Professional Documents
Culture Documents
Group08 Q1
Group08 Q1
Group08 Q1
Annex I. Location
The objective of this Project is the design of a Counterdique for a new marina in
the Catalan coast. Our structure is located in the region of El Garraf, between the
localities of Sitges and Garraf.
As we can see in the figure below, there is already an industrial harbour in this
location which is used exclusively by the concrete factory that is located just next to
it. What we pretend is to convert this harbour in a marina adding a counterdike to
create a place where sporadic tourists could go to enjoy the environment. Thus,
our main objective is to conserve the beaches and the surroundings and cause the
minimum effect on the current situation.
Figure 1. Location of the counterdike
To analyse the wave climate we will use a method called Peak Over Threshold
(POT). The first thing that we had to do was to find a wave height threshold in
order to define storm conditions. According with ROM 02.90 and considering our
location on the catalan coast, this threshold has a value of 2 meters. Taking in to
account this wave heigh, we obtained 33 different storms in the 10 years that were
covered by our data, giving a lambda factor of 3,3 storms/year.
To define the storms, we have considered all the data with a wave height grater
than 2 meters and duration longer than 6 hours. None of our storms had a duration
longer than 4 days, in such a case we had cut it in to 2 different storms. If we find 2
storm conditions separated by a calm period shorter than 6 hours, we have
considered it in to a single storm.
Now we will work only with storm data. The next step is to find the probabilistic
function that fits better with our conditions in order to relate the wave height and
the non-exceeded probability. We will use a Weibull function, which follows the
expression below.
!
𝐻−𝐴
𝐹 𝐻 = 1 − 𝑒𝑥𝑝 − , 𝐻>𝐴
𝐵
! !!! !
𝑌𝑟 = −𝐿𝑛(1 − 𝐹 𝐻 ) = !
, Where 𝐹 𝐻 = 1 − !!!
Adjusting this new variable using the minimum square method, we obtain the best
R-square value for a C factor equal to 0,8
C=0,8
6
y
=
1,4879x
-‐
3,1543
5
R²
=
0,9769
4
Yr
3
2
1
0
1
2
3
4
5
6
Hmo
Figure 2. C factor regression
From this linear regression we can find the values of A and B factors as follows.
𝐻−𝐴
= 1,4879𝐻 − 3,1543
𝐵
And we obtain the following result:
Weibull
1,2
A
2,11996774
B
0,672088178
1
C
0,8
0,8
F(H)
0,6
0,4
0,2
0
1
2
3
4
5
6
Hmo
Figure 3. Weibull distribution
Now, we are interested in knowing how the return period and the wave height are
related. We will use the following formula whit a lambda factor that represents de
number of storms per year.
1 𝑠𝑡𝑜𝑟𝑚𝑠 33
𝑇𝑟 = , 𝜆 = = = 3,3
(1 − 𝐹(𝐻))𝜆 𝑦𝑒𝑎𝑟𝑠 10
2
1
0
0
2
4
6
8
10
12
Return
period
Figure 4. Relation between wave high and return period
𝐻 = 2,9281 ∗ 𝑇 !,!"##
We also need the relation of wave height and wave period in order to do our
design. Thus, with the wave height of each storm and its correspondent peak
period we have found the regression that fits better, with a grater value of R-
square. In this case, we were looking for a potential function, but we found that a
linear regression gives a higher R2 value.
Wave
period
Wave
period
16
16
14
14
12
12
Period
Period
10
10
8
8
6
6
4
4
0
2
4
6
1
3
5
7
Hs
y
=
5,6755x0,4519
R²
=
0,22255
Hs
y
=
1,5286x
+
4,8664
R²
=
0,28448
We obtain the following expression that relate the wave height (H) with the wave
period (T)
𝑇 = 1,5286 ∗ 𝐻 + 4,8664
There are only few directions that arrive directly to our structure, so the next
analysis that we have to do is to select these wave directions and find the most
critical one. That means, the direction that contains the highest waves.
In order to calculate the wave height in each direction we need the direction factors
K. The procedure to calculate them is the next one:
As we do not have enough data to calculate it, we can use this plot from the web
www.puertos.es, where it is represented the peak water level for each month since
1996.
We can see that the maximum value is achieved in 2003 when the water level
increased nearly 1 meter. Even so, we are going to consider a smaller value in
order to represent a bigger range of years. If we consider 1 meter of mean water
level oscillation we are overdimensionating our structure because it is a value that
has been achieved only once in 15 years. Thus, we will take a value of 0,8. This
value is a more representative one as it has been reached some other times.
