Qs Final Output Santos Ivan S.

You might also like

Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 50

Santos, Ivan S.

February 7, 2024
BSCE 3A

ACTIVITY NO.1 - EARTHWORKS


CEP381C: QUANTITY SURVEYING COMPUTATION

PROBLEM: Estimate the quantities required for excavation, backfill, and soil-fill for your residential building project.

COMPUTATION:

ITEM NO. SCOPE / ITEM DESCRIPTION SET LENGTH (m) WIDTH (m) HEIGHT (m) VOLUME (m^3)
1.0 EXCAVATION
F-1 1 1.50 1.50 1.50 3.38
F-2 8 1.20 1.20 1.30 14.98
WF 1 58.60 0.45 0.60 15.82
MH 6 0.50 0.50 0.62 0.93
ST 1 2.40 1.50 2.20 7.92
TOTAL 43.03
SOIL FILL
GROUND FLOOR AREA 1 11.10 8.00 0.50 44.40
TOTAL 44.40

SUMMARY:

ITEM NO. SCOPE UNIT QUANTITY REMARKS


1.1 EXCAVATION m^3 43.03 -
1.2 BACKFILL m^3 34.18 -
1.3 SOIL-FILL m^3 57.72 30% Allowance

ASSUMPTIONS:

Assumed height of wallfooting is 0.60


Columns are neglected for excavation.
Footings & columns are neglected for backfill.
Santos, Ivan S.
BSCE 3A

ACTIVITY NO.2 - CONCRETE FOR FOOTI


CEP381C: QUANTITY SURVEYING

PROBLEM : Estimate the required cement, sand, and gravel for the footings, and co

COMPUTATION:

ITEM NO. SCOPE / ITEM DESCRIPTION


2.0 FOOTING-BUILDING
F-1
F-2
WF

3.0 COLUMN-BUILDING
C-1
C-2
PC (EXTENDED C1-C2)

SUMMARY:

ITEM NO. SCOPE


2.0 FOOTING-BUILDING
2.1 CEMENT 40KG
2.2 SAND
2.3 GRAVEL
3.0 COLUMN-BUILDING
3.1 CEMENT 40KG
3.2 SAND
3.3 GRAVEL

ASSUMPTIONS:
Assumed PC as an extension of column 1 and 2 with a fixed height of 1.50 m and a
February 15, 2024

O.2 - CONCRETE FOR FOOTINGS AND COLUMNS


C: QUANTITY SURVEYING COMPUTATION

d gravel for the footings, and columns applicable to your residnetial building.

SET LENGTH (m) WIDTH (m) HEIGHT (m) VOLUME (m^3)

1 1.50 1.50 0.30 0.68


8 1.20 1.20 0.30 3.46
1 54.40 0.45 0.30 7.34
TOTAL 11.48

1 0.40 0.20 8.60 0.69


8 0.40 0.20 8.40 5.38
9 0.20 0.20 1.50 0.54
TOTAL 6.61

UNIT QUANTITY REMARKS

bag 109
m^3 6.03 With 5% allowance
m^3 12.05

bag 63
m^3 3.47 With 5% allowance
m^3 6.94
a fixed height of 1.50 m and a dimension of 200 mm by 200 mm.
Santos, Ivan S.
BSCE 3A

PROBLEM: Estimate the required cement, sand, an


elements required for your residential building plan

COMPUTATION:

ITEM NO.
4.0

5.0

6.0

7.0

8.0
9.0

CANOPY (RIGHT SIDE VIEW

CANOPY (LEFT SIDE VIEW

REAR STAIRS (BACKDOOR

LEFT SIDE STAIRS (DOOR)

SUMMARY:

ITEM NO.
4.0
4.1
4.2
4.3
5.0
5.1
5.2
5.3
6.0
6.1
6.2
6.3
7.0
7.1
7.2
7.3
8.0
8.1
8.2
8.3

9.0

9.1
9.2
9.3

ASSUMPTIONS:

Thickness of the ledge is equal to the suspended sla


Slab on balcony is not included / indicated as suspe
used is equal to the slab details.
March 1, 2024

ACTIVITY NO.3 - CONCRETE FOR SLABS, BEAMS, STAIR AND OTHER


STRUCTURAL MEMBER AND NON-STRUCTURAL ELEMENTS
CEP381C: QUANTITY SURVEYING COMPUTATION

M: Estimate the required cement, sand, and gravel for the slabs, beams, stair and other structural and non-structural
required for your residential building plan.

