Professional Documents
Culture Documents
Estimates - DPWH Const of MP City Center at CIty Hall Complex Binatagan
Estimates - DPWH Const of MP City Center at CIty Hall Complex Binatagan
Name of Project:24F00343 Construction of Circumferential Road Network (Training Ground), 9th Infantry Spear Division, PA, Camp Elias Angeles, San Jose
Pili, Camarines Sur, Phase II, Pili, Camarines Sur (3rd Legislative District)
Location:Pili, Camarines Sur (3rd Legislative District)
Part I FACILITIES FOR THE ENGINEER
a.1.1 (3) Construction of Field Office for the Engineer
1 LOT Lump Sum 30,000.00 /month 5.67 mos 170,100.00
170,100.00
LABOR
1.00 man Foreman 600.00 /day for 3.00 days 1,800.00
1.00 men Skilled Laborer 500.00 /day for 3.00 days 1,500.00
2.00 men Common Laborer 350.00 /day for 3.00 days 2,100.00
Cost of Labor 5,400.00
LABOR
1.00 man Foreman 600.00 /day for 1.00 days 600.00
1.00 men Skilled Laborer 500.00 /day for 1.00 days 500.00
1.00 men Common Laborer 350.00 /day for 1.00 days 350.00
Cost of Labor 1,450.00
B.9 MOBILIZATION/DEMOBILIZATION
1 LOT
LABOR
1.00 man Foreman 600.00 /day for 10.00 days 6,000.00
1.00 men Skilled Laborer 500.00 /day for 10.00 days 5,000.00
5.00 men Common Laborer 350.00 /day for 10.00 days 17,500.00
Cost of Labor 28,500.00
LABOR
1.00 man Foreman 600.00 /day for 15.00 days 9,000.00
- men Skilled Laborer 500.00 /day for 15.00 days -
10.00 men Common Laborer 350.00 /day for 15.00 days 52,500.00
Cost of Labor 61,500.00
EQUIPMENT
1.00 unit Backhoe 12,500.00 /day for 15.00 days 187,500.00
1.00 unit DumpTruck 8,500.00 /day for 15.00 days 127,500.00
Cost of Equipment 315,000.00
LABOR
1.00 man Foreman 600.00 /day for 25.00 days 15,000.00
- men Skilled Laborer 500.00 /day for 25.00 days -
3.00 men Common Laborer 350.00 /day for 25.00 days 26,250.00
Cost of Labor 41,250.00
EQUIPMENT
1.00 UNIT Plate Compactor 12,500.00 /day for 25.00 days 312,500.00
1.00 UNIT Backhoe 8,500.00 /day for 25.00 days 212,500.00
Cost of Equipment 525,000.00
LABOR
1.00 man Foreman 600.00 /day for 20.00 days 12,000.00
- men Skilled Laborer 500.00 /day for 20.00 days -
3.00 men Common Laborer 350.00 /day for 20.00 days 21,000.00
Cost of Labor 33,000.00
EQUIPMENT
1.00 UNIT Plate Compactor 12,500.00 /day for 20.00 days 250,000.00
1.00 UNIT Backhoe 8,500.00 /day for 20.00 days 170,000.00
Cost of Equipment 420,000.00
A MATERIALS
115.00 cu.m Aggregate Sub Base Course 2,000.00 /cu.m 230,000.00
. w/ 15% shrinkage Cost of Materials P 230,000.00
B. LABOR
1.00 man Foreman 75.00 /hr for 40.00 hr 3,000.00
- men Skilled Laborer 62.50 /hr for 40.00 hr -
2.00 men Common Laborer 43.75 /hr for 40.00 hr 3,500.00
Cost of Labor 6,500.00
C EQUIPMENTS
1.00 unit Motorized Road Grader 2,173.00 /hour for 40.00 hours 86,920.00
Cost of Equipment P 86,920.00
A MATERIALS
1,063.00 bags Cement 360.00 /pc 382,680.00
56.00 cu.m Sand 2,500.00 /kg 140,000.00
113.00 cu.m Gravel 2,700.00 /cu.m 305,100.00
700.00 bd-ft Coco Lumber 25.00 /lit 17,500.00
30.00 kgs Asstd CWN 95.00 /pc 2,850.00
Cost of Materials 848,130.00
B LABOR
1.00 man Foreman 75.00 /hr for 120.00 hr 9,000.00
4.00 men Skilled Laborer 62.50 /hr for 120.00 hr 30,000.00
12.00 men Common Laborer 43.75 /hr for 120.00 hr 63,000.00
Cost of Labor 102,000.00
C EQUIPMENTS
1.00 unit One Bagger Concrete Mixer 190.00 /hr for 120 hr 22,800.00
1.00 unit Concrete Vibrator 152.00 /hr for 120 hr 18,240.00
Minor Tools (10% of Labor cost) 10,200.00
Cost of Equipment 51,240.00
B. EQUIPMENTS
1.00 unit Backhoe (0.80 cu.m) 1,500.00 /hour for 205 hours 307,500.00
Cost of Equipment P 307,500.00
MATERIALS
372.00 pcs Phenolic Board 1,720.00 /pc 639,840.00
4,300.00 bd.ft Good Lumber 75.00 /bd.ft 322,500.00
65.00 kgs Assorted CW Nails 75.00 /kg 4,875.00
Cost of Materials 967,215.00
LABOR
1.00 man Foreman 600.00 /day for 20.00 days 12,000.00
4.00 men Skilled Laborer 500.00 /day for 20.00 days 40,000.00
6.00 men Common Laborer 350.00 /day for 20.00 days 42,000.00
Cost of Labor 94,000.00
EQUIPMENT
40.00 pcs H-Frame with Complete Access 80.00 /day for 20.00 days 64,000.00
Cost of Equipment 64,000.00
MATERIALS
8.00 cu.m Sand 600.00 /cu.m 4,800.00
765.00 kg Reinforcing Steel bars 60.00 /kg 45,900.00
325.00 bag Portland Cement 350.00 /bag 113,750.00
3,100.00 pcs 6" CHB 18.00 /pcs 55,800.00
18.00 kg #16 G.I. Tie Wire 75.00 /kg 1,350.00
Cost of materials 221,600.00
3.00 unit Welding Machine 1,400.00 /day for 45.00 days 189,000.00
3.00 unit Cutting Outfit 350.00 /day for 45.00 days 47,250.00
Cost of Equipment 236,250.00
MATERIALS
216.00 kgs Structural Steel Truss 60.00 /kg 12,960.00
1,680.00 kgs Acetylene 18.00 /kg 30,240.00
3,276.00 kgs Oxygen 145.00 /kg 475,020.00
2,968.00 kgs Welding Rod 155.00 /kg 460,040.00
Cost of materials 978,260.00
1.00 unit Welding Machine 1,650.00 /day for 35.00 days 57,750.00
Cost of Equipment 57,750.00
MATERIALS
12.00 kgs Structural Steel Purlins 60.00 /kg 720.00
265.00 kgs Welding Rod 155.00 /kg 41,075.00
Cost of materials 41,795.00
SUMMARY