Project Name THERMAX NEW FACTORY PROJECT Contractor PT. CITRA KARSA DINAMIKA
INSTALL BATAKO FORMWORK FOR PILE CAP AND TIE BEAM INSTALL REBAR PILE FOR CAP AND TIE BEAM
SLUMP TEST BEFORE POURING CONCRETE POURING CONCRETE PILE CAP AND TIE BEAM K 350
HSSE Job Desc - Today Job Desc - Next Day
Cumulative Manhour for This 1. Bar cutting and bar bending 1. Bar cutting and bar bending
Week 2. Cutting of pile 2. Cutting of pile
Cumulative Manhour until This 3. Install batako formwork 3. Install batako formwork
Month 4. Soil excavation 4. Soil excavation
Safety Trainning 5. Sand filling and lean concrete 5. Sand filling and lean concrete
6. Install rebar 6. Install rebar
- Demo body harness 7. Pouring concrete as A ( 1-5 ) 7. Fabrikasi multiplex formwork
- Demo ERP
- Demo PPE / APD
- Demo Fire Ext.
- Demo Scafold
PI & NM Tools Issues
Excavator Fibrator Something heavy rain at the site
- Near Miss Genset Lampu tembak
Material Approval
Rebar DP di 10, 13, 16, 19, 22 mm
Ready mix K 350 ex. Merah Putih
Prepared by, Dede Rusna.K