SCOPE / ITEM DESCRIPTION SET LENGTH (m) WIDTH (m) HEIGHT (m) VOLUME (m)
SECOND FLOOR BEAM
DB-1 1 40.28 0.20 0.25 2.01
DB-2 1 20.68 0.20 0.25 1.03
CB-1 1 5.57 0.20 0.25 0.28
TOTAL 3.32
ROOF BEAM
RB-1 1 49.80 0.15 0.30 2.24
RCB-1 1 3.99 0.15 0.30 0.18
TOTAL 2.42
SLAB ON GRADE
SOG (A1) 1 1.35 2.05 0.10 0.28
SOG (A2) 1 2.55 2.05 0.10 0.52
SOG (A3) 1 5.85 3.85 0.10 2.25
SOG (A4) 1 0.80 2.20 0.10 0.18
SOG (A5) 1 4.00 5.65 0.10 2.26
SOG (A6) 1 3.30 3.85 0.10 1.27
SOG (A7) 1 2.25 2.50 0.10 0.56
SOG (A8) 1 2.25 1.20 0.10 0.27
TOTAL 7.59
SUSPENDED SLAB
S-1 (A1) 1 6.05 8.20 0.10 4.96
S-1 (A2) 1 0.95 4.20 0.10 0.40
S-1 (A3) 1 5.63 4.00 0.10 2.25
S-1 (A4) 1 2.65 1.15 0.10 0.30
S-1 (A5) 1 3.40 1.60 0.10 0.54
TOTAL 8.45
STAIR
SOFFIT-1 1 1.64 0.90 0.12 0.18
SOFFIT-2 1 2.92 0.90 0.12 0.32
SOFFIT-3 1 1.08 0.90 0.12 0.12
LANDING-1 1 0.98 0.95 0.10 0.09
LANDING-2 1 2.03 0.98 0.10 0.20
LANDING BEAM 1 2.03 0.15 0.15 0.05
LANDING SLAB-1 1 0.98 0.98 0.05 0.05
LANDING SLAB-2 1 2.03 0.98 0.05 0.10
STEPS 16 0.90 0.30 0.20 0.86
STEPS ( SLAB)-1 16 0.90 0.33 0.05 0.24
STEPS (SLAB)-2 16 0.90 0.15 0.03 0.06
STAIR FOOTINGS 1 0.30 0.30 0.15 0.01
1 0.80 0.80 0.20 0.13
TOTAL 2.41
LEDGE, LINTEL BEAM,
STIFFENER CLUMN, ETC.
LEDGES 1 5.43 0.48 0.10 0.26
BALCONY (SLAB) 1 1.48 1.60 0.10 0.24
CANOPY (RIGHT SIDE VIEW) 2 0.70 0.30 0.08 0.03
CANOPY (REAR VIEW) 3 0.70 0.32 0.08 0.05
1 2.05 0.65 0.08 0.11
CANOPY (LEFT SIDE VIEW) 4 0.70 0.30 0.08 0.07
1 2.3 0.65 0.08 0.12
FRONT STAIRS (FOYER) 1 2.00 1.68 0.15 0.50
1 1.25 2.28 0.15 0.43
1 1.65 2.88 0.15 0.71
REAR STAIRS (BACKDOOR) 1 1.23 2.05 0.15 0.38
1 1.53 2.65 0.15 0.61
LEFT SIDE STAIRS (DOOR) 1 0.60 2.00 0.15 0.18
1 0.68 2.16 0.15 0.22
1 0.96 2.76 0.15 0.40
TOTAL 4.31

