KEYPLAN

6 5 4 3 2 1
30000
RP - 3
TP - 5 TP - 6
6000 6800 5200 6000 6000

RP - 9 RP - 10 RP - 1

C21 C17 C13 C9 C5 C1


A
PC21 PC17 PC13 PC9 PC5 PC1

TP - 1
RP - 4 RP - 2

6000
TP - 13

RP - 5 RP - 8

C22 C18 C14 C10 C6 C2


B
RP - 6 RP - 7

PC22 PC18 PC14 PC10 PC6 PC2

18000
6000
C23 C19 C15 C11 C7 C3
C
PC23 PC19 PC15 PC11 PC7 PC3

6000
TP - 2

CONTROL BLDG.
D
CURRENT ACCOMPLISHMENT AS OF APRIL 24-30, 2024 PC24
C24

PC20
C20

PC16
C16

PC12
C12

PC8
C8

PC4
C4

LEGEND: TP - 3 TP - 4

- PREVIOUS ACCOMPLISHMENT OF DRIVEN PILES (WITH REFUSAL)


17
Pile Status: (17.70%)
96 - PREVIOUS ACCOMPLISHMENT OF DRIVEN PILES (NO REFUSAL & TILTED PILE)

Pile with no refusal & tilted: 1pos (PC-24; #3) - CURRENT ACCOMPLISHMENT OF DRIVEN PILES (WITH REFUSAL AS OF APRIL 24-30, 2024)

Pile still for driving due to breakdown: 1pos (PC-21; - CURRENT ACCOMPLISHMENT (PDA TESTING - DONE LAST APRIL 24, 2024)

- CURRENT ACCOMPLISHMENT (PIT TESTING - DONE APRIL 24, 2024)


#2) - CURRENT ACCOMPLISHMENT (PILE FOR CONTINUATION OF DRIVING WORKS AS OF APRIL 24-30, 2024)

Fabrication of Piles: 97 96 (100%)


Delivered Piles: 59 96 (61.46%)
Current Stockpile on Piles: 42pcs.

MAIN CONTROL BUILDING LAYOUT