NETWORK CRASHING 1. Larson & Toubro Ltd is planning to execute a project. Project Manager identified no. of activities involved in the project also he has calculated normal and crash cost for each of the activity. Project Manager wishes to complete the project as early as possible with available resources. Overhead cost of the project is Rs. 3000 per day. Calculate optimum time and optimum cost within which project can be completed.
Prof. A. S. Thorbole Department of Civil Engineering 2
NETWORK CRASHING 1. Normal Time Duration(Days) Cost(Rs.) Activity
2. Crash Time (i-j)
Normal Crash Normal Crash
3. Normal Cost 1-2 6 3 7000 14500
4. Crash Cost 2-3 4 1 6000 9000
5. Direct Cost 2-4 5 3 8000 15000
6. Indirect Cost 3-4 5 3 5000 11000
7. Total Cost
Prof. A. S. Thorbole Department of Civil Engineering 3
NETWORK CRASHING Activity Duration(Days) Cost(Rs.) Cost Slope (i-j) Normal Crash Normal Crash
Prof. A. S. Thorbole Department of Civil Engineering 4
A B C 1 2 3 4 6(3) 4(1) 5(3) E 5(3)
1st Stage Crashing
Crash activity 2-3 by 3 days Direct Cost = 7000+6000+8000+5000 + 3X1000 = 29000 Indirect Cost = 12 X 3000 = 36000 Total Cost = 65000 A B C 1 2 3 4 6(3) 1(0) 5(3) E 5(3) Prof. A. S. Thorbole Department of Civil Engineering 5 A B C 1 2 3 4 6(3) 1(0) 5(3) E 5(3)
2nd Stage Crashing
Crash activity 1-2 by 3 days Direct Cost = 29000 + 3X2500 = 36500 Indirect Cost = 9 X 3000 = 27000 Total Cost = 63500 A B C 1 2 3 4 3(0) 1(0) 5(3) E 5(3) Prof. A. S. Thorbole Department of Civil Engineering 6 A B C 1 2 3 4 6(3) 1(0) 5(3) E 5(3)
3rd Stage Crashing
Crash activity 3-4 & 2-4 simultaneously by 2 days Direct Cost = 36500 + 2X6500 = 49500 Indirect Cost = 7 X 3000 = 21000 Total Cost = 70500 A B C 1 2 3 4 3(0) 1(0) 5(3) E 5(3) Prof. A. S. Thorbole Department of Civil Engineering 7 1st Stage Crashing Crash activity 2-3 by 3 days Direct Cost = 7000+6000+8000+5000 + 3X1000 = 29000 Indirect Cost = 12 X 3000 = 36000 Total Cost = 65000 2nd Stage Crashing Crash activity 1-2 by 3 days Total 70500 Direct Cost = 29000 + 3X2500 = 36500 Cost 65000 Indirect Cost = 9 X 3000 = 27000 Total Cost = 63500 63500 3rdStage Crashing Crash activity 3-4 & 2-4 simultaneously by 2 days Direct Cost = 36500 + 2X6500 = 49500 Time Indirect Cost = 7 X 3000 = 21000 Total Cost = 70500 Prof. A. S. Thorbole Department of Civil Engineering 8 NETWORK CRASHING Activity Duration(Days) Cost(Rs.) (i-j) Normal Crash Normal Crash 1-2 6 3 7000 14500 1-3 8 5 4000 8500 2-3 4 1 6000 9000 2-4 5 3 8000 15000 3-4 5 3 5000 11000 Prof. A. S. Thorbole Department of Civil Engineering 9 NETWORK CRASHING Activity Duration(Days) Cost(Rs.) Cost Slope (i-j) Normal Crash Normal Crash
Prof. A. S. Thorbole Department of Civil Engineering 10
D 8(5) A B C 1 2 3 4 6(3) 4(1) 5(3) E 5(3) 1st Stage Crashing Crash activity 2-3 by 2 days Direct Cost = 7000+4000+6000+8000+5000 + 2X1000= 32000 Indirect Cost = 13 X 3000 = 39000 Total Cost = 71000 D 8(5) A B C 1 2 3 4 6(3) 2(1) 5(3) E 5(3) Prof. A. S. Thorbole Department of Civil Engineering 11 D 8(5) A B C 1 2 3 4 6(3) 2(1) 5(3) E 5(3) 2nd Stage Crashing (1-2 & 1-3 =4000, 2-3 & 1-3=2500, 3-4 & 2-4=6500) Crash activity 2-3 & 1-3 by 1 day Direct Cost = 32000 + 1X2500= 34500 Indirect Cost = 12 X 3000 = 36000 Total Cost = 70500 D 7(5) A B C 1 2 3 4 6(3) 1(0) 5(3) E 5(3) Prof. A. S. Thorbole Department of Civil Engineering 12 D 7(5) A B C 1 2 3 4 6(3) 1(0) 5(3) E 5(3) 3rd Stage Crashing (1-2 & 1-3 =4000, 3-4 & 2-4=6500) Crash activity 1-2 & 1-3 by 2 day Direct Cost = 34500 + 2X4000= 42500 Indirect Cost = 10 X 3000 = 30000 Total Cost = 72500 D 5(0) A B C 1 2 3 4 4(3) 1(0) 5(3) E 5(3) Prof. A. S. Thorbole Department of Civil Engineering 13 1st Stage Crashing Crash activity 2-3 by 2 days Direct Cost = 7000+4000+6000+8000+5000 + 2X1000= 32000 Indirect Cost = 13 X 3000 = 39000 Total Cost = 71000 2nd Stage Crashing (1-2 & 1-3 =4000, 2-3 & 1-3=2500, 3-4 & 2-4=6500) Crash activity 2-3 & 1-3 by 1 day Direct Cost = 32000 + 1X2500= 34500 Indirect Cost = 12 X 3000 = 36000 Total 72500 Total Cost = 70500 Cost 71000 3rd Stage Crashing (1-2 & 1-3 =4000, 3-4 & 2-4=6500) Crash activity 1-2 & 1-3 by 2 day 70500 Direct Cost = 34500 + 2X4000= 42500 Indirect Cost = 10 X 3000 = 30000 Time Total Cost = 72500 Prof. A. S. Thorbole Department of Civil Engineering 14