ADP-211201-025 R1 Room Integrity (A)
ADP-211201-025 R1 Room Integrity (A)
Hold
Para. Description of Hold
No.
Page 2 of 37
Abu Dhabi Plaza – Astana, Kazakhstan Document No.
Work Package 4 – Main Works ADP-211201-025
Item
Comments On Rev.000 Contractor’s Response
No.
Page 3 of 37
Abu Dhabi Plaza – Astana, Kazakhstan Document No.
Work Package 4 – Main Works ADP-211201-025
Comply.
Added in Section 7.1 bullet points.
8
All input data will be detailed
during RFIC with CxA.
Page 4 of 37
Abu Dhabi Plaza – Astana, Kazakhstan Document No.
Work Package 4 – Main Works ADP-211201-025
Table of Contents
1.0 Purpose
3.0 References
4.0 Definitions
5.1 Competency
5.2 Role & Responsibilities of Commissioning Engineer
5.3 Role & Responsibilities of QC Engineer
5.4 Role & Responsibilities of Foreman
5.5 Roles & Responsibilities of HSE Supervisor
5.6 Role & Responsibilities of Specialist /Certified Person
7.1 General
7.2 Safety Precautions
7.3 Pre-Commissioning
7.4 Commissioning
9.1 Induction
9.2 PPE
9.3 Hazard Identification, Risk Assessment & Control
9.4 Toolbox Talks
9.5 Permit to Work
9.6 Training of Personnel
10.0 Attachments
10.1 FM-MS-ADP-211201-025-001
10.2 FM-MS-ADP-211201-025-002
10.3 Enclosure Integrity Verification Form (Sample)
10.4 Approved Shop Drawing/Schematics (To be supplied later)
10.5 Required Peak Pressure (Approved Design Calculation Sample)
10.6 ITP
10.7 JSTI
10.6 Risk Assessment
Page 5 of 37
Abu Dhabi Plaza – Astana, Kazakhstan Document No.
Work Package 4 – Main Works ADP-211201-025
1.0 PURPOSE
The main purpose of this method statement is to ensure that all the works for Enclosure Integrity Testing
are executed in accordance with the standard specifications. Main purpose of Enclosure Integrity Testing
is predict the enclosure retention time and the Peak Pressure calculation in the event that the Clean
Agent Fire Suppression System is discharged.
This method statement covers the Enclosure preparation for the Testing, Integrity test providing and leak
detection procedures in case the Integrity test fault.
3.0 REFERENCES
4.0 DEFINITIONS
The Commissioning Manager has the overall responsibility for the implementation of this Method
Statement, also will individually assess the manpower required for Enclosure Integrity Testing to meet
the schedule. Typically these will include:
Commissioning Engineer
QC Engineer
Foreman
HSE Supervisor
Specialist Representative
5.1 Competency
The competency of all construction personnel shall be controlled in accordance with the
Competent Persons Designation Procedure Ref: ADP-013529-066.
Page 6 of 37
Abu Dhabi Plaza – Astana, Kazakhstan Document No.
Work Package 4 – Main Works ADP-211201-025
The foreman will carry out his duties by maintaining continuous coordination with the
Commissioning Engineer on daily basis, and ensure proper distribution of the workforce in the
required and planned locations.
To ensure that his assistant foreman/charge hand are aware of the job requirements and they
have enough information to carry out their duties properly.
To ensure in consultation with the site engineer that the manpower involved in the works are
moving as agreed and planned for the work.
To ensure that the daily work is progressing as planned and advice the Commissioning Engineer
of any requirement for additional resources.
To ensure full coordination with the safety officer to maintain safe working and proper
housekeeping of the site, following the approved safety measures and further ensure that all his
working team are aware of the same to prevent accident and losses.
To inform the Commissioning Engineer and of the areas ready for inspection.
• Assist the Site Engineer in conducting Tool box talks prior to starting the activity.
• Ensure PPE shall be worn as appropriate according to the nature of job.
• Ensure safety precautions shall be followed as per established project HSE requirements and
Project Quality Plans safety plan.
Page 7 of 37
Abu Dhabi Plaza – Astana, Kazakhstan Document No.
