Professional Documents
Culture Documents
Die Casting Procedure
Die Casting Procedure
Die Casting Procedure
DIE CASTING
(Control of Production and Service Provision)
Clause 8.5.1
ISO 9001: 2015
Head
Reviewed by Lt. Col(retd)Nasir Mehmood
(MT/DC)
Head
Lt. Col(retd)Nasir Mehmood
(MT/DC)
Approved by
Riaz Moazzam COO
Revision No.: 01
Doc. No. QP/DC/8.5.1-B
Date: 04/04/2024
Pakistan Machine Tool Factory, Karachi
2. Scope: -
This procedure concentrates mainly on Pressure Die Casting Process in the Die Casting
Department. Machining of the components in this department is covered under the quality
procedure Process Control Doc. No: QP/PPC/8.5.1.
3. Responsibility: -
3.1 Head of Production is responsible for compliance with the procedure to ensure that the
production is carried out as per details mentioned in the procedure and documents
mentioned therein.
3.2 Incharge Die Casting is responsible for maintaining & counter checking the process
parameters and meeting the quality requirements mentioned in the procedure and related
documents.
3.3 Incharge Quality Control is responsible for ensuring that the production is being carried out
under controlled process parameters as per Machine Setting Sheet (Annexure-9.1) & QC
Checklist (Annexure-9.3) meeting all the quality requirements.
3.4 Head Maintenance Department is responsible for maintaining the machine & equipment in
such an acceptable condition that the process parameters referred in this procedure,
especially those mentioned in the Machine Setting Sheet (Annexure-9.1) are controlled &
demonstrable within required limits.
4. Authority: -
Head of Manufacturing Division is authorized for the approval and any amendment in this
procedure.
5. Execution: -
5.1 General: -
The execution procedure has been divided into three steps in the following sequence:
Each of these has been divided & subdivided in the following sub clauses.
Page 1 of 6
5.2 INPUTS: -
5.2.1 Man Power: -
The manpower directly involved in production is employed on the basis of qualification,
training and experience. Minimum qualification for Die Casting Machine Operator is 8 th
class pass with training on DC machines at PMTF or outside experienced in this trade.
However, qualification requirement is relaxed in favor of skill, experienced & quality
consciousness.
5.2.2 Material: -
a) Mostly two types of Aluminum alloys, PMTF standard AS12U1 & AC-9 are used. Inspected
& okayed material ingots as per casting drawing (available in the department) are supplied
by production Control Department which are separately stacked in the designated store
area. The gates, runners, cover flows & rejected components are also re-melted with these
ingots with a ratio which does not exceed one part of scrap to two parts of the virgin
material.
b) INSERTS as per Inserts (available in the Department) duly inspected & okayed are
delivered by production Control Department which are separately stored in the containers
with identification tags.
c) lubricants for plungers etc. presently being used is:
TYBE TRENNEX (854G), Graphace-3700 & Tie Lubricant Flux B-200R.
d) Die Spray presently being used is:
TRENNEX 550 WL (BARREL).
e) Coverall (flux) is used to protect molten metal from oxidation by making a buffer between
it and the atmosphere. The slag formed should be removed from surface lest it is poured
with the molten resulting in defective casting.
f) CURCIBLE for Melting and Holding furnaces are procured in Silicon Carbide material as
per PMTF stock Nos. 8192 125 & 192 130.
g) Undercoat & primers plunger Tip (70mm) Fuse Coating.
Page 2 of 6
5.2.4 Methods/Documents: -
a) Finish part drawing is the basic document for component manufacturing. Rough part
drawing of casting is made on the basis of these finish drawings. If the component is
delivered without machining the casting drawing is the final document for product
acceptance. When machining is carried out, it is done according to manufacture
layout/Operation Instructions as specified in Quality Procedure Doc. QP/PPC/7-2.
b) Setting Sheet for Die Casting machines as per Annexure 9.1 is the main document for
setting the process parameters. This is prepared for every single component and contains all
the information related to component. Die, material, machine, furnace, machining settings,
die spray, lubricants etc.
c) Quality Control Checklist (Annexure 9.3) is the document pertaining to continuous
monitoring of the process parameters & important quality characters of the output. This
contains checks for metal temperature, surface finish, destructive porosity, cracks, damages,
inserts location, flash and biscuits etc. also the critical dimension are checked & recorded in
a separate Critical Dimensions list maintained for each type of component.
5.3 Die Casting Process: -
5.3.1 General: -
Pressure Die Casting is a processed in which molten metal (mostly Aluminum Alloys in
case of PMTF) is injected into a precisely dimensioned steel mould, within which pressure
is maintained until solidification has been completed. This pressure is applied hydraulically
by the moving portion of the machine against the stationary portion and is called the
locking pressure/force. This locking force, in tons, is the measure of the machine capacity,
and is used to select the machine required for a particular component. Other important
features of the process are the injection pressure & speeds, temperature of the molten
material, timings (specially the dwell time during which die remains closed under pressure)
cooling of the dies etc. ejection of the components use of die spray & lubricants.