We considered that our coast is tilted 70 degrees from the North direction. We also
supposed that the isobaths are parallel to the shoreline in order to apply the
expressions that we have learnt in class.
First of all we have to compute the return period of the structure in order to work
with waves of the same return period, which would be the most dangerous ones.
In the ROM 0.2-90 there is an expression to calculate the structure’s return period.
−𝐿
𝑇=
𝐿𝑛(1 − 𝐸)
Where T is the return period in years and, L is the lifetime of the construction and E
the maximum admissible risk. From the tables below we have considered the
values that fit better with our counterdike.
As the counterdike is for a marina, no related with industrial aims, the estructure
has a generic nature. The level security is 1 as it is a local construction with a low
risk of losing human lives or causing environmental damages. So we take L=25
We consider the risk for the start of the damage as we consider our structure a
flexible one, easy to repair in case of failure and with a low risk of losing human
lives. Thus, we take a risk coefficient E=0,5
Introducing these values in to the formula given above, we get a return period for
the structure T=36 years
Considering the relationship between the return period and the wave height that we
computed in annex II, for a return period of 36 we get a wave height of 7,96
metres.
In the table above we can see the wave height and the periods for each direction
(The wave height is computed as 7,96*K for each direction). The period is
computed using the relationship that we got in annex II between wave height and
wave period.
From these values we can calculate the celerity, the group celerity and the wave
length in deep water as follows:
𝑔 · 𝑇! 2𝜋 · ℎ 1 4𝜋 · ℎ 𝐿 𝐿
𝐿= · tanh , 𝑐!! = 𝑛 · 𝑐! = · 1 + ·
2𝜋 𝐿 2 sinh 4𝜋 · ℎ 𝐿 𝑇
Finally we need the incident angle and the propagate angle that we relate using the
Snell equation.
sin ∝! sin ∝ 𝑐
= , ∝= sin!! · sin ∝!
𝑐! 𝑐 𝑐!
Now we are ready to compute the design wave height of our counterdike.
𝑐!! ∝!
𝐻 = 𝐻! · 𝐾! · 𝐾! = 𝐻! · ·
𝑐!! ∝!
The maximum wave height due to the propagation arrives from the South direction
and reaches a height of 10,39 metres. However, supposing a breaking coefficient
Hb/hb=0,6, we obtain a Breaking wave high of Hb=3,6 metres. As we are in a
situation where Hp>Hb, that is an impossible situation, we will work in breaking
conditions assuming a design wave height equal to 3,6 metres
Iribarren-Hudson
The Iribarren-Hudson equation to scale the elements of the armour layer is the
next one:
𝜌!"!#!$% · 𝐻 !
𝑀!" =
𝐾! · ∆! · cotg 𝛼
In our case:
𝐾! = 2 𝑤𝑎𝑣𝑒𝑠 𝑏𝑟𝑒𝑎𝑘𝑖𝑛𝑔
!!"!#!$%
∆= !!"#$%
− 1 = 1′65
With the mass value we can find the nominal diameter of the armour elements with
the next expression:
! !
𝑊 ! 𝑀!" !
𝐷!!" = 1.0 · =
𝛾 𝜌!"!#!$%
For the elements of the core, the mass is related with the mass of the elements of
the armour and the nominal diameter is calculated as for the armour.
𝑀!"
𝑀!"! =
20
!
𝑀!"! !
𝐷!!"! =
𝜌!"!#!$%
We will dimension the elements for three different slopes: 2:3, 1:2 and 1:3
cotgα 1,5 2 3
M50 (kg) 18792,798 14094,599 9396,399
Dn50 (m) 1,921 1,746 1,525
M50c (kg) 939,640 704,730 469,820
Dn50c (m) 0,708 0,643 0,562
To dimension the structure with this method we need to calculate a factor N that is
the number of waves that arrive in a storm. To do this we have relate the wave
high of our storms with its duration, so we were able to calculate the duration of a
storm with a wave high of 3,6 metres, that is our design wave high.
