Professional Documents
Culture Documents
Rehabilitation of Canal - Rombang
Rehabilitation of Canal - Rombang
Municipality: Sibalom
Date: June 11, 2013
PROGRAM OF WORKS
NATURE OF WORKS
x Construction
Installation
Repair
Improvement
DETAILED ESTIMATES
Item I Billboard
Qty = 1.00 unit
Direct Cost
1 unit - Billboard @ 1,500.00 /unit = 1,500.00
B. Labor
4 Mason for 2.5 days @ 250.00 /day = 2,500.00
6 Laborers for 2.5 days @ 200.00 /day = 3,000.00
Total Cost of Labor = 5,500.00
Direct Cost = 122,446.00
Profit = 12,244.60
OCM = 6,122.30
Tax = 13,926.60
TOTAL COST = 154,739.50
Unit Cost = 663.52
Page 1 of 110
Item IV Slab on Fill t = 0.075 m
Qty = 24.62 sq.m
A. Materials
17 bags - Portland Cement @ 240.00 /bag = 4,080.00
2 cu.m - Gravel @ 430.00 /cu.m = 860.00
2 cu.m - Sand @ 250.00 /cu.m = 500.00
13.8 cu.m - Filling Materials @ 250.00 /cu.m = 3,450.00
18 pcs - 10mm x 6m RSB @ 130.00 /pc = 2,340.00
1 kgs - #16 Tying Wire @ 70.00 /kg = 70.00
Total Cost of Materials 11,300.00
B. Labor
4 Mason/Carpenter for 2.5 days @ 250.00 /day = 2,500.00
4 Laborers for 2.5 days @ 200.00 /day = 2,000.00
Total Cost of Labor = 4,500.00
Direct Cost = 15,800.00
Profit = 1,580.00
OCM = 790.00
Tax = 1,797.07
TOTAL COST = 19,967.07
Unit Cost = 811.01
B. Labor
2 Welder for 7 days @ 250.00 /day = 3,500.00
2 Laborers for 7 days @ 200.00 /day = 2,800.00
Total Cost of Labor = 6,300.00
Direct Cost = 18,186.00
Profit = 1,818.60
OCM = 909.30
Tax = 2,068.31
TOTAL COST = 22,982.21
Unit Cost = 877.04
B. Labor
2 Carpenter for 2 days @ 250.00 /day = 1,000.00
2 Laborer for 2 days @ 200.00 /day = 800.00
1,800.00
Direct Cost = 2,424.00
Profit = 242.40
OCM = 121.20
Tax = #DIV/0!
TOTAL COST = #DIV/0!
Unit Cost = #DIV/0!
Page 3 of 110
68 pcs - 0.20 x 0.20 Unglzed tiles @ 13.00 /pc = 884.00
6 bags - Portland Cement @ 240.00 /bag = 1,440.00
3 pack - Tile Grout @ 65.00 /pack = 195.00
6 pcs - Tile Trim @ 65.00 /pc = 390.00
2,909.00
B. Labor
2 Mason for 2 days @ 250.00 /day = 1,000.00
2 Laborer for 2 days @ 200.00 /day = 800.00
1,800.00
Direct Cost = 4,709.00
Profit = 470.90
OCM = 235.45
Tax = #DIV/0!
TOTAL COST = #DIV/0!
Unit Cost = #DIV/0!
Item IX Painting
Qty = Err:508 sq.m
A. Materials
Masonry:
Qty = 328.68 sq.m
1 gal - Concrete Neutralizer @ 480.00 /gal = 480.00
11 gal - Flat Latex White @ 524.00 /gal = 5,764.00
16.5 gal - Semi-gloss Latex White @ 620.00 /gal = 10,230.00
1 gal - Masonry Putty @ 340.00 /gal = 340.00
4 lit - Latex tinting Color @ 200.00 /lit = 800.00
Carpentry:
Qty = Err:508 sq.m
### gal - Flat Wall Enamel @ 590.00 /gal = Err:508
### gal - Semi-gloss Enamel @ 590.00 /gal = Err:508
2 lit - Tinting Color Oil @ 220.00 /lit = 440.00
6 kgs - Patching Compound @ 45.00 /kg = 270.00
Accessories:
15 pcs - Sand Paper #120 @ 15.00 /pc = 225.00
2 pcs - Pallet @ 15.00 /pc = 30.00
1 pcs - 9" Roller Brush @ 90.00 /gal = 90.00
1 pcs - 7" Roller Brush @ 80.00 /gal = 80.00
2 pcs - Baby Roller Brush @ 60.00 /gal = 120.00
2 pcs - 4" Paint Brush @ 110.00 /gal = 220.00
2 pcs - 2-1/2" Paint Brush @ 55.00 /gal = 110.00
2 pcs - 1" Paint Brush @ 23.00 /gal = 46.00
Err:508
B. Labor
2 Painter for 9 days @ 250.00 /day = 4,500.00
2 Laborer for 9 days @ 200.00 /day = 3,600.00
8,100.00
Direct Cost = Err:508
Profit = Err:508
OCM = Err:508
Tax = Err:508
TOTAL COST = Err:508
Unit Cost = Err:508
B. Labor
2 Electrician for 6 days @ 250.00 /day = 3,000.00
2 Laborers for 6 days @ 200.00 /day = 2,400.00
5,400.00
Direct Cost = 24,594.00
Profit = 2,459.40
OCM = 1,229.70
Tax = 2,797.23
TOTAL COST = 31,080.33
Page 5 of 110
Unit Cost = 31,080.33
SUMMARY
Item Description Unit Qty Unit Direct Cost Amount
I Billboard cu.m 1.00 1,500.00 1,500.00
II Foundations and Columns cu.m #NAME? #NAME? #NAME?
III CHB Wall w/ Plastering on sq.m 233.21 663.52 154,739.50
Both Sides
IV Slab on Fill sq.m 24.62 811.01 19,967.07
V Roofing and Roof Framing ln.m 26.20 877.04 22,982.21
VI Carpentry Works
VI-A Ceiling (Interior & Exterior) sq.m 25.71 Err:509 Err:509
VI-B Partitions sq.m 0.00 #DIV/0! #DIV/0!
VII Doors & Windows sq.m 14.16 Err:509 Err:509
VIII Tile Works sq.m 0.00 #DIV/0! #DIV/0!
IX Painting lot Err:508 Err:508 Err:508
X Plumbing Works lot 1.00 25,761.26 25,761.26
and Accessories
XI Electrical Works lot 1.00 31,080.33 31,080.33
XII Forms and Scaffoldings lot 1.00 5,929.45 5,929.45
TOTAL = Err:509
Recommended by:
EARL M. CUAYSON
Municipal Engineer
Page 6 of 110
1 unit Billboard 4' X 4' @ 600.94 /unit = 600.94
125 bags Portland Cement @ 0.00 /cu.m = 0.00
5 cu.m Gravel @ 473.00 /cu.m = 2,365.00
### pcs 12mm x 6m RSB @ 0.00 /pc = #NAME?
### pcs 10mm x 6m RSB @ 0.00 /pc = #NAME?
### kgs #16 Tying Wire @ 0.00 /kg = #NAME?
240 pcs 2-1/2" Teckscrew @ 2.00 /pc = 480.00
1 can 1/4lit Vulca Seal @ 132.00 /can = 132.00
8 pcs 4mm x 38mm x 6m A/B @ 406.00 /pc = 3,248.00
10 pcs 1.2mm x 2" x 3" x 6m C-purlins @ 322.50 /pc = 3,225.00
7 pcs 38mm x 4mm x 6m F/B @ 354.00 /pc = 2,478.00
7 pcs 1" x 12" x 8' Hardifascia @ 468.00 /pc = 3,276.00
3 pcs 0.40mm x 2.44m Pre-painted Gutter (see detail) @ 409.00 /pc = 1,227.00
3 pcs 0.40mm x 2.44m Pre-painted Spanish Gutter @ 409.00 /pc = 1,227.00
4 pcs 0.40mm x 2.44m Pre-painted Ridge Roll @ 313.00 /pc = 1,252.00
5 pcs 0.40mm x 2.44m Pre-painted Flashing @ 348.50 /pc = 1,742.50
10 kgs Welding Rod @ 110.00 /pc = 1,100.00
1 pc Reviter @ 352.00 /pc = 352.00
113 pcs 3/16 x 1" Blind Revits @ 2.30 /pc = 259.90
9 pcs 1/4" x 4' x 8' Marine Plywood @ 0.00 /pc = 0.00
30 pcs 2" x 2" x 12' Good Lumber @ 0.00 /pc = 0.00
23 pcs 2" x 8' Cornice @ 200.00 /pc 4,600.00
2 kgs 4" Concrete Nails @ 132.00 /kg = 264.00
7 kgs 4" CWN @ 0.00 /kg = 0.00
6 kgs 2-1/2" CWN @ 0.00 /kg = 0.00
4 kgs 1-1/4" CWN @ 0.00 /kg = 0.00
2 set D1 (1.0 x 2.10m) Panel Door w/ @ 6,950.83 /set = 13,901.67
2" x 5" Jamb & Complete Accessories
1 set D2 (2 - 0.60m x 2.10m) Panel Door w/ @ 10,520.83 /set = 10,520.83
2" x 5" Jamb & Complete Accessories
1 set D3 (0.7 x 2.10m) PVC Door @ 1,470.00 /set = 1,470.00
with Complete Accessories
1 set W1 (2 - 0.60 x 1.20m) Fixed Window w/ @ 4,066.67 /set = 4,066.67
counter hole & Alum. Frame Analok & Complete Accessories
1 set W2 (1.20 x 1.20m) Fixed Window w/ @ 4,066.67 /set = 4,066.67
counter hole & Alum. Frame Analok & Complete Accessories
2 set W3 (2 - 0.30 x 0.60m) Sliding Window w/ Alum. @ 1,016.67 /set = 2,033.35
Frame Analok & Complete Accessories
1 set W4 (2 - 0.60 x 1.20m) Sliding Window w/ Alum. @ 4,066.67 /set = 4,066.67
Frame Analok & Complete Accessories
40 pcs Louver Block @ 21.50 /pc = 860.00
0 pcs 0.20 x 0.20 Glazed tiles @ 11.50 /pc = 0.00
68 pcs 0.20 x 0.20 Unglzed tiles @ 11.50 /pc = 782.00
3 pack Tile Grout @ 54.50 /pack = 163.50
6 pcs Tile Trim @ 31.50 /pc = 189.00
0 pcs 16"x16" Unglazed Tiles (Vetrified) @ 49.00 /pc = 0.00
1 gal Concrete Neutralizer @ 436.00 /gal = 436.00
6 gal Flat Latex White @ 515.00 /gal = 3,090.00
9 gal Semi-gloss Latex White @ 608.50 /gal = 5,476.50
1 gal Masonry Putty @ #NAME? /gal = #NAME?