5.3.2 Important Quality Characteristics: -
A good die cast component should be free from porosity, cracks, blisters, non-filling of the
component contours, and cold i.e. when the two metal streams fail to join/meet. Good
surface finish is also a requirement, especially for decorative components or those used
without painting etc. Although all these defects are important to be controlled, the porosity
comes out to be the single most important feature to be kept under control in case of Die
Cast components. The dimensional & other requirements mentioned in individual
component drawing are met apart from these general parameters.
Following are the general quality requirements:
1) For Auto Transmission Honda & Suzuki components, the strength is the main
parameter controlling the quality along with good surface finish. Strength is achieved by
minimizing the porosity.
2) For Gas Meter components porosity and cracks are the main quality parameters to be
checked. The porosity is controlled to a minimum and impregnation (Moguliding) is
carried out to ensure leakage free components (reference Surface Treatment procedure.
Page 3 of 6
p) Breaking of overflows, gates etc. is done with care do that the components are not
damaged. Mechanical using die & press is being introduced gradually to phase out
manual gate breaking where required.
5.3.4 Machine Setting Sheet: -
Process parameters as described in 5.3.3 are determined/calculated by Incharge Die Casting
for each component and tabulated in the Machine Setting Sheet (Annexure 9.1) of the
respective components Machine is set and all the parameters are counter
checked/monitored with the help of process Control Sheet (Annexure 9.2) before start of
operation. The Machine Setting Sheet is always available on the machine during production
of the component.
5.3.5 Quality Control Checklist: -
Quality Control checklist (Annexure 9.3) is used continuous monitoring of the process &
quality parameters with a predetermined frequency.
5.4 Quality of Output: -
a) At the time first use of a new die all dimension and characteristics/parameters are
checked as per Casting Drawing or Inspection Instruction of the component. If found OK in
all respects the component samples are submitted to the customer for inspection, functional
test and approval. Production is carried out after receiving the written approval from the
customer. The approved sample is kept at PMTF for reference of surface finish, porosity etc.
b) For repeated use of the same die, without replacement of any functional part of it, only
those dimensions are checked which are liable to be disturbed by in complete closing of die
dimensions & parameters is prepared in the light of previous experience and customer
complaints. This list is maintained as “Critical Dimension List”. These dimensions are
checked and recorded by Quality Assurance Inspectors in the QC Checklist (Annexure 9.3)
as a part of their continuous process monitoring activity.
c) Porosity is checked by cutting/breaking the component at least once a day, and
comparing it with the standard or the approved sample.
d) 100% visual inspection of the production lot is carried out for the defect mentioned in
5.3.2, Quality Parameters.
e) Dents, damages, unwanted residual edges of runners/gates and other defects, if any, are
removed by fitting/ filing, using emery paper. Surface finish is improved by using emery
paper if the requirements are higher than that achievable by the die/process.
f) Nonconforming products are decided as per procedure of Doc. No: QP/QA/8.7. Rejected
components are melted with the raw material as described in 5.2.2 (a) of this procedure.
Inserts of these melted components are scraped if these had been machined. Unmachined
inserts are reused if the hardness and geometrical parameters specially ovality, are found
acceptable.
Page 5 of 6
g) Gas meter components are sent for Impregnation/Moguliding for filing of micro-
porosity to avoid gas leakage during use (Ref. Surface Treatment Procedure Doc. No:
QP/ST/8.5.1-D.
h) Pressure testing of Gas Meter components is carried out for leakage with the help of the
Testing Equipment available in the department which allows compressed air to enter into
the cavity of the component which is clamped against a rubber sealing piece with the help
of mechanical clamps. The air pressure for testing is 20 psi and frequency of check is 50-75 pcs.
Per day. The components failing in the test are rejected straightway and corrective action is
taken accordingly.
6. Quality Records: -
6.1 Quality Checklist Form No: 2718 137.
6.2 Customer Approval/Acceptance Report.
6.3 Inspection Certificate Form No: 2718 106.
6.4 Final Inspection Certificate Form No: 2716 006.
7 Definition: -
7.1 Pressure Die Casting:
A Casting process in which molten is injected into a steel mould within which pressure is
maintained until solidification is complete.
8. Reference: -
8.1 ISO 9001:2015 Standards.
8.2 Quality Procedures Doc. No: QP/PPC/8.5.1, QP/ST/8.5.1-B.
8.3 Casting, Finish part & Insert drawings, O.Is for machined components.
8.4 Critical Dimension List.
8.5 Casting Inspection Check Sheet (Inspection Instruction).
8.6 List of Components Die Cast in PMTF.
8.7 Aluminum Die Casting Trouble-Shooting Guide.
9. Appendix: -
9.1 Machine Setting Sheet.
9.2 Process Control Checklist.
9.3 Quality Control Checklist.
9.4 Aluminum Die Casting Trouble-Shooting Guide.
Page 6 of 6
Document No.
SURVEY OF CHANGE
Signature
Edition Date Changes Page(s)
Prepared by Approved