Plu-Mst-001, Upvc Drainage
Plu-Mst-001, Upvc Drainage
CONTENTS المحتويـــــــــــــــــــــات
Equipment & Resource to be Used المعـــدات و المصـادر التي يجـب إستخدامــها 6.0
Appendices الملحقــــــــــــــــــــــــــــات
Drawings, BOQ and Specifications References مراجع المواصفـات و جدول الكميات ومخططــات .2
1|P a g e
SM28_MS_02.02
Reference No رقم المرجع
Project Management Office مكتب أدارة المشاريع
360 SM MS 001
REV. Date بيــــــان طــــــريقة العمــــــــل
00 07-04-2022 Work Method Statement
This method statement describes the sequence of activities involved for fixing UPVC
Drainage Pipe installation works to be performed by Al Ain General Contracting Company
LLC.
This method statement will be applicable for Contract No. PGC/CFD/572/60/2021/360
3.0 Methodology
3.1 Pre-Works
a) Approved type of pipes and fittings for drainage will be ordered and supplied to site.
b) Materials should be stored in a covered dry place at all time.
c) The materials received at site need to be inspected and ensured that the materials
are as per approved material submittal.
3.2 Works
Pre Works:
o The trench shall be excavated by a Hand/back hoe Loader/Excavator after
the area of excavation is identified, the formation of the trench must consist
of stable, uniform and smooth soil devoid of irregularities for direct laying of
pipes. The minimum width of the trench must be equal to the pipe diameter
plus 150mm.
o The excavated material shall be placed on one side of the trench leaving the
other side clear for pipe handling, and the bed of the trench should be
smoothened out evenly to provide a uniform support for the pipe.
Sequence of Installation:
2|P a g e
SM28_MS_02.02
Reference No رقم المرجع
Project Management Office مكتب أدارة المشاريع
360 SM MS 001
REV. Date بيــــــان طــــــريقة العمــــــــل
00 07-04-2022 Work Method Statement
o Fix solid blocks at the bottom of the trench, where drainage pipes to be laid
as per the required slope.
o Lay the drainage pipes with adequate slope and proper supports.
o Measure length of pipe required, making due allowance for any pipe fittings
to be used. Cut the pipe to the measured length. Ensure that the ends are
cut square and clean all burs.
o The spigot and socket to be jointed should be carefully examined for any
damage which could impair the jointing procedure.
o The spigot insertion depth should be measured as the depth from the mouth
to the shoulder of the socket.
o The jointing system for drainage pipe system is ‘lubricant and solvent weld’.
o The mating areas of the spigot and the socket should be thoroughly cleaned
using the pipe cleaner and a clean rag.
o Using a brush apply an even layer solvent cement to the spigot and socket
mating surfaces. The cement/lubricant should be applied in a lengthwise
direction and not with a circular motion. The cement/ lubricant should be
applied simultaneously to the spigot and socket by two people.
o Leave the joint undisturbed for five minutes and then handle with reasonable
care.
o Plug all open ends of the pipe work.
o All horizontal drainage piping shall be installed with 0.3% slope unless
otherwise indicated.
3|P a g e
SM28_MS_02.02
Reference No رقم المرجع
Project Management Office مكتب أدارة المشاريع
360 SM MS 001
REV. Date بيــــــان طــــــريقة العمــــــــل
00 07-04-2022 Work Method Statement
o Proper block and rebar support is given to avoid dislocation of pipes in case
of pressure.
o Ensure the connections are well fixed to avoid leakage during pressure/leak
test.
o Locate the pipes for floor drains, floor clean outs, wash basin, water closet
and other sanitary wares as per the approved shop drawing.
o Completing the work in a neat manner and workmanship following the
manufacturer’s installation instructions. Installed unites will be plumed and
levelled, firmly anchored in locations indicated in the drawings maintained
recommended clearances.
o After completing the installation works, the pipes have to be tested for
leakages following the acceptance procedure and inspection to be raised for
the same.
