SUMMARY;

004/PO-WKJ/PAPA/XI/2023 dated 30/11/2023.


Items summary : 2 RTV-1159 + 2 ABT-1103/N + Antennas and Light. Protections
Will be shipped today

Order: 014/PO-WKJ/XII/2023 dated 08/12/2023.


Items summary : 6 RTV-1159 + 3 ABT-1103/N + Antennas and Light. Protections
Can be shipped by next week (week 16)

Order: 003/PO-VISI/III/2024 dated 05/02/2024.


Items summary : 5 MF/HF + 5 RTV-1077/E + 5 EMUS
Can be shipped around 30th of April (week 18)

Order: 004/PO-VISI/IV/2024 dated 01/04/2024.


Items summary : 2 MF/HF + 2 RTV-1077/E + 2 EMUS
Can be shipped mid June (week 24)

Just an amendement.
For Order: 003/PO-VISI/III/2024 dated 05/02/2024.
Items summary : 5 MF/HF + 5 RTV-1077/E + 5 EMUS
This has been amended last week adding one unit to previous order 001/PO-WKJ/II/2024 dated 05/02/2024.
Initial order was for: 4 MF/HF + 4 RTV-1077/E + 4 EMUS.
What we can deliver by end of april is 4 MF/HF + 4 RTV-1077/E + 4 EMUS.
Additional unit added in the last order, I will update you, because it has been additional and production not ready.
05/02/2024.

duction not ready.


Purchased Order Elman Estimate Date
PO No. Status
Year Release Date Date
004/PO-WKJ/PAPA/XI/2023 CLOSED 2023 30/11/2023 4/10/2024
014/PO-WKJ/XII/2023 CLOSED 2023 8/12/2023 4/17/2024
003/PO-VISI/III/2024 OPEN 2024 5/2/2024 4/30/2024
004/PO-VISI/IV/2024 OPEN 2024 01/04/2024 June
Later Update
006PO-WKJIV2024 OPEN 2024 15/04/2024
Elman Estimate Date RTV ABT TPO VHF Splitter Software

Week RTV-1159 1077/E 1103/N 1164 MF/HF EMUS Pelagus


2 2 1
W16 6 3
W18 4 4 4
W24 2 2 2
1 1 1
3 1 2 4 1
Software
Console
With ENC

1 Elman Palembang