SCOPE / ITEM DESCRIPTION UNIT QUANTITY REMARKS


SECOND FLOOR BEAM
CEMENT 40KG bag 32
SAND m^3 1.74 With 5% allowance, 3000 psi
GRAVEL m^3 3.49
ROOF BEAM
CEMENT 40KG bag 23
SAND m^3 1.27 With 5% allowance, 3000 psi
GRAVEL m^3 2.54
SLAB ON GRADE
CEMENT 40KG bag 72
SAND m^3 3.98 With 5% allowance, 3000 psi
GRAVEL m^3 7.97
SUSPENDED SLAB
CEMENT 40KG bag 80
SAND m^3 4.44 With 5% allowance, 3000 psi
GRAVEL m^3 8.87
STAIR
CEMENT 40KG bag 23
SAND m^3 1.27 With 5% allowance, 3000 psi
GRAVEL m^3 2.53
LEDGE, LINTEL BEAM,
STIFFENER COLUMN,
ETC.
CEMENT 40KG bag 41
SAND m^3 2.26 With 5% allowance, 2500 psi
GRAVEL m^3 4.53

s of the ledge is equal to the suspended slab.


alcony is not included / indicated as suspended slab. So, I added it to the other structural member. The thickness
ual to the slab details.
Santos, Ivan S.
BSCE 3A

PROBLEM: Estimate the reinforcement for footing


rebar length for all structural elements. Provide a dr
splicing at every floor level.

COMPUTATION:

ITEM NO.
10.0
11.0

SUMMARY:

ITEM NO.
10.0
10.1
10.2
10.3
11.0
11.1
11.2
11.3
11.4

ASSUMPTIONS:

Assuming 135 degree hook (length = 6db).


Assumed a typical detail of wall footing and used d
Spacing at rest is assumed to be 125 mm for C1 and
Spacing at rest is assumed to be 130 mm for PC1 (e
Assumed PC1 having 4-12 mm rebar.
I set PC1 in the cutitng list as an extended column t
I used 1 tie @ 50 mm spacing before starting the 10
ACTIVITY NO.4 - REBAR FOR FOOTINGS AND COLUMNS
CEP381C: QUANTITY SURVEYING COMPUTATION

M: Estimate the reinforcement for footing and columns required for your resindential building plan. Use only grade 33 bar and 6.0 m
th for all structural elements. Provide a drawing of the column details or a cutting list of each typical column. Use only 50% rebar
every floor level.

SCOPE / ITEM DESCRIPTION SET PIECES DIAMETER (mm) LENGTH (m)


FOOTINGS
F1x 1 9 16 2
F1y 1 9 16 2
F2x 8 7 16 1.5
F2y 8 7 16 1.5
WF-GRIDLINE 3
BOTTOM BAR 1 4 10 6
MAIN BAR 1 2 10 6
1 1 10 3
WF-BETWEEN GRIDLINE 3-2
BOTTOM BAR 1 3 10 6
MAIN BAR 1 1 10 6
WF-BETWEEN GRIDLINE 2-1
BOTTOM BAR 1 3 10 6
MAIN BAR 1 1 10 6
WF-BETWEEN GRIDLINE 2-1
BOTTOM BAR 2 3 10 3
MAIN BAR 2 1 10 3
WF-GRIDLINE 1
BOTTOM BAR 1 3 10 6
MAIN BAR 1 1 10 6
1 1 10 1
WF-PASSING GRIDLINE 1
BOTTOM BAR 1 3 10 3
MAIN BAR 1 1 10 3
WF-GRIDLINE A
BOTTOM BAR 1 6 10 6
MAIN BAR 1 2 10 6
1 1 10 1.5
WF-BETWEEN GRIDLINE A-B
BOTTOM BAR 1 3 10 6
MAIN BAR 1 1 10 6
1 1 10 1
WF-GRIDLINE B
BOTTOM BAR 1 3 10 6
MAIN BAR 1 1 10 6
1 1 10 1.5
WF-BETWEEN GRIDLINE B-C
BOTTOM BAR 1 3 10 3
MAIN BAR 1 1 10 3
WF-GRIDLIN C
BOTTOM BAR 1 6 10 6
MAIN BAR 1 2 10 6

