Daily Report: General Rigging Down

You might also like

Download as xls, pdf, or txt
Download as xls, pdf, or txt
You are on page 1of 2

DAILY REPORT

Report No 5
Date: 25-Oct-22
Rig Name B1 Well Name Type Objective: RIG REFURBISHING Company

WELL No Days : 1 Days Since Last Injury:

Present Operation: GENERAL RIGGING DOWN


Next Operation:

Proposed TD FT R.O.P FT Depth FT Total Footge FT Rig Move From: Move To:

Rotary RPM Flow Rate GPM Move Distance: Time:

BHA:

Pump No. 1: SPM Liner Size: SPM Pressure: T/Pressure Toolpusher


Mud SPM Liner Size:
Pump No. 2: SPM Pressure: SCR Company Man
Pumps
Pump No. 23 SPM Liner Size: SPM Pressure:

Hole Size Casing Size Casing Shoe Mud Weight

BOP A-Date Last P/T: B - PRESSURE C -Date Last F/T:

TON MILE A-SINCE LAST CUT B-Length of Rope Remaining: Safety Meeting:

REPAIRS A-Last 24 Hrs B-Month: TOTAL PERSONNELS 7 SET CARD TRIC CARD

From To OPERATION
0600 DISCONNECT POWER CABLE OF DROWWRKS AND SECURE
RIG DOWN TRIP TANK
REMOVE ALL HANDRAILS OF RIG FLOOR
REMOVE AIR LINE ON RIG FLOOR
1800 CONT PREPAIR PIPE BOX FOR RIG MOVE

NEED ONE LOAD DIESEL (GENERATOR SHUT DOWN DUE NO DIESEL)


NEED MECH TO FIX WATER LEAK ON FORKLIFT

Diesel Used 1731 Diesel Balance -


Water Used 25490 Water Balance
Field Break: Received: Requirements:
PERSONNEL IN RIG PERSONNEL IN CAMP 7 OPERATOR OTHERS

No. of Vehicles: Condition of Vehicles:

Bit No.: Size: Mfr.: Type: WOB: RPM: Grading:

140 Wt.: 0 90 Wt.: 0 50/20 Wt.: 0 46 Wt.: LTR 40 Wt.: LTR 37 Wt.: 0 10 Wt.: 0

Oxygen: Full Empty Acetylene: Full 0 Empty Nitrogen: Full 0 Empty 0