INSPECTION REQUEST FORM

Contractor : Nael Construction and Contracting LLC


Consultant : KHATIB & ALAMI

Project Title : Sewerage & Stormwater Drainage System for Nad Al Shiba 3rd IR Ref. No. : DS-196/2-P4-HC-7554

Project No. : DS-196/2 Date : 8-May-24


B.O.Q Items : d/4/3A Discipline : Civil

Description of Work : Installation of Base , Shaft and Coverslab. Area 1


( CH-V-NB-18/7/3-2 Type A )
Work Location (drawing attached) : Yes Sector : N/A Road, Building etc., N/A

Work to be Inspected :

Work Ready for Inspection at : (Time) : (Date)

Inspection Requested By : Request Received By :


(for CONTRACTOR) (for CONSULTANT)

Date : 08-May-24 Time : 8:28:00 AM Date : Time :

SKETCH / NOTES / MEASUREMENTS :

Sketches,Sattached
INSPECTION REPORT :
Inspection of Work Completed : (Time) (Date)
Permission to Proceed with the work : Approved

Approved Subject To (See Comments)


Not Approved (See Comments)

Others (PLS. Specify) (See Comments)


Land Surveyor Comments :
Shop drawing to be updated.

Inspector Comments :

Material Inspector Comments :

Surveyor (Name) : Musab AbdAlrhman Signature : Date : 10.05.2024


Inspector (Name) : Signature : Date :
A. R. E (Name) : Signature : Date :
R. E (Name) : Signature : Date :

Received by Contractor :
Contractor's
: Signature : Date :