TOTAL

COLUMNS
MAIN REBARS
C1 1 16 16 6
1 4 12 3
C2 8 8 12 6
8 4 12 3
8 4 16 3
8 4 16 6
PC1 (EXTENDED C1-C2) 9 4 12 2

TOTAL

LATERAL TIES
C1 1 81 10 1
C2 8 79 10 1
PC1 9 18 10 1
TOTAL

SCOPE / ITEM DESCRIPTION UNIT QUANTITY REMARKS


FOOTINGS
16 mm pcs 34 321.98
10 mm pcs 52 192.36
#16 GI Tie Wire kg. 12 10 % allowance
COLUMNS
16 mm pcs 64 606.08
12 mm pcs 94 500.73
10 mm pcs 146 540.09
#16 GI Tie Wire kg. 37 10 % allowance

135 degree hook (length = 6db).


a typical detail of wall footing and used different plans as basis that is similar to my plan. (Used 3-10 mm rebars).
t rest is assumed to be 125 mm for C1 and C2 in ground floor.
t rest is assumed to be 130 mm for PC1 (extended column of C1-C2).
PC1 having 4-12 mm rebar.
in the cutitng list as an extended column that lies on the beam.
e @ 50 mm spacing before starting the 100 mm @ h/4.
APRIL 29, 2024

y grade 33 bar and 6.0 m


n. Use only 50% rebar

TOTAL (m)

18
18
84
84

24
12
3

18
6

18
6

18
6

18
6
1

9
3
36
12
1.5

18
6
1

18
6
1.5

9
3

36
12
204 16 mm
308 10 mm

96
12
384
96
96
192
72
384 16 mm
564 12 mm

81
632
162
875 10 mm

MARKS

21.98
92.36
allowance
06.08
00.73
40.09
allowance
Santos, Ivan S.
BSCE 3A

PROBLEM: Estimate the reinforcement for beams, s


building plan, use only grade 33 rebar and 6.0 m reba

COMPUTATION:

ITEM NO.
12.0

13.0

14.0
DB2-CB1 BETWEEN GRIDLI

DB2-CB1 BETWEEN GRIDLI

DB2-CB1 BETWEEN GRIDLI

DB2-CB1 BETWEEN GRIDLI

15.0
16.0
17.0

SUMMARY:

ITEM NO.
12.0
12.1
12.2
13.0
13.1
13.2
13.3
14.0
14.1
14.2
14.3
15.0
15.1
15.2
15.3
15.4
16.0
16.1
16.2
16.3

17.0

17.1
17.2

ASSUMPTIONS:

No layout of one-way slab is provided in the plan. So


main bar and the 10 mm bar as distribution bar. I also
Assumed spcing for the steps' rise and run is 150 mm
I inclunded the beam that supports the truss into othe
Assumed 10 mm diameter @ 0.2 m o.c for canopy. B
Assumed 10 mm diameter @ 0.2 m o.c for ledges. B
Assumed other stairs in door entrance as a pure poure
ACTIVITY NO.5 - REBAR FOR BEAMS, SLABS, STAIRS, AND OTHER STRUCTURAL AND
NON STRUCTURAL ELEMENTS.
CEP381C: QUANTITY SURVEYING COMPUTATION

M: Estimate the reinforcement for beams, slabs, stairs, and structural and non-structural elements required for your residential
lan, use only grade 33 rebar and 6.0 m rebar length for all structural elements.

SCOPE / ITEM DESCRIPTION SET PIECES DIAMETER (mm) LENGTH (m)


SLAB ON GRADE
SOG-A1X 1 25 10 6
SOG- A1Y 1 20 10 6
SOG-A2X 1 13 10 6
SOG- A2Y 1 10 10 6
SOG-A3X 1 14 10 6
SOG- A3Y 1 12 10 6
TOTAL
SUSPENDED SLAB
S1-A1
MAIN BARS-A1X 1 59 12 6
DISTRIBUTION BARS-A1Y 1 40 10 6
TOP BARS-A1Y 1 24 10 6
S1-A2
MAIN BARS-A2X 1 34 12 6
DISTRIBUTION BARS-A2Y 1 34 10 6
TOP BARS-A2Y 1 19 10 6