Work Package 4 – Main Works ADP-211201-025
The following tools & equipment will be used during the Enclosure Integrity Testing & Peak Pressure
Calculation.
Standard Mechanical Tool Kit
Retrotec Door Fan Model 5000
Dual Channel Digital Micro Manometer
Thermo anemometer KIMO
Laser Distance meter Bosch
Laptop computer with installed Retrotec Fan Testic Integrity software v.5.9.26
Photo/video camera
Portable Smoke generator TINY CX
Smoke pen
Screw driver set
Floor tile lifter
Door stops
PPE (Hand Gloves, Safety Goggles)
Torch, Measuring Tape, Masking or Duct Tape
Sheets of Plastic or Cardboard, Warning Signs
Calibrated Thermometer
Note: All tools and equipment’s will be inspected and colour coded before use at site.
7.1 General
Make available at site, an approved copy of shop drawing for the intended commissioning.
Room Integrity Testing System shall be supervised by an authorized representative from
Specialist / Certified person.
JV to clearly demonstrate the input data on the Retrotec software being used by Specialist/
Certified person to the Client Commissioning Management team.
All safety precaution shall be followed as per established project safety plan.
Only experienced and skilled technician shall be engaged for carrying out the commissioning of
Room Integrity Testing.
Appropriate warning signs and tapes shall be placed during testing and commissioning as
required.
All PPE shall be worn as appropriate according to the nature of job.
Work area shall be maintained neat and clean.
Page 8 of 37
Abu Dhabi Plaza – Astana, Kazakhstan Document No.
Work Package 4 – Main Works ADP-211201-025
7.3 Pre-Commissioning
Ensure installation is completed with RFIT for Fire Sealant signed off
Ensure that the working area is clean and safe to work.
7.4 Commissioning
7.4.1 Enclosure evaluation and room preparation for the test
Inspect all operable doors, hatches, and movable partitions for their ability to remain shut down
during the test.
Measure the clean agent protected enclosure volume. Record all dimensions and compare with
ones in project documentation received from customer. Deduct the volume of large solid objects
to obtain the net volume.
Measure the highest point in the clean agent protected enclosure.
Get the allowable pressure rating of the protected room (including door, windows, A/C ducts,
ceiling etc.) from the contractor/client.
Calculate the effective floor area by dividing the net protected volume by the maximums clean
agent protected enclosure height.
Get the user’s personnel or contractor to set up the room in the same state as when a discharge
would occur, that its, HVAC shutdown, dampers closed and so on. Confirm that all dampers and
closable openings are in discharge-mode position.
Ensure that the electric power supply required for operating the equipment are from a suitably
rated, reliable source, with adequate protection means.
Set up the door fan in the most convenient doorway leading into the space. Choose the doorway
that opens into largest return path area.
Follow the manufacturer’s instructions regarding equipment setup. Draw the fan location in test
sheet graph as shown sample in figure 7.4.1 below.
Figure 7.4.1
Page 9 of 37
Abu Dhabi Plaza – Astana, Kazakhstan Document No.
Work Package 4 – Main Works ADP-211201-025
Remove papers and objects likely to be affected by the air currents from the discharge of the
door fan.
Check floor drains and sink drains for traps with liquid if applicable.
Secure all doorway and openings as for a clean agent discharge.
Connect the tubing for the room pressure gauge. Ensure the tube is at the floor slab elevation
and extend at least 10ft (3m) away from the outlet side of the door fan away from its air stream
path, and away from all significant air stream (i.e., HVAC air flows or openings where air flow
could impinge on the tube)..
Ensure that the open ends of the flexible tubing near the fan unit are away from its air stream
path and any other air flows which might affect the readings.
Inspect the wall perimeter (above and below the false floor) and the floor slab for major leaks.
Note location and size of major leaks. Track down major air flow currents.
Activate the blower and adjust the enclosure pressure to -15Pa or maximum negative pressure
achievable (up to -15Pa).
Inspect all dampers with smoke to ensure they are closed properly. Record problems and notify
individuals responsible for the enclosure of the problems.
Inspect doors and hatches to ensure correct closure. Record problems and notify individuals
responsible for the enclosure of the problems, test should stop to ensure sealing of the enclosures
.then redo the test again.
