1.MS - FLOORING (GRANITE, TILE) - Rev 0
1.MS - FLOORING (GRANITE, TILE) - Rev 0
1.MS - FLOORING (GRANITE, TILE) - Rev 0
Rev : 0
FLOORING (GRANITE & TILE) th
Date : 30 Jan’21
Pages : 1 of 5
PROJECT
EMPLOYER
CLIENT
REPRESENTATIVE
CONTRACTOR
AMMENDMENT RECORD
th Review &
0 30 Jan’21 QA/QC Engineer QA/QC Manager PM/PD-Projects
Approval
PROJECT: ITPP-KHARADI
Doc Ref : MS 01
Rev : 0
FLOORING (GRANITE & TILE) th
Date : 30 Jan’21
Pages : 2 of 5
TABLE OF CONTENTS
1. OBJECTIVE ..................................................................................................................... 3
2. SCOPE............................................................................................................................. 3
3. REFERENCE ................................................................................................................... 3
6. PROCEDURE .................................................................................................................. 4
7. RESPONSIBILITIES ........................................................................................................ 5
8. ATTACHMENTS .............................................................................................................. 5
List of Attachments
Inspection and Test Plan (ITP)
Checklist (CL)
PROJECT: ITPP-KHARADI
Doc Ref : MS 01
Rev : 0
FLOORING (GRANITE & TILE) th
Date : 30 Jan’21
Pages : 3 of 5
1. OBJECTIVE
The objective of this method statement is to carryout flooring work (granite and tile) by
meeting the technical specification and complying with Standards.
2. SCOPE
The scope of this method statement includes shifting, laying (granite & tile) of flooring with
pattern given in the drawing at “ITPP Kharadi -Pune” project, while executing it in
accordance with Technical specifications.
3. REFERENCE
5. MATERIAL USED
PROJECT: ITPP-KHARADI
Doc Ref : MS 01
Rev : 0
FLOORING (GRANITE & TILE) th
Date : 30 Jan’21
Pages : 4 of 5
6. PROCEDURE
Granite/Tile shall be fabricated and finished at factory as per approved drawing and
delivered to site. Upon receipt of site, delivery note shall be verified by QC engineer
along with store keeper. They shell be stocked properly and protect from any
damages.
Cement and grout materials shall be stored in designated locations as per
manufacturer recommendations. First in first out method shall be fallowed for issuing
materials.
Sand shall be stacked at designed location and protected adequately from
contamination.
Ensure all required materials are shifted and kept in near area for tile & granite work.
B. Sequence of work:
Clean the floor area free from dust & debris.
Remove all the unwanted dead mortars and required floor chippings to create
allowance to meet FFL.
Obtain MEP clearance in-prior and ensure proper packing at junctions.
Mark top level (Bull mark) of the flooring and the required gradient given in the
drawing.
Place mortar CM – 1:4 ratio as per BOQ/Technical spec/ other fixing materials
(adhesives, bonding agents etc.,) for required thickness.
Level the mortar for the required level to place the flooring material
(Granite & Tiles).
Mark the starting point of laying as per shop drawing.
Fixing the approved flooring materials (Granite & Tiles) with cement slurry / other
fixing materials (adhesives, bonding agents etc.,) from the starting point given in the
shop drawing.
Necessary spacers to be provided to achieve even spacing and lining of flooring
material (Granite &, Tiles ).
Make the top same level to meet top level given in drawing and the required gradient.
PROJECT: ITPP-KHARADI
Doc Ref : MS 01
Rev : 0
FLOORING (GRANITE & TILE) th
Date : 30 Jan’21
Pages : 5 of 5
Necessary cleaning & grouting to be done after placing the flooring material.
Necessary curing to be done.
Required protection to be done on the flooring.
7. RESPONSIBILITIES
8. ATTACHMENTS
PROJECT: ITPP-KHARADI
QUALITY MANAGEMENT SYSTEM
L&W BUILDING SOLUTIONS PVT.LTD
INSPECTION TEST FORMAT
L&W
Component / Method of Frequency of L&W
S.No: Nature of Check / Test Reference Document Format of Record Execution Client
Process Check Check QC Engineer
Engineer
Submission &
Document Before start the Project Specification &
1 Approval of work Review Method Statement - H A
Review works Approved Drawings
method statement
Surface preparation
Visual / Approved Drawings &
6 and mortar dabs Surveillance Each Location RFWI & Check List C H S
Measurement Approved MS
installation
C - Check, I - Inspection, A-Approval, P - Perform, M - Monitor, R - Review, LTR - Lab Test Report , H - Hold ,W - Witness, S - Surveillance
QUALITY MANAGEMENT SYSTEM
L&W BUILDING SOLUTIONS PVT LTD
QAQC / FLOORING / 001-Rev 00
Name of the Project ITPP-KHARADI Date:
Building/Structure/Location:
Ref Drawing Number: Method Statement Number: MS - 01
FLOORING (GRANITE & TILE)
SL NO DESCRIPTION YES NO REMARKS
A GENERAL
B LAYING
C POST COMPLETION