Professional Documents
Culture Documents
QR 2
QR 2
REVISED 0.0
With saying thank you to Allah SWT the completion for the Quarterly Report I – Implementation
Consultant Report (IC) Regional SPAM Wosusokas Central Java is finished in March 2022. This
quarterly report describes the progress of the IC Team's performance and the development of the
Regional SPAM Wosusokas Project Central Java in the first quarterly period, January 2022 until
March 2022.
The information in the Quarterly Report I are mainly focuses on the activities of:
• Development of information on preparation for regional SPAM development that has been
carried out by IC consultants in the form of land identification and planning/DED WTP and
MDP as well as the process of preparing WTP tender documents
• Discussion on the absorption of Regional SPAM capacity in each Regency/City in the form
of programs and budgets.
We thank the parties who have helped in the smooth completion of the preparation of the Quarterly
Report 2 – IC Regional SPAM Wosusokas Central Java.
Klaus Kirchenbaur
Team Leader
IC Regional SPAM Wosusokas
IC SPAM REGIONAL WOSUSOKAS – Contract 06/PKK/PSPAM-KONS-IC.01/2021 Page i
Quarterly Report 1
1 EXECUTIVE SUMMARY............................................................................................................... 6
2 PROJECT BACKGROUND AD OBJECTIVES.................................................................................... 6
3 SECTOR ENVIRONMENT............................................................................................................. 8
4 CONSULTANT’S ACTIVITIES DURING THE REPORTING PERIOD ................................................... 9
4.1 Overview and General Setup ........................................................................................................................ 9
4.2 General activities ......................................................................................................................................... 9
4.3 Review of Existing DED ................................................................................................................................. 10
4.3.1 Review of DED for WTP ......................................................................................................................................... 10
4.3.2 Review of DED for water distribution network ...................................................................................................... 11
4.4 Preparation of prequalification documents................................................................................................... 12
4.5 Preparation of tender documents for WTP ................................................................................................... 13
4.6 Review of current ESIA aspects ..................................................................................................................... 14
4.7 Meetings ...................................................................................................................................................... 14
4.8 Workplan and staffing schedule ................................................................................................................... 15
Annexes:
Annex 1 - List of project documents
Annex 2 – Summary of project meetings
Annex 3 – Work Progress
KEY DATA
LIST OF ACRONYMS
Acr. Description
AMDAL Analisis Mengenai Dampak Lingkungan / Environmental Impact Assessment (EIA)
BAPPEDA Badan Perencanaan Pembangunan Daerah / Provincial Development Planning Agency
Badan Perencanaan Pembangunan Nasional / Ministry of
BAPPENAS
National Development Planning / National Development Planning Agency
BBWS Balai Besar Wilayah Sungai / River Basin Authority
BPKAD Badan Pengelolaan Keuangan & Aset Daerah / Regional Asset Management Agency
BPPW Balai Prasarana Permukiman Wilayah / Regional Center for Settlement Infrastructures
CD Commencement date
DG Directorate General
IC Implementation Consultant
ICB International Competitive Bidding
IFI International Financing Institute
IM Inception Meeting
IR Inception Report
PQ Prequalification
RPJMN Rencana Pembangunan Jangka Menengah Nasional / National Medium-Term Development Plan
SIPPA Surat Ijin Pengambilan dan Pemanfaatan Air / water extraction permit
TD Tender Documents
1 EXECUTIVE SUMMARY
This first Quarterly Report (QR1) is covering the period 1st January 31st March 2022. The report was prepared
following the instructions and the standard form of the ToR. Chapters not relevant with the activities carried
out, such as for instance chapter 5 “Progress of Construction Works” were left blank not to modify the
standard structure of the document.
In this second quarter from the start of the project activities on 1st October 2021, the following was achieved
and /or undertaken:
• Redesign of the process of the WTU and the adaptation of the layout. IC was requested to include
review/completion of the DED among its tasks. The process has been completed so far but finalizing
the documentation to a level which allows a hassle free tendering is not yet achieved.
• Call for Expression of Interest on with the corresponding evaluation of the potential bidders. As no
satisfying result could be achieved the repetition of the process was initiated and launched on 4th of
March 2022. The process is actually ongoing.
• Distribution system DED review – Following initial review of the documentation, several
shortcomings were observed, including the need to incorporate a new topographic survey among
the IC tasks. This part has been finished and agreements finally have been signed with the offtakers
concerning the distribution of abstracted quantities from the system. Final legal ratification is about
to be concluded. By executing a corresponding mathematical simulation of the entire system and the
results are incorporated in the new design. However the level of documents needs still final finishing.
The actual level is not up to the necessary threshold which allows a tender process and construction
within an acceptable level of problems.
• Meetings – following request from PMU, regular weekly meetings were instated. These and other
special meetings brought the total number of meetings held to 16 for the 3- months reporting period;
according to this change.
• The IC was requested to assist in the budget revision requested by the ministry. This activity was not
set in the ToR to the required extent hence the process absorbed quite a lot of time and manpower.
• A site visit was carried out together with the Client on 25th of January to the WTP site and the sites
of the offtakers reservoirs. The IC received in this opportunity leading instructions for the ongoing
designs from the client. During the event were found some social and physical restrictions which
influenced and will impact considerably on the layout and construction of the JDU. Another site visit
in the frame of the review of current ESIA aspects with a a joint survey of land ownership with BPPW,
BBWS and PDAB was carried out to re-identify land owned by residents that could potentially be
affected by the SPAM Development (JDU). The survey was conducted in 3 villages (Giritirto,
Giripurwo and Giriwono). It was found out that in all villages there is land owned by residents (SHM
& Letter C) that is affected.
To support the implementation of the above works, services of an Implementation Consultant (IC) have been
contracted to the JV HYDEA-SWS Consulting- KOGAS for a total value of 3,000,988 €. The tasks of the IC
include:
Task 1: Review/update existing DED
Task 2 : Assistance during Tendering
Task 3: Supervising works of construction
Task 4: Assistance during Defect Liability Period
The IC contract has a duration of 38 calendar months and the commencement date was established on 1st
October 2021.
3 SECTOR ENVIRONMENT
The development of the Government of Indonesia's policy on environmental management has undergone
changes through Government Regulation No. 22 of 2021 concerning the Implementation of Environmental
Protection and Management. The changes in government regulations, among others, regulate risk-based
environmental management from human activities or business entities including development in the drinking
water sector which is regulated through Minister of Environment and Forestry Regulation Number 4 of 2021
concerning the list of businesses and/or activities that are required to have an analysis. regarding
environmental impacts, environmental management efforts and environmental monitoring efforts or a
statement of ability to manage and monitor the environment.
Drinking Water Supply System (SPAM) is a strategic sector as regulated in Government Regulation of the
Republic of Indonesia No. 122 of 2015 concerning the Drinking Water Supply System. The Government of the
Republic of Indonesia continues to strive for the development of a Drinking Water Supply System (SPAM) to
improve service outcomes to the community in an effort to improve public health, including efforts to
prevent water-borne diseases, including the current COVID-19 pandemic. Drinking water is an important
sector for preventing the spread of the Covid-19 disease, this is in accordance with the Decree of the Minister
of Health of the Republic of Indonesia No. HK.01.07/MENKES/382/2020 to ensure the availability of safe
quality water to support personal hygiene,
The government's plan related to SPAM is stated in Presidential Regulation no. 18 of 2020 concerning the
National Medium-Term Development Plan (RPJMN) for 2020-2024 which contains regulations regarding the
provision of access to safe and decent drinking water by 2024. This effort is carried out through the
development of piped drinking water supply and not piped networks, the target is water access drinking
water is 87.75 percent, the target of 2024 access to safe drinking water is 100 percent. Then, access to safe
drinking water in 2019 is only 6.8 percent targeted to reach 15 percent in 2024. Furthermore, pipe network
SPAM 20.14 percent in 2019 is targeted to reach 30 percent in 2024. In addition, the rate of water loss from
2019 is 33 percent to 25 percent by 2024. This commitment is an effort and supports the global action plan
for Sustainable Development Goals (SDG's) 6.1 which calls for access to 100% safe and affordable universal
drinking water by 2030. 59 of 2017 concerning the Implementation of the Achievement of the Sustainable
Development Goals.