TOTAL

SECOND FLOOR BEAM


MAIN REBAR
DB1-GRIDLINE 3 1 16 16 6
DB1-GRIDLINE 1 1 11 16 6
DB1-CB1-GRIDLINE A 1 19 16 6
1 5 16 3
DB1-CB1-GRIDLINE B 1 19 16 6
1 5 16 3
DB1-CB1-GRIDLINE C 1 19 16 6
1 5 16 3
DB2 BETWEEN GRIDLINE 2-3 2 6 16 6
DB2 BETWEEN GRIDLINE 1-2 2 6 16 6
DB2 PASSING GRIDLINE 1 1 3 16 6
DB2-CB1 BETWEEN GRIDLINE A-B 1 7 16 6
BOTTOM EXTRA BAR
DB1-GRIDLINE 3 1 2 16 6
DB1-GRIDLINE 1 1 1 16 6
1 1 16 1
DB1-CB1-GRIDLINE A 1 3 16 6
DB1-CB1-GRIDLINE B 1 3 16 6
DB1-CB1-GRIDLINE C 1 3 16 6
DB2 BETWEEN GRIDLINE 2-3 2 2 16 3
DB2 BETWEEN GRIDLINE 1-2 2 2 16 3
DB2 PASSING GRIDLINE 1 1 2 16 1.5
DB2-CB1 BETWEEN GRIDLINE A-B 1 2 16 2
TOP EXTRA BAR
DB1-GRIDLINE 3 1 3 16 6
DB1-GRIDLINE 1 1 2 16 6
1 1 16 1.5
DB1-CB1-GRIDLINE A 1 4 16 6
1 1 16 3
DB1-CB1-GRIDLINE B 1 4 16 6
1 1 16 3
DB1-CB1-GRIDLINE C 1 4 16 6
1 1 16 3
DB2 BETWEEN GRIDLINE 2-3 2 6 16 1.5
DB2 BETWEEN GRIDLINE 1-2 2 6 16 1.5
DB2 PASSING GRIDLINE 1 1 1 16 6
DB2-CB1 BETWEEN GRIDLINE A-B 1 2 16 6
1 1 16 3
TOTAL
STIRRUPS
DB1-GRIDLINE 3 1 47 10 1
DB1-GRIDLINE 1 1 35 10 1
DB1-CB1-GRIDLINE A 1 69 10 1
DB1-CB1-GRIDLINE B 1 75 10 1
DB1-CB1-GRIDLINE C 1 72 10 1
DB2 BETWEEN GRIDLINE 2-3 2 24 10 1
DB2 BETWEEN GRIDLINE 1-2 2 24 10 1
DB2 PASSING GRIDLINE 1 1 11 10 1
DB2-CB1 BETWEEN GRIDLINE A-B 1 26 10 1
TOTAL
ROOF BEAM
MAIN REBAR
RB1-GRIDLINE 1 1 10 12 6
RB1-GRIDLINE 2 1 10 12 6
RB1-GRIDLINE 3 1 10 12 6
RB1-RCB1-GRIDLINE A 1 16 12 6
RB1-RCB1-GRIDLINE B 1 16 12 6
RB1-RCB1-GRIDLINE C 1 16 12 6
TOP EXTRA BAR
RB1-GRIDLINE 1 1 3 16 6
RB1-GRIDLINE 2 1 3 16 6
RB1-GRIDLINE 3 1 3 16 6
RB1-RCB1-GRIDLINE A 1 3 16 6
1 10 12 1
RB1-RCB1-GRIDLINE B 1 3 16 6
1 10 12 1
RB1-RCB1-GRIDLINE C 1 3 16 6
1 10 12 1

