MALL-SOF Weekly Dashboard Report by RPM
MALL-SOF Weekly Dashboard Report by RPM
MALL-SOF Weekly Dashboard Report by RPM
Electrical Services Incl; Lightings, ELV and Telco Services 12-Sep-22 21-May-23 Awarded to Dexon Electrical Engineering Sdn. Bhd. Awarded on 02-Jun 23 Section 4A and 4B Podium Works :
Fire Protection and Alarm Services 26-Aug-22 9-Jun-23 Awarded to Globe Engineering Sdn. Bhd. Awarded on 05-July 23 i) Section 4A: Casted 4th slab for L2 at Z4a. Completed rebar work for L3 slab in Zone 2B and started slab formwork for L3 in Zone 1a.
ACMV & BAS services 18-Oct-22 16-Jun-23 Awarded to Megatara Sdn. Bhd. Awarded on 05-July 23 ii) Section 4B : To cast 3rd slab in L1. Started scaffoding works for slab formwork for L2 in Zone 5.
LPG Services 26-Oct-22 30-Apr-23 Awarded to Kejuruteraan Jayagas Sdn. Bhd. Awarded on 13-April 23 iii) Section 4AB : ISSB plans to cast ramp slab from LG2 to Ground floor by 07 Aug '23 and it is delayed for 28 days.
Security System 4-Nov-22 26-May-23 To be awarded by end July '23 Pending Award Consultant Matters
Aluminum & Glazing Works 4-Nov-22 9-Jun-23 To be awarded by end Aug '23 Pending Award i) SAA replied to ISSB's inquiry on non fire rated door discrepancies at B5 to B1 in Sections 1 and 4 on 04 Aug '23.
Ironmongeries for normal door 21-Jul-23 N/A NLP is preparing the BQ & tender document Pending tender calling ii) SAA have issued GA plans for SOFs to ISSB on 03 Aug '23.
BMU 21-Jul-22 15-Oct-23 Pending KLMSB to approve tenderers list. Pending tender calling iii) ISSB has re-confirmed that the fire rated doors for B5 to B1 in Sections 1 and 4 to be delivered to site by 09 Aug '23.
3 L5M - L8 1-Aug-23 31-Mar-25 Related to Zone 2 6A 1 INFRA 1-Aug-23 30-Jun-24 Pending Syabas/IWK Approval ii) ISSB has committed to remove their current illegal worker quarters located at B3 in Section 4 by end of Jun '23 to Mid Aug '23.
In progress. To start in door frame
1 B5 - L2 15-Oct-22 30-Jun-24 15.14%
installation works by early Aug '23.
-0 Days 6B 1 INFRA 1-Oct-23 30-Jun-24 Pending Syabas/IWK Approval Consultant Matters
4A 2 L3 - L5 3-Jul-23 31-Dec-24 Related to Zone 1 7 1 JD3 RAMP 1-Jun-23 30-Jun-24 8.04% Pending TMP Approval - 9 Days i) PME is to issue an instruction to ISSB/Mitsubishi for an additional escalator at Cinema area at Tower D.
Pending handing over by Tunnel
3 L5M - L6 1-Aug-23 31-Mar-25 Related to Zone 2 8 1 TUNNEL TBC 30-Jun-24
contractor.
ii) SAA will issue instruction to ISSB to defer the escalators' delivery and installation from B2-LG2 in relation to MRT linkage.
In progress, added barbenders to
1 B5 - L2 15-Oct-22 30-Jun-24 8.67%
mitigate delays
- 0 Days 9 1 LINKBRIDGE 1-Sep-23 30-Jun-24 KLM to advise. iii) GPS to issue construction plans by 26 Jul '23 11 Aug 23 for link bridge column pier pilecap located within the site boundary.
4B 2 L3 - L5 1-Jun-23 31-Dec-24 Related to Zone 1 10 3 SOF L7 - 25 15-Jan-24 15-Sep-25 iv) PME informed that TNB had determined the power source to be from Persiaran Dutamas to Jalan Kelapa Hijau which is circa 2.5 km.TNB will issue an official letter by end July '23 11 Aug '23.
BOMBA
3 L5M - L6 1-Aug-23 31-Mar-25 Related to Zone 2 11 1 15-Dec-23 30-Jun-24
ACCESS GF
2 KLMSB's request for changing 4 hours insulated fire rated roller shutters to fire rated wall in Basement floors. SAA is to conduct the presentation to KLMSB before deciding to move in which direction. Live
AEON already called a tender for ID Consultants Package and shared the tender
KLMSB has determined the retail mall glass railing design as per Option 3. SAA will send the detail to AEON for their
1 Aeon Design scope. In Progress outcome with KLMSB for their review. KLMSB and AEON to discuss further on Low Risk 2 7/Aug/2023 KLMSB In Progress
info.
the fees proposal.
Due to pending ADO approval, ISSB propsoed the material used for sewer
SAA will provide an amendment option for fire compartmentation in retail mall by 09 Aug '23, as requested by AEON.
2 Pending Syabas/IWK approval from authorities. In Progress inspection man-hole within the site boundary to be RC against bricks as stated Low Risk 3 11/Jul/2023 AEON In Progress
Now is pending AEON's comments/acceptance.
in the PME construction plan.
3 Pending TMP approval for JD3 ramp from DBKL In Progress ISSB reported that DBKL has approvd their TMP with conditions on 02 Aug '23. -
Project Component Fasa 1B
MALL & SOF (KLMidTown) 1) 1 Blok 7 Tingkat Podium Ruang Niaga
Weekly Programme Dashboard Fasa 1C
2) 2 Blok Menara Pejabat (B&C) 20 Tingkat (4 Unit)
Fasa 2A
3) 8 Tingkat Podium dan 4 Tingkat Separa Besmen
Location: Lot 81623, Jalan Dutamas 2, Mukim Batu, Daerah Kuala Lumpur.
Reporting Period: 29-July-2023 to 04-August-2023
Construction Manager: Tan Ooi Guan Report Date: 7/Aug/2023
Progressing L2 columns/walls in Zone 3 - Section 4A Progressing L2 slab formwork - Section 4B To cast core wall in L1 at Zone 6 - Section 4B
Progressing last slab in L2 - Section 4A Progressing L1 slab formwork in Zone 8 - Section 4B Progressing L2 slab formwork in Zone 5 - Section 4B
Workforce
Man Power Previous Pax Current Pax Remark
Carpenters 47 48
Mivan 0 0
Barbender 36 40
Concretor 6 6
Skim Coater 10 5
General Worker 17 17
8 8
Brick Installer