Professional Documents
Culture Documents
Form Timesheet
Form Timesheet
No. Kontrak :
No. Perintah Kerja :
Judul Pekerjaan : VLP COMPRESSOR RELOCATION FROM BADAK TO MUTIARA CENTRAL PLANT
Lokasi : MUTIARA CENTRAL PLANT
Tanggal : 19/Januari/2024
Detail Pekerjaan : Modify Walkway for Skid Metering Platform
A. Tenaga Kerja
JAM KERJA
NO DESKRIPSI POSISI TOTAL KETERANGAN
START FINISH
1 Jumah April Adam Supervisor/PA 7:00:00 17:00:00 10:00:00
2 Joko Sutono Foreman 7:00:00 17:00:00 10:00:00
3 Boyman Agil Mumar Fitter 7:00:00 17:00:00 10:00:00
4 Sofiansah Fitter 7:00:00 17:00:00 10:00:00
5 Diansyah Helper 7:00:00 17:00:00 10:00:00
6 Ismail Helper 7:00:00 17:00:00 10:00:00
7
8
9
10
B. Peralatan Kerja
JAM KERJA
NO DESKRIPSI UNIT TOTAL KETERANGAN
START FINISH
1 Cutting Torch 2 7:00:00 17:00:00 10:00:00
2 Grinder 2 7:00:00 17:00:00 10:00:00
3 Mesin Las Miller 1 7:00:00 17:00:00 10:00:00
4
5
______________ _______________
Supervisor Inspector