Contractor: EJ-R Building Designs and Services

Client: Joerile Joey & Eva Abuan


Site Name: Two Storey Residential
Site Address: Central East, Bauang, La Union
Lot Area: sq m
Subject: Qoutation for Cabinetry
Date:

AS PER PLAN
ITEM NUMBER WORK DESCRIPTION QTY UNIT
Unit Cost Total Cost

CONSTRUCTION PRELIMINARIES 3,000.00


CP 01 Mobilization / Demolition and As-Built/Shop Drawing Preparation -
CP 01-1 Architectural and Structural Plans lot - -
CP 01-2 Mobilization 1.00 lot - -

CP 02 Securing of Necessary Permits (Signed and Sealed) -


CP 03 Provision of Temporary Power / Facilities -
CP 04 Handling, Hauling and Delivery of all Supplied Items (from supplier to site) 3,000.00
CP 04-1 Transport of small miscellaneous items (such as powertools, equipments, etc.) 1.00 lot 3,000.00 3,000.00

CP 05 Site Clearing / Lay-out and Earthworks -


CIVIL / STRUCTURAL WORKS -
ARCHITECTURAL / FINISHING WORKS 23,547.50
AW 05 Paint Works 2,975.00
AW 05-1 Base Paint 3.00 gal 250.00 750.00
AW 05-2 Latex Paint (Semi Gloss Finish) 4.00 gal 250.00 1,000.00
AW 05-7 Plastering 25.00 sq m 25.00 625.00
AW 05-8 Sandpaper 5.00 lm 120.00 600.00

AW 06 Carpentry Works 20,572.50


AW 06-2 Cabinets
AW 06-2.1 Marine Plywood 3/4 23.50 sqm 525.00 12,337.50
AW 06-2.2 Hinges and Rollers 21.00 pcs 275.00 5,775.00
AW 06-2.3 Dish Rack 2.00 pcs 1,230.00 2,460.00

MISCELANEOUS 884.16
MW 01 Personal Protective Equipment 353.21
MW 01 Skull Guard, Gloves,Safety Shoes, etc. 1.00 lot 117.74 117.74
MW 01-1 First-aid Kit 1.00 lot 235.48 235.48

MW 02 Emergency Fund 530.95


MW 02 Fund for Accidents ( Refundable if not used ) 1.00 lot 530.95 530.95

*All material prices may vary depending on the market price


*Note: Not Detailed Estimate
*Light Fixtures Not Included

ITEM NUMBER WORK DESCRIPTION TOTAL MATERIAL COST LABOR COST


CP CONSTRUCTION PRELIMINARIES ₱ 3,000.00 ₱ 390.00
CW CIVIL / STRUCTURAL WORKS ₱ - ₱ -
EW ELECTRICAL WORKS ₱ - ₱ -
PW PLUMBING WORKS ₱ - ₱ -
AW ARCHITECTURAL/ FINISHING WORKS ₱ 23,547.50 ₱ 11,773.75
MW MISCELANEOUS ₱ 884.16

₱ 27,431.66 ₱ 12,163.75

TOTAL COST ₱ 39,595.41


CONTRACTOR'S MARK UP ₱ 6,094.52

TOTAL CONSTRUCTION COST ₱ 45,689.93

Prepared by:
Rimando, Erwin P
Representative of EJ-R Building Design & Services