TOTAL

STIRRUPS
RB1-GRIDLINE 1 1 47 10 1
RB1-GRIDLINE 2 1 48 10 1
RB1-GRIDLINE 3 1 47 10 1
RB1-RCB1-GRIDLINE A 1 69 10 1
RB1-RCB1-GRIDLINE B 1 75 10 1
RB1-RCB1-GRIDLINE C 1 72 10 1
TOTAL
STAIRS
FOOTING (BOTHWAYS) 1 10 12 1
VERTICAL BAR 1 7 12 1
HORIZONTAL BAR 1 4 12 1.5
WALL FOOTING
MAIN BAR 1 10 12 0.2
VERTICAL BAR 1 2 10 1.5
STIRRUPS 1 4 10 1
LANDING BEAM
MAIN REBAR 1 6 12 3
STIRRUPS 1 14 10 0.5
LANDING1-SOFFIT1
BOTTOM BAR 1 6 10 3
TOP 1 6 10 3
LANDING2-SOFFIT2
BOTTOM BAR 1 6 10 6
TOP BAR 1 6 10 6
LANDING-SOFFIT3
BOTTOM BAR 1 6 10 2
TOP BAR 1 6 10 2
LANDING SLAB2 1 5 10 3
LANDING SLAB1 1 5 10 1
SOFFIT1 1 8 10 1
SOFFIT 2 1 15 10 1
SOFFIT3 1 5 10 1
STEPS
HOLDER 16 1 10 1
RISE AND RUN 16 6 10 1

TOTAL

OTHER STRUCTURAL AND NON-


STRUCTURAL ELEMENTS
BEAM SUPPORTING TRUSS
MAIN BAR 2 6 10 6
STIRRUPS 2 49 10 0.5
CANOPY
RIGHT SIDE VIEW 2 3 10 0.5
REAR SIDE VIEW 3 3 10 0.5
1 10 10 1
LEFT SIDE VIEW 4 3 10 0.5
1 11 10 1
LEDGES 1
Lx 1 28 10 0.5
Ly 1 3 10 6
TOTAL

SCOPE / ITEM DESCRIPTION UNIT QUANTITY REMARKS


SLAB ON GRADE
10 mm pcs 94 347.73
#16 GI TIE WIRE kg 8 10% allowance
SUSPENDED SLAB
12 mm pcs 93 495.40
10 mm pcs 117 432.81
#16 GI TIE WIRE kg 21 10% allowance
SECOND FLOOR BEAM
16 mm pcs 169 1600.43
10 mm pcs 72 266.34
#16 GI TIE WIRE kg 42 10% allowance
ROOF BEAM
16 mm pcs 18 170.46
12 mm pcs 83 442.13
10 mm pcs 60 221.95
#16 GI TIE WIRE kg 19 10% allowance
STAIRS
12 mm pcs 8 42.62
10 mm pcs 51 188.66
#16 GI TIE WIRE kg 6 10% allowance
OTHER STRUCTURAL AND NON-
STRUCTURAL ELEMENTS
10 mm pcs 32 118.38
#16 GI TIE WIRE kg 3 10% allowance

of one-way slab is provided in the plan. So, it was based on other details of floor plan similar to it. I used my 12 mm bar as my
nd the 10 mm bar as distribution bar. I also added a top bar provided to the critical section L/4.
spcing for the steps' rise and run is 150 mm o.c.
d the beam that supports the truss into other structures. Assumed 2 set of this beam with 8 m length.
10 mm diameter @ 0.2 m o.c for canopy. Bar is along the width.
10 mm diameter @ 0.2 m o.c for ledges. Both ways.
other stairs in door entrance as a pure poured concrete.
April 29, 2024

d for your residential

TOTAL (m)

150
120
78
60
84
72
564 10 mm

354
240
144

204
204
114
558 12 mm
702 10 mm

96
66
114
15
114
15
114
15
72
72
18
42

12
6
1
18
18
18
12
12
3
4

18
12
1.5
24
3
24
3
24
3
9
9
6
12
3
1009 16 mm

47
35
69
75
72
48
48
11
26
431 10 mm

60
60
60
96
96
96

18
18
18
18
10
18
10
18
10
108 16 mm
498 12 mm

47
48
47
69
75
72
358 10 mm

10
7
6

2
3
4

18
7

18
18

36
36

12
12
15
5
8
15
5

16
96
43 12 mm
306 10 mm

72
49

3
4.5
10
6
11

14
18
188 10 mm

MARKS

7.73
llowance

5.40
2.81
llowance

00.43
6.34
llowance

0.46
2.13
1.95
llowance
2.62
8.66
llowance

8.38
llowance

d my 12 mm bar as my
Santos, Ivan S.
BSCE 3A
ACTIVITY NO.6 - M
CEP381C: QUANTITY SUR