This procedure enables the authority having jurisdiction to obtain an indication of the door fan and
system calibration accuracy upon request. The field calibration check should be done in and
separate enclosure. Seal off any HVAC registers and grilles if present. Install the door fan as per
manufacturer instructions. Determine a bias pressure if exists. Check openings across the
enclosure envelope for air flow with chemical smoke or fog. If any appreciable flow or pressure
exists, choose another room or eliminate the source.
Install a piece of rigid material less than 3mm thickness (free of any penetrations) in an
used fan port or other convenient enclosure opening large enough to accept an
approximately 0,1m2 sharp edged round square opening.
Ensure that the door fan flow measurement system is turned to properly measure
pressurization or depressurization and operate the fan to achieve a convenient pressure
drop, preferably 10Pa.
As the pressure achieved, note down initial EqLA value & Repeat for the EqLA
measurement with adjusting the fan to the other direction, then average the two results.
Create a sharp edged round or square opening in the rigid material. The area of this
opening should be at least 33% of the initial EqLA measured. Typical opening sizes are
approximately 0,05m2, 0,1m2 and 0,2m2, depending on the initial leakage of the enclosure.
Adjust the fan to the other direction, then average the two results.
Field calibration is acceptable if the difference between the first and second EqLA value
is within +15% of the opening area cut in the rigid material.
If the difference in EqLA values is greater than 15%, the door fan apparatus should be
recalibrated according to the manufacturer’s recommendations and to ASTM E779-10,
ASTM E1258, or CAN/CGSB-149.10-M86.
Page 10 of 37
Abu Dhabi Plaza – Astana, Kazakhstan Document No.
Work Package 4 – Main Works ADP-211201-025
Retention time is the amount of time it takes until the first piece of protected equipment is no longer
protected or the concentration of clean agent is less than minimal one. To measure and record
the data required for calculating the retention time via software, perform the following:
Fill up the required data needed in the software as indicated: actual room volume,
maximum flooded height, maximum protected height and agent quantity.
Install the door fan to the enclosure doorway and setup the system accordingly to the
equipment manufacturer guide.
Ensure that tested room is prepared for the testing.
Measuring the static pressure (bias) – seal the fan opening with the cover. Observe the
pressure gauge for at least 30 seconds, this is done before and after the test. Record
the readings.
Record the temperature inside the room by using the thermometer, record the
temperature outside the enclosure by using the thermometer.
Observe the room pressure gauge for at least 30 seconds. Look for minor fluctuations in
pressure set in 10Pa and record the reading. Determine the flow direction with smoke or
other indicating method.
Observe the room pressure gauge for at least 30 seconds. Look for minor fluctuations
in pressure set in 50Pa and record the reading. Determine the flow direction with smoke
or other indicating method.
After entering all the required data, the software will automatically calculate the actual
initial agent concentration.
The following steps will be prepared for two modes: pressurization and depressurization modes:
Operate the blower door with appropriate range in order to get differential pressure drop
point required.
Record the pressure values on the channel A and channel B of the differential
manometer.
Repeat for another pressure drop points required.
Enter the data into software to calculate the equivalent leakage area as well as the
retention time.
The retention time is calculated via the software; reports should be generated and printed
out and compared with the acceptance criteria
The retention time that was calculated must be equal to or exceed the holding time period
which is minimum 10 minutes.
The report coming from the software calculations result will be generated and printed
out.
Page 11 of 37
Abu Dhabi Plaza – Astana, Kazakhstan Document No.
Work Package 4 – Main Works ADP-211201-025
Enter the values needed in the software: relative humidity, which is usually default in the
software and discharge time which is usually 10 seconds after NFPA.
Enter the enclosure pressure limit which is to be provided by the civil/structural design.
Usually we consider the pressure limit of the weakest part of the enclosure.
After data is entered, the software will calculate the positive and negative peak pressure
based on given parameters. The enclosure pressure limit should be greater value than
the calculated positive or negative peak pressure otherwise additional pressure relief
vent will be provided.
MEP RFIC should be issued by T&C Engineer for verification before submission to CSC & CxA.