2 lit Latex tinting Color @ 170.00 /lit = 340.00
2 gal Flat Wall Enamel @ 579.50 /gal = 1,159.00
3 gal Semi-gloss Enamel @ 579.50 /gal = 1,738.50
1 gal Chocolate Brown @ 579.50 /lit = 579.50
3 kgs Patching Compound @ 36.50 /kg = 109.50
1 gal Paint thinner @ 385.00 /gal = 385.00
10 ft Sand Paper #100 @ 53.50 /pc = 535.00
2 pcs Pallet @ 16.00 /pc = 32.00
1 pcs 9" Roller Brush @ 83.50 /pc = 83.50
1 pcs 7" Roller Brush @ 73.00 /pc = 73.00
2 pcs Baby Roller Brush @ 47.00 /pc = 94.00
2 pcs 4" Paint Brush @ 52.00 /pc = 104.00
2 pcs 2-1/2" Paint Brush @ 49.00 /pc = 98.00
2 pcs 1" Paint Brush @ 10.50 /pc = 21.00
1 unit Waterless Unisex Urinal (Oregano type) @ 17,378.50 /pc = 17,378.50
1 set Sink w/ Complete Accesssories @ 1,872.00 /pc = 1,872.00
Page 7 of 110
1 pcs 4" x 4" Floor Drain @ 88.50 /pc = 88.50
4 pcs 4" x 3m x S1000 PVC Pipe @ 0.00 /pc = 0.00
3 pcs 2" x 3m x S1000 PVC Pipe @ 0.00 /pc = 0.00
2 pcs 4" x 4" PVC Wye @ 0.00 /pc = 0.00
4 pcs 4" x 45 PVC Elbow @ 0.00 /pc = 0.00
1 pcs 4" x 2" PVC Tee @ 0.00 /pc = 0.00
2 pcs 4" x 2" PVC Wye @ 0.00 /pc = 0.00
2 pcs 2" x 45 PVC Elbow @ 24.00 /pc = 48.00
4 pcs 2" x 90 PVC Elbow @ 0.00 /pc = 0.00
1 pcs 2" P-trap @ 0.00 /pc = 0.00
2 pcs 4" PVC Clean-out w/ Cover @ 0.00 /pc = 0.00
3 can 200cc PVC Solvent @ 0.00 /pc = 0.00
2 pcs 1/2" x 3m PVC Blue Pipe @ 0.00 /pc = 0.00
2 pcs 1/2" x 90 PVC Elbow Plain @ 0.00 /pc = 0.00
1 pcs 1/2" G.I Tee @ 22.00 /pc = 22.00
1 pcs 1/2" PVC Female Adapter @ 15.00 /pc = 15.00
1 rolls Teflon Tape @ 0.00 /pc = 0.00
1 pcs 1/2" Ball Valve @ 0.00 /pc = 0.00
1 set 4-Branches Panel Board @ 0.00 /set = 0.00
1 set 15A Circuit Breaker Switch @ 0.00 /set = 0.00
1 set 20A Circuit Breaker Switch @ 0.00 /set = 0.00
1 set 60A Circuit Breaker Switch @ 364.00 /set = 364.00
6 set 2-gang Conv. Outlet @ 0.00 /set = 0.00
1 set 3-gang Switch @ 270.50 /set = 270.50
1 set 2-gang Switch @ 203.00 /set = 203.00
2 set 1-gang Switch @ 135.50 /set = 271.00
1 set ACU-outlet @ 0.00 /set = 0.00
11 pcs Utility Box @ 31.50 /pc = 346.50
8 pcs Junction Box @ 31.50 /pc = 252.00
6 rolls Electrical Tape (Big) @ 31.50 roll = 189.00
30 pcs 20mm PVC Electrical Pipe(Atlanta) @ 81.50 /pc = 2,445.00
2 pcs 25mm PVC Electrical Pipe(Atlanta) @ 120.00 /pc = 240.00
50 pcs 1/2 PVC Clip @ 3.50 /pc = 175.00
1.5 box 3.5mm2 THHN Electical Wire @ 4,056.00 /box = 6,084.00
14 m 5.5mm2 THHN Electical Wire @ 0.00 /m = 0.00
16 m 8.0mm2 THHN Electical Wire @ 60.00 /m = 960.00
1 pcs 3/4" Service Entrance Cup w/ Adopter @ 78.00 /pc = 78.00
6 pcs 4" x 4" Plastic Receptacle @ 33.50 /m = 201.00
6 pcs CFL 18W Philips @ 187.50 /m = 1,125.00
8 pcs 1/4 x 2" x 8' Molding @ 52.00 /pc = 416.00
2 pcs 10' Piano Hinges @ 140.00 /pc = 280.00
12 pcs 1 x 3 cabinet handle @ 38.00 /pc = 456.00
12 pcs Drawer lock @ 65.00 /pc = 780.00
1 kg 2" Finishing Nail @ 70.00 /kg = 70.00
1 kg 1" Finishing Nail @ 70.00 /kg = 70.00
1 lit Stick Well @ 140.00 /lit = 140.00
1 lit Solignum (clear) @ 488.00 /lit = 488.00
12 pcs Catches magnetic @ 10.00 /pc = 120.00
Page 8 of 110
Date AMOUNT EXPENSED REMARKS
Labor Qty units Description Unit Cost Amount Total
Amount expense
to Date
17-Jun-16 3 cu.m Gravel 500.00 1,500.00 1,500.00
3 cu.m sand 300.00 900.00 2,400.00
20-Jun-16 3 cu.m mixed s&g 300.00 900.00 3,300.00
1 pc 1/2" x 4' x 8' marine 780.00 780.00 4,080.00
1 box 4" CWN 1,060.00 1,060.00 5,140.00
5 kg 2-1/2" CWN 54.00 270.00 5,410.00
3 kg 1-1/2" CWN 56.00 168.00 5,578.00
2 roll nylon 20.00 40.00 5,618.00
2 pcs tombo spade 480.00 960.00 6,578.00
21-Jun-16 68 pcs 12mm x 6m 176.00 11,968.00 18,546.00 C.I# 055849
100 pcs 10mm x 6m 122.00 12,200.00 30,746.00 C.I# 055849
28 pcs 16mm x 6m 310.00 8,680.00 39,426.00 C.I# 055849
16 pcs 16mm x 9m 485.00 7,760.00 47,186.00 C.I# 055849
77 pcs 9mm x 6m 74.00 5,698.00 52,884.00 C.I# 055849
1 roll #16 tying wire (32kg) 1,460.00 1,460.00 54,344.00 C.I# 055849
9 pcs 1/2 x 4 x 8' marine 780.00 7,020.00 61,364.00 C.I# 055849
23-Jun-16 3 cu.m Gravel 500.00 1,500.00 62,864.00
24-Jun-16 3 cu.m mixed s&g 300.00 900.00 63,764.00
24-Jun-16 3 cu.m mixed s&g 300.00 900.00 64,664.00
441 bd.ft coco lumber 15.00 6,615.00 71,279.00
27-Jun-16 30 bags portland 273.00 8,190.00 79,469.00
28-Jun-16 3 cu.m mixed s&g 300.00 900.00 80,369.00
29-Jun-16 2 pcs bulb 11W 99.00 198.00 80,567.00
1 pcs receptacle 18.00 18.00 80,585.00
02-Jul-16 3 cu.m mixed s&g 300.00 900.00 81,485.00
3 cu.m F sand 300.00 900.00 82,385.00
04-Jul-16 3 cu.m F sand 300.00 900.00 83,285.00
05-Jul-16 1.5 cu.m Gravel 500.00 750.00 84,035.00
30 bags portland 273.00 8,190.00 92,225.00
