Professional Documents
Culture Documents
UnitRateVariability Alex12007
UnitRateVariability Alex12007
net/publication/260593861
CITATIONS READS
0 1,001
3 authors, including:
SEE PROFILE
All content following this page was uploaded by Refaat Hassan Abdel-Razek on 18 February 2016.
INTRODUCTION
There have been numerous attempts over the years to measure and
improve labor productivity in construction industry. Milestones researches
and studies in the field of construction productivity in Egypt include Abdel -
Razek1,2,3, Abdel-Razek et al. 4, Abdel-Razek and McCaffer 5, Abd Elshakour 6,
and Abdel-Hamid7. Productivity improvement is the key to improve the labor
standard of living, the construction companies' profitability, the construction
industry flourishment, and indeed the nation wealth.
Poor management and other factors can cause unnecessary
changeability in construction conditions that leads to variable performance.
In recent years, lean construction principles have received much considera -
tion as a new way to improve construction performance and labor productiv -
MG-1
ity. In this paper, lean construction principles are demonstrated. On e of
these principles is reducing variability in production rate. According to
Thomas et al. 8, reducing variability in labor productivity will result in
improved labor performance. This principle is examined to show the impact
of variability of labor productivity on project performance.
The objectives of this paper are:
a. To list and explain briefly the various lean construction principles, and
b. To examine the relationship between unit rate variability and project
performance.
The word lean was defined by Howell 9 as "Give customers what they
want, deliver it instantly, with no waste." The term "lean" was coined by the
research team working on international auto production to reflect both the
waste reduction nature of the Toyota production system and to contrast it
with craft and mass forms of production 10.
Craft production produces a customer product one at a time using highly
skilled workers and simple and flexible tools 11. The flexibility that craft
production provides is an advantage, but it is achieved at a cost. Mass
production produces large volumes of standardized products using semi -
skilled workers and expensive, single-purpose machines 11.
In contrast to the above stated definitions of craft and mass production,
lean production combines the advantages of craft and mass production. It
provides volumes of a variety of products at a relatively low cost by using
resources of multi–skilled workers at all levels of organization and highly
flexible, increasingly automated machines 11. Lean production aims at
eliminating waste. According to Koskela 12, wastes include overproduction,
waiting, transporting, too much machining (over processing), inventories,
moving, and making defective parts and products. Howell10 defined waste as
failure to meet the unique requirements of a client.
Lean construction is a new way to manage construction. Lean
construction results from the application of a new form of production
management to construction 10.
MG-2
Material, labor Products
Production process
Subprocess A Subprocess B
Scrap
Fig. 2. Production as a flow process: simplistic illustration. The shaded boxes represent non value-
adding activities, in contrast to value-adding processing activities (Koskela12).
MG-3
c. Reduce variability in labor productivity,
d. Improving flow reliability,
e. Eliminate waste, and simplify the operation, and
f. Benchmark.
The following sections describe briefly these principles.
Just-In-Time (JIT)
MG-4
Benchmarking
Baseline Productivity
MG-5
Table 1 Characteristics and classifications of the studied projects
No. Project Name Type of Project Work Start date End Location
days date
1 Elmona Residential & 19 11/4/04 13/5/04 Zagazig
project Commercial
2 Elaboor Residential 21 1/5/04 26/5/04 Elaboor
village
3 Shalik Mall Residential & 19 1/3/04 24/3/04 Zagazig
Commercial
4 Elzhour Residential 40 13/3/04 4/5/04 Zagazig
project
5 M.Hassan Residential 22 5/4/04 3/5/04 Zagazig
project
6 Elaboor Residential 39 1/3/04 29/5/04 Elaboor
project a
7 Elaboor Residential 31 11/3/04 29/5/04 Elaboor
project b
8 Elaboor Residential 42 13/5/04 23/7/04 Elaboor
project c
9 Elaboor Residential 34 16/5/04 12/7/04 Elaboor
project d
10 Oraby project Commercial 16 11/5/04 31/5/04 Zagazig
11 Elkodda Residential & 16 3/3/204 23/3/04 Zagazig
project Commercial
MG-6
The PMI is a dimensionless parameter that reflects the contribution of
project management to the cumulative labor performance on the project. The
lower the PMI, the better was the project management’s influence on overall
performance. Higher numbers are indicative of poorer labor performance.
The PMI values for studied projects are calculated and summarized in Table
3 and presented in Fig. 4. PMI values of the studied projects range from
0.202 to 4.23. From Fig. 4, seven projects (i.e. about 64% of the studied
projects) have PMI values > 0.5 and three projects (i.e. about 27% best
projects) have PMI values < 0.4.
