QUALITY CHECKLIST FOR SITE WORKS

22 PAINTING TASK
EXTERIOR YARD WORKS

ARCHITECTURAL STRUCTURAL INTERIOR SERVICES & UTILITY

EXTRIOR

Building Unit Designation Name: Project ID:


Name of the Contractor Group: Location:
Construction Drawing Ref. No.: Quantity:

CL : 22-B
Sl.No. Description YES NO NA
x Is format CL:21-A for Tiles works complied with?
1 Check clearnce/approval from previous activity (curing).
2 Check for any wall cracks, Curing period completed or not ?
3 Check the material/paints as approved make ?
4 Check color shade approved ?
5 Cleaning of walls to be checked (Scrapping), Surface finishing ?
6 Cracks, Dampness, any leakages to be identified and repaired ?
7 Apply primary coat ?
8 Application of coat as per tech specification to be checked ?
Check others materials covered neatly with masking tape (protection of other materials from damage like Electrical
9
switches plate, door/window joints, glass partitions, wardrobes) ?
10 Check for no of coat applied & final touch up work are completed ?
11 Check for overall coverage andy brush marks ?
12 Check for cleaning in flooring, window/door glasses & joinery ?
13 Is there any fitting after painting ?
14 Check for any incomplete and addition and alteration ?
15 Check for floor polishing before final coat ( in case of Marble flooring) ?
16 Qualified & trained workforce were used ?
17 Rectification for defect with suitable crack filler done & no cracks or scales remain ?
18 Surfaces are clean, dry and free from oil & grease ?
19 MEP works completed and Clearance obtained ?
20 All surfaces are prepared by sanding to receive the painting system ?
21 All installed doors/windows, service fixtures/fittings are protected with tape/ polythene before application of paint system
22 Approved Color and Color System is being used ?
23 The specifications/ manufacturer’s instructions are strictly being followed ?
24 The primer coats are applied evenly to the entire surface ?
25 The Stucco(putty) coats are applied evenly to the entire surface and sanding has been provided ?
26 First Coat Painting is done as per required thickness ?
27 Final Coat Painting is done as per required thickness ?
28 All painting equipment has been cleaned and washed after the completion of work ?
29 Cleaning the area and unmasking & removal of any paint marks on Fixtures/ Fittings/ Hardware etc. completed ?
30 Other issues ?

CORRECTIVE ACTION PROPOSED- Item wise.


If 'No' is marked, please specify reasons and thereafter corrective action proposed.
(Add additional sheets, if necessary)

Comments:

Contractor's Rep.: Client Rep.: Lines & Visions Int. Rep.: