Professional Documents
Culture Documents
Chapter 6
Chapter 6
Investment
Sensitivity
deicisons under
analysis
uncertainity
EV
Adjusted PV and
DPB
Chapter 6
Investment Risk adjusted
decisions under discount factor
risk
Simulation
Investments are carried out in the future meaning there is always uncertainty regarding the
projected cashflows, the life of the projects & discount factors. In this chapter, uncertainty is
factored into the investment appraisal.
Risks can be quantified using mathematical modelling (using probability theory) whereas
uncertainties cannot.
E.g., Insurance companies charge premiums on a vehicle based on several factors. In that,
the risk of getting into an accident is also accounted for.
E.g., It is difficult for a business to estimate the chance of a hacker breaching into their
system with the intent to manipulate data
E.g., In a project, NPV is dependent on several variables such as selling price, variable cost,
investment cost, discount factor etc.
How high should discounting factor increase to reverse the original decision to undertake the
project? (By how much the variable needs to change so that the original investment decision
is reversed)
This is calculated as,
𝑁𝑃𝑉
𝑆𝑒𝑛𝑠𝑖𝑡𝑖𝑣𝑖𝑡𝑦 𝑚𝑎𝑟𝑔𝑖𝑛 = 𝑥 100
𝑃𝑉 𝑜𝑓 𝐶𝐹 𝑢𝑛𝑑𝑒𝑟 𝑐𝑜𝑛𝑠𝑖𝑑𝑒𝑟𝑎𝑡𝑖𝑜𝑛
Lower the sensitivity margin, the higher the sensitivity of the variable to the original
decision
PV of CF under consideration –
• E.g., Sales volume changes. This leads to changes in sales revenue and variable costs.
Therefore, PV of CF under consideration should be a contribution.
• E.g., Selling price changes. This leads to a change in sales revenue. Therefore, PV of
PV of CF under consideration should be sales revenue.
Cost of the investment - $250,000. Useful life - 3 years. Sales revenue & variable cost per
annum are $300,000 & $175,000. Scrapped value of$40,000.
Incremental fixed costs per annum is $20,000.
Calculate the sensitivity of the following factors to the initial investment decision
a) initial investment
b) scrap value
c) selling price
d) unit variable cost
e) annual fixed cost
f) sales volume
g) cost of capital
𝐸𝑉 = Σ𝑝𝑥
whereas
A firm has two mutually exclusive projects which generate the following NPVs under 3
economic states which are likely to arise with the following probabilities.
A project costs $500,000 today. It has a cost of capital of 10%. The project lasts for 3 years.
It is expected to generate the following probabilistic net cashflows per annum.
NCF Probability
100,000 0.3
300,000 0.5
700,000 0.2
Suitability of EV
When evaluating and selecting projects based on EV, the following 3 conditions should be
held
The probability of business coming across a loss in Feb is 5% and Mar is 3%. The joint
probability of business coming across losses in both Feb & Mar is
5% x 3% = 1.5%
Sometimes exam questions may require you to calculate JPs. Calculation of JPs will differ
based on whether outcomes are mutually exclusive or not.
1. If the events are mutually exclusive – then add the individual probabilities of
different outcomes together to get the JP.
2. If the events are not mutually exclusive – then add the individual probabilities
together and then deduct the joint probability of them both occurring.
E.g., Assume you are likely to pay $5000 at a probability of 50% in the next month
and $10,000 at a probability of 65% in the month after that. The probability of
making one payment or the other is
A company has estimated cash flows for a project over the next 2 years at the following
probabilities.
Year 1 Year 2
Probability Cashflows Probability Cashflows
20% 50,000 30% 100,000
80% 100,000 70% 150,000
The proposed investment will cost $200,000 which will be paid at the beginning.
Adjusted payback
The shorter the payback, the faster the recovery of the initial investment, the lower the
overall risk.
To have shorter payback, the project must generate large positive cashflow in the initial
years.
A project has following cashflows into the future. Calculate its payback assuming the cost of
capital is 5%.
Year Cashflow
0 (110,000)
1 45,000
2 35,000
3 42,000
Discount payback method has the same advantages and disadvantages as the basic payback
method, except now, the cashflows consider the TVM concept.
Adjusted payback & discounted payback methods are not typically used in appraising
projects under uncertainty and risk
1. Risk of the project – Higher the risk, the higher the discount rate
2. Cost of borrowing funds at the loan rate
3. Rate of return demanded by shareholders
If the project under consideration is highly risky compared to the existing business risks of
an organisation, then the discount rate needs to be adjusted for risk.
Simulation
In sensitivity analysis, only one variable changes at a given time and the resulting impact of
the original decision is identified.
Simulation shows the effect of more than one variable changing at the same time. E.g., the
effect on NPV when labour cost increases by 10%, material costs increase by 25% and
investment expenditure falls by 5%.
All possible outcomes are accounted for High cost of construction of the simulation
model