coco lumber 2,000.00 94,225.00
08-Jul-16 3 cu.m W sand 300.00 900.00 95,125.00
3 cu.m Gravel 500.00 1,500.00 96,625.00
30 bags portland 273.00 8,190.00 104,815.00
12-Jul-16 3 cu.m mixed s&g 300.00 900.00 105,715.00
50 pcs 10mm x 6m 118.00 5,900.00 111,615.00
18-Jul-16 125 pcs 4" CHB 10.00 1,250.00 112,865.00
20 bags portland 273.00 5,460.00 118,325.00
21-Jul-16 3 cu.m mixed s&g 300.00 900.00 119,225.00
15 bags portland 273.00 4,095.00 123,320.00
22-Jul-16 3 cu.m mixed s&g 300.00 900.00 124,220.00
3 cu.m mixed s&g 300.00 900.00 125,120.00 Taj
3 cu.m mixed s&g 300.00 900.00 126,020.00 204.00
medicine(galono) 500.00 126,520.00
3 cu.m mixed s&g 300.00 900.00 127,420.00 new
25-Jul-16 10 bags portland 273.00 2,730.00 130,150.00
9 cu.m mixed s&g 300.00 2,700.00 132,850.00 new
9 cu.m mixed s&g 300.00 2,700.00 135,550.00 204.00
26-Jul-16 6 cu.m mixed s&g 300.00 1,800.00 137,350.00 new
27-Jul-16 20 bags portland 273.00 5,460.00 142,810.00
3 cu.m mixed s&g 300.00 900.00 143,710.00
3 cu.m Gravel 300.00 900.00 144,610.00
29-Jul-16 6 cu.m W sand 300.00 1,800.00 146,410.00
3 cu.m Gravel 500.00 1,500.00 147,910.00
3 cu.m mixed s&g 300.00 900.00 148,810.00
02-Aug-16 200 pcs 4" CHB 10.00 2,000.00 150,810.00
30 bags portland 270.00 8,100.00 158,910.00 c.i# 56808
16 pcs 16mm x 9m 485.00 7,760.00 166,670.00
14 pcs 16mm x 6m 280.00 3,920.00 170,590.00
50 pcs 16mm x 6m 107.00 5,350.00 175,940.00
15 kg #16 tying wire (32kg) 60.00 900.00 176,840.00
1 box 4" cwn 780.00 780.00 177,620.00
1 kg 1-1/2" cwn 58.00 58.00 177,678.00
1 kg 1-1/2" conc nails 80.00 80.00 177,758.00
04-Aug-16 3 cu.m W sand 300.00 900.00 178,658.00
06-Aug-16 3 cu.m W sand 300.00 900.00 179,558.00
11-Aug-16 3 cu.m F sand 300.00 900.00 180,458.00
12-Aug-16 52 pcs 5mm x 1-1/2" x 6m A/B 688.00 35,776.00 216,234.00 C.I EI
37 pcs 1.2mm x 2" x 3" x 6m C-purlins 400.00 14,800.00 231,034.00
6 pcs 3/16 x 1-1/2" x 6m F/B 245.00 1,470.00 232,504.00
1 gal p-thinner 280.00 280.00 232,784.00
1 gal metal primer 363.00 363.00 233,147.00
12 kg welding rod 100.00 1,200.00 234,347.00
3 pcs 2-1/2" p-brush 23.00 69.00 234,416.00
3 pcs roller brush 45.00 135.00 234,551.00
15-Aug-16 3 cu.m Gravel 300.00 900.00 235,451.00
19-Aug-16 30 bags portland 270.00 8,100.00 243,551.00
2 pcs 1/2" x 4' x 8' marine 780.00 1,560.00 245,111.00
Roofing & Accessories 31,500.00 276,611.00
3 cu.m mixed s&g 300.00 900.00 277,511.00
23-Aug-16 350 pcs 4" CHB 10.00 3,500.00 281,011.00
10 bags portland 270.00 2,700.00 283,711.00
24-Aug-16 3 cu.m F sand 300.00 900.00 284,611.00
29-Aug-16 35 bags portland 275.00 9,625.00 294,236.00
30 pcs 10mm x 6m 108.00 3,240.00 297,476.00
3 kg #16 tying wire (32kg) 60.00 180.00 297,656.00
31-Aug-16 5 kg #16 tying wire (32kg) 60.00 300.00 297,956.00
1 roll electrical tape 25.00 25.00 297,981.00
01-Sep-16 300 pcs 4" CHB 10.00 3,000.00 300,981.00
6 pcs 1/8" x 1" a/b 215.00 1,290.00 302,271.00 ci# 025408
40 pcs 10mm x 6m 107.00 4,280.00 306,551.00
6 cu.m mixed s&g 300.00 1,800.00 308,351.00
3 cu.m F sand 300.00 900.00 309,251.00
05-Sep-16 200 pcs 4" CHB 10.00 2,000.00 311,251.00
50 bags portland 275.00 13,750.00 325,001.00
1 pcs teckscrew adapter 70.00 70.00 325,071.00
07-Sep-16 40 pcs 1/2" pvc elect'l conduit pipe 72.00 2,880.00 327,951.00 os 0617
16 pcs utility box 35.00 560.00 328,511.00 os 0617
1 pcs 8 holes panel board 1,395.00 1,395.00 329,906.00
09-Sep-16 rice 700.00 330,606.00
200 pcs 4" CHB 10.00 2,000.00 332,606.00
14-Sep-16 3 cu.m F sand 300.00 900.00 333,506.00
30 bags portland 270.00 8,100.00 341,606.00
16-Sep-16 40 pcs 10mm x 6m 107.00 4,280.00 345,886.00
3 cu.m F sand 300.00 900.00 346,786.00
19-Sep-16 200 pcs 4" CHB 10.00 2,000.00 348,786.00
35 bags portland 270.00 9,450.00 358,236.00
27-Sep-16 10 pcs #20 x 1/2" x 6m G.I pipe 270.00 2,700.00 360,936.00
1 pcs 1/8" x 1" F/B 270.00 270.00 361,206.00
30-Sep-16 25 bags portland 270.00 6,750.00 367,956.00
07-Oct-16 30 bags portland 270.00 8,100.00 376,056.00
3 cu.m F sand 300.00 900.00 376,956.00
Republic of the Philippines
Province of Antique
Municipality of Sibalom
-oOo-
INDIVIDUAL PROGRAM OF WORK
Date Prepared: 18-Jan-24
PROJECT TITLE: Construction and Repair of School Buildings and PROJECT COST: #NAME?
Facilites (Construction of Stage- Phase II) SOURCE OF FUND:
PROJECT LOCATION: Special Education Fund 2023
Rombang, Sibalom, Antique CAL. DAYS TO COMPLETE: 19.5 C.D
MODE OF IMPLEMENTATION:
(By Admininstration) DATE FINISHED:
MINIMUM EQUIPMENT REQUIREMENTS TECHNICAL PERSONNEL REQUIRED
Description NO. DESCRIPTION NO.
Foreman 1
Laborer #NAME?