COMPUTATION:

ITEM NO. SCOPE / ITEM DESCRIPTION


18.0 WALL
4" CHB
FIRST FLOOR
SECOND FLOOR
5" CHB
ROOF
MORTAR
FIRST FLOOR
CEMET 40 KG
SAND
SECOND FLOOR
CEMENT 40 KG
SAND
ROOF
CEMENT 40 KG
SAND
REBARS (Grade 33 - 10 mm Ø)
FIRST FLOOR
VERTICAL BAR
HORIZONTAL BAR
SECOND FLOOR
VERTICAL BAR
HORIZONTAL BAR
ROOF
VERTICAL BAR
HORIZONTAL BAR

PLASTERING (BOTH SIDE)


FIRST FLOOR
CEMENT 40 KG
SAND
SECOND
CEMENT 40 KG
SAND
ROOF
CEMENT 40 KG
SAND

SUMMARY:

ITEM NO. SCOPE / ITEM DESCRIPTION


17.0 WALL
4" CHB
5" CHB
REBAR (6 m - 10 mm Ø)
CEMENT 40 kg
SAND
#16 GI TIE WIRE

ASSUMPTIONS:

Vertical bar spacing for CHB is 0.60.


Horizonal bar spacing is every 3 layer of CHB.
May 27, 2024

ACTIVITY NO.6 - MASONRY WORKS


381C: QUANTITY SURVEYING COMPUTATION

LENGTH HEIGHT AREA FACTOR UNIT QUANTITY

51.11 3.75 191.66 12.5 pcs 2396


55 2.9 159.5 12.5 pcs 1994

47 1.3 30.55 12.5 pcs 382

51.11 3.75 191.66 0.525 bag 101


51.11 3.75 191.66 0.044 m^3 8.44

55 2.9 159.5 0.525 bag 84


55 2.9 159.5 0.044 m^3 7.02

47 1.3 30.55 0.525 bag 17


47 1.3 30.55 0.44 m^3 13.45

51.11 3.75 191.66 2.13 m 408.24


51.11 3.75 191.66 2.15 m 412.07

55 2.9 159.5 2.13 m 339.74


55 2.9 159.5 2.15 m 342.93

47 1.3 30.55 2.13 m 65.08


47 1.3 30.55 2.15 m 65.69
TOTAL: 1633.75

54.71 3.75 205.16 0.300 bag 123


54.71 3.75 205.16 0.025 m^3 10.26

58.6 2.9 169.94 0.300 bag 102


58.6 2.9 169.94 0.025 m^3 8.5

47 1.5 35.25 0.300 bag 21


47 1.5 35.25 0.025 m^3 1.76

UNIT QUANTITY REMARKS

pcs 4390 -
pcs 382 -
pcs 272 1006.19
bag 448 -
m^3 49.43 -
kg 20.12 -
Santos, Ivan S.
BSCE 3A ACTIVITY NO.7 - ROOFING WORKS
CEP381C: QUANTITY SURVEYING COMPUTATION
May 27, 2024
OFING WORKS
YING COMPUTATION
Santos, Ivan S.
BSCE 3A
ACTIVITY NO.8 - DOORS AND WINDOWS
CEP381C: QUANTITY SURVEYING COMPUTAT

COMPUTATION:

ITEM NO. SCOPE / ITEM DESCRIPTION SET


20.0 DOORS AND ACCESSORIES
May 27, 2024

- DOORS AND WINDOWS


Y SURVEYING COMPUTATION
Santos, Ivan S.
BSCE 3A
ACTIVITY NO.9 -
CEP381C: QUANTITY SURVEYING COMPUTATION
May 27, 2024
Santos, Ivan S.
BSCE 3A
ACTIVITY NO.9 -
CEP381C: QUANTITY SURVEYING COMPUTATI
May 27, 2024

TIVITY NO.9 -
Y SURVEYING COMPUTATION
Santos, Ivan S.
BSCE 3A
ACTIVITY NO.9 -
CEP381C: QUANTITY SURVEYING CO
May 27, 2024

ACTIVITY NO.9 -
QUANTITY SURVEYING COMPUTATION

You might also like