Leak testing:
o Once the installations are complete, internal inspection will be done by Site
Engineer/QAQC to ensure the quality of work.
o Site Engineer /QAQC will submit request for final inspection of pipe
installation, if found acceptable proceed to filling of water.
o The piping system to be tested shall be closed by plugging and blanking all
openings in the system in an approved manner.
o Suitable plugs are inserted at the lower end of the drain or sewer and at the
head of any connections.
o A suitable bend together with a vertical length of pipe is fitted at the head of
the sewer or drain to provide the necessary test head.
o Close openings in piping system and fill with water to point of overflow.
Water level must not drop and inspect joints for leak.
o The pipes under test should be left filled with water for min 24hours.
o So ensure that all piping and joints are no leak.
o During the water test, precautions should be taken to prevent any movement
of the drain pipe.
o After the internal inspection by the QAQC invite client representative for final
checking and inspection.
o After successful testing & Inspection of pipe work, covering of pipe work can
proceed as per approved drawing details.
Backfilling:
4|P a g e
SM28_MS_02.02
Reference No رقم المرجع
Project Management Office مكتب أدارة المشاريع
360 SM MS 001
REV. Date بيــــــان طــــــريقة العمــــــــل
00 07-04-2022 Work Method Statement
o After approval of the tested pipes from the engineer, the pipes will be buried
by back filling the loose sand layer by layer.
o All ends shall be plugged after completion of test to protect from debris.
o Do not use material with sharp edges for back filling.
o Concrete encasement to be provided for the pipes with depth less than 60
cm.
o Backfilling to be compacted in 300 mm layers.
o Do not use heavy compactors until there is at least 500 mm cover.
o Labels & Identification will be provided as per material submittal.
6.0- Equipment & Resources to be Used 6.0- المعـــدات و المصـادر التـــي يجـب إستخدامــها
No. Equipment Description No. Equipment Description
1 Toolbox 9 Marker
2 Ladder/scaffolding 10 Level
3 Measuring tape 11 Hose pipe
4 uPVC Pipes & fittings 12 Solvent cement
5 Line dory 13 Warning tapes
6 Nails 14 Excavator (hand/back hoe loader/ excavator)
5|P a g e
SM28_MS_02.02
Reference No رقم المرجع
Project Management Office مكتب أدارة المشاريع
360 SM MS 001
REV. Date بيــــــان طــــــريقة العمــــــــل
00 07-04-2022 Work Method Statement
SEE ANNEX - A
Permits Required Yes No Assessments Required (attach if “Yes) Yes No
Hot works Coshh
Crane Check List Noise
Excavation Manual handling
Confined space entry Other (state)
Riser Shafts
SEE ANNEX - A
Training Certification Required Yes No Training Certification Required Yes No
Scaffold Mobile Elevating Platform
Forklift Mobile Access Tower
Dumper Banks man
Excavator Abrasive Wheels
Overall assessment of risk prior to the Low Moderate Substantial High
implementation of control measure
Emergency Arrangement ترتيبات الطوارئ
First Aid Measures Required Rescue / Security Measures Required
6|P a g e
SM28_MS_02.02
Reference No رقم المرجع
Project Management Office مكتب أدارة المشاريع
360 SM MS 001
REV. Date بيــــــان طــــــريقة العمــــــــل
00 07-04-2022 Work Method Statement
Work inspection request shall be received by consultant prior to start of activity at site.
Consultant representative shall check and approve the equipment certificates and personnel
qualifications to perform the job at site.
Consultant representative shall check and witness randomly with regard to the installation of
pipes at site.
Any Non-compliance and Risk assessment the consultant representative have all the
discretion to stop the work at site at any given moment.