One of these targets is carried out through a regional drinking water supply system and implemented in
several provinces, one of which is the Wosusokas Regional Drinking Water Supply System (SPAM)which is
planned to meet drinking water needs in Wonogiri Regency, Sukoharjo Regency, Surakarta City, and
Karanganyar Regency in Central Java Province, Indonesia, with a source raw water from Gajah Mungkur
Reservoir located in Wonogiri Regency.
With the development of the Wosusokas Regional Drinking Water Supply System (SPAM), it will create and
increase job opportunities by providing convenience, protection, and empowerment for national industry
and trade as an effort to be able to absorb the widest possible Indonesian workforce while taking into account
the balance and progress between regions in the national economic unity. . The construction of the
Wosusokas Regional Drinking Water Supply System (SPAM) with a system capacity of 750 liters/second is
distributed to 4 districts/cities along approximately 80 km through the use of water resources and activities
for the construction of Water Treatment Plants (IPA), Main Distribution Networks (JDU) and land acquisition
which will have an impact on environment. Therefore, environmental protection and management efforts
(PPLH) in this project are carried out in accordance with Government Regulation no.
Another policy used in the implementation of regional SPAM development construction is the Minister of
Public Works and Public Housing Regulation no. 9 of 2021 concerning Guidelines for the Implementation of
Sustainable Construction. In the regulation Article 3 (1) the implementation of Construction Services for
constructing buildings and/or civil buildings must implement Sustainable Construction. (2) Sustainable
Construction as referred to in paragraph (1) has 3 (three) basic pillars including: a. economically feasible and
can improve the welfare of the community; b. maintains environmental preservation; and c. reduce social
disparities in society. As an effort to implement the above policy, the development of the Wosusokas
Regional Drinking Water Supply System (SPAM) applies Safeguards in the construction implementation as an
effort to protect the environment and social environment as necessary risk identification and mitigation
activity.
oversight plans and finishing the detailed design plans during the consulting period of the running tender.
The consultant will propose the necessary personnel and logistic needs to the client in order to fix the
necessary setup for completion of the works by means of an addendum to the existing consulting contract.
This addendum will also ratify the necessary changes in the personnel structure of the IC in the past periods
Staff mobilization
The Consultant staff has been almost fully mobilized during the inception period, most of the staff from the
date of the start of the services, i.e. 1st October, 2021. As agreed during the contract negotiations, during
the inception phase of the project the participation of the international key experts, including the Team
Leader and the Sub-Team Leader, has been ensured as part-time home support, due to current travel
restrictions to Indonesia. The team leader finally mobilized on 10th of January and started the activities on
site after his arrival on site in Semarang on 15th of January.
Logistic organization
As per ToR, the following project have been established:
• One office of about 100 m2 in Jakarta with one office room and one meeting room, and fully
operational since 7th October;
• One office of about 400 m2 in Semarang, fully operational since 15th October 2021
Suitable arrangements were made for hiring vehicles to ensure adequate transport facilities from Semarang
to the project sites. The logistic setup was completed in the last period and has proven its efficiency.
Documentary review
The document collection and review of the received documents have finished however the IC must state that
up to date no memories of calculations were put at disposition of the IC in order to compare the drawings
with their corresponding base. Necessary calculations carried out were showing partly considerable
discrepancies with the setups in the drawings.
p. Preparation of REKOMTEK (Technical Recommendation) for segment 14 km of JDU network pipe and
Railway crossing.
Deliverables and outputs during the second Quarter period on the scope of review of DED for water
distribution network is described as follow
1. 13 Weekly meeting PPT materials
2. 3 Monthly progress reports
3. Design Memo (Draft version)
4. Hydraulic Report (Draft version)
5. Technical Specification (Draft version)
6. Review DED Report (Draft version)
7. Long section, Cross section, standard drawing and other associated drawing (draft version) for package
1 and 2.
8. Topography report (draft version)
9. Geotechnical report
10. Bill of Quantity for JDU network (draft version)
11. REKOMTEK (Technical Recommendation) for segment 14 km of JDU network pipe and Railway crossing.
12. KMZ file of final update on the pipe route for MDP/JDU network
13. Several issues during the Second Quarter period on the scope of review of DED for water distribution
network are identified as follow:
14. Topographic Survey handover was delayed. The drawing process for the main distribution pipe network
cannot meet the deadline established.
15. The reallocation of the water quantities between Wonogiri and Surakarta is still not in a legally defined
stage. Hence the final calculation for offtaker reservoirs and pipeline diameters are provisionally
executed.
The evaluation of the application refers to KfW’s Procurement Guideline, January 2021 version. The format
of the PQ also adopted from KfW’s standard.
There is no documentation provided for the minutes of public opening of the Prequalification documents and
the PQ evaluation report. However, the PQ evaluation resulted to none of the Applicants have met the
qualification requirements
Accordingly, a new PQ process was launched on February 23, 2022, after obtaining the no objection from
KfW to the new PQ documents. This was followed with the process mentioned below:
Date of Notification at GTA’ website : February 28, 2022
Announcement at SPSE ICB system : March 4, 2022
Date of submission of EOI / Application : April 5, 2022
Date of opening of Application : April 5, 2022
PQ Evaluation Process (planned) : 5 April to 25 April, 2022
It is expected that with the current progress, the WTP contractor will be on board in early August 2022.
The JDU package's Prequalification document follows the same standard as the WTP package's
Prequalification document, which has received a NoL from KfW. At the end of this Quarterly Report 2, IC is
now preparing the Prequalification document and waiting for the final results of the Cost Estimate Review
(RPB) discussion at the Directorate General of the Ministry of Public Works and Housing
4.7 Meetings
Since the kick-off meeting, PMU requested to hold weekly meetings as a means to closely monitor the
progress of the IC activities. In addition, several meetings with local institutions and authorities were held
during the second quarter.
A total of 13 meetings were held from 5th January until 30th March 2022 both at the Semarang office and
Jakarta Office online.
A full list of the meetings with synthetic reports is appended in Annex 2.
Design review and construction supervision of other WS Date of Months from commencement
works submission ToR Planned Achieved
Commencement date (CD) 01/10/2021 -- -- --
Draft Inception report 08/11/2021 1 1.3 1.3
Inception meeting (IM) 19/11/2021 -- -- --
MoM 26/11/2021 -- 2.1 2.1
Final Inception report 03/12/2021 2 2.1 2.1
Revised DED 30/03/2022 2 2 6.0 6.0
Final DED 30/04/2022 3 7.0
2 As highlighted by the Consultant in his proposal, that indication was inconsistent with Section 5 of the ToR
Design review and construction supervision of other WS Date of Months from commencement
works submission ToR Planned Achieved
Draft Tender Documents 13/04/2022 6 6.5
Final Tender documents 14/05/2022 7 7.5
Launch of Tender 14/05/2022 -- 7.5
Submission of Bids 30/06/2022 -- 9.0
Submission of Bid Evaluation Reports 29/07/2022 -- 10.0
Signing of Construction Contracts/commencement date
30/08/2022 -- 11.0
(CD)
Provisional acceptance 30/08/2024 -- 35.0
Final project report 30/10/2024 -- 37.0
Final acceptance 30/08/2025 -- 47.0
Service completion report 30/10/2025 -- 49.0
These are considered once approved, the basis for the project performance monitoring in terms of expected
achievements, as also explained in Section 12 below.
Presence
No. Position Name Mobilisation Date
QR2 Cumul.
