Professional Documents
Culture Documents
J910-Ss-Ed-015 - 1 of 1 - Rev-0 - (Girt at View Line C)
J910-Ss-Ed-015 - 1 of 1 - Rev-0 - (Girt at View Line C)
1 2 3 4 5 6
GR4-3
SG-43
EL.+18.875 SG-42
GR4-2 SG-41
1625
SG-40 SG-26
GR1-10
SG-39
GR4-1 SG-38
1500
SG-37 SG-7
SG-24
SG-36
GR4-2 SG-35 GR1-5 GR1-9
1500
SG-24 SG-26
SG-7
SG-34
SG-33
GR4-1 SG-32 GR1-6 SG-6 SG-9 GR1-2 GR1-8
SG-9
1500
SG-7 SG-12
SG-31
SG-30
SG-29 GR1-5 SG-6 GR1-2 GR1-1 GR1-8
SG-9 SG-9
13875
1500
SG-7 SG-12 SG-9
EL.+11.485
GR1-4 SG-9 GR1-2 GR1-1 GR1-1 GR1-8
SG-6 SG-9
1500
SG-7 SG-12
1500
SG-7
2400
0
REV DESCRIPTION
DATE DRAWN CHECKED APPROVED
NO
PROJECT :
850
JAWA 9 & 10 COAL FIRED
EL.+5.000
7000 7000 7000 7000 5850 STEAM POWER PLANT
33850 OWNER :
EPC CONTRACTOR :
SUB CONTRACTOR :
DRAWING TITLE :
J910-SS-ED-015 A3 0