9.0 Responsibilities
9.1 Project Manager (PM):
a. Overall responsible for the safe execution of the works.
b. Plan the materials, plant and equipment required for this activity.
c. Obtain all relevant approvals for Local Authority Requirements.
d. Obtain required permits from Engineering Department.
e. Ensure that all work procedures are followed correctly to the satisfaction of the Client,
Consultant and Local Authorities.
f. Point of contact for co-ordinating with Local Authorities on behalf of ALGECO.
9.2 Project Engineer / Site Engineer / Foreman:
a. Responsible for the safe execution of the works at site
b. Supervision of personnel.
c. Compliance of the works to the approved drawings, Specifications, and to the
satisfaction of the Client / Consultant and Local Authority requirements.
a. Responsible for the execution, monitoring and supervision of the works.
b. Providing task related TBT (Toolbox Talk) to personnel.
c. Implementing and monitoring Quality and OHSE requirements.
d. Report to the Project Manager on a regular basis.
9.3 Surveyor:
a. Responsible for the setting out, marking co-ordinates and level prior to and during the
works in accordance with the approved drawings.
b. Report to the Project Manager on a regular basis.
9.4 QA/QC Engineer / Inspector
7|P a g e
SM28_MS_02.02
Reference No رقم المرجع
Project Management Office مكتب أدارة المشاريع
360 SM MS 001
REV. Date بيــــــان طــــــريقة العمــــــــل
00 07-04-2022 Work Method Statement
a. Responsible for the development of the QA/QC Plan and procedures for this activity.
b. Assist and advise the Project Manager to implement the QA/QC system and
procedures.
c. Ensure the requirements of the Specification are incorporated in the Method Statement.
d. Maintain all QA / QC documents and records specific to the works carried out, and
submit as required by the Consultant / Client.
e. Responsible to ensure that the developed quality management system and procedures
are implemented satisfactorily for this activity
f. Documents / records are maintained for this activity.
g. Report to the Project Manager on a regular basis.
9.5 Civil Engineer / Technical Engineer:
a. Responsible to rectify and modify shop drawings and submit to consultant for review
and approval.
b. Prepare materials sample and submittal to consultant for approval.
c. Assist Project Manager for any development and modification for the shop drawings
and submit RFI (Request for Information) if necessary, to consultant for review and
approval.
9.6 OHSE Manager:
a. Responsible for the development of the OHSE system including Plan, OHSE
Procedures, Task Risk Assessment and requirement of adequate PPE in order to
execute the activity safely.
b. Advise and assist the Project Manager for implementing the OHSE system.
c. Report to the Project Director on a regular basis.
9.7 OHSE Engineers / Officers:
a. Responsible for the development of the OHSE system including Plan, OHSE
Procedures, Task Risk Assessment and requirement of adequate PPE in order to
execute the activity safely.
b. Advise and assist the Project Manager for implementing the OHSE system.
a. Report to the Project Manager / Coordinator on a regular basis.
b. Duties and responsibilities include planning and scheduling the safety provisions of the
works at project sites with the Construction Team.
c. Work closely with the Project Manager to assist / advise OHSE measures at the
workplaces.
d. Inspecting and recording the site safety activities and advising the site personnel for
safe work at sites.
e. Inspecting the welfare facilities of the working crew at sites.
f. Inspecting the traffic management arrangements at sites.
8|P a g e
SM28_MS_02.02
Reference No رقم المرجع
Project Management Office مكتب أدارة المشاريع
360 SM MS 001
REV. Date بيــــــان طــــــريقة العمــــــــل
00 07-04-2022 Work Method Statement
g. OHSE Engineers / Officers will be reporting to the OHSE HOD on a regular basis.
SEE ANNEX –A
Appendices الملحقــــــــــات
1.Risk Assessments 1.تقييمــــــــــــــــــات المخاطـــــــــــــــــــــــــــــر
Hazard Identification Yes No Hazard Identification Yes No
Slip and Trips Coshh
Manual Handling Noise
Hand Tolls Work at Heights
Excavations Dust/Fumes
Machinery/Lifting Equipment Lighting
Fire 3rd party (Contractor)
Fall of Material Environmental
Electrical Other
Who Might Be Harmed?
