RABIGH-3
1 BASE DESIGN FOR 110KV GAS INSULATED SWITCHGEAR
Substation
RABIGH-3
2 BASE DESIGN FOR 110KV GAS INSULATED SWITCHGEAR
Substation
RABIGH-3
3 BASE DESIGN FOR 110KV GAS INSULATED SWITCHGEAR
Substation
RABIGH-3
4 BASE DESIGN FOR 110KV GAS INSULATED SWITCHGEAR
Substation
RABIGH-3
5 BASE DESIGN FOR 110KV GAS INSULATED SWITCHGEAR
Substation
RABIGH-3
6 BASE DESIGN FOR 110KV GAS INSULATED SWITCHGEAR
Substation
RABIGH-3
7 BASE DESIGN FOR 110KV GAS INSULATED SWITCHGEAR
Substation
RABIGH-3
8 BASE DESIGN FOR 110KV GAS INSULATED SWITCHGEAR
Substation
RABIGH-3
9 BASE DESIGN FOR 110KV GAS INSULATED SWITCHGEAR
Substation
RABIGH-3
10 FACTORY ROUTINE INSPECTION PLAN-GIS
Substation
RABIGH-3
11 BASE DESIGN FOR 110KV LCC
Substation
RABIGH-3
12 110KV LCC DESIGN (AD06)
Substation
RABIGH-3
13 110KV LCC DESIGN (AD22)
Substation
RABIGH-3
14 PARTIAL DISCHARGE SYSTEM FOR 110KV GIS
Substation
RABIGH-3
15 CABLE LIST/CABLE CONNECTION BETWEEN LCC TO GIS
Substation
RABIGH-3
16 TECHNICAL SUBMITTAL FOR LV POWER & CONTROL CABLE
Substation
RABIGH-3
17 TECHNICAL MATERIAL DESIGN FOR POWER CABLE CLAMPS
Substation
RABIGH-3
18 110KV LINE PROTECTION RELAY SETTING CALCULATION
Substation
RABIGH-3 CABLE LIST & TERMINATION SCHEDULE (FOR GE SUPPLIED
19
Substation EQUIPMENT)
RABIGH-3
20 PREPARATION OF INTERFACE MARKUP DRAWINGS
Substation
RABIGH-3
21 PROTECTION PANEL LIST AT RABIGH-3 END
Substation
RABIGH-3
22 PROTECTION RELAY LIST AT RABIGH-3 END
Substation
RABIGH-3
23 METERING BASE DESIGN AT RABIGH-3 END
Substation
RABIGH-3
24 AC/DC LOAD CALCULATIONS AT RABIGH-3 END
Substation
RABIGH-3
25 110KV FEEDER PROTECTION PANEL (SET-1) - (AD06 )
Substation
RABIGH-3
26 110KV FEEDER PROTECTION PANEL (SET- 2) - (AD06)
Substation
RABIGH-3
27 110KV FEEDER PROTECTION PANEL (SET-1) - (AD22)
Substation
RABIGH-3
28 110KV FEEDER PROTECTION PANEL (SET- 2) - (AD22)
Substation
RABIGH-3
29 AMI SYSTEM DESIGN AT RABIGH-3 END
Substation
RABIGH-3 CUSTOMER METERING PANEL -ENERGY METERING AT
30
Substation RABIGH-3 END
RABIGH-3
31 INTERFACE PANEL AT RABIGH-3 END
Substation
RABIGH-3
32 GATE WAY PANEL (WITH OFMR) AT RABIGH-3 END
Substation
33 RABIGH-4 (IWP) PROTECTION PANEL LIST AT RABIGH-4 END
LAYOUT - RABIGH-3
Tiejun/ACWA
Tiejun/ACWA
Tiejun/ACWA
Tiejun/ACWA
Tiejun/ACWA
Tiejun/ACWA
Tiejun/ACWA
Tiejun/ACWA
Tiejun/ACWA
Tiejun/ACWA
Tiejun/ACWA
Tiejun/ACWA
Tiejun/ACWA
Tiejun/ACWA