Project No.: C7426
Project Title: Kandhkot Wellhead Gas Compression Project
Report No.
C7426-REP-00-P-0003
CONTROLLED DOCUMENT
PAKISTAN PETROLEUM LIMITED
Process Operations and Control Philosophy
0 | 30/6/08 | Issued for Feed Study hig
Rev | oaTe DESCRIPTION PREPARED | CHECKED | APPROVED
(C7426-REP-00-P-0003 Rev 0.doc. ‘Sheet 1 of 13 = eonsKandhkot Gas Wellhead Compression - FEED Report No.
€7426-REP-00-P-0003
Contents
Process Operations and Control Philosophy 1
1 INTRODUCTION 3
44 Background 3
1.2 Objective 3
2 Compressor Control Philosophy 4
24 Compressor Operating Scenarios 4
22 Control Elements Available 6
Control System Description 6
Primary Control 6
Secondary Control 9
3 Utilities Control Philosophy 10
341 The Fuel Gas System 10
3.2 Condensate Recover System 10
3.3, Flare System "1
3.4 Compressed Air System 4
35 Inert Gas System 12
3.6 Power Generation System 12
37 Raw Water System 12
38 Potable Water System 12
3.9 Firewater System 12
3.10 ‘Chemical Injection System 13
67426-REP-00-P.0003 Rev Oxdoc Shoot 2 of 13Kandhkot Gas Wellhead Compression - FEED Report No.
14
1.2
(67426-REP-00-P-0003 Rev O.doe Sheet 3 of 13
(€7426-REP-00-P-0003
INTRODUCTION
Background
Pakistan Petroleum Limited (PPL) owns and operates the Kandhkot Gas Field
situated in the Sindh province of Pakistan, located about 400 km north-east of
Karachi at an elevation of 70 meters AMSL. Kandhkot Gas Field has three gas-
bearing domes namely SouthEast Dome, NorthEast Dome and West Dome. Each
dome consists of three gas reservoirs in Habib Rahi Limestone (HRL), Sui Upper
Limestone (SUL) and Sui Main Limestone (SML) formations, The West Dome is
producing from SML reservoir, North East Dome from SML and SUL reservoirs and
the South East Dome is producing from all the three reservoirs.
The existing gas treatment facilities at ‘Kandhkot Gas Plant’ comprises of Slug
Catcher, Flash Separator, Raw Gas Scrubbers and Dehydration Units. The gas is
thus treated and dehydrated prior to injection into the transmission pipeline.
Due to continuing production since 1987, the field is now entering the depletion phase
and it will not be possible to export the gas from Kandhkot Gas Plant at the delivery
pressure (700 psia) by year 2007-2008. Hence, PPL envisaged providing Gas
Compression facility at Kandhkot Gas Plant to cater for the continuing deciine in field
pressure.
Objective
The objective of this document is to outline the requirements for the Compressor and
Utilities control system. The compressor's anti-surge, performance and load-sharing
functions will be designed to protect the compressor from surge and provide the
control performance by load-sharing between trains to oblain the required plant
throughputs.
The control system shall include one anti-surge controller per compressor stage and
one load-sharing controller per compressor train
Ata minimum the control system for the Compressors and the Utilities shall meet the
control objectives detailed in this document.
This document outlines the Compression equipment and Utilities control philosophy
and will serve as the basis for the EPCC contractor during detailed design.Kandhkot Gas Wellhead Compression - FEED
Report No.
C7426-REP-00-P-0003
2 Compressor Control Philosophy
2.4 Compressor Operating Scenarios
Me Year 1 to Year 4 (Includes Suction Pressure Control)
— r c
: aa
: [asc} -{asc!
+
fspoea
conto
(C7426-REP-00-P-00083 Rev O.doe
Sheet 4 of 13,
Export
PipelineKandhkot Gas Wellhead Compression - FEED
Report No.
C7426-REP-00-P-0003
2-Year 5 to Year 10 (No Suction Pressure Control)
[speca
[Controte
W
/
i eer
: +
ee Vooalhn i
pi | 16)
+S oP >
.* ; Export
ascl-! ‘Jase Pipeline
Note: The discharge pressure of the compressors (PIC-1 above) or the discharge
pressure of the Dehydration Plant (PIC-2) can be selected as the control basis for
the compressors, depending on the client's preference.