Refer to ITP No. ADP-211201-006 and strictly follow inspections steps.
Refer to QMP-ADP-014000-625 for RFIC submission process.
Work should be approved by consultant (submitting RFIC).
9.1 Induction
Prior to commencing work all personnel shall have attended the HSE induction course conducted by the
JV HSE department. No work shall be undertaken by personnel who have not attended the Project HSE
induction. In all aspects, work is to be carried out in a safe manner and in accordance JV approved Health
and Safety Plan and in accordance with HSE requirements
All personnel involved in the Testing and Commissioning will comply with the Project requirements for
PPE:
Work Boots with toe protectors
Safety Helmet
Eye Protection with side shields
HV Gloves
Dust masks (as required)
Rubber Mat
Additional PPE identified by the task risk assessment shall also be provided. Personnel shall sign and be
responsible for their own items of PPE issued to them and the Engineer shall ensure that his team is
complying with the minimum required PPE and that damaged or defective PPE is replaced or repaired
immediately.
Hazard identification, risk assessment and control are detailed in the appropriate risk assessment and
Job Safety Task Instruction (JSTI) attached herewith. Hazards may vary as the works progress and shall
be re-evaluated. All personnel undertaking testing and commissioning activities shall be aware of
particular location hazards. The Project Risk Assessment Procedure ADP-013529-028 is to be referred
to during the planning stages. Should changes occur during the course of commissioning which alters
the associated risks then the risk register shall be updated to reflect any additional risk and mitigation
measure.
The attached JSTI is provided to cover the initial work tasks relating to Enclosure Integrity Testing & Peak
Pressure Calculation - JSTI (attached). This JSTI is prepared based on theoretical information interpreted
Page 12 of 37
Abu Dhabi Plaza – Astana, Kazakhstan Document No.
Work Package 4 – Main Works ADP-211201-025
from the project documents. A further assessment will be required at the actual work site to verify the
control measures and address any additional hazards. Reference is to be made to the relative Health,
Safety, Environmental & Security procedures to control the risks associated with activities where they
occur.
Prior to the commencement of site activities the Engineer, with support from the HSE Officer, shall
conduct a pre-start toolbox talk with all the crew present. The MEP Supervisor shall explain the Enclosure
Integrity Testing & Peak Pressure Calculation activities, focusing on the hazards and risks involved in the
activity and the mitigation measures that shall be taken as detailed in the Risk Assessment. Regular
Toolbox talks shall be conducted in order to prevent complacency within the crew. The Engineer shall
conduct a Pre-start toolbox talk for the new person/s prior to starting work.
A Permit shall be obtained when and where applicable in accordance with the requirements of Permit to
Work Procedure (ADP-013529-034) prior to performing the Installation, Enclosure Integrity Testing &
Peak Pressure Calculation. The supervisor will ensure that all relevant risk assessments, method
statements and permit to work control measures are in place and that all relevant procedures contained
within these documents are fully understood by the operative personnel.
All personnel involved in Enclosure Integrity Testing & Peak Pressure Calculation works shall be
trained in accordance with the requirements of the Project HSE Program. No personnel shall be
assigned tasks that they have not received appropriate training in or have been assessed for
competency. Further training shall be given as required and when additional training is identified
during the risk assessment process.
All personnel involved in Enclosure Integrity Testing & Peak Pressure Calculation activities shall
be assessed for qualifications, competency and if they have the required trade skills and
experience, or trained in accordance with the requirements of the project standards.
10.0 Attachments
10.1 FM-MS-ADP-211201-025-001
10.2 FM-MS-ADP-211201-025-002
10.3 Enclosure Integrity Verification Form (sample)
10.4 Approved Shop Drawing/Schematics (To be supplied later)
10.5 Required Peak Pressure (Approved Design Calculation Sample)
10.6 JSTI
10.7 Risk Assessment
Page 13 of 37
ARABTEC CONSOLIDATED CONTRACTORS COMPANY LTD.
