Item No.

/Description : 900(1)c2 Structural Concrete for Footing and Slab on Fill (Class A
Unit of Measurement : m3
Output per hour : 0.357 m3

Designation No. of Person/s No. of Hour/s Hourly Rate


A. Labor

a. Construction Foreman 1 1.00 ₱ 134.71


b. Skilled Laborer 1 1.00 ₱ 99.11
c. Unskilled Laborer 4 1.00 ₱ 76.25

Sub-Total for A
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate
B. Equipment

a. One Bagger Mixer 1 1.00 ₱ 185.40


Minor Tools (10% of Labor Cost)

Sub-Total for B
C. Total (A+B)
D. Output per Hour = 0.357 m3
E. Direct Unit Cost (C/D)
Name and Specifications Unit Quantity Unit Cost
F. Materials
a. Gravel m3 1.00 ₱ 824.21
b. Sand m3 0.50 ₱ 687.12
c. Portland Cement bags 9.00 ₱ 252.36

Sub-Total for F
G. Direct Unit Cost (E+F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15% / 12% / 10% / 8% of G
I. Contractor's Profit (CP) 10% / 8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note:
1. This cost sheet shall be used for concreting footings and slab on fill by using manual mixing and manual po
and Slab on Fill (Class A, 28 days)

Hourly Rate Amount

₱ 134.71 ₱ 134.71
₱ 99.11 ₱ 99.11
₱ 76.25 ₱ 305.00

₱ 538.83
Hourly Rate Amount

₱ 185.40 ₱ 185.40
₱ 53.88

₱ 239.28
₱ 778.11

₱ 2,179.57
Unit Cost Amount

₱ 824.21 ₱ 824.21
₱ 687.12 ₱ 343.56
₱ 252.36 ₱ 2,271.24

₱ 3,439.01
₱ 5,618.58
12% / 10% / 8% of G ₱ 561.86
10% / 8% of G ₱ 561.86
5% of (G + H + I) ₱ 337.11
(G + H + I + J) ₱ 7,079.41