(07426-REP-00-P-0003 Rev 0.doc
‘Sheet 5 of 13Kandhkot Gas Wellhead Compression - FEED Report No.
22
23
234
€7426REP-00-P.0003 Rev O.doc ‘Sheet 6 of 13
C7426-REP-00-P-0003
Control Elements Available
In order to limit the negative effects of process disturbances it is important to employ
‘as much positive integration within the control loops of a particular control system,
and between the separate control systems themselves, as possible. The control
elements involves are:
- Compressor Individual Suction Pressure Controllers
- Compressor Individual anti-surge controllers
- Gas Turbine Speed for each 2-stage train
= Cold Station Recycle for combined trains
Control System Description
The following compressor control scheme is elaborated under primary and secondary
controls.
Primary Control
Suction Pressure Control
During the first 3 to 4 years of operation of the compression facility, throttling of the
suction pressure will be necessary to ensure the compressors will operate within their
operating curves, away from surge. Suction pressure control will be an automatic
operation however the pressure set-point will need to be selected manually to
maximise the suction pressure in order to ensure the most efficient compression
operation (The less pressure lost across the throttling valve the better). The pressure
controller should act fast enough to allow turn-down and tum-up of the compressors
as gas consumption in the export pipeline varies over the course of the day, without
significantly affecting the suction pressure,
There will be a maximum allowable suction pressure above which the compression
system will rip. The reason for this is to limit the pressure relief case resulting from a
blocked discharge of the compressors (and hence allow a smaller flaring capacity),
whilst still ensuring that it is set high enough to maximise the suction pressure whilst
operating the compressor within it's operating envelope. This pressure is 2300 kPag
(Refer CAL-00-P-0013).
When the flowing pressure at the slug catcher has decreased to a pressure at which
the compressor can operate without suction pressure control (somewhere below
2300 kPag), then itis envisaged that the suction pressure control valves on each train
be replaced with a fultbore removable spool to minimise unnecessary pressure
losses,Kandhkot Gas Wellnead Compression - FEED Report No.
C7426-REP-00-P-0003
Discharge Pressure Control
‘The main objective of the control system is to control the pressure of gas in the export
pipeline to the consumer. It is unlikely that consumption of gas will be constant and so
the compressor system will need to respond to the increased and decreased demand
for gas. The two primary control elements which will allow this flexibility in operation
are:
= Gas Turbine Speed for each 2-stage train
= Cold Station recycle for combined trains
Note: Although it is not a normal operation, it is possible to operate all three
‘compressor trains in parallel. The control system will be detailed in such a
ways that this is made possible.
During normal operation it is envisaged that two compressor trains will be operating
with a combined throughput near 210 MMscfd (each with two stages of compression).
With increased gas consumption in the export pipeline, the pressure transmitter
installed in the pipeline (or alternatively the one installed upstream of the DHP), will
sense the low pressure. This signal is sent to the Load Sharing Controller (LSC) of
each train where the speed of each Gas Turbine is increased incrementally to ensure
that each compressor train operates at the same distance from surge as each other.
Speed control, in conjunction with suction pressure control (for the first 3 to 4 years of
operation), will be able to handle most increases and decreased in gas consumption
by maintaining the required pipeline pressure of 700 psia (4725 kPag).
When the demand for gas reduces beyond what speed control can adequately cope
ith, it will be necessary to recycle gas. The use of the anti-surge controller (ASC)
and associated recycle valves to perform this function is to be investigated during
detail design. For the purpose of this control scheme description it is assumed that
the cold station recycle (as detailed in the FEED study), is installed and operational.
The speed controller will be used to control the pressure at a set-point of
approximately 4725 kPag in the export pipeline. The same pressure transmitter on
the pipeline will be used to operate the cold station recycle, although with a higher
set-point (say 4800 kPag).
In the case that the consumer demand for gas is decreasing, the speed controller will
first reduce the speed in order to maintain the lower set pressure of 4725 kPag. If the
demand is still too low such that the reduced speed alone cannot decrease the
throughput (and discharge pressure) enough, then the pressure will rise to the cold
station recycle set-point and the recycle valve will open as required to maintain this
set-point. If the amount of gas being recycled is high on both compressors then it may
be considered by operations to stop one compression train completely.