ANGELIQUE A. VETE 0
Engineering Assistant Engineer I
Approved:
I. Demolition
Qty = 1.00 lot
Labor:
3 Laborer for 2 days 400.00 /day = 2,400.00
Sub-total = 2,400.00
Total Direct Cost = 2,400.00
Unit Cost = 2,400.000
II. Drain Grating Cover
Qty = 36.00 m
A. Materials
6 pcs 2"x2"x20' Angle Bar 1,800.00 /bag = 10,800.00
23 pcs 1-1/2"x1-1/2"x 4mm Flat Bar 618.00 /cu.m = 14,214.00
6 kgs Welding Rod 108.00 /cu.m = 648.00
1 gal Metal Primer 1,020.00 /pc = 1,020.00
6 pcs 10mmØ RSB 170.00 /pc = 1,020.00
Sub-total = 27,702.00
Labor:
1 Foreman for 5 days 600.00 /day = 3,000.00
1 Skilled (Welder) for 5 days 500.00 /day = 2,500.00
2 Laborer for 5 days 400.00 /day = 4,000.00
Sub-total = 9,500.00
Total Direct Cost = 37,202.00
Unit Cost = 1,033.389
Summary:
I. Materials 27,702.00
II. Labor 11,900.00
III. Contigency 398.00
Total Project Cost= 40,000.00
ANGELIQUE A. VETE
Engineering Assistant Kagawad for Infrastracture
Page 12
Member Run Rise Hypoteneous Slope= rise/run No of Pcs Sets Total Length To Order
No of Pcs m Total
Rafter 1
Bottom 4.90 5.02 49.21 7.02 1.02
T.C 7.02 1.14 50.51 7.11 0.16 7.11
Diag 0.40 0.15 0.18 0.43 0.38 0.43
6.40 6.53 83.60 9.14 1.02
Rafter 2
Bottom
T.C 4.70 1.14 23.39 4.84 0.24 4.84
Diag 0.40 0.15 0.18 0.43 0.38 0.43
Rafter 3
Bottom
T.C 5.02 1.14 26.50 5.15 0.23 5.15
Diag 0.40 0.15 0.18 0.43 0.38 0.43
RAFTER 1
T.C & B.C 2.00 1.00 2.00 7.11 14.21
Diagonal 18.00 1.00 18.00 0.43 7.69
Vert 18.00 1.00 18.00 0.15 2.70
RAFTER 2
T.C & B.C 2.00 1.00 2.00 4.84 9.67
Diagonal 13.00 1.00 13.00 0.43 5.59
Vert 13.00 1.00 13.00 0.15 1.95
RAFTER 3
T.C & B.C 2.00 1.00 2.00 5.15 10.30
Diagonal 13.00 1.00 13.00 0.43 5.59
Vert 13.00 1.00 13.00 0.15 1.95
RAFTER 4
T.C & B.C 2.00 1.00 2.00 2.42 4.84
Diagonal 7.00 1.00 7.00 0.43 3.01
Vert 7.00 1.00 7.00 0.15 1.05
RAFTER 5
T.C & B.C 2.00 1.00 2.00 2.57 5.15
Diagonal 7.00 1.00 7.00 0.43 3.01
Vert 7.00 1.00 7.00 0.15 1.05
Sub-total Rafters 44.17 8 - 1-1/2" x 3/16 A/B
Sub-total Vert & Diag. 33.59 6 - 1OMM X 6M RSB
Roofing:
Main 4.90 5.00 5.35 26.20 5 - 0.40mm x 5.35 m Rib Type
Purlins
@ Roof 7.00 1.00 7.00 5.02 35.14
@ Ridge 2.00 1.00 2.00 7.11 14.21
@ eaves 1.00 2.00 2.00 5.15 10.30
Sub-total Purlins 59.65 10 - 1.2mm x 2" x 3" x 6m C-Purlins
Flashing
Front & Rightside 5.00 1.00 5.00 9.98 49.92 5 - 0.40mm x 2.4 m x 0.40 Flashing
Fascia Board
Front, L/S & R/S 7.00 1.00 7.00 15.00 105.03 7 - 1" x 12" x 2.4 m HardiFascia
Gutter
Rear 3.00 1.00 3.00 4.90 14.70 3 - 1" x 12" x 2.44 m Gutter (See detail Plan)
Leftside 3.00 1.00 3.00 5.02 15.06 3 - 1" x 12" x 2.44 m Spanish Gutter
Ridge Roll
Rafter 1 1.00 1.00 1.00 7.11 7.11 4 - 1" x 12" x 2.4 m Ridge roll
Fascia Frame
Front 4.84
L/S 5.02
R/S 5.15
15.00
Vert 38.00 1.00 38.00 0.30 11.40
Hor 2.00 1.00 2.00 15.00 30.01
41.41 7 - 1-1/2" x 1-1/2" x 4.5mm F/B
No. Structure Member Grid/location Wave L H Set Quantity Bar Pcs Total No. Length Wt/m Total To Cut To Order Total Remarks
Area Volume Unit Ln.m Dia of Pcs Wt Wt
sq.m cu.m mm m kg kg
straight
bar
RB 0.30
1 top & Bottom straight bar RB A, C & E, 1-6 0.25 8.00 0.30 3 1.80 16 4 12 8.60 1.579 162.95 1@ 8.60 m = 8.60 12 pcs - 16 mm x 9.00 m 170.53 12 pcs - 8.60 m for 1
1@ 0.40 m = 0.40 12 pcs - 0.40 m excess
9.00
2 top & Bottom straight bar RB 3 & 6, A-F 0.25 8.00 0.30 2 1.20 16 4 8 8.60 1.579 108.64 1@ 8.60 m = 8.60 8 pcs - 16 mm x 9.00 m 113.69 8 pcs - 8.60 m for 2
1@ 0.40 m = 0.40 8 pcs - 0.40 m excess
9.00
3 top cut end RB 3 & 6, D'-F 1.70 2 16 3 6 2.70 1.579 25.58 2@ 2.70 m = 5.40 3 pcs - 16 mm x 6.00 m 28.42 6 pcs - 2.70 m for 3
1@ 0.60 m = 0.60 3 pcs - 0.60 m excess
6.00
4 top & Bottom straight bar RB 1, A-E 0.25 6.30 0.30 1 0.47 16 4 4 7.54 1.579 47.62 1@ 6.00 m = 6.00 4 pcs - 16 mm x 6.00 m 37.90 4 pcs - 6.00 m for 4
4@ 1.50 m = 6.00 1 pcs - 16 mm x 6.00 m 4 pcs - 1.50 m for 4
5 top & Bottom straight bar RB F, 3-6 0.25 5.10 0.30 1 0.38 16 4 4 5.70 1.579 36.00 1@ 5.70 m = 5.70 4 pcs - 16 mm x 6.00 m 37.90 4 pcs - 5.70 m for 5
1@ 0.30 m = 0.30 4 pcs - 0.30 m excess
6.00
6 top & Bottom straight bar LB 0.10 8.50 0.30 1 0.26 12 2 2 3.50 0.888 6.22 1@ 3.50 m = 3.50 2 pcs - 12 mm x 6.00 m 10.66 2 pcs - 3.50 m for 6
1 2 2 2.10 0.888 3.73 1@ 2.10 m = 2.10 2 pcs - 2.10 m for 6
1 2 2 2.90 0.888 5.15 1@ 0.40 m = 0.40 2 pcs - 0.40 m excess
6.00
RB 0.30
20 pcs - 16 mm x 9.00 m
10 kgs - #16 tying wire 637.27
No. Structure Member Grid/location Wave L H Set Quantity Bar Pcs Total No. Length Wt/m Total
Area Volume Unit Ln.m Dia of Pcs Wt
sq.m cu.m mm m kg kg
CHB 0.10 case1 straight
case2
C1 0.35 bar
lapping
RB 0.30
1 top & Bottom straight bar RB (7, C-F) 0.20 6.99 0.30 1 0.42 16 4 4 7.69 1.579 48.57
2 top & Bottom straight bar RB (5, B-E) 0.20 5.75 0.30 1 0.35 16 4 4 6.58 1.579 41.53
3 top & Bottom straight bar RB (2&4, D-F) 0.20 4.99 0.30 2 0.60 16 4 8 5.69 1.579 71.88
4 top & Bottom straight bar RB (3, B-F) 0.20 9.08 0.30 1 0.54 16 4 4 10.42 1.579 65.81
5 top & Bottom straight bar RB (2', C-E) 0.25 3.18 0.30 1 0.24 16 4 4 3.88 1.579 24.51
6 top & Bottom straight bar RB (2, D-F) 0.20 5.00 0.30 1 0.30 16 4 4 5.70 1.579 36.00
7 top & Bottom straight bar RB (B, 3-6) 0.20 5.75 0.30 1 0.35 16 4 4 6.45 1.579 40.74
8 top & Bottom straight bar RB (D, 2-7') 0.20 12.60 0.30 1 0.76 16 4 4 13.30 1.579 84.00
9 top & Bottom straight bar RB (E&F, 2-7) 0.20 11.90 0.30 2 1.43 16 4 8 12.94 1.579 163.46
10 top & Bottom straight bar RB (B', 5-7') 0.20 3.70 0.30 1 0.22 16 4 4 4.10 1.579 25.90
11 top & Bottom straight bar RB (6, B-B') 0.20 2.08 0.30 1 0.12 16 4 4 2.48 1.579 15.66
12 top & Bottom straight bar RB (6, E-F) 0.20 3.32 0.30 1 0.20 16 4 4 3.66 1.579 23.12
13 top & Bottom straight bar B1&B2 (7', B'-D) 0.20 2.00 0.30 1 0.12 16 4 4 2.34 1.579 14.78
14 top & Bottom straight bar B1&B2 (C, 2'-3) 0.20 2.57 0.30 1 0.15 16 4 4 2.97 1.579 18.76
Sub-total Volume of RB 5.33
Stair Railing handrail 2 6.17 12.34
post 7 1.00 7
19.34
4@ 6.00 m = 24.00
SUMMARY
### pcs - 16 mm x ### m #REF!
### pcs - 16 mm x ### m #REF!
### pcs - 12 mm x 9.00 m #REF!
### pcs - ### mm x 6.00 m #REF!
### pcs - 10 mm x ### m #REF!
### #REF!
16 pcs - 2-1/2" x 6m Stainless
No. Structure Member Grid/location Wave L H Set
stirrups
Sub-total
elbow stair
ramp
catch basins
Quantity Bar Pcs Total No. Length Wt/m Total To Cut
Area Volume Unit Ln.m Dia of Pcs Wt
sq.m cu.m mm m kg kg
0.00
6.17 12.34
1.00 7
19.34 4@ 6.00 m
16
6.5
68.25
90.75
74.75
26
100.75
9.03
6.195
9.548
3.6225
13.23
7.9275
4.2
4.1475
57.9005
5.25
3.50
3.125
11.875
8.1
5.58
10.8
6.75
10.8
2.34
37.62
10.75
16
19.5
8
24.75
15.75
46
18.75
13
13
158.75
170.625
4.40
3.25
4.70
11.60
23.95
3 15.30
2 12.70
1 2.25
1 8.00
3 57.60
95.85
10
4
14
To Cut To Order Total Remarks
Wt
= 24.00
SUMMARY
### pcs - 16 mm x ### m #REF!
### pcs - 16 mm x ### m #REF!
10 pcs - 12 mm x 9.00 m #REF!