H
-‐
dura?on
60
50
y
=
12,777x
-‐
18,775
R²
=
0,593
dura?on
40
30
20
10
0
0
2
4
6
H
𝐷 = 12,777 ∗ 𝐻 − 18,775
For H = 3,6 metres we obtain a duration of 27,2 hours that are equivalent to 98000
seconds. With the wave period associated to this wave high Tp = 10,37 s, we
obtain a N factor equal to:
98000
𝑁= = 9450 𝑤𝑎𝑣𝑒𝑠
10,37
The security factor S has a value of 2. The structure is protected by the mean dike
of the harbour, that it is why the waves do not arrive with a lot of energy to the
counterdike. We have considered a permeability of 0,4 so we will design our
counterdike with 3 layers (armour, filter and core). This permeability is due to the
fact that the structure is not a very important structure, so we can admit some
permeability, but we do not want fluxes of water in our harbour, thus the
permeability cannot be extremely high.
The next step is to know the type of breaking. In order to do that, we must calculate
the model and the critical Iribarren parameter and compare them:
𝐿!
𝐻!
𝐼𝑟! =
cotg 𝛼
!
!!!"#
Ir! = 6! 2 · P !"#$ · tanα
cotgα 1,5 2 3
Ir,m 4,55 3,41 2,28
Ir,c 4,42 3,77 3,01
In the fist case we have Surging conditions and in the last two cases, plunging. The
equations to scale the armour elements are:
!"#
𝐻! 𝑆
𝑆𝑢𝑟𝑔𝑖𝑛𝑔 ∶ = 1.0 · 𝑃!!"#$ · · 𝑐𝑜𝑡𝑔α · 𝐼𝑟! !
∆ · 𝐷!!" 𝑁
!"#
𝐻! 𝑆
𝑃𝑙𝑢𝑛𝑔𝑖𝑛𝑔 ∶ = 6.2 · 𝑃!,!" · · 𝐼𝑟! !!,!
∆ · 𝐷!!" 𝑁
For the elements of the core, the nominal diameter is related with the nominal
diameter of the elements of the armour and the mass is calculated as for the
armour, the same happens for the elements of the filter.
𝐷!!"
𝐷!!"! = , 𝑀!"! = 𝜌!"!#!$% · 𝐷!!"! !
8
𝐷!!"
𝐷!!"! = , 𝑀!"! = 𝜌!"!#!$% · 𝐷!!"! !
2
The results are shown in the next table:
cotgα 1,5 2 3
Dn50 (m) 1,876 1,822 1,361
M50 (kg) 17488,02 16040,83 6682,35
Dn50f (m) 0,938
0,911
0,681
M50f (kg) 2186,00 2005,11 835,29
Dn50c (m) 0,234
0,228
0,170
M50c (kg) 34,16 31,330 13,052
As we can see we obtain smaller values with this method than with the Iribarren-
Hudson method. Our solution will be the highest slope. The reason of this election
is that we have already reduce the space in the harbour in order to maintain the
beach, so a softer slope would reduce the space for boats even more.
cotgα 1,5
Dn50 (m) 1,876
M50 (kg) 17488,02
Dn50f (m) 0,938
M50f (kg) 2186,00
Dn50c (m) 0,234
M50c (kg) 34,16
The high of the counterike will be 11 metres (6m of the mean water level + 0,8 of
the mean water level oscilations + 3,6 of the wave high + 0,6 as a security factor).
The width of the core is 7 metres to allow the circulations of two trucks during the
construction. The toe must have a length doble the diameter of the elements of the
armour, and the thickness of the armour must have the same value, 7,5 m. The
thickness of the filter layer must have 1,5 times the size of the elements of the
armorur
We have considered the first option as we renounce to space inside the harbour
but we maintain the beach, attracting more tourism. It has also a smaller visual
impact. The fist option will cause minimum changes in the coastal because is an
internal structure so all the damage has already been caused by the mean dike
and we can appreciate that it has not cause almost any impact.
In addition the coast of this part of Catalonia is very rocky, so the impact in the
sediment transport that we can expect is almost zero.
The only impact that this counterdike can cause is the possibility of reflecting
waves to the beach increasing the wave height. To minimise this reflection we
have decided to do a rubble mound instead of a vertical structure.
Counterdike in Cèrbere
The volume of the section of the counterdike has been computed as a triangle with
a mean high of 10 metres and a base of 26,7 metres as we can see in the figure
above. We obtain a volume of 133,5 m2 for lineal unit. The length of this
counterdike is 140 metres odd, so the total volume is about 18690 m3.
The total price of this counterdike is 1.738.032,24 €, so the price for a cubic metre
is 93€
Counterike in Garraf
The length of our counterdike is 170 metres, leaving 50 metres in the entrance of
the harbour.
The approximate volume for the designed section is 181,5 m2, so the total volume
is about 30855 m3.
This budget is not very accurate because the sizes of the stones in the project of
Cèrbere are different than those in our project.