A KEY EXPERT
1 Team Leader/Civil Engineer Klaus Kirchenbaur October 2021 (*) 2,64 3,64
2 Sub Team Leader Marco Boccasini October, 2021 0 0
(resigned )
3 Coordinator Specialist Tri Joko October 1st, 2021 3 6
4 Structure Engineer Fathurrahman October 1st, 2021 3 6
5 Water Treatment Engineer Kukuh Pranandana Not mobilized 0 0
Bramanto Geritno February 1st,2022 2 2
6 Water Supply Network Leo Sando Silvaldo October 1st, 2021 3 6
Engineer
7 Electro-Mechanical Sardjiono December 1st, 2021 3 4
Engineer/SCADA Expert
8 Procurement Ilham Abla October 1st, 2021 2 5
Expert/Document Specialist (resigned Feb, 2022 )
Rizal Helbari Untung April 1st, 2022 0 0
Rivai
9 Senior Cost Estimator Dwianto Rasisto October 1st, 2021 2 5
(resigned 1st Feb 2022)
10 Local Expert for Harsono October 1st, 2021 2 5
Environment & Social (resigned 1st Jan 2022)
Safeguard Yanuar Arifin March 1st, 2022 1 1
B NON KEY EXPERT
1 Geotechnical Engineer Juniarso October 1st, 2021 3 6
2 Architecture/Landscape Febri Yenny October 1st, 2021 3 6
Expert
Presence
No. Position Name Mobilisation Date
QR2 Cumul.
C JUNIOR
ENGINEER/SPECIALIST
1 Junior Structure Engineer Agus Salim October 1st, 2021 3 6
(Civil Engineer)
2 Junior Water Treatment Bramanto Geritno October 1st, 2021 1 4
Engineer (Substitute to WTP
Expert on Feb, 2022)
Budi Wijaya February 1st, 2022 2 2
3 Junior Water Treatment Edy Wuryanto October 1st, 2021 2 5
Engineer (Resigned on Feb, 2022)
Purwanto March 1st, 2022 1 1
4 Junior Electro-Mechanical Paul Charis October 1st, 2021 3 6
Engineer/SCADA Expert
5 Junior Electro-Mechanical Dhasuki October 1st, 2021 1 1
Engineer/SCADA Expert (Resigned on Nov, 2022)
6 Junior Electro-Mechanical Irfan Arsyad October 1st, 2021 3 6
Engineer/SCADA Expert
7 Junior Geothecnical Rizal Yoga Prasetya October 1st, 2021 3 6
Engineer
8 Junior Procurement Khairul Huda Not mobilized 0 0
Expert/Document Specialist Rossalia Stevania March 1st, 2022 1 1
9 Junior Pandu Wicaksono October 1st, 2021 0 3
Architecture/Landscape
Expert
10 Junior Local Expert for Env. Ernamayanti October 1st, 2021 3 6
& Social Safeguards
11 Junior Cost Estimator -1 Indrawan October 1st, 2021 1 4
Muhammad
12 Junior Cost Estimator -2 Arief Widoseno October 1st, 2021 1 4
13 Junior Cost Estimator -3 Purwanto October 1st, 2021 1 4
D FIELD SUPERVISOR
1 Site Engineer (WTP) Rusman Sihotang Not mobilized 0 0
2 Site Engineer (Main Johan Arif Not mobilized 0 0
Distribution Pipe-1) Kharismanto
3 Site Engineer (Main Nurul Zakiyah Not mobilized 0 0
Distribution Pipe-2)
4 Construction Hendri Not mobilized 0 0
Supervisor/Inspector
(Water Treatment Plant)
5 Construction Harjan Ginting Not mobilized 0 0
Supervisor/Inspector (Main
Distribution Pipe -1)
6 Construction Indrawan Not mobilized 0 0
Supervisor/Inspector (Main Muhammad
Distribution Pipe -2)
7 Construction Reynaldi Imam Setya Not mobilized 0 0
Supervisor/Inspector (Main
Distribution Pipe -3)
Presence
No. Position Name Mobilisation Date
QR2 Cumul.
8 Construction Wisnu Hariadi Not mobilized 0 0
Supervisor/Inspector (Main
Distribution Pipe -4)
E SUPPORTING STAFF
1 Office Manager Lili Jajuli October 1st, 2021 3 6
(administrative Manager)
2 Bilingual Secretary (Based Tri Fauziah October 1st, 2021 3 6
Jakarta)
3 Bilingual Secretary (Based M. Taufiq Ichsani October 1st, 2021 3 6
Central Java)
4 Computer operator (Based Supono October 1st, 2021 3 6
Jakarta)
5 Computer operator (Based Dhaka M. Ahmad October 1st, 2021 3 6
Semarang)
6 Operator CAD/Drafter-1 Bambang Novi October 1st, 2021 3 6
7 Operator CAD/Drafter-2 Ibnu Ahmad Husein October 1st, 2021 3 6
8 Operator CAD/Drafter-3 Ridho Supradiansyah October 1st, 2021 3 6
9 Quantity Surveyor-1 M. Iqbal Darfi October 1st, 2021 3 6
10 Quantity Surveyor-2 Mierza Malik October 1st, 2021 3 6
Ibrahim
11 Quantity Surveyor-3 Puguh C. Nugroho October 1st, 2021 3 6
12 Office Boy (Based Jakarta) Siswadi October 1st, 2021 3 6
13 Office Boy (Based Tri Haryanto October 1st, 2021 3 6
Semarang)
6 FINANCIAL INFORMATION
IC has disbursed Advance Payment 11,5% from the total contract amount of 3.000.988 Euro. The amount
has been disbursed is 345.113,62 Euro.
• The first quarterly invoice was submitted for a total value of 245,211 €.
• The second quarterly invoice will be submitted in April, the actual value is still under discussion.
7 QUALITY MANAGEMENT
The Quality Management of the project implementation by the IC is carried in accordance with standard
quality management procedures familiar to the three companies (ISO 9001 and ISO 14001 certifications).
The IC has focused the activities concerned with quality management to the details in the elaboration of the
tender documents especially regarding safety and warranty processes. Corresponding recommendations will
be applied in cooperation with the client in the specific parts of the BoS.
The JV has activated experts’ mobilization and replacement where needed and offices and logistical set up
to ensure smooth project implementation.
8 ESHS COMPLIANCE
During the reporting period, the Consultant has set up the internal Health and safety procedures to provide
and maintain a healthy and safe work environment and safe systems of work to be applied to all aspects of
safety in project offices and during site visits including safety of personnel, security, hygiene in workplace
and the application of Covid19 prevention procedures and protection.
Also, the Consultant provide private Incident and medical insurance for the International Experts.
Local experts are provided with contracts respecting Indonesian labour regulations and laws in terms of
employment and working conditions of all personnel engaged in the project.
A part from the internal ESHS organisation of the IC, during the quarter report, the Consultant has reviewed
the ESIA aspects of the project components as explained in chapter 4.6 and will be working to make sure that
the Tender documents will include all the ESHS requirements in compliance to Indonesian and KFW
regulations.
The IC team has reviewed current ESHS compliance requirements in the technical specifications of the first
draft of Tender Documents submitted to the Client.
Replacement of the international sub The contract sub-team leader resigned due to
team leader by a national sub-team family problems. His peculiar condition of
leader being an expatriate with strong experience on
Indonesian design and construction
regulations makes it impossible to be
replaced. It is proposed to modify the job
description to cope with the actual
requirements, which is for a local engineer to
assist the international team leader on
coordinating the national experts and on
national design and construction regulations.
To be proposed:
The original Contract
A fully justified and thorough proposal will be presented and discussed during the upcoming period.
10 RISK ASSESSMENT
• New DED detail drawings cannot be finished due to time constraints and labor. As already drawn up in
the Inception report the client chose the option 1 , tendering with the original DED. However there were
no memos of calculation available for the original DED a thorough checking of the design was not
possible. Up to now, the Consultant has not received the memories of calculation. Finally and also as a
result of investigations of raw water quality the Consultant found out that the original treatment process
was not meeting the requirements the consultant changed the process of the WTP in accordance with
the client. Nevertheless the tender process was started without finishing all the detail drawings. This will
certainly lead to frictions in the construction process as the documents are not harmonized and
consequently to delays and increase of construction costs.