### pcs - ### mm x 6.00 m #REF!
### pcs - 10 mm x ### m #REF!
### #REF!
16 pcs - 2-1/2" x 6m Stainless
No. Structure Member Grid/location Wave L H Set Quantity Bar Pcs Total No. Length Wt/m Total
Area Volume Ln.m Dia of Pcs Wt
sq.m cu.m mm m kg kg
Layout 9.60 9.60 4 92.16 2 8 9.60
Filling Works gound flr area A-E & 1-2 8.00 6.30 1.42 1 50.4 71.316
2-6 & E-F 6.00 1.70 0.67 1 10.2 6.783
Sub-total Backfilling 60.6 78.10
FOUNDATIONS
1 Footing (F1) 1.00 1.00 0.30 11 3.30 12 14 154 1.00 0.888 136.75
2 wall footing Main Bar 0.30 0.00 0.15 1 0.00 10 0 0 0.30 0.616 0
Temp 0.00 1 10 2 2 0.00 0.616 0
136.75
COLUMNS
3 (C1) 1E. 3E, 6E 0.30 0.30 5.30 3 1.43 16 4 12 5.49 1.579 104.06
1C. 3C, 4C, 6C 0.30 0.30 5.90 4 2.12 16 4 16 6.09 1.579 153.91
1A. 3A, 4A, 6A 0.30 0.30 6.80 4 2.45 16 4 16 7.63 1.579 192.81
1,107.33
CHB Walls Factor unit/qty W L H Set Area Vol Ln.m Pcs Total no.of layer
1 CHB Wall 12.50 pcs/sq.m 1 233.21 2916 2916
mortar settings:
sand 0.006 cu.m/sq.m 1 1.400
cement 12 bags/cu.m (class b) 1.400
filler:
mixed S&G 0.003 cu.m/pc 2916 8.750
cement 8.5 bags/cu.m (class a) 8.750
RSB (vert & hor) 4.28 ln.m/sq.m 10 998.1388 0.616 614.8535
Tying Wire #16 0.032 kg/sq.m 233.21 0.3 7.46272
Plastering:
sand 0.016 2 328.68 5.259
cement 18 bags/cu.m (class a) 5.259
SEPTIC TANK Factor unit/qty W L H Set Area Vol Ln.m Pcs Total no.of layer
1 CHB Wall 12.50 pcs/sq.m 1 21.00 263 263
mortar settings:
sand 0.006 cu.m/sq.m 1 0.130
cement 12 bags/cu.m (class b) 0.130
filler:
mixed S&G 0.003 cu.m/pc 263 0.790
cement 8.5 bags/cu.m (class a) 0.790
RSB (vert & hor) 4.28 ln.m/sq.m 10 89.88 0.616 55.36608
Tying Wire #16 0.032 kg/sq.m 21 0.3 0.672
Plastering:
sand 0.025 2 30.00 0.750
cement 18 bags/cu.m (class a) 0.750
1 Top & Bottom Slab longitudinal 1.20 4.00 0.10 2 9.6 0.96 12 5 10 4.00 0.888 35.52
cross 2 12 16 32 1.20 0.888 34.10
No. Structure Member Grid/location Set MATERIALS Pcs Total No. Length Total
of Pcs m Length
1 Truss A T.C 3 1/4X2 4 12 5.62 67.44
B.C 3 1/4X2 2 6 8.00 48.00
sub-total 115.44
vert. 3 1/4X1-1/2 4 12 0.30 3.60
3 1/4X1-1/2 4 12 0.85 10.14
3 1/4X1-1/2 4 12 1.33 15.90
3 1/4X1-1/2 4 12 1.84 22.08
3 1/4X1-1/2 2 6 2.34 14.01
diag. 3 1/4X1-1/2 4 12 2.08 24.96
3 1/4X1-1/2 4 12 1.66 19.92
3 1/4X1-1/2 4 12 1.29 15.48
3 1/4X1-1/2 4 12 0.99 11.82
sub-total 137.91
SUMMARY OF COLUMNS
28 pcs - 16 mm x 6.00 m 1,215.19
16 pcs - 16 mm x 9.00 m
60 pcs - 12 mm x 6.00 m
109 pcs - 10 mm x 6.00 m 91%
To Order
Filling Works gound flr area 5-7 & C-F 6.50 3.00 0.70 1 19.5 13.65
1-2 & A-D 5.50 1.00 0.70 1 5.5 3.85
A-F & 2-5 10.50 8.90 0.70 1 93.45 65.42
Sub-total Backfilling 118.45 82.92
FOUNDATIONS
1 Footing (F1) 1.50 1.50 0.32 12 8.64 16 16 192 1.50 1.579 454.75 4@
3 (CF) bottom bar 1.40 2.00 0.31 1 0.87 16 7 7 2.00 1.579 22.11 3@
bottom bar 16 11 11 1.40 1.579 24.32 4@
top bar 16 7 7 1.40 1.579 15.47
top bar 16 7 7 2.00 1.579 22.11
4 wall footing Main Bar 0.40 90.83 0.25 1 9.08 10 303 303 0.40 0.616 74.6592 15 @
Temp 0.40 90.83 1 10 3 3 90.83 0.616 167.8538 1 @
Sub-total Volume of Foundations 20.82
913.90
COLUMNS
Up to the level of 2nd floor only
5 (C1) (C, 3,5,7), (D, 1,2) 0.35 0.35 5.36 14 9.19 16 8 112 6.00 1.579 1,061.09
(E, 3,4,5,6),
(F, 2,3,4,6,7)
6 (C2) (A, 1,3,5), (B, 3,5) 0.30 0.30 5.36 5 2.41 16 8 40 6.00 1.579 378.96
2,014.62
589.42
Straight Main Bar (A-D) & (1-2) 5.50 1.00 1 5.50 10 4 5.60 0.616 13.80
Rebars-Temp (A-B') & (1-5) 3.51 9.90 1 34.75 10 12 10.00 0.616 73.92
(B'-D) & (1-7) 2.00 12.90 1 25.80 10 7 13.00 0.616 56.06
(D-E) & (2-7) 1.67 11.98 1 20.01 10 6 12.08 0.616 44.65
(E-F) & (2-3) 3.32 4.00 1 13.28 10 12 4.10 0.616 30.31
(E-F) & (4-7) 3.32 6.01 1 19.95 10 12 6.11 0.616 45.17
544.30
8 LB header gound floor only 0.10 42.99 0.20 1 0.86 12 2 2 42.99 0.888 76.35024 1 @
sill 0.10 25.96 0.20 1 0.52 12 2 2 25.96 0.888 46.10496 1 @
stirrups 10 345 345 0.20 0.616 42.504 30 @
9 LB header Second Floor 0.10 49.05 0.20 1 0.98 12 2 2 49.05 0.888 87.1128 1 @
stirrups 10 246 246 0.20 0.616 30.3072 30 @
10 V.S gound floor only 0.10 0.30 6.48 8 1.56 12 2 16 6.48 0.888 92.12467 1 @
stirrups 10 33 264 0.30 0.616 48.7872 20 @
MASONRY Factor unit/qty W L H Set Area Vol Ln.m Pcs Total no.of layer
FTG TO FFL hole
1 CHB Wall 12.50 pcs/sq.m 90.83 1.10 1 99.91 1249 1249
mortar settings:
sand 0.100 90.83 0.013 1 0.620 5.50
cement 12 bags/cu.m (class b) 0.620
filler:
mixed S&G 0.003 cu.m/pc 1249 3.750
cement 8.5 bags/cu.m (class a) 3.750
Plastering
sand 0.016 2 99.91 3.197
cement 18 bags/cu.m (class a) 3.197
2nd Flr to RB Factor unit/qty W L H Set Area Vol Ln.m Pcs Total no.of layer
1 CHB Wall 12.50 pcs/sq.m 1 #NAME? ### #NAME?
mortar settings:
sand 0.006 cu.m/sq.m 1 ### 0.00
cement 12 bags/cu.m (class b) ###
filler:
mixed S&G 0.003 cu.m/pc ### ###
cement 8.5 bags/cu.m (class a) ###
Plastering:
sand 0.025 2 #NAME? ###
cement 18 bags/cu.m (class a) ###
RSB (vert & hor) 4.28 ln.m/sq.m 10 #NAME? 0.616 #NAME?
Tying Wire #16 0.032 kg/sq.m #NAME? 0.3 #NAME?
