NETWORK CRASHING

1. By Relaxing technical specifications


2. By employing extra resources

Prof. A. S. Thorbole Department of Civil Engineering 1


NETWORK CRASHING
1. Larson & Toubro Ltd is planning to execute a project.
Project Manager identified no. of activities involved in the
project also he has calculated normal and crash cost for
each of the activity. Project Manager wishes to complete
the project as early as possible with available resources.
Overhead cost of the project is Rs. 3000 per day.
Calculate optimum time and optimum cost within which
project can be completed.

Prof. A. S. Thorbole Department of Civil Engineering 2


NETWORK CRASHING
1. Normal Time Duration(Days) Cost(Rs.)
Activity

2. Crash Time (i-j)


Normal Crash Normal Crash

3. Normal Cost 1-2 6 3 7000 14500

4. Crash Cost 2-3 4 1 6000 9000

5. Direct Cost 2-4 5 3 8000 15000

6. Indirect Cost 3-4 5 3 5000 11000

7. Total Cost

Prof. A. S. Thorbole Department of Civil Engineering 3


NETWORK CRASHING
Activity Duration(Days) Cost(Rs.) Cost Slope
(i-j) Normal Crash Normal Crash

1-2 6 3 7000 14500 2500


2-3 4 1 6000 9000 1000
2-4 5 3 8000 15000 3500
3-4 5 3 5000 11000 3000

Prof. A. S. Thorbole Department of Civil Engineering 4


A B C
1 2 3 4
6(3) 4(1) 5(3)
E
5(3)

1st Stage Crashing


Crash activity 2-3 by 3 days
Direct Cost = 7000+6000+8000+5000 + 3X1000 = 29000
Indirect Cost = 12 X 3000 = 36000
Total Cost = 65000
A B C
1 2 3 4
6(3) 1(0) 5(3)
E
5(3)
Prof. A. S. Thorbole Department of Civil Engineering 5
A B C
1 2 3 4
6(3) 1(0) 5(3)
E
5(3)

2nd Stage Crashing


Crash activity 1-2 by 3 days
Direct Cost = 29000 + 3X2500 = 36500
Indirect Cost = 9 X 3000 = 27000
Total Cost = 63500
A B C
1 2 3 4
3(0) 1(0) 5(3)
E
5(3)
Prof. A. S. Thorbole Department of Civil Engineering 6
A B C
1 2 3 4
6(3) 1(0) 5(3)
E
5(3)

3rd Stage Crashing


Crash activity 3-4 & 2-4 simultaneously by 2 days
Direct Cost = 36500 + 2X6500 = 49500
Indirect Cost = 7 X 3000 = 21000
Total Cost = 70500
A B C
1 2 3 4
3(0) 1(0) 5(3)
E
5(3)
Prof. A. S. Thorbole Department of Civil Engineering 7
1st Stage Crashing
Crash activity 2-3 by 3 days
Direct Cost = 7000+6000+8000+5000 + 3X1000 = 29000
Indirect Cost = 12 X 3000 = 36000
Total Cost = 65000
2nd Stage Crashing
Crash activity 1-2 by 3 days Total 70500
Direct Cost = 29000 + 3X2500 = 36500 Cost 65000
Indirect Cost = 9 X 3000 = 27000
Total Cost = 63500
63500
3rdStage Crashing
Crash activity 3-4 & 2-4 simultaneously by 2 days
Direct Cost = 36500 + 2X6500 = 49500 Time
Indirect Cost = 7 X 3000 = 21000
Total Cost = 70500
Prof. A. S. Thorbole Department of Civil Engineering 8
NETWORK CRASHING
Activity Duration(Days) Cost(Rs.)
(i-j) Normal Crash Normal Crash
1-2 6 3 7000 14500
1-3 8 5 4000 8500
2-3 4 1 6000 9000
2-4 5 3 8000 15000
3-4 5 3 5000 11000
Prof. A. S. Thorbole Department of Civil Engineering 9
NETWORK CRASHING
Activity Duration(Days) Cost(Rs.) Cost Slope
(i-j) Normal Crash Normal Crash

1-2 6 3 7000 14500 2500


1-3 8 5 4000 8500 1500
2-3 4 1 6000 9000 1000
2-4 5 3 8000 15000 3500
3-4 5 3 5000 11000 3000

Prof. A. S. Thorbole Department of Civil Engineering 10


D
8(5)
A B C
1 2 3 4
6(3) 4(1) 5(3)
E
5(3)
1st Stage Crashing
Crash activity 2-3 by 2 days
Direct Cost = 7000+4000+6000+8000+5000 + 2X1000= 32000
Indirect Cost = 13 X 3000 = 39000
Total Cost = 71000 D
8(5)
A B C
1 2 3 4
6(3) 2(1) 5(3)
E
5(3)
Prof. A. S. Thorbole Department of Civil Engineering 11
D
8(5)
A B C
1 2 3 4
6(3) 2(1) 5(3)
E
5(3)
2nd Stage Crashing (1-2 & 1-3 =4000, 2-3 & 1-3=2500, 3-4 & 2-4=6500)
Crash activity 2-3 & 1-3 by 1 day
Direct Cost = 32000 + 1X2500= 34500
Indirect Cost = 12 X 3000 = 36000
Total Cost = 70500 D
7(5)
A B C
1 2 3 4
6(3) 1(0) 5(3)
E
5(3)
Prof. A. S. Thorbole Department of Civil Engineering 12
D
7(5)
A B C
1 2 3 4
6(3) 1(0) 5(3)
E
5(3)
3rd Stage Crashing (1-2 & 1-3 =4000, 3-4 & 2-4=6500)
Crash activity 1-2 & 1-3 by 2 day
Direct Cost = 34500 + 2X4000= 42500
Indirect Cost = 10 X 3000 = 30000
Total Cost = 72500 D
5(0)
A B C
1 2 3 4
4(3) 1(0) 5(3)
E
5(3)
Prof. A. S. Thorbole Department of Civil Engineering 13
1st Stage Crashing
Crash activity 2-3 by 2 days
Direct Cost = 7000+4000+6000+8000+5000 + 2X1000= 32000
Indirect Cost = 13 X 3000 = 39000
Total Cost = 71000
2nd Stage Crashing (1-2 & 1-3 =4000, 2-3 & 1-3=2500, 3-4 & 2-4=6500)
Crash activity 2-3 & 1-3 by 1 day
Direct Cost = 32000 + 1X2500= 34500
Indirect Cost = 12 X 3000 = 36000 Total 72500
Total Cost = 70500 Cost 71000
3rd Stage Crashing (1-2 & 1-3 =4000, 3-4 & 2-4=6500)
Crash activity 1-2 & 1-3 by 2 day 70500
Direct Cost = 34500 + 2X4000= 42500
Indirect Cost = 10 X 3000 = 30000 Time
Total Cost = 72500
Prof. A. S. Thorbole Department of Civil Engineering 14