ABU DHABI PLAZA – ASTANA, KAZAKHSTAN
QC ACCEPTANCE STATUS
REQUESTED DOCUMENTATION SUBMITTED
YES NO REMARKS
1. T&C MS
3. All the apparent leaks must be sealed and hardware item installed
9. Plan view is sketch showing dimensions below and calculate floor area, heights and
volume
14. Leak Check is done(by blowing air in to get +15 Pa room pressure & use smoke to
locate leaks in)
COMMENTS/DISCRIPANCIES:
JV Commissioning Engineer
JV QA/QC Engineer
(CSC) AECOM KZ
(CxA) CML
FM-MS-ADP-211201-025-001
ARABTEC CONSOLIDATED CONTRACTORS COMPANY LTD.
ABU DHABI PLAZA – ASTANA, KAZAKHSTAN
1. T&C MS
1. Is there a suspended ceiling? _______ Bring a Flex Duct and second fan______ or plastic for covering the ceiling leaks________so that the BCLA
2. Dampers installed on all external HVAC ducts _______ Can they be shut for the Door Fan test? ________
Dampers installed on fresh air inlet ducts _______ Can they be shut for the Door Fan test? ________
3. All the apparent leaks must be sealed and hardware item installed? ___________
4. Door way sizes? Height ________, Width_________ 4.1 HVAC shutdown is arrange? __________
5. Maximum number of test fans needed? __________ 5.1 Small room problem? _________
6. Test type and units: NFPA2001 metric___________ NFPA2001 Imperial _________ ISO14520 metric _________ ISO14520 Imperial _________
JV Commissioning Engineer
(CSC) AECOM KZ
(CxA) CML
Notes: (e.g. Non – standard equipment needed for test such as extra fans or tape and poly)
FM-MS-ADP-211201-025-002
ARABTEC CONSOLIDATED CONTRACTORS COMPANY LTD.
ABU DHABI PLAZA – ASTANA, KAZAKHSTAN
8. Sketch plan view showing dimensions below and calculate floor area, heights and volume. Sketch side view of heights. Show doors
Open, closed and mark where Door Fan will be mounted.
9. Net protected volume : Floor Area _________ X Maximum protected height ____________ = _____________ ft.ᵌ | mᵌ
11. Enclosure height: About Ceiling (0 if not protected) _______ + Room _______ +Sub floor _______ = _______ ft. | m
JV Commissioning Engineer
(CSC) AECOM KZ
(CxA) CML
FM-MS-ADP-211201-025-002
ARABTEC CONSOLIDATED CONTRACTORS COMPANY LTD.
ABU DHABI PLAZA – ASTANA, KAZAKHSTAN
13. Agent: Actual quantity determined from tags _______________ Weight __________________ lb. | Kg.
15. Set up Door Fan, ensuring the door panel system is no tighter than the closed door.
16. Leak check. Blow air to get +15Pa room pressure & use smoke to locate leaks in:
Dampers________, Lower slab________, Sub floor________, Stub wall________, Walls________ & Ceiling________.
17. Total Enclosure Leakage: Test________, Enter untested values________, Sub floor only________.
19. Smoke with Door Fan OFF: Moves out of the room________, Moves into the room________, Doesn’t move________.
20. Bias pressure during Total Enclosure Leakage test. Measure across each perimeter door that showed smoke movement. Use the hand held gauge.
23. Flow Away from operator: Range________ Test #________. 23.1 Room pressure (Pa) __________Fan pressure (Pa) _________ / Flow__________.
24. Flow Towards operator: Range________ 24.1 Room pressure (Pa) __________Fan pressure (Pa) __________ / Flow__________.
27. Set up HVAC, dampers and doorway openings to Hold time conditions. YES_______, No can’t be done_______.
Same as for Total Enclosure Leakage test_______.
JV Commissioning Engineer
(CSC) AECOM KZ
(CxA) CML
FM-MS-ADP-211201-025-002
ARABTEC CONSOLIDATED CONTRACTORS COMPANY LTD.
ABU DHABI PLAZA – ASTANA, KAZAKHSTAN
28. Smoke with Door Fan OFF: moves out of the room________, moves into the room________, doesn’t move________.
29. Determine the Bias pressure during Hold time according to how the room would be set up during the agent retention period. _____________Pa.
