Quality Checklist For Site Works: 18 Mep Clearnce Task A-Electrical & Mechanical Works
Quality Checklist For Site Works: 18 Mep Clearnce Task A-Electrical & Mechanical Works
CL : 18-A
Sl.No. Description YES NO NA
x1 Is format CL:017-A for Wet-Areas Waterproofing complied with?
START OF WORK
1 Approved drawing is available.
2 Make and related accessories are approved by client
3 Method Statement is approved by client
4 MTC / Third party test reports are available as applicable
5 Make is approved by client
6 All measuring equipment/ tools are calibrated
7 Ensure Plumbing layout is marked on the walls/floors as per the approved drawing
8 Ensure chasing of walls with required width & depth is completed for placing of pipes
9 Ensure waterproofing is completed inside the chased area as per approved Method Statement
10 Ensure placing, fixing & alignment of pipes is done as per the drawing
11 Ensure sleeves installed for piping are as per approved drawing
12 Ensure proper support (fixtures / clamps) to pipe provided as per drawing.
13 Ensure pipes and fitting ends are capped (plugged)
14 Ensure Pressure test conducted and found no leakages from pipes as per specification
15 Ensure chased area is plastered as per the specification and cured properly
16 Ensure vent pipe is installed