• Solution: Finish the detail drawings until the signature of the construction contract. Therefore, the client
should include the required manpower, (experts and auxiliary personnel, logistics etc.) in the consultant’s
contract.
• A similar situation exists in the part of the distribution network. In order to finalize the redesign of the
and the survey carried out along the planned track of the JDU, new calculations and hydraulic models
were executed. Derived from this base were developed the plans for the setup of the JDU. However the
designs were orientated versus the old available plans from DED and FS but unfortunately the workload
was more than planned in the Consultant’s offer due to changes of landownership at the offtaker stations
and the river crossings. Thus, the manpower and time was not sufficient to conclude all the documents
for the tenders. The Consultant has developed the overall plans BoQ and BoS but there is still missing the
translation of all documents in English language and the detail drawings. For JDU, WTP and offtaker
stations including the architectural and landscaping parts.
• Solution: The Consultant proposes to extend the consulting contract the way that the additional works
will be covered during the time of consultations for the bid in case of the WTP. In case of the JDU these
tasks can be performed until the beginning of the bidding . The detailed drawings must be ready after
signature of theb construction contract.
• Due to over exploitation of the water resources of the Gaja Mungkur lake, the sea level has dropped
dramatically during the last years sea. The resulting low coverage of the intake orifice of the raw water
pumps presents a jeopardy of air intrusion from suction vortices, The coverage of water over the pump
inlet is likely too low. Vortex shedding is taking place as each pump is abstracting 0.5 m3/s which will
form a Karmán vortex streets from the supporting cylindrical piles of the intake structure. These initial
vortices may very likely induce dangerous intake vortices. According to the experience of the Consultant
the coverage should be at least 4 m from the intake orifice meaning the sea-level should not be drawn
down lower than 127,60 MASL.
• Solution: The Consultant proposes to intervene with the operator of the abstraction system (mainly
irrigation) that the abstracted quantities on a long run will be less than the provided inflow from the
inflow and rain. As temporary solution it is also possible to reduce the individual quantity of abstraction
per pump to 250 l/s. This will also reduce the risk of eventually degradation of stagnant water (due to
anaerobic processes) in the transmission lines to the silos. The actual pumps must actually operate
intermittent (3 pumps @ 500l/s and 750l/s required).
• The Gajah Mungkur reservoir must be considered as a high-risk area. Gunong Lawu, Gunong Merawi as
well as nearby a recent lava dome (about 5,2 km WNW from the intake structure) are active volcanic
structures. Unweathered lava flows are witnesses near the intake. Besides these obvious risks, there is
doubtlessly the risk of heavy earthquakes. From the Gunong Lawu grooves may carry lahar flows from
the mountain top to the reservoir. Heavy ashfalls in case of eruption can be expected with the
consequent deterioration of the raw water for the WTP. Therefore, the Consultant considers the
Wosusokas installations must be categorized with a potentially high risk of failure.
• Solution: Considering also that the system is a single source system it will be wise to propose to the
offtakers not to abandon the actual sources but put them in standby for emergencies.
• The Consultant was asked to recommend pipe material regarding a preference for the local Indonesian
production. In this context the Consultant has worked out an expertise showing that it’s possible to use
as pipe materials HDPE and steel pipes (spiral welded steel). However the consideration was carried out
by checking the optimized joining method for the supplied pipe shots (butt welding for HDPE pipes and
U-weld with root layer for steel pipes) and the best method for adequate coating material for potable
water. Meanwhile the Consultant has received details of the method for pipe welding and coating
proposed by the possible suppliers. Unfortunately the proposed method is not up to state of the art (see
also DIN EN 12502-4). It does not comply with the requirements of structural resistance whilst pipe lying
nor with the standard requirements for rustproofing at the interior of the pipes. Additionally it came up
recently that the construction sites are often very narrow roads with high groundwater table and passing
through social hotspots. Hence there is not sufficient space for proper pipe preparation and lying as well
as constraints for the time of open trench. The contractor might be seriously hampered to perform
and/or complete the works in those sites.
• Solution: Large and long steel pipelines for water transport are preferably lined with an internal coating
of cement mortar to protect against corrosion. Corrosion resistance can be further improved by adding
suitable plastics. The main advantages of this type of coating are: low cost extensive resistance to
corrosive water up to a pH value greater than 4.0; This resistance does not apply to deionized water; Self-
healing of small cracks that go to the iron surface. Propose in the construction contracts that the
contractor can propose alternative materials and connections (e.g. connections with socket and spigot,
flanged installations above earth and bridges, electro fusion etc.)
• Concerned with the use of the proposed spiral welded steel pipes the Consultant points out that the use
of said material implies the obligatory installation of cathodic corrosion protection. Calculation of the
minimum energy consumption for the satisfactorily coated and installed material is about 2 W/m. With
a percentage of about 60% of steel pipes in the system it can be calculated that the yearly energy
consumption will be about 800 MWh. This estimated consumption will result in costs higher than 80.000
€ (actual cost=1kWh @ 1500IDR) of steel pipes installed according to standards. This cost will
exponentially grow with the unavoidable deterioration of the inner and outer coating and must be added
to the OPEX costs of the system. Thus will influence on the tariffs, which are considered already too high.
It must be added that cathodic protection will not work on pipes which are exposed to the air. These
pipes are prone to corrosion as during night times dew conditions are created on the outer surface of
the pipe due to the in the pipe and hotter temperature outside with high relative humidity. Also it must
be taken into account that protecting measures after repair works are very difficult or impossible.
Considerable additional costs may occur.
• Solution: Carry out a thorough economic and financial analysis comparing of Capex and Opex impacts
from different technical solutions on water tariffs which results in a selection of a pipe systems with an
optimal technical solution at minimum costs which also includes the consideration of possible constraints
in investment, building process, O&M as well as environmental and vulnerability issues.
11 OUTLOOK/RECOMMENDATIONS
Based on the findings during the inception period and the following activities up to date, the Consultant
states that there are serious constraints and jeopardies affecting the implementation of the project.
The most important impacts and constraints can be itemized as:
Feasibility study as bases for the DED is not well developed with basic values for the DED missing
or incomplete. No actualization of data has been performed so far with the exception of changes in
locations and alignments of piping to the off taker tanks and JDU. In this case the tracks and designs
have new survey and are up to date.
Due to the mentioned shortfalls the DED is in considerable parts inconsistent and incomplete (see
also the Inception Report)
Changes in the setup (property of land for construction works, missing and incomplete survey etc.)
are imposing considerable changes and foisting additional input and work on the Consultant in
elaborating new designs.
External pressure on the PMU requiring the early start of the bidding process for the WTP before
the complete technical documentation is ready and approved, carries intrinsic the danger that later
changes in the bidding process and more omissions and errors in the construction will increase
considerably the overall costs of the project (rule of ten).
The budget of the project is already subdivided in portions in order to set up packages for tendering.
Thus, the subdivided tendering and execution imposes a serious threat to a homogeneous and
harmonized equipment of the finalized project regarding optimization of O&M
Considering all constraints and mainly the pressure in starting the tender process, the Consultant proposes
the following actions:
Stepwise fast-track re-development of the design of the WTP parallel to the ongoing preparations
of the tender by:
• Creating the necessary database for sounder decisions in order to safeguard the sustainability
of the project
• Using the database performing a fast review of the treatment process with eventually redesigns.
Introducing the special constraints indicated by the Client in said design
• Stepwise approval of the changes.
• Finish the DED in stages with the required precision parallel to the tender process. The partial
results will be ready not later when the tender process requires the presence of adequate and
concise drawings, BoQ and BoS
• Reinforce the Consultants manpower to achieve the mentioned challenges in the production
phase of the DED, mainly in working out the detailed drawings in acceptable level.
Reaching binding agreements with the off takers regarding the interface between the SPAM
Wosusokas and their distribution system as well as the required quantities of water. The
agreements must include the staging of the consumption.
