BI-010-93103

THREE WEEKS LOOK AHEAD PLAN - EXTERNAL WORKS


ALMEER TECHNICAL SERVICES CO.
Septemeber2023
SL # Activity Start Date Finish Date Remarks
01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30
PSS FOUNDATION BACKFILLING 3‐Sep‐2023 3‐Sep‐2023
1 Backfilling for PSS foundation L05-PSS370 3-Sep-2023 3-Sep-2023
PSS FOUNDATION COMPACTION & FDT 4‐Sep‐2023 5‐Sep‐2023
1 Compaction & FDT for L05-PSS370 4-Sep-2023 5-Sep-2023
2 Compaction & FDT for L07-PSS371 4-Sep-2023 5-Sep-2023
3 Compaction & FDT for L07-PSS345 4-Sep-2023 5-Sep-2023
4 Compaction & FDT for L07-PSS348 4-Sep-2023 5-Sep-2023
PSS FOUNDATION INSTALLATION 6‐Sep‐2023 6‐Sep‐2023
1 PSS foundation installation for L05-PSS370 6-Sep-2023 6-Sep-2023
2 PSS foundation installation for L07-PSS371 6-Sep-2023 6-Sep-2023
3 PSS foundation installation for L07-PSS345 6-Sep-2023 6-Sep-2023
4 PSS foundation installation for L07-PSS348 6-Sep-2023 6-Sep-2023
PSS INSTALLATION 2‐Sep‐2023 4‐Sep‐2023
1 Installation of L01-PSS359 2-Sep-2023 2-Sep-2023
2 Installation of L01-PSS360 2-Sep-2023 2-Sep-2023
3 Installation of L01-PSS361 2-Sep-2023 2-Sep-2023
4 Installation of L02-PSS345 3-Sep-2023 3-Sep-2023
5 Installation of L02-PSS348 3-Sep-2023 3-Sep-2023
6 Installation of L02-PSS352 3-Sep-2023 3-Sep-2023
7 Installation of L02-PSS362 4-Sep-2023 4-Sep-2023
8 Installation of L02-PSS366 4-Sep-2023 4-Sep-2023
9 Installation of L07-PSS342 4-Sep-2023 4-Sep-2023
PSS GROUNDING INSTALLATION 3‐Sep‐2023 10‐Sep‐2023
1 Installation of grounding cable for L01-PSS359 3-Sep-2023 7-Sep-2023
2 Installation of grounding cable for L01-PSS360 3-Sep-2023 7-Sep-2023
3 Installation of grounding cable for L01-PSS361 3-Sep-2023 7-Sep-2023
4 Installation of grounding cable for L02-PSS345 4-Sep-2023 9-Sep-2023
5 Installation of grounding cable for L02-PSS348 4-Sep-2023 9-Sep-2023
6 Installation of grounding cable for L02-PSS352 4-Sep-2023 9-Sep-2023
7 Installation of grounding cable for L02-PSS362 5-Sep-2023 10-Sep-2023
8 Installation of grounding cable for L02-PSS366 5-Sep-2023 10-Sep-2023
9 Installation of grounding cable for L07-PSS342 5-Sep-2023 10-Sep-2023
PSS GROUNDING TESTING 8‐Sep‐2023 16‐Sep‐2023
1 Installation of grounding cable for L01-PSS359 8-Sep-2023 12-Sep-2023
2 Installation of grounding cable for L01-PSS360 8-Sep-2023 12-Sep-2023
3 Installation of grounding cable for L01-PSS361 8-Sep-2023 12-Sep-2023
4 Installation of grounding cable for L02-PSS345 10-Sep-2023 15-Sep-2023

1/2
BI-010-93103
THREE WEEKS LOOK AHEAD PLAN - EXTERNAL WORKS
ALMEER TECHNICAL SERVICES CO.
Septemeber2023
SL # Activity Start Date Finish Date Remarks
01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30
5 Installation of grounding cable for L02-PSS348 10-Sep-2023 15-Sep-2023
6 Installation of grounding cable for L02-PSS352 10-Sep-2023 15-Sep-2023
7 Installation of grounding cable for L02-PSS362 11-Sep-2023 16-Sep-2023
8 Installation of grounding cable for L02-PSS366 11-Sep-2023 16-Sep-2023
9 Installation of grounding cable for L07-PSS342 11-Sep-2023 16-Sep-2023
PSS TESTING & PRE‐COMMISSIONING 17‐Sep‐2023 6‐Oct‐2023
1 Testing & Pre-commissioning of for L01-PSS359 17-Sep-2023 19-Sep-2023
2 Testing & Pre-commissioning of for L01-PSS360 18-Sep-2023 20-Sep-2023
3 Testing & Pre-commissioning of for L01-PSS36 19-Sep-2023 21-Sep-2023
4 Testing & Pre-commissioning of for L02-PSS345 24-Sep-2023 26-Sep-2023
5 Testing & Pre-commissioning of for L02-PSS348 25-Sep-2023 27-Sep-2023
6 Testing & Pre-commissioning of for L02-PSS352 26-Sep-2023 28-Sep-2023
7 Testing & Pre-commissioning of for L02-PSS362 2-Oct-2023 4-Oct-2023
8 Testing & Pre-commissioning of for L02-PSS366 3-Oct-2023 5-Oct-2023
9 Testing & Pre-commissioning of for L07-PSS342 4-Oct-2023 6-Oct-2023