To Cut To Order Total Remarks
Wt
1.50 m = 6.00 48 pcs - 16 mm x 6.00 m 454.75 192 pcs - 1.50 m for 1
SUMMARY
72 pcs - 16 mm x 6.00 m 940.85
70 pcs - 10 mm x 6.00 m 97%
1.25 m = 5.00 144 pcs - 10 mm x 6.00 m 532.22 576 pcs - 1.25 m for 7
SUMMARY
152 pcs - 16 mm x 6.00 m 2,123.81
185 pcs - 10 mm x 6.00 m 95%
SUMMARY
30 pcs - 16 mm x 6.00 m 650.12
99 pcs - 10 mm x 6.00 m 91%
Total 1,445,000.00
SUMMARY
Expenses Collected Profit
To Date
Engineer 1,162,478.93 1,445,000.00 282,521.07
Project: Const. of 2-storey Building
Owner: Mr. & Mrs. Ricky Unica
Date AMOUNT EXPENSED REMARKS
Labor Qty units Description Unit Cost Amount Total
Amount expense
to Date
27-Feb-15 1,240.00 Payroll for (Feb 27) 1,240.00
3 cu.m gravel 650.00 1,950.00 3,190.00
SCS vale 27Feb15 1,664.00 4,854.00
28-Feb-15 dave's mktg S.I # 1390 10,157.00 15,011.00
01-Mar-15 kris mktg S.I # 71210 3,525.00 18,536.00
6 cu.m sand 500.00 3,000.00 21,536.00
02-Mar-15 slicing coco 2,184.00 23,720.00
OS# 179569 25,082.00 48,802.00
OS# 179568 100,477.00 149,279.00
3 cu.m gravel 650.00 1,950.00 151,229.00
dried fish 150.00 151,379.00
03-Mar-15 CSI # 22494 65.00 151,444.00
07-Mar-15 8,890.00 Payroll for (Mar 1-7) 160,334.00
3 cu.m gravel 650.00 1,950.00 162,284.00
09-Mar-15 dried fish 150.00 162,434.00
4 pcs container 45.00 180.00 162,614.00
14-Mar-15 10,380.00 Payroll for (Mar 9-14) 172,994.00
19 pcs 2" x 2" x 10' coco 56.67 1,076.73 174,070.73
80 pcs 2" x 2" x 8' coco 45.33 3,626.40 177,697.13
24 pcs 16mm x 6m 295.00 7,080.00 184,777.13
16-Mar-15 dried fish & 2lit Oil 500.00 185,277.13
30 bags portland 261.00 7,830.00 193,107.13
3 cu.m sand 500.00 1,500.00 194,607.13
59 pcs 2" x 2" x 10' coco 56.67 3,343.53 197,950.66
19 pcs 2" x 2" x 8' coco 45.33 861.27 198,811.93
diesel for portland 500.00 199,311.93
17-Mar-15 3 cu.m gravel 650.00 1,950.00 201,261.93
1 pcs bowl 650.00 650.00 201,911.93
18-Mar-15 WS # 41864 12,730.00 214,641.93
2 pcs liplip 200.00 400.00 215,041.93
20 kg rice 38.00 760.00 215,801.93
3 cu.m sand 500.00 1,500.00 217,301.93
C.I # 7341 1,192.00 218,493.93
19-Mar-15 100 bags portland 261.00 26,100.00 244,593.93
diesel for portland 500.00 245,093.93
170 pcs 2" x 2" x 8' coco 45.33 7,706.10 252,800.03
3 cu.m gravel 650.00 1,950.00 254,750.03
20-Mar-15 3 cu.m gravel 650.00 1,950.00 256,700.03
21-Mar-15 3 cu.m gravel 650.00 1,950.00 258,650.03
13,140.00 Payroll for (Mar 16-21) 271,790.03
23-Mar-15 3 cu.m gravel 650.00 1,950.00 273,740.03
40 kg rice 37.00 1,480.00 275,220.03
diesel 150.00 275,370.03
10 pcs 12mm x 6m 165.00 1,650.00 277,020.03
25-Mar-15 1 box 4"CWN 1,000.00 1,000.00 278,020.03
3 cu.m sand 500.00 1,500.00 279,520.03
27-Mar-15 450 pcs 4"CHB 11.78 5,300.00 284,820.03
28-Mar-15 3 cu.m mixed s&g 500.00 1,500.00 286,320.03
11,760.00 Payroll for (Mar 22-28) 298,080.03
30-Mar-15 C.I # 46871 22,280.00 320,360.03
400 pcs 4"CHB 12.13 4,850.00 325,210.03
22 kg rice 37.00 814.00 326,024.03
01-Apr-15 3 cu.m mixed s&g 500.00 1,500.00 327,524.03
3 cu.m mixed s&g 200.00 600.00 328,124.03
02-Apr-15 7,900.00 Payroll for (Mar 29-Apr 2) 336,024.03
3 cu.m sand 500.00 1,500.00 337,524.03
3 cu.m mixed s&g 200.00 600.00 338,124.03 disposal anini-y
05-Apr-16 CSI # 22494 36,415.00 374,539.03
06-Apr-16 37 kg rice 37.00 1,369.00 375,908.03
C.I # 7501 1,630.00 377,538.03
3 cu.m mixed s&g 500.00 1,500.00 379,038.03
08-Apr-16 6 cu.m gravel 650.00 3,900.00 382,938.03
3 cu.m mixed s&g 500.00 1,500.00 384,438.03
09-Apr-16 6 cu.m mixed s&g 500.00 3,000.00 387,438.03
10-Apr-16 80 bags portland 261.00 20,880.00 408,318.03
100 pcs 10mm x 6m 111.00 11,100.00 419,418.03
11-Apr-15 13,390.00 Payroll for (Apr 3-11) 432,808.03
50 pcs Bamboo Poles 92.80 4,640.00 437,448.03
12-Apr-15 S.I # 1334 8,297.00 445,745.03
13-Apr-15 5 pcs 1/2 x 4 x 8 marine 730.00 3,650.00 449,395.03
2 pcs liplip 180.00 360.00 449,755.03
38 kg rice 37.00 1,406.00 451,161.03
14-Apr-15 3 cu.m mixed s&g 500.00 1,500.00 452,661.03
16-Apr-15 6 cu.m mixed s&g 500.00 3,000.00 455,661.03
17-Apr-16 6 cu.m mixed s&g 500.00 3,000.00 458,661.03
18-Apr-15 3 cu.m mixed s&g 500.00 1,500.00 460,161.03
12,490.00 Payroll for (Apr 12-18) 472,651.03
20-Apr-15 1 pc 2" pvc wye 20.00 20.00 472,671.03
2 pc 2" pvc elbow 28.00 56.00 472,727.03
38 kg rice 37.00 1,406.00 474,133.03
meat 200.00 474,333.03
liquor 200.00 474,533.03
3 cu.m gravel 650.00 1,950.00 476,483.03
3 cu.m mixed s&g 500.00 1,500.00 477,983.03 from sch
22-Apr-15 3 cu.m gravel 650.00 1,950.00 479,933.03
1 box 4" CWN 1,000.00 1,000.00 480,933.03
7 pc 16mm x 6m 285.00 1,995.00 482,928.03
2 kg 2-1/2" CWN 56.00 112.00 483,040.03
10 kg #16 Tying Wire 60.00 600.00 483,640.03
4 pcs 1/2" x 4 x 8 ord. plywd 665.00 2,660.00 486,300.03
25-Apr-15 3 cu.m gravel 1" 680.00 2,040.00 488,340.03
26-Apr-15 1 kg 2-1/2" CWN 56.00 56.00 488,396.03
1 kg 1-1/2" CWN 58.00 58.00 488,454.03
15,590.00 Payroll for (Apr 19-25) 504,044.03
27-Apr-15 38 kg rice 37.00 1,406.00 505,450.03
meat 200.00 505,650.03
350 pcs 4"CHB 11.78 4,122.22 509,772.25
02-May-15 10,086.00 Payroll for (Apr 26 - May 2) 519,858.25
50 bags portland 262.00 13,100.00 532,958.25
04-May-15 350 pcs 4"CHB 11.78 4,122.22 537,080.47
38 kg rice 37.00 1,406.00 538,486.47
08-May-15 3 cu.m sand 500.00 1,500.00 539,986.47
steel deck 51,327.00 591,313.47
09-May-15 11,445.00 Payroll for (May 3-9) 602,758.47
3 cu.m mixed s&g 500.00 1,500.00 604,258.47
11-May-15 rice 1,500.00 605,758.47
100 bags Portland 266.00 26,600.00 632,358.47
15 pcs 12mm x 6m 158.00 2,370.00 634,728.47
14-May-15 35 lit diesel 37.00 1,295.00 636,023.47 pick up steeldek
allowance 580.00 636,603.47
15-May-15 350 pcs 4"CHB 11.78 4,122.22 640,725.70
20 pcs 10mm x 6m 108.00 2,160.00 642,885.70
10 pcs 12mm x 6m 158.00 1,580.00 644,465.70
10 pcs 16mm x 6m 285.00 2,850.00 647,315.70
1 roll #16 Tying Wire 2,400.00 2,400.00 649,715.70
10 kls 2-1/2" CWN 60.00 600.00 650,315.70
3 cu.m sand 500.00 1,500.00 651,815.70
16-May-15 3 cu.m sand 500.00 1,500.00 653,315.70
220 pcs 10mm x 6m 108.00 23,760.00 677,075.70
5 kls welding rod 100.00 500.00 677,575.70