Finishing the DED of the distribution system by matching above mentioned points
Check the possibility to tender the whole project by creating only two packages. One for the WTP
and one for the distribution network
Subdivide the package distribution into lots so that one contractor can bid for one and/or several
lots. This will allow smaller (local contractors as subcontractors) to enter in the competition. The
Consultant considers this procedure as the way which allows also to harmonize the equipment in
the interest of better (and cheaper) O&M when the project is commissioned.
Minutes of Meeting
Reference No.: IC-038/MoM/I/2022
Judul Rapat : Rapat Koordinasi Progres Persiapan Topic : Coordination Meeting Regional SPAM
Pelaksanaan SPAM Regional Wosusokas Preparation Progress
Wosusokas (Pertemuan Mingguan 16) (Weekly Meeting 16)
Hari/Tanggal : Rabu, 19 Januari 2022 Day/Date : Wednesday, 19 January 2022
Waktu : 11.00 s.d Selesai Time : 11.00 a.m till Finished
Tempat : Zoom Meeting Online Place : Zoom Meeting Online
Peserta Rapat : Daftar Hadir terlampir Participants : Attendance List Attach
1. Penjelasan Rencana Kerja IC SPAM Regional Wosusokas 1. IC Regional SPAM Wosusokas Workplan
- Konstruksi WTP jika memungkinkan akan dilaksanakan - WTP Construction to be carried out in 20 Months if
dalam 20 Bulan, selesai pada Januari 2024 possible and is completed in January 2024
- Konstruksi JDU akan dilaksanakan dalam 16 Bulan - MDP construction will be implemented in 16 Months
- Sehingga uji komisioning dapat dilakukan Bersama- - The commissioning test is planned to be carried out in
sama pada Februari 2024 February 2024
- Pemindahan alokasi air curah 50 l/s dari Wonogiri ke - The Transfer of 50 l/s bulk water allocation from
Surakarta Wonogiri to Surakarta follow up
- Amandemen PKS tahun 2022, agar dilakukan - Amendment of PKS in 2022, so that an amendment is
amandemen juga pada kontrak IC also made to the IC contract
5. Struktur 5. Structural
- Luas area lahan Reservoir Grobog, Tenongan, dan - The Grobog, Tenongan, and Duwet reservoir land areas
Duwet berdampak pada perubahan kontruksi dari are affected by the change in the construction which
concrete ke Glass Fused Steel were previously using concrete to Glass Fused Steel
- Konstruksi Bangunan atas, jembatan, lintasan sesuai - Construction of Upper buildings, bridges, remain in
konstruksi DED yang telah direncanakan accordance with the planned DED construction
- Tumpuan jembatan/perlintasan menungu hasil uji - Bridge/crossing pedestals construction planning are
geoteknik/soil sondir waiting for the geotechnical test result (Dutch Cone
- Diperlukan kepastian ukuran pembebasan lahan Penetrometer Test)
reservoir offtake untuk merancang layout. Tim PDAB - It is necessary to determine the size of the offtake
akan melakukan pengukuran ulang dan mengusahakan reservoir land acquisition to design the layout. The
kebutuhan layouting reservoir offtake dari tim IC PDAB team will conduct re-measurements and work
- IC melalui arahan PPK akan mengagendakan Joint for IC’s layout requirements
survey dengang PDAM PT. Tirta Utama dalam - IC based on CMO's instruction will schedule a joint
perhitungan konstruksi lahan reservoir survey with PDAM PT. Tirta Utama for the calculation
of reservoir land construction
6. Geoteknik 6. Geotechnical
- 45 titik sudah selesai, minggu depan selesai utk boring - 45 points next week are fixed for the boring / cone
/ cone penetration testnya penetration test
7. Safeguards 7. Safeguards
Tim Safeguards mengidentifikasi lokasi yang merupakan The Safeguards team identifies public facilities locations
fasilitas public (hot spot) yang akan berpotensi terdampak (hot spots) that will potentially be affected by the pipeline
proses konstruksi pipa construction process
- Pada area Reservoir Mojolaban teridentifikasi 2 lokasi - In the Mojolaban Reservoir area there are 2 hotspots
hotspot location
- Di Karanganyar- Reservoir Plesungan teridentifikasi 7 - In Karanganyar - Plesungan Reservoir has 7 hotspots
titik hotspot - In Karangwuni there is 1 hotspot point
- Di Karangwuni terdapat 1 titik hotspot - In the Duwet Reservoir area, 4 hotspots have been
- Di area Reservoir Duwet teridentifikasi 4 titik hotspot identified
Kesimpulan Conclusion
- Perubahan alokasi air curah 50 l/s dari Wonogiri ke - 50 l/s bulk water allocation changes from Wonogiri to
Kota Surakarta sebaiknya untuk pekerjaan tahap 2. Surakarta City should be the focus of Stage II work. The
Perubahan ini menunggu regulasi terbaru dari change is waiting for the latest regulation from the
pemerintah Kota Surakarta Surakarta City government
- Perlu diskusi lebih lanjut terhadap perubahan - Further discussion is needed on changes to the
kapasitas debit sebagai bentuk tindak lanjut surat dari discharge capacity as a follow-up letter from the
Direktur Air Minum. IC melalui arahan Balai akan Director of Drinking Water. IC based on Balai’s
memfasilitasi pertemuan ini dalam bentuk Workshop instruction will facilitate this meeting into Workshop
- Kelengkapan skenarion JDU, klarifikasi atas tmbhn 50 - IC is ready to discuss together regarding the
l/s. IC siap diskusi bersama completeness MDP scenario, clarification of the
- Untuk melengkapi kebutuhan Rekomtek mengenai izin additional 50 l/s
sampling kualitas air minum akan dilaksanakan dengan - To complete the need for Rekomtek regarding drinking
mengundang semua stakeholders melalui pertemuan water quality sampling permits, it will be carried out
tingkat Kabupaten/Kota by inviting all stakeholders through district/city level
- Ada 3 persiapan Rekomtek yang proses pengajuanya meetings
didampingi Balai (persuratan, otorisasi permintaan - There are 3 preparations for Rekomtek for the
data, dan lainnya) submission process that requires support from Balai
- Balai akan mengupdate perkembangan persiapan (letters, authorization of data requests, and others)
pembangunan SPAM Regional Wosusokas kepada - Balai will update Regional SPAM Wosusokas
PDAM/PDAB, sehingga diharapkan ada input/feedback preparations construction progress to PDAMs/PDABs,
sebagai perbaikan bersama so it is expected that there will be input/feedback as a
- Balai merencanakan pertemuan pembahasan progress joint improvement
2 bulan sekali. - Balai plans to schedule a meeting to discuss progress
in every 2 months.
Minutes of Meeting
Reference No.: IC-040/MoM/I/2022
Judul Rapat : Weekly Meeting 18 Topic : Weekly Meeting 18
Hari/Tanggal : Rabu, 2 Februari 2022 Day/Date : Wednesday, 2 February 2022
Waktu : 10.00 s.d Selesai Time : 10.00 till Finish
Tempat : Kantor IC Semarang Place : IC Semarang Office
Zoom Online Zoom Meeting Online
Peserta Rapat : Daftar Hadir Terlampir Participants : Attendance List Attached
Arsitektur & Lansekap (Revisi Layout WTP) Architecture & Landscape (WTP Layout Revision)
- Tim Arsitektur & Lansekap mendata markings pepohonan - Architecture & Landscaping Team lists tree markings with
dengan kategorisasi pohon yang bisa dipindah dan yang perlu categorization of trees that can be moved and that need to
ditebang be cut down
- Dari data tersebut selanjutnya diidentifikasi berapa banyak - From the data further identified how many trees to be asked
jumlah pohon untuk dimintakan izin kepada Dinas for permission to the Forest Service / Environment for
Kehutanan/Lingkungan Hidup untuk diproses lebih jauh further processing.
