Professional Documents
Culture Documents
Session 23-26 - MPS Complete
Session 23-26 - MPS Complete
Copyright 2013-2014
days, weeks or months, depending upon the firm and its
products).
Sunday, April 23, 2023 THAPAR UNIVERSITY, PATIALA 1
Difference in the format used in Aggregate Plan and MPS
For a particular planning period, the sum of quantities in the MPS is equal to that in the
corresponding aggregate plan.
Each planning period of aggregate plan (in the example above, planning period is month’s period) is
further split into smaller planning periods in MPS (here, split into weeks). The critical function of
master production scheduling is to allocate the aggregate production quantities efficiently over its
planning periods (e.g. production quantity of 600 units of September month shown in aggregate plan
has been allocated as 150, 100, 200 and 150 units respectively in weeks 1, 2, 3 and 4 respectively of
this month). This allocation is based on several factors which include :
historic demand
Copyright 2013-2014
marketing and promotional considerations
lot size of each product type in each period of MPS is decided on the basis of set- up costs,
working capital required for production of a lot etc.
capacity limitations; this includes labour, machine, storage capacities, availability of spares.
• It is on the basis of the above mentioned factors that timing and size of MPS quantities
2 is
determined.
FUNCTIONS OF MASTER PRODUCTION SCHEDULE
Copyright 2013-2014
Master Production Schedule is the main input for Material
Requirements Planning system of the firm. When end items appear on the
MPS, it signals the MRP system to purchase/ produce necessary components
for meeting delivery schedules. 3
FUNCTIONS OF MASTER PRODUCTION SCHEDULE
Copyright 2013-2014
aggregate plan will have to be revised to adjust either production
requirements or increase authorized resources.
Sunday, April 23, 2023 THAPAR UNIVERSITY, PATIALA 4
FUNCTIONS OF MASTER PRODUCTION SCHEDULE
Copyright 2013-2014
Sunday, April 23, 2023 THAPAR UNIVERSITY, PATIALA 5
Steps in Master Production Scheduling Process
Copyright 2013-2014
6
TYPES OF MASTER PRODUCTION SCHEDULE
Two basic formats are used in Master Production Schedule: the first type of format is used for firms
based on make to stock approach and the second format is for firms based on make to order
approach. Thus, there are two basic types of master schedules.
MPS for Make to Stock Firms: Demand forecasts are the main input for master production schedule
of firms based on make to stock strategy. The format used for MPS of such firms is shown as follows:
Copyright 2013-2014
The MPS shown in the above figure is using a planning horizon of roughly a quarter
of a year (here, 13 weeks) and the planning periods are in weeks. MPS is said to have
three portions namely Firm, Flexible and Open portion.
7
TYPES OF MASTER PRODUCTION SCHEDULE
‘Firm’ portion of the MPS is in the very immediate future. No changes or revisions can be
made to the production quantities listed in this portion. This is because this portion
encompasses minimum lead times necessary for components. For quantities listed in this
portion, orders have been placed for materials, components etc. required or they have
reached; routing and scheduling functions have been completed. Thus production quantities
listed in ‘firm’ portion are practically freezed and no changes are accepted. In the example
shown in the above Figure, period up to the sixth week is being considered as firm portion. As
each week passes, seventh week is advanced to the ‘firm’ portion.
Copyright 2013-2014
The portion beyond the ‘firm’ portion up to the planning horizon is called ‘flexible’ portion. If
some production quantities listed in the ‘firm’ portion could not be completed, they are passed
to the ‘flexible’ portion. Changes in the early parts of ‘flexible’ portion should be discouraged.
The portion of MPS beyond the planning horizon is termed as ‘open’ portion. This
portion can accommodate changes as it is away at a very distant future and the time
available is more than component lead times. It is this portion where trial-and-error work
and rework activities are taking place to decide on lot sizes, valid priorities, and other
details.
Copyright 2013-2014
9
TYPES OF MASTER PRODUCTION SCHEDULE
MPS for Make to Order Firms: The master schedule for firms based on make to order
approach is shown in Figure below:
Consider a company producing customized products of five different types. Suppose the
plant capacity is 60 standard hours per day.
MPS Format for manufacturing organizations based on Make to Order Strategy
Copyright 2013-2014
10