17,460.00 Payroll for (May 10-16) 695,035.70
17-May-15 allowance 1,500.00 696,535.70
18-May-15 3 cu.m gravel 650.00 1,950.00 698,485.70
6 pcs 2" x 90deg pvc elbow 29.00 174.00 698,659.70
1 pcs 200cc solvent 135.00 135.00 698,794.70
1 pcs 4" x 3m pvc pipe s1000 680.00 680.00 699,474.70
1 pcs 2" x 3m pvc pipe s1000 240.00 240.00 699,714.70
6 m welding cable 0.5mm 200.00 1,200.00 700,914.70
1 pc welding rod holder 125.00 125.00 701,039.70
2 kg concrete nails 2" 80.00 160.00 701,199.70
23-May-15 3 cu.m sand 500.00 1,500.00 702,699.70
1 kls Welding Rod 100.00 100.00 702,799.70
0.5 kls concrete nails 2" 82.00 41.00 702,840.70
24-May-15 18,550.00 Payroll for (May 17-23) 721,390.70
25-May-15 allowance 1,500.00 722,890.70
3 cu.m gravel 650.00 1,950.00 724,840.70
10 pcs 10mm x 6m 108.00 1,080.00 725,920.70
27-May-15 50 bags Portland 263.00 13,150.00 739,070.70
4 pcs 2" x 90deg pvc elbow 29.00 116.00 739,186.70
2 pcs 302081 bearing 465.00 930.00 740,116.70
28-May-15 3 cu.m sand 500.00 1,500.00 741,616.70
29-May-15 50 bags Portland 263.00 13,150.00 754,766.70
30-May-15 19,610.00 Payroll for (May 24-30) 774,376.70
01-Jun-15 allowance 800.00 775,176.70
04-Jun-15 50 pcs 10mm x 6m 108.00 5,400.00 780,576.70
30 pcs 16mm x 6m 298.00 8,940.00 789,516.70
3 cu.m sand 500.00 1,500.00 791,016.70
06-Jun-15 11,055.00 Payroll for (June 1-6) 802,071.70
08-Jun-15 allowance 800.00 802,871.70
11-Jun-15 40 bags Portland 267.00 10,680.00 813,551.70
5 kg #16 Tying Wire 60.00 300.00 813,851.70
2 cu.m gravel 158.00 316.00 814,167.70
50 pcs 10mm x 6m 108.00 5,400.00 819,567.70
1 kls 1-1/4" CWN 60.00 60.00 819,627.70
13-Jun-15 10,730.00 Payroll for (June 7-13) 830,357.70
19-Jun-15 3 cu.m gravel 500.00 1,500.00 831,857.70
1 pcs 2" x 3m pvc pipe s1000 240.00 240.00 832,097.70
1 box 4" CWN 1,000.00 1,000.00 833,097.70
20-Jun-15 9,680.00 Payroll for (June 14-20) 842,777.70
24-Jun-15 3 cu.m sand 500.00 1,500.00 844,277.70
40 pcs 16mm x 9m 525.00 21,000.00 865,277.70 susana
30 pcs 10mm x 6m 109.00 3,270.00 868,547.70 susana
16 pcs 16mm x 6m 276.00 4,416.00 872,963.70 susana
25-Jun-15 10 kg #16 Tying Wire 60.00 600.00 873,563.70
27-Jun-15 8,780.00 Payroll for (June 21-27) 882,343.70
01-Jul-15 3 cu.m sand 500.00 1,500.00 883,843.70
40 pcs 10mm x 6m 109.00 4,360.00 888,203.70 susana
15 kg #16 Tying Wire 60.00 900.00 889,103.70
2 kls 2-1/2" CWN 54.00 108.00 889,211.70
1 kls 1-1/4" CWN 58.00 58.00 889,269.70
05-Jul-15 9,680.00 Payroll for (June 28 toJuly 4) 898,949.70
06-Jul-15 28 bags Portland 268.00 7,504.00 906,453.70
3 cu.m gravel 500.00 1,500.00 907,953.70
10 pcs 1/2" x 3m pvc orange 72.00 720.00 908,673.70
3 pcs 3/4" x 3m pvc orange 109.00 327.00 909,000.70
20 pcs 10mm x 6m 109.00 2,180.00 911,180.70
11-Jul-15 8,300.00 Payroll for (July 5-11) 919,480.70
13-Jul-15 allowance 1,050.00 920,530.70
15-Jul-15 20 pcs 10mm x 6m 109.00 2,180.00 922,710.70
300 pcs 4"CHB 11.78 3,533.33 926,244.03
20 bags Portland 268.00 5,360.00 931,604.03
6 pcs 2" x 90 pvc elbow 29.00 174.00 931,778.03
18-Jul-15 11,820.00 Payroll for (July 12-18) 943,598.03
20-Jul-15 allowance 1,050.00 944,648.03
3 cu.m sand 500.00 1,500.00 946,148.03
40 pcs 5mm X 1-1/2 X 3m A/B 688.00 27,520.00 973,668.03
6 pcs 12mm X 6m RSB 158.00 948.00 974,616.03
10 kls welding rod 100.00 1,000.00 975,616.03
23-Jul-15 3 cu.m mixed s&g 500.00 1,500.00 977,116.03
20 pcs 10mm X 6m RSB 109.00 2,180.00 979,296.03
3 cu.m mixed s&g 500.00 1,500.00 980,796.03
25-Jul-15 10,580.00 Payroll for (July 19-25) 991,376.03
27-Jul-15 allowance 750.00 992,126.03
30-Jul-15 300 pcs 4"CHB 11.78 3,533.33 995,659.36
15 pcs 10mm X 6m RSB 109.00 1,635.00 997,294.36
4 gal epoxy primer w/ catalyst 650.00 2,600.00 999,894.36
5 kg welding rod 100.00 500.00 1,000,394.36
1 pc paint brush 2-1/2" 47.00 47.00 1,000,441.36
1 pc roller brush 4" 45.00 45.00 1,000,486.36
3 btl lacquer thinner 35.00 105.00 1,000,591.36
15 bags Portland 268.00 4,020.00 1,004,611.36
35 pcs 1-1/2" x 6m A/B (16.2kg) 645.00 22,575.00 1,027,186.36
17 pcs 1.2mmx2'x3'x6m c-prlins 380.00 6,460.00 1,033,646.36
01-Aug-15 5,000.00 Payroll for (Jul 26 Aug 1) 1,038,646.36
04-Aug-15 allowance 750.00 1,039,396.36
08-Aug-15 3,200.00 Payroll for (August 3-8) 1,042,596.36
10-Aug-15 allowance 650.00 1,043,246.36
300 pcs 4"CHB 11.78 3,533.33 1,046,779.70
20 bags Portland 270.00 5,400.00 1,052,179.70
15 pcs 10mm X 6m RSB 109.00 1,635.00 1,053,814.70
2 gal epoxy primer w/ catalyst 650.00 1,300.00 1,055,114.70
3 btl lacquer thinner 35.00 105.00 1,055,219.70
2 m wire mesh 1/8" 115.00 230.00 1,055,449.70
15-Aug-15 6,100.00 Payroll for (August 9-15) 1,061,549.70
19-Aug-15 2 gal epoxy primer w/ catalyst 650.00 1,300.00 1,062,849.70
2 pcs paint brush 2" 37.00 74.00 1,062,923.70
22-Aug-15 6,200.00 Payroll for (August 15-22) 1,069,123.70
24-Aug-15 1 gal epoxy primer w/ catalyst 650.00 650.00 1,069,773.70
allowance 840.00 1,070,613.70
2 kg #16 Tying Wire 60.00 120.00 1,070,733.70
28-Aug-15 24 pcs 1.2mmx2'x3'x6m c-prlins 380.00 9,120.00 1,079,853.70
15 pcs 10mm X 6m RSB 106.00 1,590.00 1,081,443.70
2 kg #16 Tying Wire 60.00 120.00 1,081,563.70
2 gal epoxy primer w/ catalyst 650.00 1,300.00 1,082,863.70
3 cu.m sand 45.00 135.00 1,082,998.70
3 btl lacquer thinner 35.00 105.00 1,083,103.70
3 pc paint brush 2-1/2" 37.00 111.00 1,083,214.70
29-Aug-15 6,200.00 Payroll for (August 15-22) 1,089,414.70
31-Aug-15 allowance 840.00 1,090,254.70
01-Sep-15 Roofing PNSC 20,000.00 1,110,254.70
02-Sep-15 30 bags Portland 275.00 8,250.00 1,118,504.70
250 pcs 4" CHB 11.78 2,944.44 1,121,449.14
03-Sep-15 Roofing PNSC 28,000.00 1,149,449.14
04-Sep-15 3 cu.m mixed s&g 500.00 1,500.00 1,150,949.14
3 pcs 3/16" x 1-1/2" FB 245.00 735.00 1,151,684.14
1 gal epoxy primer w/ catalyst 650.00 650.00 1,152,334.14
2 btl lacquer thinner 35.00 70.00 1,152,404.14
3 kg welding rod 100.00 300.00 1,152,704.14
1 box 5/32 x 1" blind revits 280.00 280.00 1,152,984.14
1 box 5/32 x 1/2" blind revits 250.00 250.00 1,153,234.14
3 pcs 5/32 drill bit 77.00 231.00 1,153,465.14