- Penempatan logo PUPR (di kiri) dan logo provinsi Jawa Tengah - Placement of PUPR logo (on left) and Central Java provincial
(di kanan) logo (on right)
- Persentase lahan bangunan 60% dan 40% untuk aspek green - Percentage of building land 60% and 40% for green building
building aspects
Geoteknik Geotechnical
- Semua titik titik yang sudah dilakukan survey sondir sudah bisa - All point points that have been done sondir survey can be
dilakukan estimasi dari data yang telah ada estimated from existing data
- Untuk outputnya bisa dimasukkan ke google maps Bersama - For the output can be entered into google maps along with
dengan data topografi agar semua data dapat terintegrasi toography data so that all data can be integrated
- Sloop stability masih menggunakan data yang lama sebelumnya, - Sloop stability still uses the old data before, after this will be
setelah ini akan dibuatkan data barunya dan bisa tersetimasi created new data and can be estimated the results of new
hasilnya dari data baru yang telah ada data that has been there.
- Tipikal kedalaman pondasi di Duwet 2,2 (paling rendah) karena - Typical foundation depth in Duwet 2.2 (lowest) due to rocky
berbatu - For tipika land is taken several reference points at the time
- Untuk tipika tanah diambil beberapa titik referensi pada saat of the survey, so not only one point that the survey
survey, jadi tidak hanya satu titik yang dilakukan survey conducted
- Untuk survey sondir ditemukan beberapa titik yang tidak - For the Cone penetration test found some points that were
ditemukan ground level waternya not found ground level water
- Dibuat preliminary design dulu saja dari data yang telah didapat - Made preliminary design first from the data that has been
obtained
Structure
Struktur - Calculation of bridge and reservoir structure has been
- Perhitungan struktur jembatan dan reservoir sudah completed
diselesaikan - Modeled on the spread of the load
- Dimodelkan penyebaran bebannya - The pump building is made in its own
- Bangunan pompa dibuat tersendiri - There is no drainage across the traces
- Tidak ada drainase disebrang trase - In the reservoir there is a river across it so that for water
- Pada reservoir plesungan terdapat sungai diseberangnya disposal it needs to be considered
sehingga untuk pembuangan air perlu diperhatikan - Jatibedug Reservoir needs further discussion of the structure
- Reservoir Jatibedug perlu diskusi lebih lanjut tim struktur team with other teams
dengan tim lainnya
Water Treatment Plant (WTP)
Instalasi Pengolahan Air (IPA) - Target sync with Team (ME -Structure) next week 100%
- Target sinkronasi dengan Tim (ME -Struktur) minggu depan 100 - Fact Findings in the survey, namely on the Water Tunnel, will
% be added water tunnel
- Fact Findings pada survey yaitu pada Water Tunnel, akan - WTP uses SDB again
ditambahkan water tunnel
- WTP menggunakan SDB kembali
Conclusion
Kesimpulan - The creation of a schedule of output activities of each field
- Pembuatan jadwal kegiatan output masing-masing bidang yang that is definitive or can be measured achievement
definitive atau dapat diukur pencapaiannya - IC Compiles and updates DED image lists with weekly
- IC Menyusun dan mengupdate daftar gambar DED dengan progress
progres mingguan - The results of topographic and geotechnical survey
- Hasil pengukuran survei topografi dan geoteknik segera measurements immediately completed the report to support
selesaikan laporannya untuk mendukung DED DED
- Verifikasi section posisi penempatan jaringan pipa memerlukan - Verification of the section of the placement position of the
justifikasi resiko jika harus pindah tempat pipeline requires justification of the risk if you have to move
- Tim Geoteknik bekerja sama dengan tim struktur places
- Tim ME & SCADA menginformasikan laporan terkait special - Geotechnical team in collaboration with structural team
valve chamber dan SCADA, resiko penempatan pipa, dan - The ME & SCADA team informs reports related to special
prosedur pemeliharaan valve chambers and SCADA, pipe placement risks, and
- Tim IC menindaklanjuti proses pengerjaan Rekomtek dengan maintenance procedures
mengagendakan kunjungan ke Kantor BBWS minggu ini/senin 7 - The IC team followed up the Rekomtek process by scheduled
Februari 2022, PT. KAI & Balai Jalan Nasional a visit to the BBWS Office this week/Monday, February 7,
- Arsitektur memerlukan penggabungan antara Silo di dalam 1 2022, PT. KAI & National Road Hall
mapping. Susun laporan Identifikasi pohon - Architecture requires merging silos in 1 mapping. Compiling
- Pendetailan pola iterasi pada WTP pada saat commissioning test tree identification reports
- Literation patterns details on WTP for the commissioning
test
_____________ _____________
[tanda tangan]
Tri Fauziah Astarini Klaus Kirchenbaur
_____________
Nurul Afifah Trijoko
[PPK]
Annex 1. Attendance list online & offline
Annex 2. Meeting Documentation
Implementation Consultant (IC) SPAM Regional Wosusokas
KfW Procurement ID : 502595
Semarang Office : Jl. Galunggung No.16, Gajahmungkur – Semarang
Jawa Tengah 50232 (024) 6426023
Jakarta Office : Jl. Jati Padang Raya 41, RT.6/RW.4 – Jati Padang
Jakarta Selatan 12540 (021) 7817707
HYDEA S.p.A - SWS Consulting Engineering - KOGAS
Minutes of Meeting
Reference No.: IC-045/MoM/II/2022
4. Survei Geoteknik sudah selesai 100%, pada Rapat Mingguan 20 akan 4. Geotechnical Survey has 100% completed, at the 20th Weekly
dipaparkan hasil pelaporannya. Meeting the report will be presented.
Feedback PPK: Pekerjaan Struktur harus selesai, karena Geoteknik CMO’s Feedback: Structural work must be completed, because
sudah selesai. Pada Rapat Mingguan 20 sudah ada kolaborasi desain geotechnical is complete. At the 20th Weekly Meeting there is
fondasi dan struktur bangunan dapat ditampilkan perkembanganya already a collaboration of foundation design and building
structure can be displayed its development
5. ME & SCADA tabel rincian items SCADA dikirimkan kepada PPK untuk 5. ME & SCADA Team to submit table details of SCADA items to
dicermati dan dipertimbangkan. CMO for reviewing and consideration
6. Arsitektur & Lansekap 6. Architecture & Landscape
- Input data posisi pohon dan digambar titik-titik pohon yang ada di - Input tree position data and draw the tree points in the
area eksisting ke layout WTP existing area to the WTP layout
- Pada reservoir Jatibedug jalan rata rata lebar 5 meter - For Jatibedug reservoir the road average width is 5 meters
- Input data pohon yang dapat di transplanting di IPA - Present transplantable tree data in for the WTP
- Pemilihan tanaman yang sesuai dengan tempat tumbuhnya - Selection of plants that correspond to where they grow
- Layout Jatibedug harus dibuat sebaik mungkin karena nantinya - Jatibedug layout should be made as best as possible
akan menjadi percontohan because later it will be a pilot
- Alternatif layout untuk kavling baru Plesungan - Alternative layouts for the new plesungan
- Perpipaan harap dapat ter ekspos - Piping hopes to be exposed
- Sekitar jalur pipa harus mudah diakses untuk pengawasan dan - The surrounding pipelines should be easily accessible for
perawatan. supervision and maintenance.
- ME diluar bangunan inti - ME outside the core building
- Offtaker outlet bisa diberi akses agar mempermudah perawatan - Offtaker outlets can be given access to facilitate
- Untuk WM 20 diharapkan sudah ada perubahan pada gambar maintenance
rervoir tenongan - For WM 20, it is expected that there will be changes to the
- Ruangan kimia harap dibuatkan di reservoir image rervoir tenongan
- Penambahan lahan di Res Tenongan bisa diusulkan sesuai layout - Chemical room please make in reservoir
terbaik. Agar dapat diupayakan diusahakan pembebasan lahannya - Land additions in Res. Tenongan can be proposed
- Desain Reservoir Tenongan, tampilkan desain lengkap sesuai according to the best layout. In order to be sought to
dengan rencana awal pada IPA dan ruang kimia secure land acquisition
- Tenongan Reservoir design, display complete design in
accordance with the original plan of the WTP and chemical
space
7. Instalasi Pengolahan Air (IPA) 7. Water Treatment Plant (WTP)
- Desain IPA pada prinsipnya dapat mengakomodasi kaidah green - The WTP design in principle to accommodate green
Building/Green WTP building / green WTP aspects.