30. Minimum protected height from lower slab to protected equipment. ____________ ft. | m
32. Enter discharged rate for extended discharge. _________ lb./min | kg/min
Comments / Discrepancies:
JV Commissioning Engineer
(CSC) AECOM KZ
(CxA) CML
FM-MS-ADP-211201-025-002
Enclosure Integrity Verification Form
Building:
Room:
Test technician:
Witness:
Date & Time of test:
Test and Does the software comply with the latest edition
Technician Details of the standard (2012)?
Page 1 of 4
Heading/tab Label of interest Verification
Total Enclosure
Leakage
Was the enclosure tested in both directions?
Page 2 of 4
Developed by Retrotec
Heading/tab Label of interest Verification
Page 3 of 4
Developed by Retrotec
Heading/tab Label of interest Verification
Page 4 of 4
Developed by Retrotec
TM
Janus Fire Systems Novec 1230 Fluid Hydraulic Flow Calculation Program
Result Printout
Calculation Program Version 2.7.1.5
Designed For: AC JV
ASTANA
ASTANA,
ATTN:
Phone:
Fax:
System Constraints
Page 1 (Continued)
Hazard Characteristics
Nozzle(s) Used: 301 - 360° Nozzle, Brass Dimensions (M): 11.55 X 4.6 X 4.9
302 - 360° Nozzle, Brass
Total Volume (Cu.m.): 260.337
Total Agent Required: 177.87 kgs
Section Pipe Size Length Elevation EQL Tee or Start Term Flow
Start End in(mm) sch M M M Valve BAR (kgs/sec)
Nozzle Performance
Nozzle Nozzle Size Stock Nozzle Drill Dia Drill Total Orifice Discharged
ID mm (in) Number Type (inches) Size Area (sq.cm.) (kg)
Venting Estimate
Enclosure Leakage Relative Safety Max. Positive Max. Negative Pos. ELA Neg. ELA
Name Area Known Humidity Factor Pressure - Pa Pressure - Pa (sq.cm) (sq.cm)
Page 3 (Continued)
Note: For Pipe Schedule(s): -SCH 40; these Pipes conform to ANSI A-53/A-106, grade A-ERW or
better
Document Title:
Inspection & Test Plan (ITP) – Enclosure Integrity Testing & Peak Pressure Calculation Page 1 of 2 Rev.001
Test Procedure
Enclosure inspection
Damper / HVAC status
Elevation
Net Protected volume
Sketch plan of Door fan
location Specification 211201
Operating temperature Approved MST
Enclosure height 211201-025 All relevant
RFIC & FM-MS-
Commissioning Agent quantity Approved Test document must be
2. H W W ADP-211201-025-
Enclosure Integrity Test Minimum agent holding time Procedure approved by
002
Set up room for Door fan Calibration Consultant.
Leak check Certificate
Total Enclosure leakage Retrotec Certificate
Bias Pressure
Temperature readings
Depressurize Test
Pressurize Test
Smoke test
Discharge rate
Legend: S – Surveillance Inspection W – Witness Inspection Point H – Mandatory Hold Point for Inspection R – Record Review
Abu Dhabi Plaza – Astana, Kazakhstan Document No.
Work Package 4 – Main Works ADP-211201-025
Document Title:
Inspection & Test Plan (ITP) – Enclosure Integrity Testing & Peak Pressure Calculation Page 2 of 2 Rev.001
Legend: S – Surveillance Inspection W – Witness Inspection Point H – Mandatory Hold Point for Inspection R – Record Review
Astana/Kazakhstan, Abu Dhabi Plaza Project Астана/Казакстан, Проект Абу Даби Плаза
Job Safety Task Instructions Form (JSTI) Форма Оценки Риска по Технике Безопасности
Step 1: Task Planning (task identification and details)/ Шаг 1: Планирование задания (выявление задачи и деталей)
Step 3: Risk Management (list any nearby activities that may impact the work) Шаг 3: Управление Рисками (перечень деятельности которые могут повлиять на работу)
Astana/Kazakhstan, Abu Dhabi Plaza Project Астана/Казакстан, Проект Абу Даби Плаза
Job Safety Task Instructions Form (JSTI) Форма Оценки Риска по Технике Безопасности
Step 4: Job Safety/Hazard Analysis/ Шаг 4: Анализ/Оценки Рисков
Activity
(What must be done? i.e. tools, Hazards Risks
equipment, and material used) (How could an injury occur?) What Can Happen Recommendations
Item
(Can hazards be eliminated or modified?)