46 m 5mm x 1m insulator 2 sided 57.90 2,663.54 1,156,128.68
Roofing PNSC 891.00 1,157,019.68
05-Sep-15 5,200.00 Payroll for (August 31-Sep 1) 1,162,219.68
2 rolls Alum tape 94.00 188.00 1,162,407.68
1 pack 2" teckscrew (25pcs) 71.25 71.25 1,162,478.93
4 top & bottom straight bar 2 16 3 6 4.09 1.579 38.71357 1- 4.09 m = 4.09 6 pc - 16 mm x 9.00 m 85.24 kgs 6- 4.09 m for 4
1- 4.70 m = 4.70 6- 4.70 m for 13
1- 0.05 m = 0.21 6- 0.05 m excess
9.00
5 temp bars @ slab 2 10 10 20 0.86 0.616 10.5952 7- 0.85 m = 5.95 9 pc - 10 mm x 6.00 m 33.26 kgs 63 - 0.85 m
1- 0.05 m = 0.05 20 0.85 m for 5
6.00 8 0.85 m for 9
24 0.85 m for 14
10 0.85 m for 15
1- 0.85 m excess
6 temp bars @ landing 1 10 4 4 1.83 0.616 4.50912 3- 1.83 m = 5.49 2 pc - 10 mm x 6.00 m 7.39 kgs 6- 1.83 m
1- 0.51 m = 0.51 4 1.83 m for 6
6.00 2 1.83 m excess
2 0.51 m excess
12 top cut bar @ landing 1 16 3 3 1.90 1.579 9.001965 3- 1.90 m = 5.70 1 pc - 16 mm x 6.00 m 9.48 kgs 3- 1.90 m for 12
1- 0.30 m = 0.30 1- 0.30 m excess
6.00
13 top & bottom straight bar 2 16 3 6 4.70 1.579 44.54112 6 - 4.7014 m from 4
14 temp bars 2 10 12 24 0.86 0.616 12.71424 24 - 0.85 m from 5
15 steps 0.25 0.86 0.18 10 0.19
16 main 10 4 40 0.53 0.616 13.0592 40 - 0.53 m from 8
17 temp bars 10 10 1 10 0.86 0.616 5.2976 10 - 0.85 m from 5
Summary
1.24 cu.m
2 pc - 16 mm x 6m
7 pc - 16 mm x 9m
173.55 kgs 18 pc - 10 mm x 6m 184.93 kgs
0.065593 ok
Stair
ground to landing 1.75 1.44 5.14 2.27 0.82
landing to 2nd floor 2.25 1.80 8.30 2.88 0.80
ties/cleats purlins 0.10 0.08 0.02 0.13 0.75 124.00 15.50 3.00 pcs - 10mm x 6m
ROOF FRAMING
ROOFING
TILE ROOF 13.90 1.00 7.65 106.34
10.80 1.00 1.87 20.20
5.35 1.00 2.10 11.24
137.77 sq.m
Insulator
1.00 14.00 7.65 107.10
1.00 2.00 10.80 21.60
1.00 2.00 5.35 10.70
139.40 ln.m
Purlins
14.00 1.00 14.00 13.90 194.60
9.00 1.00 9.00 1.87 16.83
10.00 1.00 10.00 3.97 39.70
2.00 1.00 2.00 7.65 15.30
266.43 45 pcs - 2" x 3" x 6.00 m C-p
tekscrew 1,066.00
Fascia Frame 145.00 1.00 145.00 0.30 43.50 3 pcs - 5mm x 1-1/2 x 6m A/B
purlins
TOTAL #NAME?
Purpose: Construction and Repair of School Buildings and Facilites (Construction of Stage- Phase II)
Rombang, Sibalom, Antique
Requested by: Cash Availability Approved by:
Signature:
Printed Name: GIAN CARLO F. OCCEÑA EVA C. ESPIRITU GIAN CARLO F. OCCEÑA
Designation: Municipal Mayor Municipal Treasurer Municipal Mayor
Province: An
Municipality : Sib
Date : april 16,
QUANTITY TAKE - OFF
PROJECT : Facilites (Construction of Stage- Phase II)
LOCATION : DISTRICT III, SIBALOM , ANTIQUE
#NAME?
length width Area
24 9.8 235.2
Excavation
height length width no.of units volume
1 1 1 21 21
Embankment
height length width no.of units volume
0.6 24 6 1 86.4
CONCRETE WORKS
Table of Concrete Proportion by Volume
Mixture Proportion Cement in Bag Sand Gravel
Class 40 kg/cu.m
AA 1 : 1-1/2 : 2-3/4 9.10 0.67 1.00
A 1:2:4 8.50 0.50 1.00
B 1 : 2.5 : 5 7.50 0.50 1.00
C 1:3:6 6.00 0.50 1.00
MASONRY WORKS
III. CHB Wall w/ Plastering on both Sides
Volume of CHB Filler per Piece
Size of CHB Thickness Width Height Cores Volume
/pc
4" 0.05 0.075 0.20 4 0.003
6" 0.10 0.075 0.20 4 0.006
Qty of CHB, Cement & Sand for mortar (filler & settings)
Vol of CHB = 10.629 cu.m 6.03
Vol of Settings = 1.70028 cu.m 0.9648
Size of CHB Qty 40kg Cement in Bag Sand
Class
"A" "B" "C" "D"
4" x 8" x 16" 3543 221.93 147.95 110.96 92.47 12.32928
4" x 8" x 16" 2010 83.94 6.9948
6" x 8" x 16" 3543 382.81 255.2 191.4 159.5 21.267
V. SLAB ON FILL
Mixture Proportion Cement in Bag Sand Gravel
Class 40 kg/cu.m
AA 1 : 1-1/2 : 2-3/4 9.10 0.67 1.00
A 1:2:4 8.50 0.50 1.00
B 1 : 2.5 : 5 7.50 0.50 1.00
C 1:3:6 6.00 0.50 1.00
Roofing L Qty
7.40 24 177.60
2.30 24 55.20
232.80 24 x24 16 x 16 12 x 12
Tile works floor A B area cement sand 0.36 0.16 0.09
stall floor 20.00 6.00 121.73 52.59 1.95 338.13
cr floor 6.00 4.00 24.00 10.37 0.38 266.67
cr wall 38.64 16.69 0.62 429.33
TOTAL AREA 184.37 79.65 2.95 338.13 0.00 696.00
Province: Antique
Municipality : Sibalom
Date : april 16,2018
55.62 283.38
160.8
area total 444.18
BRGY. SUB-PROJECT WORK SCHEDULE/GANTT CHART
Name of Sub-Project:
Physical Target:
Location:
Region: VI
Province: Antique
Municipality: Sibalom
Barangay: District III
%
Item Physical
Description Amount Qty unit Wt. % Acco
No. Target
m W1 W2 W3
###
I #NAME? #NAME? ### ### #NAME? planned
actual
###
###
###
###
###
II #NAME? #NAME? ### ### #NAME? planned ###
actual
###
III #NAME? #NAME? ### ### #NAME? planned ###
actual
###
###
###
###
###
###
###
###
###
VII #NAME? #NAME? ### ### #NAME? planned ###
actual
VIII #NAME? #NAME? ### ### #NAME? planned ###
actual
IX #NAME? #NAME? ### ### #NAME? planned ###
actual
X #NAME? #NAME? ### ### #NAME? planned ###
actual
XI #NAME? #NAME? ### ### #NAME? planned ###
actual
XII #NAME? #NAME? ### ### #NAME? planned ###
actual
XIII #NAME? #NAME? ### ### #NAME? planned ###
actual
XIV #NAME? #NAME? ### ### #NAME? planned ###
actual
XV #NAME? #NAME? ### ### #NAME? planned ###
actual
XVI #NAME? #NAME? ### ### #NAME? planned ###
actual
###
###
###
###
###
XVII #NAME? #NAME? ### ### #NAME? planned ###
actual
XVIII #NAME? #NAME? ### ### #NAME? planned ###
actual
#NAME?
TOTAL DIRECT COST #NAME?
Planned % Physical Target Weekly #NAME? #NAME? #NAME?
Cumulative #NAME? #NAME? #NAME?
Actual % Physical Target Weekly
Cumulative
Slippage
Prepared By:
###
###
###
###
### ### ### ### ###
W3
### ### ### ###
#NAME?
#NAME?
### ### ### ###
### ###
### ###
Recommended by:
### ### ###
### ### ###
W4
### ### ###
#NAME?
#NAME?
### ###
Recommendations
### ###
### ###
### ###
### ###
### ### ### W5
#NAME?
#NAME?
### ### ###
### ###
### ###
### ###
### ### ###
W6
#NAME?
#NAME?
### ### ###
###
### ###
###
###
W7
###
#NAME?
#NAME?
Duration
###
###
###
### ###
### ### ###
W8
#NAME?
#NAME?
### ###
###
###
###
###
W9
###
#NAME?
#NAME?
###
###
###
###
###
W10
###
#NAME?
#NAME?
###
###
###
### ###
### ###
W11
Approved by:
###
#NAME?
#NAME?
###
MUNICIPAL MAYOR
### ### ###
W12
### ###
#NAME?
#NAME?
### ###
### ###
### ###
### ###
### ###
W13
###
#NAME?
#NAME?
### ###