When consumer demand increases, the pipeline pressure will begin to drop.
Accordingly, the pressure will decrease, causing the cold station recycle valve to
close to maintain its set-point of 4800 kPag. If the pressure continues to fall beyond
the LSC set-point of 4725 kPag, the compressor speeds will be increased in parallel
to increase the pipeline pressure.
(67426 REP-00-P-0003 Rev 0.doe Shoot 7 of 13,Kandhkot Gas Wellhead Compression - FEED Report No.
C7426-REP-00-P-0003
Load Sharing Control (LSC)
The Load Sharing Control System is a control package used to best manage the
compressors to operate equidistant from surge. In turn the load-sharing controllers
will send a set point to their respective fuel controllers/governors to allow each train to
operate at the correct speed to satisfy the above requirement. However, in the event
of a process disturbance the master controller will bypass the balancing feature of
‘equalised anti-surge deviation from set point and cause the load sharing controllers to
act directly on the capacity control elements of the compressor (speed set point) or
through the anti-surge controllers directly on the individual anti-surge recycle valves,
in order to return the primary variable (export pipeline discharge pressure) to set point
as quickly as possible and with the minimum process disturbance. When the primary
process variable is again satisfied, then the load sharing controllers will balance the
load via the equal anti-surge deviation from set-point as previously explained.
The capacity contro! system (master, load sharing and anti-surge controllers) shall
have fallback strategies available to allow operation (at reduced capacity if
necessary) in the event a transmitter fails, while warning of the failure.
Compressor Individual Anti-Surge Control (ASC)
Each compressor stage in each compression train will have its own anti-surge control
system to prevent damage of the compressors. Each of these controllers will measure
suction and discharge pressure and temperature and will also measure the suction
flow rate. These parameters will map the operating point of the individual
compressors on their respective operating curves. When a compressor comes too
close to its surge limit, the surge valve associated with that machine will open to
recycle gas and prevent surge from occurring. The advantage of individual anti-surge
controllers on compressors is that the each machine will be able to operate closer to
its surge line without recycling when necessary for one compressor stage, but not for
the other stage on the same shaft.
€7426REP-00-P-0008 Rev O.doe Sheet 8 of 13,Kandhkot Gas Wellhead Compression - FEED Report No.
C7426-REP-00-P-0003
2.3.2. Secondary Control
The following control objectives are for machine protection purposes:
High Discharge Pressure Limiting Control
Compressor stage discharge pressure high limiting control is required to protect the
compressor stage, train and downstream process from reaching a higher than des
operating pressure in the event of a control system failure or blocked discharge.
High Suction Pressure Limiting Control
There will be a maximum allowable suction pressure above which the associated
compression train will trip. The reason for this is to limit the pressure relief case
resulting from a blocked discharge of the compressors (and hence allow a smaller
flaring capacity), whilst still ensuring that it is set high enough to maximise the suction
pressure whilst operating the compressor within i's operating envelope. This
pressure is 2300 kPag (Refer CAL-00-P-0013) for the first stage compressor. The
requirement and or value for the second stage suction high pressure trip is to be
investigated during detailed design (pending vendor input).
Low Suction Pressure Limiting Control
A low suction pressure trip is associated with each stage on each train of
‘compression. The purpose of these trips is to ensure the compressors (during normal
operation) operate with a minimum suction pressure. This is a requirement of the
compressor manufacturer. This is to be further investigated during detailed design by
the EPCC contractor.
High Suction and Discharge Temperature Limiting Control
‘The compressor casings have a maximum temperature limit. A maximum suction and
discharge temperature will be supplied to the EPCC contractor by the selected
compressor vendor for incorporation of these trips.
Note: All shutdown requirements for both the Compression Facility and the
associated Utilities are detailed in the Cause and Effects Diagram (DS-00-P-0045
Rev 0).
C7426REP-00-P-0008 Rev O.doc Sheet 9 of 13Kandhkot Gas Wellhead Compression - FEED Report No.
