Activity ID Activity Name Planned Duration Remaining Schedule % Start Finish Total Float Qtr 1, 2024 Qtr 2, 2024

e % Start Finish Total Float Qtr 1, 2024 Qtr 2, 2024 Qtr 3, 2024
Duration Complete Feb Mar Apr May Jun Jul

RCBU ( ‫)ﻣﺷروع ﺗﻧﻔﯾذ ﺷﺑﻛﺎت اﻟﺻرف اﻟﺻﺣﻲ ﺑﺣﻲ اﻟﻌﺎرض اﻟﻣرﺣﻠﺔ اﻻوﻟﻲ‬
‫ﻣﺷروع‬ 405 405 0% 01-Apr-24 16-Jul-25 -119

RCBU.1 DE MOBILIZATION 0 0 0% 16-Jul-25 16-Jul-25 -119

RCBU.2 MOBILIZATION 0 0 0% 01-Apr-24 01-Apr-24 -119 01-Apr-24, RCBU.2 MOBILIZATION

RCBU.3 ENGINEERING 45 45 0% 01-Apr-24 22-May-24 -119 22-May-24, RCBU.3 ENGINEERING

RCBU.4 PROCURMENT 50 50 0% 24-Apr-24 20-Jun-24 186 20-Jun-24, RCBU.4 PROCURMENT

RCBU.4.1 ORDER 30 30 0% 24-Apr-24 28-May-24 196 28-May-24, RCBU.4.1 ORDER

A1120 Internal & Finishing Insulation for Manhole 5 5 0% 06-May-24 11-May-24 211 Internal & Finishing Insulation for Manhole
A1100 Accsessories for Manhole 5 5 0% 23-May-24 28-May-24 196 Accsessories for Manhole
A1080 External Insulation Material 5 5 0% 06-May-24 11-May-24 151 External Insulation Material
A1060 Precast Concrete Manhole 10 10 0% 24-Apr-24 05-May-24 161 Precast Concrete Manhole
A1040 Corrugated high density polyethylene pipes 30 30 0% 24-Apr-24 28-May-24 6 Corrugated high density polyethylene pipes

RCBU.4.2 DELIVARY 40 40 0% 06-May-24 20-Jun-24 186 20-Jun-24, RCBU.4.2 DELIVARY


A1130 Internal & Finishing Insulation for Manhole 10 10 0% 12-May-24 22-May-24 211 Internal & Finishing Insulation for Manhole
A1110 Accsessories for Manhole 10 10 0% 29-May-24 09-Jun-24 196 Accsessories for Manhole
A1090 External Insulation Material 10 10 0% 12-May-24 22-May-24 151 External Insulation Material
A1070 Precast Concrete Manhole 20 20 0% 06-May-24 28-May-24 161 Precast Concrete Manhole
A1050 Corrugated high density polyethylene pipes 20 20 0% 29-May-24 20-Jun-24 6 Corrugated high density polyethylene pipes

RCBU.5 CONSTRCUTION 405 405 0% 01-Apr-24 16-Jul-25 -119

A1200 Finishing Works 15 15 0% 21-Jul-24 06-Aug-24 161


A1190 Installation Manhole 45 45 0% 29-May-24 20-Jul-24 161
A1180 Asphalt Works 30 30 0% 12-Jun-25 16-Jul-25 -119
A1170 Backfilling Works 60 60 0% 03-Apr-25 11-Jun-25 -119
A1160 Installation Pipes 120 120 0% 14-Nov-24 02-Apr-25 -119
A1150 Digging works 150 150 0% 23-May-24 13-Nov-24 -119

A1140 Surveying works 15 15 0% 01-Apr-24 17-Apr-24 -89 Surveying works

RCBU.6 TESTING & COMMENDATION 15 15 0% 07-Aug-24 24-Aug-24 161

A1210 Testing 15 15 0% 07-Aug-24 24-Aug-24 161

You created this PDF from an application that is not licensed to print to novaPDF printer (http://www.novapdf.com)
Qtr 3, 2024 Qtr 4, 2024 Qtr 1, 2025 Qtr 2, 2025 Qtr 3, 2025
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul
16-Jul-25, RCBU (

16-Jul-25, RCBU.1 DE MOBILIZATION

PROCURMENT

DELIVARY

y polyethylene pipes
16-Jul-25, RCBU.5 CONSTRCUTION

Finishing Works
Installation Manhole
Asphalt Works
Backfilling Works
Installation Pipes
Digging works

24-Aug-24, RCBU.6 TESTING & COMMENDATION

Testing