Instruction:

The following are to be submitted in this tab:

1. Activity No. 6 – Masonry Works


2. Activity No. 7 – Roofing Works
3. Activity No. 8 – Doors and Windows
4. Activity No. 9 – Ceiling Works
5. Activity No. 10 – Tile Works
6. Activity No. 11 – Painting Works
7. Complete scanned copy of your residential plan with the Instructor’s signature.

Follow a similar format to the previous activities. Include in your estimate all the materials indicated in
the plan.
Name: ___________________ Date: ________________
Section: ________

ACTIVITY NO. 5 – REBAR FOR BEAMS, SLABS, STAIRS, AND OTHER STRUCTURAL AND
NON-STRUCTURAL ELEMENTS
CEP 381C: Quantity Surveying Computation

Problem:

Estimate the reinforcement for beams, slabs, stairs, and other structural and non-structural elements
required for your residential building plan. Use only Grade 33 rebar and 6.0m rebar length for all structural
elements.

Computation:

Item Diameter Length Total


Scope / Item Description Set Pieces
No. (mm) (m) (m)
16.0 Slab on Grade

Total
17.0 Suspended Slab

Total
18.0 Grade/Tie Beam
Main Rebar

Stirrups

Total
19.0 Second Floor Beam
Main Rebar

Stirrups

Total
20.0 Roof Beam
Main Rebar

Stirrups

Total
21.0 Stairs

Total
Summary:

Item
Scope / Item Description Unit Quantity Remarks
No.
16.0 Slab on Grade
16.1 10mmɸ pcs
16.2 #16 GI Tie Wire kg.
17.0 Suspended Slab
17.1 10mmɸ pcs
17.2 #16 GI Tie Wire kg.
18.0 Grade/Tie Beam
18.1 16mmɸ pcs
18.2 12mmɸ pcs
18.3 10mmɸ pcs
18.4 #16 GI Tie Wire kg.
19.0 Second Floor Beam
19.1 16mmɸ pcs
19.2 12mmɸ pcs
19.3 10mmɸ pcs
19.4 #16 GI Tie Wire kg.
20.0 Roof Beam
20.1 16mmɸ pcs
20.2 12mmɸ pcs
20.3 10mmɸ pcs
20.4 #16 GI Tie Wire kg.
21.0 Stair
21.1 16mmɸ pcs
21.2 12mmɸ pcs
21.3 10mmɸ pcs
21.4 #16 GI Tie Wire kg.

Note:

• Add the scope of work or item required to your plan that is not listed in the format; the
item numbering may be changed as per the project requirements.
• Indicate in the remarks the allowances used and the equivalent weight in kilograms of
each rebar item.
• List in bullet form the assumptions used after the summary table, if there are any,
especially if no detail is shown in the plan.