Professional Documents
Culture Documents
RFQ of Cooling Tower
RFQ of Cooling Tower
Project Name: DISMANTLING & ASSEMBLY OF COOLING TOWER Location: ROBINSONS IMUS, CAVITE
3 Pipe Dismantling & assembly for Machine Connection 1 lot 95,000 95,000
Amount 1,557,400
Discount %
Discount Amount 0
Special Discount
No signature is required
INCLUSIONS:
1. Mobilization / Demobilization
2. Dismantling of 1 Unit Cooling Tower
3. Assembly of 1 Unit Cooling Tower
4. Minor Consumables (Bolts, Nuts, Angle Bars, C-Channel, Welding Rods, Etc)
5. T&C Assistance
6. Pipe Dismantling & Assembly
EXCLUSIONS:
Terms of Payment
Author Conforme:__________________________
Date_____________________________
STATUS
Status History
Changed By Status
https://coliconstruct.kintone.com/k/67/print?record=348 1/1