Own Personnel Yes No Office Staff or Visitors Yes No
Other Contractors’ Yes No Members of the Public Yes No
First Aid Reportable Major Disablement Fatal
Potential Severity of Injury or Illness
1 2-5 6-20 21-100 10+
Number of workers exposed to hazard
Happens Happens Happens on Happens Certain to
Probability of injury or illness rarely each Year most jobs regularly happen
2. Drawings, BOQ and Specifications References 2. مراجع المواصفـات و جدول الكميات ومخططــات
No. Ref. to B.O.Q / Spec. Ref. QY. Unit Material Description
Specification Ref: PIPES
SPRECIFICATION PROVIDED IN UPVC ABOVE AND UNDERGROUND DRAINAGE PIPES &
1 - -
THE DRAWING (PGC-ASC-180016- FITTINGS
P2-C-00-P-0002)
No. Drawing Reference Drawing Title
PGC-ASC-180016-P2-C-A1-P-2001, PGC-
ASC-180016-P2-C-B1-P-2001, PGC-ASC-
180016-P2-C-B1-P-2002, PGC-ASC-180016-
P2-C-C1-P-2001, PGC-ASC-180016-P2-C-
1 ALL DRAINAGE LAYOUTS OF PLUMBING
C1-P-2002, PGC-ASC-180016-P2-C-C1-P-
2003, PGC-ASC-180016-P2-C-D1-P-2001,
PGC-ASC-180016-P2-C-D1-P-2002, PGC-
ASC-180016-P2-C-D1-P-2003, PGC-ASC-
9|P a g e
SM28_MS_02.02
Reference No رقم المرجع
Project Management Office مكتب أدارة المشاريع
360 SM MS 001
REV. Date بيــــــان طــــــريقة العمــــــــل
00 07-04-2022 Work Method Statement
180016-P2-C-D1-P-2004, PGC-ASC-180016-
P2-C-E1-P-2001, PGC-ASC-180016-P2-C-E1-
P-2002, PGC-ASC-180016-P2-C-F1-P-2001,
PGC-ASC-180016-P2-C-F1-P-2002, PGC-
ASC-180016-P2-C-G1-P-2001, PGC-ASC-
180016-P2-C-H1-P-2001, PGC-ASC-180016-
P2-C-H1-P-2002, PGC-ASC-180016-P2-C-J1-
P-2001, PGC-ASC-180016-P2-C-J1-P-2002
تشهد
The company certifies that all information above found to
الشركةبأنكاللمعلوماتالتيأصدرتتحتهذاالتقديمقدتمالتحققمنهاووجدتمطابقة
be in compliance with the Contract documents.
معوثائقالعقد.
Al Ain General Contracting Company L.L.C. الشركة
االسم االسم
Name Name
Resident Engineer Comments مالحظاتالمهندسالمقيم
فقطتعبىءإذاتماإلشارةعلىالمربعالمخصصأعالهبالشخصذاتالصلة:مالحظاتمديرالمشروع
Project Manager Comments: (to be filled ONLY if the escalation box above to the relevant person is Ticked)
Review Status (by Final Approver) )حالةالمراجعة (منخالآلخرموافقة
NO OBJECTION= A موافق
No Objection AS Noted = B موافقمعالمالحظات
REVISE & RESUBMIT = C يراجعويعادتقديمه
REJECTED = D مرفوض
Comments raised to PM = E مالحضات تم رفعها لمدير المشروع
Comments مالحظات
10 | P a g e
SM28_MS_02.02
Reference No رقم المرجع
Project Management Office مكتب أدارة المشاريع
360 SM MS 001
REV. Date بيــــــان طــــــريقة العمــــــــل
00 07-04-2022 Work Method Statement
11 | P a g e