GENERAL NOTES

I. GENERAL: 4. FOUNDATION BED:


LEGENDS MEANING
ABBREVATIONS:
In the interpretation of drawings, indicated dimensions shall govern. All dimensions Foundation bed shall be excavated to the lines and grades as shown in the PLAN
and sizes shall not be scaled for construction purposes, unless otherwise indicated, plans.Care must be observed in the removal of excavated materials and
BENCHMARK
all dimensions are in meters. shall not be used as embankment for depressions or fill sections. Peat, BM - BENCHMARK

muck and other unsuitable foundation shall be excavated and removed, to BRIDGE
CU.M - CUBIC METER
II. DESIGN CRITERIA: expose suitable bed that is satisfactory to the Project Engineer.
SQ.M - SQUARE METER NORTH
1. DPWH STANDARD SPECIFICATION (2013) 5. EMBANKMENT: DIRECTION

2. NSCP, Volume II, (2010 Edition)


STA. - STATION
3. FCSEC-I: Technical Standards & Guidelines for Flood Control Structures Embankment materials shall meet the compaction and construction requirements
specified under Item 104-2 Selected Borrow of DPWH Standard Specs, 2013 MLLW - MEAN LOWER LOW WATER
Edition.
III. DESIGN CONSIDERATION: MHHW - MEAN HIGHEST HIGH WATER
6. WATER LEVEL:
1. Stability of Slopes is analyzed by Simplified Bishop's Method. MEAN LOWER LOW WATER = 3.16 m
MEAN HIGHEST HIGH WATER= 7.50 m
IV. MATERIAL/CONSTRUCTION REQUIREMENTS:

1. CLASS "A" CONCRETE V. CONSTRUCTION JOINT:


1. Construction joints shall be properly filled up with asphalt sealant
a.) fc = 21 MPa @ 28 days to avoid water intrusion in the foundation bed.
b.) Construction specification for Concrete shall be in accordance with 2. Construction joints shall be spaced at 50 m on center.
AASHTO & DPWH Standards 3. Asphalt sealant to be use shall be in accordance to DPWH Standard
Specifications, 2013 Edition.
2. REINFORCING STEEL BARS:
VI. AS STAKE:
a.) fy = 275 MPa (Grade #40) The corresponding "as staked" plan shall be SURVEYED by the contractor and
b.) Construction specification for RSB shall be in accordance with subject for approval by the DISTRICT ENGINEER.
AASHTO & DPWH Standards.
c.) All reinforcements surfaces shall have min. clear cover of 75 mm.

3. HEXAPODS :(SPURDIKE & TOE / SCOUR PROTECTION)


a.) Concrete shall be class "A" In Accordance to Item 405, Structural
Concrete (DPWH Standards Specifications, 2013)
b.) Alignment of the spurdike shall be deflected upstream in making a
deflection angle of 10° to 15° and 5° to 10° with the line perpendicular to
the bank at straight and concave sections respectively.
c.) The arrangement, height, length and width of the crest of the spurdike
shall be based on the details as shown in the plan.

PROJECT NAME AND LOCATION: SHEET CONTENTS: DRAFTED: REVIEWED: SUBMITTED: RECOMMENDED: APPROVED: SET NO. SHEET NO.

REPUBLIC OF THE PHILIPPINES CONVERGENCE AND SPECIAL SUPPORT PROGRAM (CSSP): DIANA R. ABALOS
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS
GENERAL NOTES
ENGINEER II (CTO) PDS
REGIONAL OFFICE II (SIPAG) - FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC 3
CAGAYAN 2ND DISTRICT ENGINEERING INFRASTRUCTURE/FACILITIES - CONSTRUCTION OF SEAWALL ABBREVIATION PREPARED BY: CSDEO
ALONG THE SHORELINE OF CLAVERIA, CAGAYAN
LEGENDS KRISTIAN T. RAGUIRAG ROMEO D. YAQUIN RELLIE V. SIMBE OSCAR G. GUMIRAN, MPA
OFFICE CLAVERIA, CAGAYAN
ENGINEER II CHIEF, PLANNING AND DESIGN SECTION ASSISTANT DISTRICT ENGINEER DISTRICT ENGINEER HDU 16
LIBERTAD, ABULUG, CAGAYAN JERICK U. QUINES
ENGINEER II DATE: DATE: DATE: DATE: