AMRAPALI, PLATINUM & TITANIUM

Project Name: Construction / Rectification of Balance works / Left Out works of PLATINUM & TITANIUM on As is
where Basis at Plot no. GH – 01, Sector -119, Noida, (UP), pertains to Amrapali group

Date of Start 12.02.2020


Date Of Completion 11.02.2021
Revised Date Of Completion (Due to COVID-19 Pandemic) 11.07.2021
FLATS HAND OVER PLANNING

Completion as on Overall
No. of Un- Completion
S. No. Tower 26.02.2021 as per Completion as on
finished Flat Schedule
NBCC Scope (%) 26.02.2021 (%)

1 J 12 Feb.-2021 89.00% 98.49%


2 A1 1 Feb.-2021 90.00% 97.75%
3 A2 0 Feb.-2021 80.00% 98.00%
4 A3 1 Feb.-2021 88.00% 97.75%
5 A4 5 Feb.-2021 95.00% 96.25%
6 C 8 Feb.-2021 76.00% 97.50%
7 F 4 Feb.-2021 62.00% 97.24%
7 A 9 Apr.-2021 86.00% 98.55%
8 B1 4 Apr.-2021 94.00% 96.50%
9 B2 1 Apr.-2021 76.00% 94.50%
10 B3 0 Apr.-2021 70.00% 98.50%
11 B4 0 Apr.-2021 80.00% 98.00%
12 B5 0 Apr.-2021 70.00% 98.50%
13 B 7 May.-2021 74.00% 97.50%
14 D 6 May.-2021 69.00% 97.47%
15 E 8 May.-2021 80.00% 98.16%
16 G 8 May.-2021 74.00% 97.50%
17 H 8 May.-2021 76.00% 97.50%
18 V 2 May.-2021 89.00% 98.03%
NOTE: List of Flats as provided by RWA & continues update, Locked unit considered as
completed.
AMRAPALI, PLATINUM & TITANIUM

Project Name: Construction / Rectification of Balance works / Left Out works of PLATINUM & TITANIUM on As
is where Basis at Plot no. GH – 01, Sector -119, Noida, (UP), pertains to Amrapali group

Date of Start 12.02.2020


Date Of Completion 11.02.2021
Revised Date Of Completion (Due to COVID-19 Pandemic) 11.07.2021
External MEP Works
Completion as on Overall Completion
Completion
Sl. No Description 26.02.2021 as per as on 26.02.2021
schedule
NBCC Scope (%) (%)
1 DGs Feb-21 95.00% 97.80%

2 Transformers Jan-21 98.00% 99.30%

3 Lifts Mar-21 70.00% 93.08%

4 WTP Sep-20 100.00% 100.00%

5 Fire-fighting works Feb-21 95.00% 98.25%

6 Basement Ventilation Feb-21 93.00% 93.00%

EXTERNAL DEVELOPMENT WORKS


Completion as on Overall Completion
Completion
Sl. No Description 28.02.2021 as per as on 28.02.2021
schedule
NBCC Scope (%) (%)
1 Road Work Feb-21 80.00% 94.00%

2 External Electrical Work Feb-21 20.00% 72.00%

3 Horticulture Work Mar-21 75.00% 91.25%