- Tim IPA perlu mulai mempersiapkan pedoman supervisi konstruksi - The WTP team need to start preparing construction
supervision guidelines
8. Dokumen Tender 8. Tender Documents
- Draft dokumen PQ untuk 4 paket JDU, agar dapat diserahkan dan - Draft PQ documents for 4 MDP packages, so that they can
direview bersama dengan Adviser pak Joko Roosmany dan pak be submitted and reviewed together with Mr. Joko
Iman minggu depan. Roosmany and Mr. Iman next week.
- Penyiapan komponen 4 paket JDU pada dokumen PQ agar - Setup of 4 MDP package components in PQ documents to
mempertimbangkan aspek teknis dan non-teknis. take into account technical and non-technical aspects.
- Opsi perencanaan komponen 4 paket JDU dapat memuat sistem - The 4 MDP package component planning option can
JDU beserta ME, reservoir dan bangunan pelengkap yang dibagi ke contain MDP system along with ME, reservoir and
4 segmen pekerjaan sehingga konsep desain dapat tipikal dan complementary buildings divided into 4 work segments so
penyusunan dalam satu PQ dokumen that design concepts can be typical and drafted in one PQ
- Opsi perencanaan lain komponen 4 paket JDU dapat memuat 4 document
lingkup aspek pekerjaan masing-masing sistem JDU, ME, reservoir - Other planning options component 4 JDU packages can
dan bangunan pelengkap, masing-masing paket mempunyai contain 4 scopes of work aspects of each JDU system, ME,
konsep desain yang berbeda-beda, sehingga penyusunan PQ reservoir and complementary buildings, each package has
dokumen dibuat masing-masing a different design concept, so that the preparation of PQ
- Saat ini sudah dipersiapkan PQ dokumen untuk 4 paket JDU documents is made each
memuat sistem JDU secara keseluruhan memuat 4 segmen - Currently, PQ documents are prepared for 4 MDP
pekerjaan dalam satu dokumen PQ packages containing the MDP system as a whole
containing 4 work segments in one PQ document.
9. Rekomendasi Teknik (Rekomtek) bersiap mengajukan konsultansi offline 9. Technical Recommendations (Rekomtek) Prepare to propose
dengan BPPW berdasarkan data survei geoteknik dan topografi untuk offline consulting with BPPW based on geotechnical and
BBWS didampingin Bu Yanti. Berparalel pengerjaan Rekomtek kepada PT. topographic survey data designated for BBWS, to be
KAI dan Balai Jalan accompanied by Mrs. Yanti. In parallel with that, IC prepares
the Rekomtek to be proposed to PT. KAI and Balai Jalan
10. Safeguards 8 poin fokus penyusunan slides yaitu Pendahuluan (latar 10. Safeguards 8 focus points for the reporting and be presented
belakang, maksud dan tujuan , ruang lingkup), 2. Metodologi safeguard int the next weekly meeting, (1) Introduction (background,
(lihat di pedoman PUPR), 3. Pemetaan/Kondisi Lingkungan (permukiman, intent and purpose, scope), (2) Safeguard methodology (see in
komersial, sosial dll), 4. Analisis Risiko (pekerjaan WTP dan JDU) : dampak PUPR guidelines), (3) Mapping /Environmental Conditions
sosial, lingkungan, Lokasi dan magnitut risiko (bobot , skoring dan Nikai (settlements, commercial, social etc.), (4) Risk Analysis (WTP
risiko), 5. Kajian mitigasi risiko (lingkungan, masyarakat dan pekerja), and JDU work): social, environmental, location and magnitude
kebutuhan peralatan dan metode yang digunakan, 6. Kelembagaan of risk (weights, scoring and Nikai risk), (5) Risk mitigation
(rincikan kelembagaan apa saja yang terlibat ; institusi, masyarakat), 7, review (environment, society and workers), equipment needs
jadwal pelaksanaan , 8, pembiayaan and methods used, (6) Institutional (detail what institutions are
involved; institutions, communities), (7), implementation
schedule, and (8) financing
Kesimpulan Conclusion
A. 27 Februari 2022 Pekerjaan struktur harus selesai, konsekuensinya PPK A. February 27, 2022 Structural work must be completed,
tidak akan menandatangani invoice bila pekerjaa tidak selesai sesuai consequently PPK will not sign invoices if workers are not
target. Selain itu, akhir Februari Tim Struktur bersurat kepada completed on target. In addition, at the end of February the
Kementerian PUPR mengenai RPB Structure Team wrote to the Ministry of PUPR regarding RPB.
B. Kordinasi Tenaga Ahli dengan Team Leader perlu ditingkatkan, B. Coordination of Experts with Team Leaders needs to be
implikasinya kordinasi Team Leader dengan PPK/Balai juga ditingkatkan. improved, the implications of coordination of Team Leader
Sehingga PPK dapat menilai output Team Leader with PPK / Balai are also improved. So that PPK can assess the
C. PPK meminta IC Menyusun tabel overall progress yang dapat output of the Team Leader
dibandingkan dengan rencana dan realisasi. PPK dapat menilai posisi C. CMO asked IC to draw up a table of overall progress that can be
perkembangan IC sesuai tahapan target kerja. Rapat mingguan compared to the plan and realization. PPK can assess the
berikutnta IC menampilkan bar chart progres dua informasi position of IC development in accordance with the stage of
- rencana (warna biru) work targets. The following weekly meeting with IC displays a
- realisasi (warna merah) two-information progress chart bar
D. Masa kritis Wosusokas di bulan Februari s.d April. IC harus support PPK - plan (blue)
untuk mempersiapkan RPB yang akan dibahas ditingkatan Direktorat - realization (red)
pusat. Bersamaan dengan itu, IC juga mempersiapkan RAB, Harga D. Wosusokas' critical period in February to April. IC must support
Perkiraan Sendiri, Kajian Struktur, Pemilihan Material, K3 dan lain PPK to prepare RPB which will be discussed at the level of the
sebagainya. central directorate. Simultaneously, IC also prepares RAB, Own
E. IC perkuat koordiansi internal, sehingga Ketika Rapat Mingguan, apa Forecast Price, Structure Study, Material Selection, K3 and so
yang disampaikan kepada Klien tepat sasaran dan kompak on.
F. PPK dapat menilai perkembangan IC dengan justifikasi berdasarkan E. IC strengthens internal coordians, so that when weekly
jadwal kerja tersebut. Sehingga, TA yang tidak memiliki performa meetings, what is delivered to the client is on target and
signifikan, akan diberikan surat peringatan dan bila perlu digantikan compact
G. PPK tidak akan menadatangani invoice IC bila pekerjaan tidak selesai F. CMO can assess the development of IC with justification based
sesuai target deadline on the work schedule. Thus, Experts that does not have
H. IC tetap menjaga dan menjalankan protokol kesehatan, tes antigen bila significant performance, will be given a warning letter and if
perlu necessary, is replaced
G. PPK will not sign IC invoices if the work is not completed
according to the target deadline
H. IC maintains and runs healthy protocols, antigen tests when
necessary
_____________ _____________
_____________
Klaus Kirchenbaur Mr. Arif Nurjiyanto
Tri Fauziah Astarini
Tri Joko
Annex 1. Attendance List (Online & Offline)
Annex 2. Documentation
SPANI
\i\lr I l1!1r(lirr' r \ir \lirru,,,
lmplementation Consultant 0C) SPAM Regional Wosusokas
KfW Procurement ID : 502595
Semarang Office : Jl. cslunggung No.l6, Gajahmungkur - Semaiang
\\'osusokas Jekarta Office
Jawa Tengah 50232 l024l 6426023
: Jl. Jati Padang Raya 4r, RT-6/RW.4 -Jati Padang
.A.
...,,",v l(Fw Jakatta Sclatan 12540 lO2l) 7A177O7
ITYDEA S. .A - SWS consulti EI ering - NOGAS
Minutes of Meeting
ReferenceN o.t O47 I MoM /lll / 2022
Pak Arif (PPK SPAM Wosusokas) Mr. Arif (CMO SPAM Wosusokas)
- Tim lC fokus pada penyelesaian penyusunan Reviu - lC focuses on completing the preparation of Cost
Perkiraan Eiaya (RPB) dan Rekomtek Estimation Review (RPB) and Technical
- Fokus keria lC minggu ini adalah revisi RPg Recommendation
- lc's focus this week is working on the RPB revision
5 Safeguards 5. Safeguards
- Pada identifikasi hotspot di sepanjang jalur - ln the identification of hotspots along the
distribusi telah dibuatkan pemetaan sumber distribution line has been made mapping the
bahaya dan skala penilaian dampak source of hazards and the scale of impact
- Penentuan tindakan mitigasi resiko di lapan8an aSsessment
bersumber dari tinjauan aktifitas yang ada - Determination of risk mitigation actions in the
field is derived from a review of existing activities
6 Dokumen Tender 6. Tende. Documents
- Tim memantau dan menindaklaniuti proses Terder - The team monitored and followed up the IPA
IPA yang telah ditayangkan ulang pada website Tender process that had been re-aired on the
GTAI dan LPSE PUPR GTAI and LPSE PUPR websites.
- Bersamaan den8an hal itu, tim Menyusun - Along with that, the team compiled a tende.
dokumen tender 4 paket.lDU yang berkordinasi document of 4 JDu packages that are closely
erat dengan tim IDU & Cost Estimote coordinated with the IDU & Cost Estimate team.
1 Arsitektur & Lansekap 7. Architecture & Landscape
- Penielasan bahan paparan - Slides presentation
Cost Estimate 8. Cost Estimate
- Pipa GSP yan8 digunakan mengacu pada Permen - GSP pipe used refers to PERMEN PUPR about steel
PUPR tentang standar pemasangan pipa baja pipe installation standards
- Dalam penyusunan RPB, tim juga akan memasukan - ln the preparation of RPB, the team will also enter
data alat-alat apa saja yg digunakan, sehingga data on what tools are used, so that it is
tepat dan sesuai apa yang dikerjakan nanti appropriate and in accordance with what is done
later.
9. Rekomtek 9. TechnicalRecommendation
- Tim telah melakukan pendekatan awal dengan - The team has made an initial approach with
BSPJN dan PT. KAl, feedbacknya positif sehing8a SBPIN and PT. KAl, the feedback is positive so
.Jumat akan dilaksanakan kunjunAan lanjutan untuk that Friday will be a follow-up visit for the hearinB
audiensi dokumen/berkas yang dibutuhkan untuk of documents / files needed for recomputing
pengajuan Relomtek submissions.
- Pada pertemuan dengan PT.KAI di hari Jumat, - At a meeting with PT. XAI on Friday, PDAM
PDAM (aranganyar akan ikut hadir (aranganyar will be present
10. lnstalasi Pengolahan Air 10. Water Treatment Plant
- Pedoman supervisi green WTP ini nantinya akan - WTP Sreen supervision guidelines will later
meniadi acuan untuk dimasukkan kedalam laporan become a reference to be included in the monthly
bulanan report.
- Penjelasan detail desain format laporan supervise - Detailed explanation of the design format of
hariar, mingguan daily, weekly, supervise reports
A. Tim ME dan Cost Estimate dating ke kantor BPPW A. The ME and Cost Estimate team came to the BPPW
tanggal 10 Maret 2022, untuk reviu dan konsultasi office on March 10, 2022, for review and consultation
hasil kerja den8an PPK ofthe results of work with CMO
B. Tim landscape kirimkan layout offtaker yang memang 8. Landscape team sends offtaker layout that requires
memerlukan lahan tambahan kepada PPK, sehingga additional land area to CMO, so that CMO / Ealai can
PPK/Balai dapat membantu mengkomunikasikan help communicate land addition with PDAB
penambahan lahan dengan PDAB C. Make sure the data on RPB in accordance with the
results of recomputing submjssions
C. Pastikan data-data pada RPB sesuai dengan hasil D. The structure team ensures the change in concrete
pentajuan Rekomtek quality from K250 to K300, if necessary, to justify the
D. Tim struktur pastikan kembali perubahan mutu beton technique.
dari X250 menjadi (300, bila perlu dibuatkan justifikasi E. At the time of closing the excavation, some
tekniknya. construction work can use sand and gravelwith soil
E. Pada saat penutupan galian, dibeberapa pekerjaan combinations. This will be considered based on the
konstruksi bisa menggunakan sirtu dan kombinasi field conditions-
tanah. Hal initentunya disesualkan dengan kondisi F. The procurement team focus preparation of PQ and 4
lapangan JDU tender documents. On Ma.ch 11, the team to
F. Tim pengadaan fokkus penyusunan PQ dan 4 dokumen have assistance discussion of the working documents
tender JDl.J. Tanggal 11 Maret jadualkan pembahasan with CMO-
asistensi dokumen kerja dengan PPK. G. lC ensures the total number of calculations of MDP
G. lC memastikan kembalijumlah perhitungan total angka consruction numbers that will enter into RPB; The
konstruksi JDU Vang akan masuk ke dalam RPB; total total contract value of lC and Construction WTP are
nilai kontrak lC dan Konstruksi IPA sudah pasti. JanSan fix. Don't over bud8et
sampai over budget H. lC maintains focus and health conditionsto complete
H. lC tetap jaSa fokus dan kondisi kesehatan guna RPB documents and revisions if any. The faster it is
menyelesaikan dokumen RPB dan revisi bila ada. repaired, the faster it is completed.
Semakin cepat diperbaiki, semakin cepat selesai
7-';
Tri Fau2iah Astarini a!s Kirrhenbau
Tri.loko
€ Arif Nurjiyanto, S-T
Annex 1. Attendance list [Online & Offline)
DAFTAR HADIR
REGIONAL WATER SUPPLY SYSTEI
vlrosusoxAs Hari / Tanggal P"tt / l tledct %2-'L-
tmphrn nt tlon Con.ult nr (|c) SPA Jam (o. oo
Rogion l YYo.utotrr
KtW Procu,!.rrot ld : 502596 Penhal VI.UY Vl.l+a1 ,) 2g
a-
TANDA
NO INSTANSI No HP
TANGAN/PARAF
1
b,o ff1,*k^ r_-
) 7T,f, \, r,^ LL.
t
3zutitrUfD -F IC tflCl)(fkA< 1"*r-
o /b
l,-
1
4r,^n"r /1r,)n 0CI zt s crrr,)
r fulu*".1,*-*- /Q a )t e7yo2 Y 21
5
N,11, 41" $a" /c oSttszttVt z: rry
U
1
\ l\t4,^ fi \C cRZ129e261U4 1
I A.."1 r,t),.[;E**> l(
L-
b
I t!" 9\"o.0. IC
lo,
ll
I
Nurut
L P" Al'p,.I llrs -
Aglah
lc-
i0
/re
.w
7 IAA (@,6./ u LC
-1 u
l5 Ittuan w*r.t t!r\ tc 085959( oSoss 2@
r( ffiiSt/a P,&t'*dlaP \L 08t{-lWftP ffi
td &ilr td *
u W "tilt- IC
S
,a
J 7
z 7
-
k
F
I
,:.
,l
ITI
u
.i
-|T
| "..rr/ flI
I
I F- B
r{f I in$nJls
JA'
a
tI'
u
!t .,, :l
n t [T]
a 4t
m
uolleluaunroo z'xauuv
IC SPAM REGIONAL WOSUSOKAS – Contract 06/PKK/PSPAM-KONS-IC.01/2021
Quarterly Report 2 INDONESIA