3.4
3.2
(67426 REP-00-P-0003 Rev 0.doe ‘Sheot 10 of 13,
€7426-REP-00-P-0003
Us
The utilities control systems operate essentially autonomously to the Compressors
but are all linked to the CSS (Combined Safety System) for shutdown purposes.
ies Control Philosophy
The Fuel Gas System
The fuel gas system can be fed with gas from three sources:
1) Dehydrated gas from downstream of the DHP (Dehydration Plant)
2) Dehydrated gas from an alternate source such as the export pipeline (for
compressor start-up purposes only)
3) Saturated wellhead gas from the slug catcher (for low pressure gas start-
up only)
For source 1 and 2 stated above, the gas is fed via pressure control to the fuel gas
knockout drum (V-5101) at 3000 kPag. If source 3 is used, the Fuel Gas Compressor
Package is used to compress the low pressure saturated wellhead gas to the
required turbine fuel gas pressure of 3000 kPag (will not be required until reservoir
pressure has significantly depleted).
‘The fuel gas passes through one of 2x100% electric heaters and is heated to a
margin above the gas’s dew point temperature.
Downstream of the fuel gas heaters, the fuel gas is filtered through one of 2x100%
filter-coalscers to remove any solids or aerosols. The gas compressor turbines are
supplied with fuel gas from the outlet of the filters. A pressure reduction valve reduces
the fuel gas pressure for use by the gas engine generators, flare purge gas,
blanketing gas and pilot gas.
Pressure relief to flare ensures that neither the high pressure or low pressure fuel gas
users see too high a pressure during process disruptions (eg. Shutdown of a
compression train)
‘A temperature and pressure compensated flowmeter is installed in the Fuel gas
System to totalise the consumption of Fuel Gas.
Condensate Recover System
The Condensate Recovery System consists of two flash vessels, one in the
Compression Area and one in the Slug Catcher Area. The liquid flow from the Slug
Catcher Flash Vessel (V-5701) is maintained by blanket gas pressure to enable the
separated liquid to flow under level control to the existing condensate storage tanks
Liquids knocked-out in the various Scrubbers in compressor trains, Inlet Gas Filters
and fuel gas system is collected and flashed in the condensate flash vessel (V-5702)
at atmospheric pressure. Flash gas is routed to flare while stabilised liquid is pumpedKandhkot Gas Wellhead Compression - FEED Report No.
3.3
3.4
C7A26-REP.00--0003 Rev 0.doe Sheet 11 of 13,
C7426-REP-00-P-0003
to the Condensate Storage Tanks. V-5702 operates at Flare Knockout Drum
pressure.
‘The Slug Catcher level control system is the only source for the Slug Catcher Flash
Vessel (V-5701). The level in the Slug Catcher is controlled by level control valves. A
restriction orifice (RO) is installed between the Slug Catcher level control valves and
the Slug Catcher Flash Vessel for Phase 1. The purpose of this RO is reduce the
possible gas blowby relief case required to be considered for the Slug Catcher Flash
Vessel (it has a lower design pressure than the Slug Catcher). This was necessary
since the level control valves are designed to enable level control during the late
years of gas production from the reservoir when the slug catcher pressure is below
1280 kPag. The resulting large valves mean that an excessive gas blowby flow would
be possible in the early years of production if the control valves failed. This RO is to
be removed when the slug catcher non-flowing pressure reduces to below 1280
kPag
Shutdown valves are provided on all liquid lines in the Condensate Recovery System
(including from the liquid sources) to protect the facility from encountering a gas blow-
by due to level control failure. The shutdown valves will be Fail Closed and will close
when a Low Low level signal is received from the associated vessel.
Flare System
The control system associated with the flare is straight forward. Alarms and finally a
High-High-High level trip in the Flare Knockout Drum will shutdown the compression
facility if the level cannot be controlled and maintained at a lower level. The amount of
liquid accumulation in the flare knockout drum is expected to be small.
Flare Drum Knockout Pumps are provided to transfer any liquid accumulation in the
Flare Knockout Drum to the Condensate Flash Vessel. The pumps will not start
automatically and the transfer is deemed a manual operation. This is done since
liquid accumulation will either be intermittent or a very slow process.
