PRODUCTIVITY RATES FOR ALL PROJECT WORKS:
(Rev 0, May 2000)
Page 3 of 7
PRODUCTIVITY RATES FOR ALL PROJECT WORKS:
(Rev 0, May 2000)
Item No. CREW SIZE Hourly Production
Production Rate Per 10 hrs.
Per Unit
MCR CERAMIC WORKS
MCR 13 Ceramic skirting by glue 1 MASON, 1 HELPER 2,5 M 25 METRE
MCR 14 Ceramic skirting by glue to halls, corridors 1 MASON, 1 HELPER 3M 30 METRE
MTW TILING WORKS
MTW 01 Mosiac / Terrazo tiles to roofs 1 MASON, 1 HELPER 1,6 16 SM
MTW 02 Mosiac / Terrazo tiles to floors 1 MASON, 1 HELPER 1,4 14 SM
MTW 03 Mosiac skirting to halls 1 MASON, 1 HELPER 2,5 25 METRE
MTW 04 Mosiac skirting flush / recessed 1 MASON, 1 HELPER 1,4 14 METRE
MTW 05 Grouting / sealing to roof / floor tiles 1 HELPER 2,5 25 METRE
MKP KERBING / BLOCK PAVING WORKS
MKP00 P.C.C. Curve kerb base (to curves) 1 MASON, 1 HELPER 2,5 25 METRE
MKP01 PCC to kerb base (Straight line) 1 MASON, 1 HELPER 3,0 30 METRE
MKP02 Haunching to kerb base (Dumpes) 1 MASON, 1 HELPER 4 40 METRE
MKP03 kerbstonse (Without PCC) 1 MASON, 1 HELPER 1,5 15 METRE
MKP04 Interlock paving on pre prepared sub - base 1 MASON, 1 HELPER 2 SM
MKP05 Screed works including preparation 1 MASON, 1 HELPER 1,5 15 SM
MKP06 Haunching ot Kerb Base (Mixing Truck) 1 MASON, 1 HELPER 10 M 100M
DRW MANHOLE/ DRAINAGE CONSTRUCTION
DRW 01 Excavation for drains / manholes 1 HELPER 5 CM
DRW 02 Backfill to drains / manholes 1 HELPER 10 CM
DRW 03 Blockwork to manholes 1 MASON, 1 HELPER 2 NOS
DRW 04 Plaster to manholes 1 MASON, 1 HELPER 2 NOS
DRW 05 Benching to manholes 1 MASON, 1 HELPER 4 NOS
DRW 06 Fix covers to manholes 1 MASON, 1 HELPER 2 NOS
DRW 07 Fix gulley traps 1 MASON, 1 HELPER 1 NO
DRW 08 Laying of P.V.C. sleeves 4" - 12" 4 HELPER 24M 240M
MLW MISCELLANEOUS LABOUR WORKS
MLW01 Bitumen paint to concrete blockwork surfaces 1 HELPER 4 40 SM
MLW02 Bitumin painting Bases / piles 1 HELPER 7.00 70
MLW03 Hacking of concrete surfaces 1 HELPER 5 50 SM
MLW04 fixing of flexcell sheets 1 HELPER 6 SM
MLW05 pile cutting/dressing 1 HELPER 1 NO
MLW06 pile cutting/dressing (small diameter) 1 HELPER 2 NOS
MLW07 Vertical sealant (12 mm) 1 HELPER 2,5 25 METRE
MLW08 Horizontal sealant (12 mm) 1 HELPER 5 50 EMTRE
MLW09 Roof preparation for lw concrete 1 MASON, 1 HELPER 5 50 SM
MLW10 Angle fillet fixing 1 MASON, 1 HELPER 4 40 EMTE
MLW11 Hourdi block shifting and fixing to slab 2 HELPER 20 200 NOS
MLW12 Polythene sheet fixing 1 HELPER 3m 30
MLW13 Shaping of Soil Blinding 1 MASON + 1 HELPER 1M 10M
MLW14 Protection Board installation 1 CARPENTER + 1 HELPER 8M2 80M2
MCW MISCELLANEOUS CARPENTARY WORKS
MCW 01 A/C subframe manufacture / fixing 1 CARPENTER 5 NOS
MCW 02 Door subframe manufacture / fixing 1 CARPENTER 4 NOS
MCW 03 Water bar fixing 1 CARPENTER 2M 20 METRE
Page 4 0f 7
PRODUCTIVITY RATES FOR ALL PROJECT WORKS:
(Rev 0, May 2000)
Item No. CREW SIZE Hourly Production
Production Rate Per 10 hrs.
