Daily Report May 10, 2016

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 1

No. Dok.

: FM/03-01/CONS
THERMAX PROJECT No. Rev. : 0.0
Tgl Rev. : 01 April 2013
PT. CITRA KARSA DINAMIKA

DAILY REPORT
Nama Project : Thermax New Factory Project Reff. Number
Client : PT. Thermax International Indonesia Issued Date 10/05/2016
PM Consultant : PT. Teamworx Indonesia Day Nr. 23 day(s)
Contractor : PT. Citra Karsa Dinamika Remain. Day 37 day(s)
No. Work Description Weather Condition
1 Morning brifing and safety talk 07.00 - 08.00 Clear
2 Cutting of pile 08.00 - 09.00 Clear
3 Install batako formwork 09.00 - 10.00 Clear
4 Install rebar 10.00 - 11.00 Clear
5 Soil excavation 11.00 - 12.00 Clear
6 Pouring concrete 12.00 - 13.00 Clear
7 Bar cutting and bar bending 13.00 - 14.00 Clear
14.00 - 15.00 Clear
15.00 - 16.00 Clear
16.00 - 17.00 Clear
17.00 - 18.00 Clear
18.00 - 19.00 Clear
19.00 - 20.00 Clear
20.00 - 21.00 Clear
21.00 - 22.00 Clear
22.00 - 23.00
23.00 - 24.00
MANPOWER MATERIAL
Working Hour(s)
No. Description Nor No. Description Qty Unit
08.00 - 16.00 OT Nor 16.00 - 22.00 Total
1 Project Manager 1,00 7,00 1,00 5,00 12,00 1 Rebar dia 10, 13, 16, 19, 22 mm 1 ls
2 Site Manager - - - - - 2 Semen abu 50 sak
3 Supervisor 1,00 7,00 1,00 5,00 12,00 3 Pasir 70 m3
4 Drafter - - - - - 4 Batako 10000 pcs
5 Safety Officer - - - - - 5 kawat bendart 100 kg
6 Administrasi - - - - - 6 Kaso 4/6 3 m3
7 Logistik 1,00 7,00 1,00 5,00 12,00 7 Ready mix K 350 49 m3
8 Surveyor 2,00 7,00 2,00 5,00 24,00 8 Paku 5, 7, 10 cm 20 kg
9 Foreman - - - - - 9 Bar cutting + bat bending 1 set
10 Ass. Foreman 1,00 7,00 1,00 5,00 12,00 10 Mu;tiplex 12, 18 mm 25 lbr
11 Masonry 8,00 7,00 8,00 5,00 96,00
12 Carpenter 4,00 7,00 4,00 5,00 48,00
13 Rebar 5,00 7,00 5,00 5,00 60,00 EQUIPMENT
14 Helper 8,00 7,00 8,00 5,00 96,00 No. Type Qty Unit
15 Cut of pilling 4,00 3,00 - - 12,00 1 Palu 3 pcs
16 Operator 1,00 7,00 - - 7,00 2 gergaji 2 pcs
17 Security project 3,00 7,00 - - 21,00 3 sendok semen 8 pcs
18 Mekanik-elektrik 1,00 4,00 - - 4,00 4 Cangkul 4 pcs
19 Helper logistik 1,00 7,00 1,00 5,00 12,00 5 Excavator 1 unit
20 Steel structure - - - - - 6 Fibrator 2 unit
21 Welder - - - - - 7 Genset 1 unit
8 Lampu tembak 6 unit
9 Kabel power 1 ls
10 Mobil pick up 1 unit
SAFETY CONDITION
Total Manhour(s) 428,00 hour(s)
Lost of Injury Time - hour(s)
Total Accident - case(s)
Total 41,00 91,00 32,00 50,00 428,00 Total Incident - case(s)
APPROVED BY ISSUED BY
PT. TEAMWORX INDONESIA PT. CITRA KARSA DINAMIKA

FARIED INDRAYANTA DEDE RUSNA.K


CONSTRUCTION MANAGER PROJECT MANAGER