DAILY REPORT CONSTRUCTION ACTIVITY SITE WKP

Project : Construction Building PIT 14


Location : West Kintap Project
Date : 25/03/2023
PIC : Ridha S. Salam / M.Saraji F.

Progress Comulative
No Job Description Due Date Documentation Status Remarks
(%) (%)
1 Ruangan MED Location : Belakang Pondok Meeting
- Clearing area 45
- Pemasangan rangka kayu 70
- Pemasangan dinding kalsiboard 90
- Pekerjaan pintu jendela 70
41,43 31/03/2023 CONTINUE
- Acian lantai 0
- Pekerjaan plafond 15
- Pekerjaan elektrikal 0

2 Bund Wall FS 26 KL Location : FS KL26


- Pengukuran area 100
- Prakitan pembesian 10
- Pekerjaan sloof dan balok 0
- Pekerjaan kolom 0
13,75 07/04/2023 CONTINUE
- Pasangan dinding batako 0
- Pemasangan rangka atap 0
- Pemasangan spandek 0
- Pekerjaan elektrikal

DEWA CON FORM .. R0 - Laporan Harian Construction Dokumen Tidak Terkendali Jika Dicetak Halaman 1 dari 3
DAILY REPORT CONSTRUCTION ACTIVITY SITE WKP
Project : Construction Building PIT 14
Location : West Kintap Project
Date : 25/03/2023
PIC : Ridha S. Salam / M.Saraji F.
Progress Comulative
No Job Description Due Date Documentation Status Remarks
(%) (%)
3 Maintenance Pos 3 Location : Pos 3
- Pemasangan dinding 100
- Pemasangan jendela mika 100
- Pengecoran lantai 50

83,33 22/03/2023 PENDING

DEWA CON FORM .. R0 - Laporan Harian Construction Dokumen Tidak Terkendali Jika Dicetak Halaman 2 dari 3
DAILY REPORT WORKSHOP ACTIVITY SITE WKP
Project : Satelite Workshop & Facilities Date 25/03/2023
Location : West Kintap Project Week 30 Periode 13/03/2023 s/d 19/03/2023

WAKTU PELAKSANAAN PEKERJAAN


- Mulai Project 19/08/2022 6
- Estimasi Selesai 31/03/2023
- Masa Pelaksanaan 225 Hari
- Waktu Pelaksanaan Terpakai 219 Hari 219

- Sisa Waktu Pelaksanaan 6 Hari


REALISASI PROGRES PEKERJAAN
- Progres On-Site 53,205 %
- Sisa Progres 46,795 %