Per Unit
CPW CONCRETE PLACEMENT WORKS
CPW01 Concrete to pile caps by pump 6 MASONS, 18 HELPERS, 1 CARPENTER 180 CM
Standard rate 1 man 1 hr. 10m3
CPW02 Concrete to PCC blinding (100 mm thick) 1 MASON, 10 HELPERS 27 CM
CPW03 Concrete to slabs/beams, by pump 6 MASONS, 18 HELPERS, 1 CARPENTER 180 CM
CPW04 Concrete to slabs / beams by crane 1 MASON, 6 HELPERS, 0.5 OPERATOR 8,10 27 CM
CPW05 Concrete to walls / columns, by pump 4 MASONS, 16 HELPERS, 2 CARPENTERS 1.2 81 CM
CPW06 Concrete by site mix 1 MASON, 12 HELPERS , 0.5 CARPENTER 1.6 9 CM
CPW07 Concrete Columns 8 HELPERS 1.40 10
CPW08 Concrete suspended slab (pump) 3 MASONS + 6 HELPERS 1.80 150
CPW09 Concrete parapets/staircases 8 HELPERS 1.00 7
CPW10 Blinding concrete 50 mm (readymix) 1 MASON + 4 HELPER 8,0 80
CPW11 Blinding concrete 50 mm (sitemix) 1 MASON + 8 HELPER 1.00 10
CPW12 Concrete footings & pile caps 1 MASON + 4 HELPER 12.00 120
CPW13 Concrete tiebeams, ground beams 1 MASON + 5 HELPER 6.00 60
CPW14 Concrete column necks 8 HELPER 1.50 15
CPW15 Concrete Ground slab 3 MASONS + 6 HELPER 1,5 15
CPW16 Concrete to precast slabs, beams 2 MASONS + 1 HELPER 3m3 30 M3
GLW GENERAL LABOUR WORKS
GLW01 Unloading reinforcement ((Flat Bed Truck) 4 HELPERS 2 Nos
GLW02 Loading reinforcement to slab (With Crane) 4 HELPERS (Flat Bed Truck loads) 40 Nos. 2 Nos
GLW03 Loading blockwork to site (with Wheel Burrow) 1 HELPER 400 Nos.
GLW04 Loading mortar to site location
GLW05 Mixing mortar for distribution 0, 3 L mixer 4 HELPER 6M3
GLW06 Site mixing of ready mix for distribution Hand mix 3M3
GLW07 Loading ready mix to site location
NTRA NON TARGET RELATED ACTIVITES
NTRA01 Stacking of formwork 2 HELPERS
NTRA02 Curing of Substructure works 2 HELPERS
NTRA03 Curing of beams / slabs Hessiant Water 2 HELPERS
NTRA04 Curing of columns (Hessiant Water) 1 MASON + 2 HELPERS 1.6 (L.M) 36 M
NTRA05 Builders work make good chases 1.2 (L.M)
NTRA06 Site cleaning 1 HELPER 25 250 M2
NTRA07 Repairs to finished works 1
Page 5 of 7
PRODUCTIVITY RATES FOR ALL PROJECT WORKS:
(Rev 0, May 2000)
Page 6 of 7
PRODUCTIVITY RATES FOR ALL PROJECT WORKS:
(Rev 0, May 2000)
RF REINFORCEMENT
RF 01 Fix Rebar to footings & tie beams 1 STEEL FIXER 25
RF 02 Fix Rebar to walls, columns, beams, solid slabs 1 STEEL FIXER 20
RF 03 Fix rebar to ribs of hourdi slab 1 STEEL FIXER 18
RF 04 Fix rebar to mesh reinforcement 1 STEEL FIXER 15
RF 05 Fix rebar to hidden beams 1 STEEL FIXER 20
EXCAVATION
EX 1 Manual Excavation 1 HELPER
EX 2 Backfill + levelling 1HELPER
EX 3 Shaping of sloped earth for blinding for bases including compaction 1 MASON + 2 HELPER
PRODUCTIVITY RATES
(Rev 0, May 2000)
Notes:
1. 1 Day = 10 hrs.
2. Gang Size: