Ciwandan Report
Ciwandan Report
- Settlement Observation
- Lightning Protection system (Inc clamp)
- Existing canopy (on Progress)
- HVAC system ( Clinker Substation)
1 Clinker - Clinker Roof not finished yet welding (see fotograph)
- BC3 49B problem on support (See Fotograph)
- Clinker tunnel and canopy finishing/Plastering
- Grouting for fan foundation
- BC3 49B problem on welding handrail (See Fotograph)
Stop Progress
2 Warehouse
On Progress
3 Workshop
- HVAC on Progress
4 Main Office - Fire Hydrant/water pipe
- On Progress
5 Pump Station and Living waterpool
- Repair Welding and Bolt Connection (Bolt Nut, washer) is not complete yet
- Section J-G, FL+16.00 - +28.00 (Clading & sheeting Wall)
10 TT1
- Section E-C, FL+00.00 - +6.700 (Cladding and Sheeting Wall)
- Repair Welding and Bolt Connection (Bolt Nut, washer) is not complete yet
11 TT2 - Section F - E, FL+13.00 - +19.500
- Repair Welding and Bolt Connection (Bolt Nut, washer) is not complete yet
12 TT3 - Section A - B, FL+5.700 - +12.500
- Welding Electrode E6013 that used on site is smaller than Mild Steel
Q235B (Tensile Strength) Please Check Mill Certificate material
- Re-bar Filling on welding bead will be occur Uncomplete fusion and
unacceptable variable
Note: Pre-tension force for design value of bolt strength not smaller than M20 = 155KN etc
NO ITEM NAME DESCRIPTION REMARKS
Handrail Welded on Platform/chk'd Plate and bad profile Fillet weld joint must be welding on beam
Support conveyor BC349B is not on right position some area find uncomplete welding
Status : Needed support / additonal beam Status : full weld all joint
1 CLINKER SILO
A few dirty wall Support belt conveyor on clinker tunnel Not Welded Yet
Status : Plestering/finishing good all tunnel clinker Status : check all & welding
NO ITEM NAME DESCRIPTION REMARKS
Base Plate Pedestal Not finished weld and many defect All Column, Inside/outside wall with Plestering/finish
welding (All Pedestal 26 + 6 sets) good
Status : All Pedestal Not Complete Welding Status : must be clean and Finishing with Plestering
Unacceptable welding work Leaking tunnel, No data Report for waterproofing Mix on
concrete / Additive Tunnel
Status : check all welding for Support B/C Status : Check all. No Expansion Joint, Water Stop.
Needed Plastering/finishing good On tunnel Pit control (additive and Conveyor Tunnel)
ADDITIVE
STORAGE and
1
CONVEYOR
TRANSFER
Status : check all , Repair and Improved Status : Plestering work ASAP (tunnel Hopper)
NO ITEM NAME DESCRIPTION REMARKS
COMPRESSOR
ROOM, PUMP
1 STATION and
COOLING
WATER
1 TT01-03
Welding Defect (uncomplete Penetration), (filling Re-Bar Filling Re-Bar in Weld Bead
in Weld bead)
Status : All Elevation must be Repair and Welded Status : Remove all Re-bar !!!!
(FL+4.000 till FL.+47.500) - No Welding Report
1 TT-04
Status : Root Weld is not finished yet Status : Remove all Rebar !!!