Figs. 5 and 6 illustrate variability in daily labor productivity for two of the
studied projects, namely project no. 8 and no. 11. The variability in daily
labor productivity for each of the studied projects can be illustrated in the
same way and can be calculated by using the following equation 8:
Variation (Vj ) =
(urij - baseline productivity j ) 2 (3)
n
Where ur ij = the daily productivity (unit rate) for workday i on project j, and n
= the number of observed workdays on project j.
The variation Vj for different projects cannot be compared directly unless
the baseline productivity values are the same. Therefore, the coefficient of
variation 8 can be calculated as:
Vj x 100
Coefficient of Variation (CVj ) = (4)
(Baseline Productivity) j
MG-7
The values of CV of studied projects range from 38.23 to 217.73. The
higher the CV, the more the project experienced abnormal workdays 8. The
CV values of studied projects are summarized in Table 4 and presented in
Fig. 7.
Fig. 4 showed that projects no. 8, no. 9, and no. 10 have PMI values >
1.00. Fig. 7 showed high variability in daily productivity in these projects.
On the other hand, project no. 1 with PMI value of 0.202, project no. 2 with
PMI value of 0.411, and project no. 11 with PMI value of 0.386 were
considered as best performing projects because PMI values are very small.
Fig. 7 showed minimal variability in daily productivity in these projects.
Thus, Projects that have good labor performance based on the project
management index also exhibit minimal variability in daily productivity
values.
Table 3 Project management index (PMI)
4.5 4.23
4
Project Management Index
3.5
2.5
1.878
2
1.5 1.154
1 0.722 0.765
0.638 0.645
0.411 0.347 0.386
0.5 0.202
0
1 2 3 4 5 6 7 8 9 10 11
Project
MG-8
8
6
5
3
2
1
0
0 2 4 6 8 10 12 14 16 18
Work Day
MG-9
250
217.73
Coefficient of productivity variation
195.73
200
150
62.26
53.02
50 38.23
0
1 2 3 4 5 6 7 8 9 10 11
Project
MG-10
project management index 4.5
4
3.5
3
(PMI)
2.5
2
1.5
1
0.5
0
0 50 100 150 200 250
Coefficient of productivity variation (cv)
CONCLUSION
MG-11
REFERENCES
MG-12
[15] Ballard, G., and Howell, G., "Towards Construction JIT," Proceedings of the
11th Annual ARCOM Conf., Association of Researchers in Construction
Management, Reading, U.K., 1995, pp. 338-346.
[16] Ballard, G., and Howell, G., "Shielding Production: An Essential Step in
Production Control," J. Constr. Engrg and Magmt., ASCE, 124 (1), 1998,
pp. 11-17.
[17] Ballard, G., and Howell, G., "Improving Work Flow Reliability," Proceedings
of the seventh Annual Conf. of Int. Group for Lean Construction, Berkeley,
1999.
[18] Tommelein, I.D., "Pull-Driven Scheduling For Pipe Spool Installation:
Simulation of Lean Construction Technique," J. Constr. Engrg and Magmt.,
ASCE, 124 (4), 1998, pp. 279-288.
[19] Thomas, H.R., and Sanvido, V.E. "Role of the Fabricator in Labor
Productivity," J. Constr. Engrg Magmt., ASCE, 126 (5), 2000, pp. 358-365.
[20] Thomas, H.R., and Zavrski, I., "Theoretical Model for International
Benchmarking of Labor Productivity." Tech. Rep. No. 9913, Pennsylvania
Transportation Institute, University Park, Pa., 1999.
[21] Thomas, H.R., "Improving Labor Flow Reliability for Better Productivity as
Lean Construction Principle," J. Constr. Engrg and Magmt., ASCE, 120 (1),
2003, pp. 47-64.
[22] Madigan D. Benchmark Method Version 3, No. ACL/ DLV/96/015, 1997,
Agile Construction Initiative, University of Bath.
[23] Osman, I., and Abdel-Razek R.H., "Measuring for Competitiveness: The
Role of Benchmarking," Proceeding of the Cairo 1st International
Conference on Concrete Structures., Cairo Univ., Cairo 2-4 January, 1996,
volume 1., pp. 5-12.
[24] Thomas, H.R., and Zavrski, I., "Construction Baseline Productivity," J.
Constr. Engrg Magmt., ASCE, 125 (5), 1999, pp. 293-303.
MG-13