‘A temperature and pressure compensated flowmeter is installed on the flare header
(downstream of the Flare Knockout Drum line) to monitor and quantify the amount of
flared gases.
Purge gas is maintained to avoid ingress of air to the flare system.
Pilot gas is provided to the Flare tip Pilots via a PCV from the low pressure fuel gas
‘supply.
Compressed Air System
Compressed air is used as Instrument air (after dehydrated) and as Plant Air (Wet
gas). Dehydrated Instrument air is pressure controlled to the end user at 700 kPag by
redundant parallel PCVs downstream of the Instrument Air Receiver. A low pressure
alarm and low low pressure trip (facility wide ESD) downstream of the PCVs are
provided to ensure the integrity of the compression facility in the case of Instrument
air loss. A low pressure alarm is also installed on the Instrument Air Receiver.
Plant air is supplied to the end user at Plant Air Receiver pressure. A PCV on the
plant air header however will close in the case that the upstream pressure (theKandhkot Gas Wellhead Compression - FEED Report No.
35
3.6
3.7
3.8
3.9
C7426-REP-00-P-0003 Rev O.doc ‘Shoot 12 of 13
C7426-REP-00-P-0003
reservoir pressure) decreases to 600 kPag. In this way, the plant air is regulated to
ensure that Insturment air is made a priority when the Plant Air or Instrument Air
requirements become large. A low pressure alarm is also installed on the Plant Air
Receiver.
Inert Gas System
The Inert Gas pressure control system operates in the same manner as the
compressed air system in such that the pressure of nitrogen from the nitrogen
receiver is let down to user pressure using two parallel PCVs and the nitrogen for
utility consumption is used at the full nitrogen receiver pressure until the receiver falls,
to 600 kPag (in which case the PCV will close to conserve nitrogen for seal
purposes).
Power Generation System
The gas engine power generators are fuelled with low pressure fuel gas supplied
from the fuel gas system. The control for the generators is by the power generator
vendor and will be located in the Electrical Switch Room.
Raw Water System
The source for raw water is bore water, delivered by submersible bore pumps to the
Firewater Storage Tank (T-5503). There are 2x100% Service Water pumps
(duty/standby). The duty pump will operate continuously with a minimum recycle back
to the Firewater tank to keep the service water line pressurised for immediate use.
The service water pumps will stop upon low level in the Firewater Tank to ensure that
there remains sufficient water volume for fire-fighting. The service water system is
deemed as non-critical.
‘Also, when the level in the Firewater Storage Tank falls to a pre-determined level, the
bore water pumps will start automatically to makeup level again.
Potable Water System
The Potable water system consists of Water Treatment Package Feed Pumps, The
Water Treatment Package (a reverse osmosis package) , a potable water storage
tank (T-5603) and potable water distribution pumps (2x100%, duty/standby). The
distribution pumps will have a minimum recycle to back to the potable water tank to
ensure potable water is always available to the end user at the required pressure,
when required.
The Water Treatment Package (Z-5600) is a vendor supplied package and will
operate with its independent control system.
Firewater System
The firewater system consists of The Firewater Storage Tank (as detailed above),
2x100% Firewater Jockey Pumps (duty/standby) and 2x100% Diesel Firewater
Pumps (duty/standby). The duty jockey pump is designed to operate with a minimum.
recycle back to the Firewater Storage Tanks to ensure the Firewater Ring-mainKandhkot Gas Wellhead Compression - FEED Report No.
3.10
(07426-REP.00-P-0003 Rev 0.doe Sheet 13 of 13
C7426-REP-00-P-0003
remains charged in case a fire breaks out. When a hydrant is opened or a monitor is
used, a jockey pump is unlikely to maintain the required pressure in the Ring-main
and a Diesel Firewater pump will start. If the Duty pumps fails to start or one pump
can't maintain the pressure alone, the Standby Diesel Firewater pump will start.
Chemical Injection System
The chemical injection system is designed to supply each compression train with
corrosion inhibitor at strategically located injection points. It will be possible to trip the
chemical injection pumps for each train separately in accord with a trip of the
respective compression train
There will also be an injection pump set-up to provide corrosion inhibitor injection to
the injection points in compression facility which are common to all trains. This pump
will be tripped in the case of an entire compression facility shutdown.