Планирование работы. Опасность Риски Меры контроля
Номер (Что надо для работы. Например: (Как может произойти (Что может произойти) (Как опасность может быть устранена)
инструменты, оборудование и травма)
материалы)
Job Safety Task Instructions Form (JSTI) Форма Оценки Риска по Технике Безопасности
Ensure that personnel engaged of working at
Serious injury to personnel height are trained and competent to the given
or even fatality due to fall task.
Fall of material from height. Supervisor must provide full body harness for
Fall from height Injury to personnel due to personnel engaged of working at height.
Working at heights Collapse of scaffold falling debris. Workplace place must be barricaded underneath
3
Cold weather Injury to personnel or even prior to start the work.
fatality due to collapse of A proper work platform should be provided
scaffolds. Monitor the temperature, and wind chill index.
Hypothermia Work rest period implemented.
Wear Winter PPE.
Provide hot beverage for employees.
Job Safety Task Instructions Form (JSTI) Форма Оценки Риска по Технике Безопасности
Job Safety Task Instructions Form (JSTI) Форма Оценки Риска по Технике Безопасности
Wear all required PPE’s.
Slips, trips and fall due to work boots/ rubber boots with toe
Slips protector
scattered materials or
Trips hard hat
rubbish. visibility vest / jacket
Fall
Foot injuries safety glass
7 Housekeeping Icy surface
Hand injuries Dust Mask ( as required )
Personnel injury due Gloves
slippery surface Anti -slip tract
Supervisor must ensure that used materials
must be stored in designated, to prevent
scattered at work area
Astana/Kazakhstan, Abu Dhabi Plaza Project Астана/Казакстан, Проект Абу Даби Плаза
Job Safety Task Instructions Form (JSTI) Форма Оценки Риска по Технике Безопасности
Step 5: Unplanned Events (if any of the following occurs, stop work and talk to your supervisor)/ Шаг 5: Незапланированные мероприятия: если следующие случаи имеют
место, то остановите работу и известите супервайзера
Nearby work hazards Chemical spills or release
Excessive noise Fires and explosions Unusual odours Heat stress
Опасности на рабочем Утечки химических
Черезмерный шум Пожар и взрывы Странный запах Тепловой удар
месте веществ
Extreme weather/high
winds
Significant near miss Change in the following work conditions:
Evacuation alarm Экстримальные
Существенное, возможное Изменение в процессе работы:
Эвакуация/тревога погодные условия и
происшествия
сильный ветер
Step 6: Unplanned Events (if any of the following occurs, stop work and talk to your supervisor) Шаг 6: Незапланированные мероприятия: если следующие случаи имеют
место, то остановите работу и известите супервайзера
Emergency telephone number: Alarm Code (for commission period)
Телефон экстренной связи: +77015301064 Код сигнализации (при пусконаладке)
Nearest Muster Point/Safety Shelter location: Nearest First Aid Station location:
Ближайший пункт Место Сбора: Ближайший пункт Первой Помощи:
Evacuation Route (Supervisor to explain to workers): Safety shower / eye washer location:
Пути эвакуации(Супервайзер должен объяснить работникам): Пункт промывки глаз:
Job Safety Task Instructions Form (JSTI) Форма Оценки Риска по Технике Безопасности
11 36
12 37
13 38
14 39
15 40
16 41
17 42
18 43
19 44
20 45
21 46
22 47
23 48
24 49
25 50
Supervisor Name:
Ф.И.О Супервайзера: ________________________________________ Signature/ Подпись: __________________ Date/Дата: ____________________________ /______/________
This JSTI is prepared based on theoretical information interpreted from the project documents. A further assessment will be required at
the actual work site to verify the control measures and address any additional hazards. Reference is to be made to the relative Health,
Safety, Environmental & Security procedures to control the risks associated with activities where they occur.