Mechanical Department Weekly Work Planning(26 May to 31 May)

Sl No. Work Details Responsible Engineer Remarks


1 Shut down supervision Keron, Sadman & Arabinda

1. Base Plate cutting 60/60


2. Top Plate cutting 60/60
3. Structural column 09/09
4. Gusset Plate 200/200
2 SWS plant structure & vessel-tower fabrication follow-up Arabinda & Sadman 5. Flat bar cutting for ladder
42 pcs
6. Beam cutting 5/5
(Praparing for installing
Gusset plate)

3 Shut-down follow-up & end report preparation Keron


4 BOQ & Pricing estimation for construction of C-7001 in-house Arabinda
5 New store design checking and supplier follow-up(CS updation)
6 Tank farm area pipeline fabrication supervision and planning
7 10000 BPD plant Open Drain-CD drawing confirmation Sadman
8 New Power-house electrical support work(fabrication drawing updating)
9 10000 BPD plant equipment(Vessel) modelling
10 10000 BPD plant procurement(local & foreign) follow-up and technical communication
11 Other foreign procurement follow-up
12 10000 BPD plant precurement master file updating Keron
13 10000 BPD plant 2D layout drawing
14 C-7001 technical communication follow-up
15 10000 BPD plant equipment(tower) modelling Arabinda
16 10000 BPD plant structure and OD-CD fabrication follow-up Keron & Sadman
17 Rotating items stock checking Kaisar
18 Contractors bill checking Arabinda & Sadman
19 Padma Meghna, Jamuna pipline survey and drawing preparation Surveyor Zelan
20 10000 BPD plant strainer BOQ preparation Arabindo
Rotating work list
1 Work Details Man power
2 H-301 blower fan maintenance work Aziz 70% complete
3 Cooling tower pump inter-change( spx to deepblue) Waiting for manpower Waiting for manpower.
4 Reformer-2 oil h-2 compressor dismental for scraping Jashim, Puloq Start on Sunday
5 Agitator motor installation work Jashim Waiting for approval.
6 Mechanical items house kepping work. Bela, Mijan 30%
7 Flare pump ready work. 4set completed, 2set running Aziz 80%
SL no Development work list Group Nos
1 SWS Vessel, Gusset Make, shell plate preparation, Saddle making
2 SWS Structure top bottom base plate cutting drilling, Gusset making
3 SWS Platform, railing making
4 SWS Ladder making 3
5 Old gate valve, fittings segregating for counting
6 Old Flare pipe line cutting and open
7 Old Flare Structure cutting and open 3
8 Flare fire water line making 1
9 Dyke-1 water flushing line, cooling line tie inn
10 Dyke -5 Fire, Foam line Fabrication & Fitting
11 Dyke -5 Beam Make for Tank Farm Pipe line Support fitting
4
12 Dyke-5 Tank 6" pipe line fabrication
13 Tank to tank Circulation line Fabrication as instructed
14 fire line around Dyke-5
15 New Exchanger Tube Bundle Make for RF-2 1
16 New Gate Make for Store and pocket gate, MCC Door Making 1
17 H-3001 to E-6015 Supply and return 6'' pipe line fabrication 2
18 RF-2 to CMX BT Tower 2" Line fabrication 1