest version. Please refer to the electronic file in the EDMS
/conversion/tmp/activity_task_scratch/757748457.doc
Doc. Ref.: PP67-PE-GEN-00-DOR-MT-I-120
Peru Block 67 Field
Development Revision: 01 Rev Date : 28-Jul-2011

Status: IFP Class: 3


Civil Works – Concrete & Site
Preparation MTO Page 20 of 20

8.1.6 Lean Concrete


Equipment Phase Cumulated Surface Volume (m3) Notes
Equipment 0 453 23
Rest 0 130 6.5
Total 29.5

8.2 Steel Re-inforcements

Item Volume (m3) Steel weight (tonnes)


Equipment 327 33
Trench 73 7
Footings 50 5
Basins 35 4
Miscellaneous Re-inforced Concrete items 14 1
Total 499 50

8.3 Geotextile

Item Location Dimension Surface for geoweb (m²) Surface for geomembrane (m²)
Road 307x4 1228 1228
Parking 8*16 128 128
Drilling area 8186
Total 9542 1356

WARNING: This document as printed may not be the latest version. Please refer to the electronic file in the EDMS
/conversion/tmp/activity_task_scratch/757748457.doc