London Tunnels

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 9

London cable tunnels

The project
London accounts for 20% of the UK’s electricity demand
and this is continuing to grow by 3-5% a year. This compares
to the UK average of 1-2% a year.

It is National Grid’s responsibility to ensure there is sufficient


transmission infrastructure available to support future energy
demand in London and, as part of our investment programme,
we are planning to build four deep tunnels which will house
new 400,000 volt (400kV) cables. The work is essential to
ensure London has a safe and secure electricity transmission
network into the future.

These tunnels will connect existing substations at:


• Hackney
• St John’s Wood
• Willesden
• Wimbledon
• Hurst
• Eltham
London cable tunnels

Traditional cable laying just


below the road surface
leads to traffic congestion

Why a tunnel?
In London most electricity is transmitted through underground
cables. They are traditionally located just beneath the road
surface and work to maintain these cables is carried out in
the road.
By housing new electricity cables in tunnels deep below the
road surface a number of advantages are achieved compared
to traditional methods:
• Major disruption to the road network throughout London
is avoided as we do not need to dig up the streets to lay
the cable
• Overall disruption to Londoners and road users during
construction is significantly reduced as the majority of the
works take place under ground
• Future repair and maintenance work can be carried out
Traffic congestion in London without disrupting traffic, businesses and residents
• Additional cables can be installed in the tunnels to meet
future demand
London cable tunnels

How do you build a tunnel?


A shaft, approximately 15m in diameter, is sunk at a large
construction site known as a drive site.

A tunnel boring machine (TBM) is then lowered down the shaft


and starts tunnelling along a pre-determined route at
approximately 120m per week.

The TBM carries out two main activities. It moves forward


cutting through the earth and it also inserts a tunnel lining of
concrete segments.

The TBM ends its journey at a reception site where another


TBM breakthrough shaft is sunk and the TBM is removed.
London cable tunnels

Cable installation
Once the tunnel is complete the high voltage cables are
pulled through the tunnel from large drums at the drive site.

These lengths are then joined together using specialist


techniques.

The cables connect to National Grid’s substations at either


end of the route via the shafts.
A cable drum delivery
Once the cables are installed, any shafts which are not
required for access or ventilation are backfilled.
London cable tunnels

Working with the community


National Grid is committed to working with local communities
and to minimising the impact of its works wherever possible.

A community relations programme will be carried out before work


begins and before any planning applications are submitted for the
headhouses which are required as part of the tunnel route.

National Grid will maintain regular contact during construction


with local communities in a number of different ways including:
• Public exhibitions
• Project leaflets
• Project updates by letter
• Dedicated community relations team
• Dedicated community relations phone number 0800 783 2855
• Local media

We are keen to support the local communities in which we


operate and are interested to hear of any community initiatives
we could support. These should be in the areas of:
• Education and skills
• Environment and energy
• Community development
London cable tunnels
Substation
Substation

Headhouses

Ground level

Temporary
Works Area

Shafts
Shafts

Tunnel

Shafts and headhouses


Intermediate shafts and headhouses are required at key points
along the route of the tunnel. The tunnel boring machine will link
these points as it progresses along the routes.

The shafts and headhouses are needed for the following reasons:

• Health & Safety – It is essential to have access points to


ensure the safety of our workforce during construction.
Tunnel shaft headhouse The shafts are also used to access the tunnel for
maintenance work once the tunnel is commissioned

• Ventilation – Ventilation equipment, in the form of fans, is


required to cool the cables and regulate the temperature
inside the tunnel

The headhouses will be designed in order to minimise their


visual impact on the local area. For example, the building
materials will be chosen to complement the surrounding
environment in agreement with the local council.
London cable tunnels

Who is National Grid?


National Grid is an international electricity and gas company
and one of the largest investor-owned energy companies in
the world. We play a vital role in delivering gas and electricity
to millions of people across Great Britain and northeastern US
in an efficient, reliable and safe manner. We believe the power
of action can play a major role in safeguarding our global
environment for future generations and tackling the effects of
climate change, providing all our customers with the highest
standards of service through network investment and through
our talented, diverse workforce.

National Grid owns the high-voltage electricity transmission


network in England and Wales and operates the system
across Great Britain. It also owns and operates the high
pressure gas transmission system in Britain and its distribution
business delivers gas to 11 million homes and businesses.
London cable tunnels
Edgware Woodford
Green Hainault
Muswell Woodford
Wood Bridge
Hill Green
Finchley Tottenham
Key
Wealdstone Hackney to St John’s Wood Proposed tunnel route
Walthamstow
12.5km, 4m diameter 400kV Barkingside Proposed tunnel shaft site

Kingsbury cable tunnel (2014) Possible future works


Hornsey Wanstead
Harrow Chadwell
Golders Heath
Green
Finsbury
Cricklewood Highgate Stoke
Newington
Wembley Hackney Leyton Ilford
Hampstead Kentish substation
Town Holloway Clapton
Kilburn Highbury
Brent Willesden to St John’s Wood
Hackney
7.4km, 4m diameter 400kV
Willesden
Forest
Gate
cable tunnel (2015) Camden
Homerton
Dagenham
Perivale Stratford
Town West
Harlesden St John’s Islington Ham Barking
East
Wood Ham
Willesden Ladbroke
substation St John’s Wood
enford Grove substation
Kensal Green Bethnal
Notting Clerkenwell- Shoreditch Green
Hill Finsbury-Barbican
Hanwell Shepherd’s Marylebone Mile Creekmouth
Bush Paddington City of End Beckton
Ealing
London
thall Holborn-Strand- Tower Hill Poplar
Acton Covent Garden North
Woolwich
Kensington
West Thamesmead
wood Kensington
een South Kensington Bermondsey
Walworth Isle of Abbey
Rotherhithe Dogs Wood
Chelsea Lambeth Woolwich
New Cross
Kew substation Deptford
South Charlton Erith
Fulham Lambeth
Peckham
Isleworth West New Cross Greenwich
Barnes
Brompton Battersea Stockwell Camberwell
w Kidbrooke
Blackheath
Richmond Putney Clapham Brixton New Cross to Eltham
Brockley
Eltham substation Welling
Herne 10.7km cable tunnel (future)
Lewisham Bexleyheath
Hill
Wimbledon to Kensal Green Wandsworth Eltham
Roehampton Hither Crayford
Forest
12.1km, 4 metre diameter Balham Dulwich
Hill
Green

Twickenham 400kV cable tunnel (2016) Bexley


Upper Catford New
Tooting Hurst to Eltham
Eltham Coldblow
West
Norwood
Grove 7.1km, 4m diameter 400kV
Park Hurst
Wimbledon Streatham cable tunnel (2014) substation
Teddington substation Sydenham North
Wimbledon Sidcup Cray
Foots
ampton Crystal Cray
Palace Chislehurst
Merton
Kingston
upon Beckenham Bromley
Thames
Mitcham
East New South Bickley
Molesey Malden Norwood
Shortlands Swanley
Petts
Surbiton Eden Wood
Thames
Ditton Thornton Park Saint Mary
Morden
H th

Hackney to St John’s Wood


Length: 12.5 km
Tunnel routes
Planned Construction: • The total length of the four tunnels is approximately 40km
Autumn 2009 – 2014
• Average depth of the tunnels is between 12m and 60m
Willesden to St John’s Wood
• The tunnel and shafts are below ground and do not
Length: 7.4 km
require planning approval
Planned Construction:
Autumn 2009 – 2015
• Headhouses built on private land require planning approval

Hurst to Eltham • Planning applications will be submitted from early 2009


Length: 7.1 km
• Total investment will be in the region of £600 million
Planned Construction:
Mid 2009 – 2014

Wimbledon to Kensal Green


Length: 12.1 km
Planned Construction:
Late 2009/early 2010 – 2016
London cable tunnels

Expected timescales
Hackney to St John’s Wood Hurst to Eltham
• Informing the community Ongoing • Informing the community Ongoing
• Planning submission Early 2009 • Planning submission Early 2009
• Start construction Autumn 2009 • Start construction Mid 2009
• Planned completion 2014 • Planned completion 2014

Willesden to St John’s Wood Wimbledon to Kensal Green


• Informing the community Ongoing • Informing the community Ongoing
• Planning submission Spring 2009 • Planning submission By Spring 2009
• Start construction Autumn 2009 • Start construction Late 2009/early 2010
• Planned completion 2015 • Planned completion 2016

You might also like